salvage protection package
TRANSCRIPT
-
8/9/2019 Salvage Protection Package
1/17
-
8/9/2019 Salvage Protection Package
2/17
-
8/9/2019 Salvage Protection Package
3/17
B
B.6
C
E
35 267 494.1
1
16'-5"(VIF)16'-5"(VIF)11'-7"(VIF)9'-8"11'-10"21'-714"12'-0
14"
10'-538
"
8
D
23'-1
3 4"
6'-10
1 4"
D
C
B.6
784.1
5 4 2
1'-10
1 2"
(VIF)
20'-9
1 8"(VIF)
12'-7
1 4"(VIF)
A
10'-018
"
6 3
F
9 1
12'-7
1 4"
(VIF)
UP3R
UP3R
UP14R
199.25'(VIF)
STOREROOM
4
BOILERROOM
3
COALVAULT
1
STOREROOM
7
STACKROOM
8
RESTROOM
13
DININGROOM
15
RESTROOM
17
RESTROOM
16CORRIDOR
14
STOREROOM12-A
STOREROOM
12
CORRIDOR
6
CORRIDOR
6
STAIRWAYA
SERVICECLOSET
5
RESTROOM
2
JAN.TOILET
10
JAN.CLOSET
11
JANITORSROOM
9
S5S4
S4
S1
S 1 T YP .
S1 TYP.
PP4
PP4
S1
1
S9
LOWER LEVEL PLAN 01SCALE: 1/8" = 1'-0"
SPP-1
LOWER LPLAN
SHEET TITLE:
DESCRIPTIODATE:
Client
DISTRICT OF COLUMBIA
901 G StreetWashington, D.C
ArchitecMARTINEZ & JOHNSON |
1238 Wisconsin AvenueWashington, D.C
202.333.44
Library ArchHOSHIDE WILLIAMS A
206.325.64
Structural EngRESTL DESIGNE
301.258.00
MEP EnginJOHN J. CHRISTIE & AS
202.364.44
SALVAGE,PRE
PROTECT
08.13.08
GEORGET
LIBRA3260 R Stree
WASHINGTO
M
THESE DRAWINGS, SPECIFICATIONS, AND(COLLECTIVELY,THE"DOCUMENTS")INCLLIMITATIONELECTRONICVERSIONSTHERDESIGNS,ANDARRANGEMENTSREPRESANDSHALLREMAINTHEPROPERTYOFMARCHITECTUREPC,ASDEFINEDBYAPPLAGREEMENTS("THEAGREEMENTS")ANDCOPYRIGHTSTATUTESOFTHEUNITEDS
DOCUMENTSSHALLBESTRICTLYLIMITEWHICHTHEYWEREPREPAREDANDDEVPERTHETERMSOFTHEAGREEMENTS. NDOCUMENTSSHALLBECOPIED,DISCLOSINCONNECTIONWITHANYOTHERWORKOTHER PERSONS FOR ANY PURPOSES,OTCOMPLETIONOFTHEPROJECT,WITHOUAUTHORIZATIONOFMARTINEZ&JOHNSOTHEDOWNLOADING,OPENING,ORVIEWVERSIONSOFTHEDOCUMENTSORVISUPRINTEDFORMTHEREOFSHALLCONSTI
EVIDENCEOFACCEPTANCEOFTHESER
KEY PLAN
P:\7590GeorgetownLibrary\Drawings\Salvage&
Protection\7590-SPP100.dwg
:8/22/2008
PRESERVE AND PROTECT NOTES:
PRESERVE DOOR, HARDWARE, AND FRAME
PRESERVE CABINETRY AND/OR SHELVES.
PRESERVE AND PROTECT ADJACENT WAINSCOT, TRIM, AND BASE
TO BE INCORPORATED INTO NEW FINISH
PRESERVE AND PROTECT IRON BALUSTRADE.
PRESERVE WINDOW AND WINDOW TRIM
PRESERVE PLASTER CROWN MOLDING
PRESERVE WAINSCOT AND BASE BOARD MOLDINGS
PRESERVE AND PROTECT EXISTING FLAGPOLE.
PP6
PP5
PP4
PP3
PP2
PP1
PP8
PP9
PP10
PP7
PRESERVE AND PROTECT FIREPLACE, MANTEL, AND HEARTH.
PRESERVE AND PROTECT WOOD PANELING.
