San Francisquito Creek Joint Powers Authority Len Materman, Executive Director

East Palo Alto January 2015

PG&E Ravenswood Substation January 2015

Upcoming changes to San Mateo County’s FEMA floodplain maps

Menlo Park East

Palo Alto

Redwood City

DRAFT floodplain maps

Palo Alto

Menlo Park

East Palo Alto

= Creek floodplain only (3,500 parcels) = Bay floodplain only with 3’ Sea Level Rise (over 2,700 parcels) = Overlap of creek and Bay floodplains (2,200 parcels)

Approximate number of parcels in the 100-year floodplains

SF Bay

X X X

= Bridge replacement = Channel widening = New levee or floodwall X

Redwood City

Mt. View

Floodplains and Planned Projects

San Francisquito Creek & S.F. Bay

The Big Picture

Menlo Park

Palo Alto

3’ of SLR with a 100-year Bay tide

East Palo Alto

Design and analyze (EIR) project elements to remove properties from the FEMA floodplain (100-year tide + 2’ freeboard), with up to 3’ of Sea Level Rise. Construction (not yet funded) may occur in phases (Phase 1 FEMA, Phase 2 SLR), and may be geographically separable.

Northern boundary

Southern boundary

Funders as of June 2015 California Dept. of Water Resources; California Coastal Conservancy; Facebook; Cities of East Palo Alto, Palo Alto, and Menlo Park; U.S. Fish & Wildlife Service

SAFER Bay Project Protect 5,000 properties & major infrastructure, restore marshes, connect communities through trails

SAFER Bay 2015 in San Mateo County:

9 reaches, 16 alternatives

The Assets

• Developed and refined list of feasible alternatives

• Engaged key stakeholders: Caltrans, SFPUC, PG&E, Midpeninsula Regional Open Space District, Facebook, Salt Pond Restoration Project, public

• Collected available data (property, geotech, hydraulic, etc.)

• Requesting right-of-way access to collect additional data

Complete feasibility analysis of alternative alignments and features, and select preferred alternative (anticipated Jan. 2016)

Complete EIR of alternatives, and design of preferred alternative (anticipated early 2018)

Permits and Construction (unknown date)

SAFER Bay Update – June 2015