Produced by: Supported by: Improving Preventive Maintenance Using Performance Based Data Peghi Webb, Process Analyst Bart Lewis, Logistics Specialist Aera Energy LLC

Upload: ranjith

Post on 01-Feb-2016

14 views

Category:

Documents


0 download

DESCRIPTION

SAP condition based maintenance in plant maintenance

TRANSCRIPT

Page 1: SAP EAM

Produced by: Supported by:

Improving Preventive Maintenance

Using Performance Based Data

Peghi Webb, Process Analyst

Bart Lewis, Logistics Specialist Aera Energy LLC

Page 2: SAP EAM

About Aera Energy LLC

How to set-up SAP® for performance based PMs

How performance based PMs are used at Aera

Benefits from using performance based PMs

Key points to take home

Questions

Overview

Page 3: SAP EAM

About Aera Energy LLC

• Oil and gas exploration and production company with onshore operations in California o Began operating on June 1, 1997

o 1200 Employees

o Produce 143,000 barrels of oil per day and 40 million cubic feet of natural gas per day

• Jointly owned by affiliates of Shell and ExxonMobil

• SAP® went into production in 1999 o Upgraded to ECC 6.0 in 2006

• North American Maintenance Excellence (NAME) award winner in 2002 and 2004

Page 4: SAP EAM

Bakersfield

Headquarters

Coalinga

San Ardo

Lost Hills Belridge

Coles Levee

Midway Sunset

Ventura

Huntington Beach

Cymric/McKittrick

Ecosystem Preserve

Where Aera Operates

Page 5: SAP EAM

Slide 5

When To Use Performance Based PMs

• Equipment is run on an irregular schedule

• Multiple equipment is alternated when needed as a

back-up

• Performance data is available or can be collected for

the equipment

Page 6: SAP EAM

Slide 6

SAP® Set-up for Performance Based PMs

• Create measuring point

o Can be attached to equipment or functional location

• Create initial measurement document

o If needed, set-up process for automated creation of

measurement documents

• Create maintenance plan

o Can be strategy, single cycle or multiple counter plan

o If using a strategy plan, create a task list using the same

strategy

• Schedule maintenance plan

Page 7: SAP EAM

Slide 7

Measuring Point

• Use counter checkbox

o Indicates that measurements

are cumulative values

• Provide counter over reading

o Sets value for when counter

goes back to zero

• Provide annual estimate

o Used to project maintenance

plan call date

Page 8: SAP EAM

Slide 8

Measurement Document

• Measurement readings can

be entered as counter

reading or the difference from

the last reading

Page 9: SAP EAM

Slide 9

Connecting SAP® to Field Data

• Map SAP® measuring point

to identifier for the field data

o This is a custom table with a

custom transaction to maintain

the data

o Used by the program that

creates measurement

documents each night from field

data

Page 10: SAP EAM

Flow of Equipment Performance Data

Corporate

Data

Warehouse SAP

Field Data

System PLC

Pump

Page 11: SAP EAM

Slide 11

Measurement Documents

• Measurement documents are

automatically created daily

o A reversal indicator can be set if

a measurement document with a

“bad” reading is created

Page 12: SAP EAM

Slide 12

Maintenance Plan

• Set the counter to the desired

measuring point

• Offset is used to define initial

counter reading for the cycle

o Also used to reset when

maintenance is performed off

schedule

Page 13: SAP EAM

Slide 13

Maintenance Plan

• Lead float is used to set the

call date and the basic start

date on the called order

o The basic finish date on the

order is set to the plan date for

performance based

maintenance plans

Page 14: SAP EAM

Slide 14

Maintenance Plan Schedule

• Cycle data shows latest

counter reading and

projected plan date based

upon annual estimate from

the measuring point

o Plan date calculation

(46776 – 45953) * 365 / 8400 = 36 days

01/03/2012 + 36 days = 02/08/2012

Page 15: SAP EAM

• Two of the highest

performing pumps west of

the Mississippi

o High pressure water

injection pumps in service

since 1973

o Pump performance

45000 bbl/day @ 4000 psi

o Motor performance

4500 HP

4160 VAC

Utilizing SAP® Performance Based PMs

Slide 15

Page 16: SAP EAM

• Manufacturers generally

recommend that preventive

maintenance be performed

on run hours or usage rather

than on calendar days (hard

time)

Utilizing SAP® Performance Based PMs

Slide 16

UNITS OF

HOURS

Page 17: SAP EAM

• Runtime is seldom spread

equally between primary and

secondary equipment

• Time based (hard time)

preventive maintenance

requires monitoring and

manual adjustments to be

effective when equipment is

actually due

o This is people dependant

Utilizing SAP® Performance Based PMs

Slide 17

Page 18: SAP EAM

• Equipment preventive

maintenance previously

based on “hard time” led

to waste

o 3 orders called while

equipment was down for

overhaul

o Orders frequently called for

idle equipment

o Material requisitions fulfilled

and not utilized

Utilizing SAP® Performance Based PMs

Slide 18

Page 19: SAP EAM

• Equipment preventive

maintenance is currently

based on runtime

o Orders generate when

equipment is due

o Material requisitions fulfilled

and utilized (no waste)

• 8 runtime based versus

16 calendar based orders

in 2 years

Utilizing SAP® Performance Based PMs

Slide 19

Page 20: SAP EAM

• Removes the question “Is it really due?”

• Provides more effective scheduling

• Eliminates need to adjust maintenance plans to stay in

compliance and possibly miss needed maintenance

• Eliminates unnecessary requisitions (materials)

• Can be used as a trigger to rotate equipment

• Reduces costs

• Reduces the possibility of human error

Utilizing SAP® Performance Based PMs

Page 21: SAP EAM

• Performance based maintenance plans use standard

SAP® EAM functionality

• Maintenance is scheduled at the right time based upon

equipment usage

o Works best for equipment run on irregular schedules

o Eliminates waste

Key Points To Take Home

Page 22: SAP EAM

Questions

Page 23: SAP EAM

Produced by: Supported by:

Peghi Webb Aera Energy LLC

[email protected]

Bart Lewis Aera Energy LLC

[email protected]