GENERAL NOTES:
1. SALVAGE, PRESERVE, AND PROTECT DOCUMENTS CONTAIN DEMOLITIONINFORMATION FOR INFORMATION PURPOSES ONLY. DO NOT DEMOLISH ANYINDICATED WALLS, CEILINGS, FLOORS, STAIRS, OR OTHER ITEMS UNLESS
INDICATED.
2. SALVAGED DOORS TO BE NUMBERED FOR FUTURE USE. NUMBER PERSPP PACKAGE.
3. SALVAGED ITEMS TO BE RE-LOCATED OFF-SITE. LOCATION TO BEDETERMINED BY OWNER/OWNER'S REPRESENTATIVE.
SALVAGE NOTES:
SALVAGE DOOR, FRAME, TRIM, AND HARDWARE FOR RE-USE S6
S5
S4
S3
S2
S1
SALVAGE WAINSCOT, BASEBOARD, AND FLOOR MOLDING FOR RE-USE
SALVAGE WALL TRIM, ARCH, PEDIMENT, AND PLINTH FOR RE-USE
SALVAGE BASE BOARDS AND FLOOR TRIM FOR RE-USE
SALVAGE CORNER CABINET FOR RE-LOCATION
SALVAGE CABINET FOR RE-LOCATION
S7 SALVAGE WOOD BENCH FOR REUSE
S8 SALVAGE RADIATOR COVERS FOR
REUSE
S9 SALVAGE IRON GATE ANDBALUSTRADE
SALVAGE,PRE
PROTECT
08.22.08
N
NOT F
DEMOLI
-
8/9/2019 Salvage Protection Package
4/17
-
8/9/2019 Salvage Protection Package
5/17
B
B.6
C
E
35 267 494.1
1
16'-5"(VIF)16'-5"(VIF)11'-7"(VIF)9'-8"11'-10"21'-714"12'-0
14"10'-5
38"
8
D
23'-1
3 4"
6'-10
1 4"
D
C
B.6
784.1
5 4 2
1'-10
1 2"
(VIF)
20'-9
1 8"(VIF)
12'-7
1 4"(VIF)
A
10'-018"
6 3
F
9 1
12'-7
1 4"
(VIF)
UP
30R
UP
14R
DN
14R
RAMPUP
7R
RAMP
209.75'(VIF)
REFERENCEROOM
101
READINGROOM
108
LOBBY107
STACKROOM
107SERVICECLOSET
102
CLOSET
103
PP7
PP7
S1
PP7PP7
PP6
PP4
S9
S2
PP1
S3
S7 PP7
PP7
S1
S3
PP6
PP5
PP4
PP5
PP4
PP4
PP5
S8
S8
1
1
1
1
1
1
FIRST LEVEL PLAN 01SCALE: 1/8" = 1'-0"
SPP-1
FIRST LEPLAN
N
SHEET TITLE:
DESCRIPTIODATE:
Client
DISTRICT OF COLUMBIA
901 G StreetWashington, D.C
ArchitecMARTINEZ & JOHNSON |
1238 Wisconsin AvenueWashington, D.C
202.333.44
Library ArchHOSHIDE WILLIAMS A
206.325.64
Structural EngRESTL DESIGNE
301.258.00
MEP EnginJOHN J. CHRISTIE & AS
202.364.44
SALVAGE,PRE
PROTECT
08.13.08
GEORGET
LIBRA3260 R Stree
WASHINGTO
M
THESE DRAWINGS, SPECIFICATIONS, AND(COLLECTIVELY,THE"DOCUMENTS")INCLLIMITATIONELECTRONICVERSIONSTHERDESIGNS,ANDARRANGEMENTSREPRESANDSHALLREMAINTHEPROPERTYOFMARCHITECTUREPC,ASDEFINEDBYAPPLAGREEMENTS("THEAGREEMENTS")ANDCOPYRIGHTSTATUTESOFTHEUNITEDSDOCUMENTSSHALLBESTRICTLYLIMITE
WHICHTHEYWEREPREPAREDANDDEVPERTHETERMSOFTHEAGREEMENTS. NDOCUMENTSSHALLBECOPIED,DISCLOSINCONNECTIONWITHANYOTHERWORKOTHER PERSONS FOR ANY PURPOSES,OTCOMPLETIONOFTHEPROJECT,WITHOUAUTHORIZATIONOFMARTINEZ&JOHNSOTHEDOWNLOADING,OPENING,ORVIEWVERSIONSOFTHEDOCUMENTSORVISUPRINTEDFORMTHEREOFSHALLCONSTI
EVIDENCEOFACCEPTANCEOFTHESER
KEY PLAN
P:\7590GeorgetownLibrary\Drawings\Salvage&
Protection\7590-SPP101.dwg
:8/22/2008
PRESERVE AND PROTECT NOTES:
PRESERVE DOOR, HARDWARE, AND FRAME
PRESERVE CABINETRY AND/OR SHELVES.
PRESERVE AND PROTECT ADJACENT WAINSCOT, TRIM, AND BASE
TO BE INCORPORATED INTO NEW FINISH
PRESERVE AND PROTECT IRON BALUSTRADE.
PRESERVE WINDOW AND WINDOW TRIM
PRESERVE PLASTER CROWN MOLDING
PRESERVE WAINSCOT AND BASE BOARD MOLDINGS
PRESERVE AND PROTECT EXISTING FLAGPOLE.
PP6
PP5
PP4
PP3
PP2
PP1
PP8
PP9
PP10
PP7
PRESERVE AND PROTECT FIREPLACE, MANTEL, AND HEARTH.
PRESERVE AND PROTECT WOOD PANELING.
GENERAL NOTES:
1. SALVAGE, PRESERVE, AND PROTECT DOCUMENTS CONTAIN DEMOLITIONINFORMATION FOR INFORMATION PURPOSES ONLY. DO NOT DEMOLISH ANYINDICATED WALLS, CEILINGS, FLOORS, STAIRS, OR OTHER ITEMS UNLESS
INDICATED.
2. SALVAGED DOORS TO BE NUMBERED FOR FUTURE USE. NUMBER PERSPP PACKAGE.
3. SALVAGED ITEMS TO BE RE-LOCATED OFF-SITE. LOCATION TO BEDETERMINED BY OWNER/OWNER'S REPRESENTATIVE.
SALVAGE NOTES:
SALVAGE DOOR, FRAME, TRIM, AND HARDWARE FOR RE-USE S6
S5
S4
S3
S2
S1
SALVAGE WAINSCOT, BASEBOARD, AND FLOOR MOLDING FOR RE-USE
SALVAGE WALL TRIM, ARCH, PEDIMENT, AND PLINTH FOR RE-USE
SALVAGE BASE BOARDS AND FLOOR TRIM FOR RE-USE
SALVAGE CORNER CABINET FOR RE-LOCATION
SALVAGE CABINET FOR RE-LOCATION
S7 SALVAGE WOOD BENCH FOR REUSE
S8 SALVAGE RADIATOR COVERS FOR
REUSE
S9 SALVAGE IRON GATE ANDBALUSTRADE
SALVAGE,PRE
PROTECT
08.22.08
NOT F
DEMOLI
-
8/9/2019 Salvage Protection Package
6/17
-
8/9/2019 Salvage Protection Package
7/17
-
8/9/2019 Salvage Protection Package
8/17
-
8/9/2019 Salvage Protection Package
9/17
GEORGETOWNNEIGHBORHOODLIBRARY,WASH.,D.C. MJA/7590
TABLE OF CONTENTS 1 OF 1
TABLEOFCONTENTS
DOCUMENTS SALVAGE,PRESERVE &PROTECT
DIVISION1-GENERALREQUIREMENTS
SECTION 01351 SPECIAL PROCEDURES FOR HISTORIC TREATMENT
01730 CUTTING AND PATCHING
01732 SELECTIVE DEMOLITION
ENDOFTABLEOFCONTENTS
-
8/9/2019 Salvage Protection Package
10/17
GEORGETOWN NEIGHBORHOOD LIBRARY, WASH., D.C. MJA/7590
SPECIAL PROCEDURES FOR HISTORIC TREATMENT 01351 - 1
SECTION 01351 - SPECIAL PROCEDURES FOR HISTORIC TREATMENT
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, apply to this Section.
1.2 SUMMARY
A. This Section includes special procedures for historic treatment on Project including, butnot limited to, the following:
1. Storage and protection of existing historic materials.
2. Temporary protection of historic materials during removal and salvage.
B. Related Sections include the following:
1. Division 1 Section "Selective Demolition" for removal of salvaged items.
1.3 DEFINITIONS
A. "Preservation": To apply measures necessary to sustain the existing form, integrity,and materials of a historic property. Work may include preliminary measures to protectand stabilize the property.
B. "Restoration": To accurately depict the form, features, and character of a property as itappeared at a particular period of time by means of the removal of features from otherperiods in its history and the reconstruction of missing features from the restorationperiod.
C. "Stabilize": To apply measures designed to reestablish a weather-resistant enclosureand the structural reinforcement of an item or portion of the building while maintainingthe essential form as it exists at present.
D. "Protect and Maintain": To install protective measures such as temporary guards; toprovide the least degree of intervention.
E. "Remove": To detach items from existing construction and legally dispose of them off-site unless indicated to be removed and salvaged.
F. "Remove and Salvage": To detach items from existing construction and deliver them toOwner ready for reuse.
G. "Existing to Remain" or "Retain": Existing items of construction that are not to beremoved and that are not otherwise indicated to be removed and salvaged.
-
8/9/2019 Salvage Protection Package
11/17
GEORGETOWN NEIGHBORHOOD LIBRARY, WASH., D.C. MJA/7590
SPECIAL PROCEDURES FOR HISTORIC TREATMENT 01351 - 2
1.4 SUBMITTALS
A. Historic Treatment Program: Submit a written plan for each phase or process includingprotection of surrounding materials during operations. Describe in detail materials,methods, and equipment to be used for each phase of work.
B. Alternative Methods and Materials: If alternative methods and materials to thoseindicated are proposed for any phase of work, provide a written description includingevidence of successful use on other, comparable projects, and program of testing todemonstrate effectiveness for use on this Project.
C. Qualification Data: For historic treatment specialists and supervisory personnel.Include list of completed projects with the scope of work and budget for each.
1.5 QUALITY ASSURANCE
A. Historic Treatment Specialist Qualifications: A firm that employs personnel, including
supervisory personnel, experienced and skilled in the processes and operationsindicated.
Historic Treatment Preconstruction Conference: Conduct conference at Project site to
record procedures established as a result of the review and distribute to affected parties.
1.6 STORAGE AND PROTECTION OF HISTORIC MATERIALS
A. Removed and Salvaged Historic Materials:
1. Clean salvaged historic items.2. Pack or crate items after cleaning. Identify contents of containers.3. Store items in a secure area until delivery to Owner.4. Transport items to Owner's storage area off-site designated by Owner.5. Protect items from damage during transport and storage.6. Do not dispose of items removed from existing construction without prior written
consent of Owner.
B. Existing Historic Materials to Remain: Protect construction indicated to remain againstdamage. When permitted by Architect, items may be removed to a suitable, protectedstorage location during historic treatment and cleaned and reinstalled in their originallocations after historic treatment operations are complete.
C. Storage and Protection: When removed from their existing location, store historic
materials within a weathertight enclosure where they are protected from wetting byrain, snow, or ground water, and temperature variations. Secure stored materials toprotect from theft.
1. Identify removed items with an inconspicuous mark indicating their originallocation.
-
8/9/2019 Salvage Protection Package
12/17
GEORGETOWN NEIGHBORHOOD LIBRARY, WASH., D.C. MJA/7590
SPECIAL PROCEDURES FOR HISTORIC TREATMENT 01351 - 3
PART 2 - PRODUCTS - (Not Used)
PART 3 - EXECUTION
3.1 PROTECTION, GENERAL
A. Ensure that supervisory personnel are present when work begins and during itsprogress.
B. Temporary Protection of Historic Materials during Construction:
1. Protect existing materials during installation of temporary protections andconstruction. Do not deface or remove existing materials.
2. Attachments of temporary protection to existing construction shall be approvedby Architect prior to installation.
3.2 HISTORIC TREATMENT PROCEDURES
A. Prohibit smoking by personnel performing work on or near historic structures.
B. Where Work requires existing features to be removed, cleaned, and reused, performthese operations without damage to the material itself, to adjacent materials, or to thesubstrate.
END OF SECTION 01351
-
8/9/2019 Salvage Protection Package
13/17
GEORGETOWN NEIGHBORHOOD LIBRARY, WASH., D.C. MJA/7590
CUTTING AND PATCHING 01730 - 1 of2
SECTION 01730
CUTTING AND PATCHING
PART I GENERAL
1.01 REQUIREMENTS INCLUDED:
A. Requirements and limitations for cutting and patching of Work included in selective
demolition work.
B. Cutting and patching incidental to work of the Section.
1. Limitations on cutting structural members.
1.02 SUBMITTALS:
A. Written request in advance of cutting or alteration which affects:
1. Structural integrity of any element of Project.2. Integrity of weather-exposed or moisture-resistant elements.
3. Efficiency, maintenance, or safety of any operational element.
4. Visual qualities of sight-exposed elements including all woodwork and
decorative plaster.
B. Include in request:
1 . Identification of Project.
2. Location and description of affected Work.
3. Necessity for cutting or alteration.
4. Description of proposed work, and products to be used.
5. Alternatives to cutting and patching.
6. Effect of work of Owner or separate contractor.
7. Written permission of affected subcontractor.
8. Date and time work will be executed.
C. All approvals for cutting and patching or drilling of structural elements must be obtaine
from the Architect in writing prior to commencing work.
PART 2 PRODUCTS
2.01 MATERIALS:
A. Those required for original installation.
B. For any change in materials, submit request for substitution.
PART 3 EXECUTION
3.01 GENERAL:
A. Execute cutting and patching to complete Work,
and to:
1. Remove samples of installed work for testing.
2. Remove and replace defective and non-conforming work.
-
8/9/2019 Salvage Protection Package
14/17
GEORGETOWN NEIGHBORHOOD LIBRARY, WASH., D.C. MJA/7590
CUTTING AND PATCHING 01730 - 1 of2
3.02 INSPECTION:
A. Inspect existing conditions, including elements subject to damage or movement du
cutting and patching.
B. After uncovering, inspect conditions affecting performance or work.
C. Beginning of cutting or patching means acceptance of existing conditions.
3.03 PREPARATION:
A. Provide supports to assure structural integrity of surroundings; devices and method
protect other portions of Project from damage.
B. Provide protection from elements for areas that may be exposed by uncovering work.
3.04 PERFORMANCE:
A. Execute work by methods that avoid damage to other work, and which will provid
proper surfaces to receive patching and finishing.
1 In general, use hand or small power tools designed for sawing and grinding, hammering and chopping. Cut holes and slots as small as possible,
neatly to size required, and with minimum disturbance of adjacent
surfaces. Temporarily coveropenings when not in use.
2. Existing Finished Surfaces: Cut or drill from the exposed or finished side int
concealed surfaces.
3. Cut concrete and masonry using a cutting machine, such as an abrasive saw
diamond-core drill.
4. Mechanical and electrical services: Cut off pipe or conduit in walls or partition
to be removed. Cap, valve, or plug and seal remaining portion of pipe
or conduit to prevent entrance of moisture or other foreign matter after
cutting.
B. Cut rigid materials using masonry saw or core drill. Pneumatic tools not allowed witho
prior written approval of the project Architect/Engineer.
C. At penetrations of fire-rated wall, ceiling, or floor construction, completely seal vo
with fire-rated, fire-resistant material, full thickness of the construction element.
END OF SECTION 01730
-
8/9/2019 Salvage Protection Package
15/17
GEORGETOWN NEIGHBORHOOD LIBRARY, WASH., D.C. MJA/7590
SELECTIVE DEMOLITION 01732 - 1 of 3
SECTION 01732
SELECTIVE DEMOLITION
PART I GENERAL
1.01 SUMMARY:
A. Furnish all labor, materials, tools, equipment and services necessary for and reasonably
incidental to complete the selective demolition work as shown on the drawings or
specified.
1. All selective demolition of historic fabric work shall be performed only by
trained and experienced workmen skilled in removal of such materials.
2. Refer to Drawings for general location of historic material to be protected.
B. Work includes salvage of existing materials for reinstallation or turn-over to Owner and
Preserve and Protect Work as shown on the Drawings.
C. Historic Preservation:
I The existing building is eligible for the National Register of Historic Places.Existing character defining or historic materials to be preserved are significant
and shall be protected in place. Character defining features to be salvaged for
reuse are to be carefully removed, and protected during
storage.
2. Refer to Section 01351.
E. Preservation and Protected Items: Refer to Drawings for location, and
quantities of work under this category.
F. Salvage and Protection Items: Refer to Drawings for location, and
quantities of work under this category.
G. Hazardous materials identification removal is not included in the scope of selectivedemolition.
1.02 DEFINITIONS:
A. Refer to Section 01351.
1.03 SUBMITTALS:
A. Photographs, sufficiently detailed, of existing conditions of adjoining
construction that might be misconstrued as damage caused by removal and salvage operations.
1.04 PROTECTION:
A. Do not interfere with use of project and surrounding buildings. Maintain free and safe passage toand from.
B. Protect all public and private property adjacent to and on the job site and including all platforms, ventutility lines, streets, sidewalks, light standards, hydrants, street signs, mail and fire alarm boxes, and mrepairs necessitated by reason of, or in the course of, operations under this contract to the completesatisfaction of the Owner of the damaged property.
-
8/9/2019 Salvage Protection Package
16/17
GEORGETOWN NEIGHBORHOOD LIBRARY, WASH., D.C. MJA/7590
SELECTIVE DEMOLITION 01732 - 2 of 3
C. If safety of structure appears to be endangered, cease operations and notify the Architect
and the Owner immediately. Take precautions to properly support structures. Do not resume
operations until safety is restored.
D. Provide and maintain temporary protection of the existing structure to remain where
removal and salvage work is being done, connections made, materials handled, orequipmentmoved.
E. Do not close or obstruct walkways, or driveways, except as otherwise shown, without the
authorization of the Owner and the District of Columbia Government. Do not store or place
materials in walkways, driveways or other means of egress.
F. Provide adequate fire protection in accordance with the District of Columbia Fire
Department requirements.
1 .09 MAINTAINING TRAFFIC:
A. Do not close or obstruct streets or sidewalks without the proper permit.
B.Conduct operations with minimum traffic interference to public or private roadways. Allequipment shall be limited to the parking area of the property .
1 10 REGULATORY REQUIREMENTS:
A. Perform removal and salvage work in accordance with applicable rules, regulations, codes, andordinances of the District of Columbia and Federal authorities, including OSHA and
EPA, and in accordance with the requirements of Public Utility Corporations having
jurisdiction over the work. Obtain and pay for all necessary permits, licenses-and
certificates and give all notices as required during the performance of the demolition
work.
B. ANSI A 10.6, "Safety Requirements for Demolition" shall govern except as otherwise
modified herein. Where the requirements specified herein or contained in the ANSIStandard differ from other applicable rules, regulations, and codes, the more stringent
requirements shall govern the work under this contract.
C. Observe the Secretary of the Interior's "Standards for Rehabilitation".
PART 2 PRODUCTS
2.01 MATERIALS:
A. Materials and items removed and not designated to become property of the Owner or
other agency as well as all debris, rubbish and other materials resulting from demolition
operations in excess of that used for fill shall become the property of the Contractor and
shall be removed from the Owner's property.
B. Storage or sale of Contractor's materials will not be permitted on the site.
-
8/9/2019 Salvage Protection Package
17/17
GEORGETOWN NEIGHBORHOOD LIBRARY, WASH., D.C. MJA/7590
SELECTIVE DEMOLITION 01732 - 3 of 3
PART 3 EXECUTION
3.01 INSPECTION:
A. Prior to the start of removal and salvage, inspect the site conditions and verify all governing
dimensions at the premises and all adjoining work on which this work is in any way
dependent. Notify the Architect of any discrepancies before proceeding with the work.
3.02 SELECTIVE DEMOLITION:
A. Perform removal and salvage in accordance with the requirements of the applicable authorities
having jurisdiction.
B. Take precautions to guard against movement, settlement or collapse of any surrounding
construction, including walls and paved areas designated to remain and be liable for any such
movement, settlement or collapse. Where shown on the drawings and/or as necessary,
install temporary shores, struts or bracing. Do not commence removal and salvage work until all
temporary construction is complete.
C. The extent of removal and salvage work is as shown on the drawings. Removal and salvage
performed in excess of that required shall be repaired at the Contractor's expense to the
satisfaction of the Architect and the Owner.
D. Burning of materials on the premises is not permitted.
E. Where existing floor and wall finish materials are removed, include removal of mastics,
setting beds and adhesives to provide clean bondable surface.
F. All debris and materials shall be disposed of offsite in a legal
manner and facility.
3.03 CLEANING UP:
A. Upon completion of all work under this section, remove all tools, materials, apparatus
and rubbish of any sort. The premises shall be left clean. Remove all debris in excess of that required
to grade the site.
END OF SECTION 01732