scaffold shrink wrapping case study : queen elizabeth olympic park

3
30 January 2015 In January 2014 Balfour Bea2y announced they had been awarded a £154m contract by London Legacy to transform the former Queen Elizabeth Olympic Stadium at Queen Elizabeth Olympic Park in London into a ‘mulI use venue’ which aLer hosIng five matches for the Rugby World Cup in 2015 will become the full Ime home for West Ham United in 2016. Part of this project involved a £41m reconfiguraIon and expansion of the stadium roof. This work, once complete, will increase the roof weight from 1400 tonnes to 4000 tonnes and create the largest canIlevered roof in the world. The project to reconfigure the roof presented a number of challenges. Firstly, work needed to take place on the original stadium roof’s support structure which was up to 37 metres (121 feet) above the ground. Secondly, a Ime schedule of 25 weeks to complete the works meant that tradiIonal scaffolding techniques would be impracIcal. As a soluIon, rather than build from the ‘bo2om up’, the scaffolding & access contractor, PHD Modular Access Ltd., implemented techniques usually used in the oil and gas industry and suspended the scaffolding structure from chains hung 1 In the summer of 2014, Rhino Shrink Wrap undertook a challenging & exciCng project to encapsulate 168 pods high around the roof of the Queen Elizabeth Olympic Stadium in London. Queen Elizabeth Olympic Park CreaIng 168 shrink wrapped ‘workshops in the sky’ to allow blasIng, welding & painIng in a controlled environment By Steve Irlam, Managing Director, Rhino Shrink Wrap

Upload: steve-irlam

Post on 19-Jul-2015

46 views

Category:

Business


0 download

TRANSCRIPT

Page 1: Scaffold Shrink Wrapping Case study : Queen Elizabeth Olympic Park

30  January  2015

In  January  2014  Balfour  Bea2y  announced  they  had  been  awarded  a  £154m  contract  by  London  Legacy  to  transform  the  former  Queen  Elizabeth  Olympic  Stadium  at  Queen  Elizabeth  Olympic  Park  in  London  into  a  ‘mulI  use  venue’  which  aLer  hosIng  five  matches  for  the  Rugby  World  Cup  in  2015  will  become  the  full  Ime  home  for  West  Ham  United  in  2016.  Part  of  this  project  involved  a  £41m  reconfiguraIon  and  expansion  of  the  stadium  roof.  This  work,  once  complete,  will  increase  the  roof  weight  from  1400  tonnes  to  4000  tonnes  and  create  the  largest  canIlevered  roof  in  the  world.  

The  project  to  reconfigure  the  roof  presented  a  number  of  challenges.  Firstly,  work  needed  to  take  place  on  the  original  stadium  roof’s  support  structure  which  was  up  to  37  metres  (121  feet)  above  the  ground.  Secondly,  a  Ime  schedule  of  25  weeks  to  complete  the  works  meant  that  tradiIonal  scaffolding  techniques  would  be  impracIcal.  As  a  soluIon,  rather  than  build  from  the  ‘bo2om  up’,  the  scaffolding  &  access  contractor,  PHD  Modular  Access  Ltd.,  implemented  techniques  usually  used  in  the  oil  and  gas  industry  and  suspended  the  scaffolding  structure  from  chains  hung  

�1

In  the  summer  of  2014,  Rhino  Shrink  Wrap  undertook  a  challenging  &  exciCng  project  to  encapsulate  168  pods  high  around  the  roof  of  the  Queen  Elizabeth  Olympic  Stadium  in  London.

Queen Elizabeth Olympic ParkCreaIng  168  shrink  wrapped  ‘workshops  in  the  sky’  to  allow  blasIng,  welding  &  painIng  in  a  controlled  environment

By  Steve  Irlam,  Managing  Director,  Rhino  Shrink  Wrap

Page 2: Scaffold Shrink Wrapping Case study : Queen Elizabeth Olympic Park

30  January  2015

around  the  exisIng  roof  structure  to  build  the  access  ‘top  down’.    The  top  down  approach  proved  highly  successful  and  in  phase  1&2  of  the  project  PHD  Modular  Access  erected  480  tons  of  Layher  Allround®  lightweight  scaffolding  to  create  168  ’workshops  in  the  sky’  where  shot  blasIng,  welding  and  painIng  work  was  required  to  take  place.

Encapsulation & Containment

Rhino  Shrink  Wrap  were  approached  by  PHD  Modular  Access  to  provide  weather  proofing  and  environmental  containment  around  each  ‘pod’  or  ‘workshop’.  TradiIonal  scaffold  sheeIng,  applied  around  the  scaffolding  in  2m  high  strips  and  a2ached  with  bungee  cords,  has  gaps  between  sheets  that  make  it  difficult  to  stop  shot  blast  residues  escaping  and  rainwater  penetraIng.  Furthermore,  tradiIonal  reinforced  sheeIng  can  be  difficult  to  fit  Ightly  which  can  lead  to  flapping  and  ulImately  detachment.  Rhino  proposed  using  a  300  micron  thick  Verisafe®  flame  retardant  shrink  wrap  sheeIng  which  once  installed  would  created  a  conInuously  bonded  and  ‘drum  Ight’  skin  around  each  pod.  

The  shrink  wrap  encapsulaIon  of  each  pod  or  workshop  had  two  key  objecIves.  Firstly  to  provide  ‘environmental  containment’  of  shot  blast  and  paint  residues  as  secIons  of  the  roof  support  structure  were  shot  blasted  back  to  bare  metal.  Secondly,  the  shrink  wrapped  ‘pods’  would  provide  a  completely  weather  proof  area  where  new  roof  fixings  could  be  welded  into  place.  Zipped  access  doors  installed  in  the  shrink  wrap  cover  each  pod  allowed  welding  and  painIng  to  take  place  in  a  controlled,  almost  ‘factory  like’  environment.  

Rhino  Shrink  Wrap  supplied  6  installers  to  carry  out  the  work,  split  into  two  teams,  each  team  led  by  a  supervisor.  Working  from  the  inside  of  the  plajorm,  the  shrink  wrap  sheeIng,  (supplied  as  a  7m  wide  x  15m  long  roll),  was  pulled  over  the  module  and  ba2ened  at  ‘ground  level’  to  a  plywood  floor  laid  inside  the  pod.  Excess  shrink  wrap  was  trimmed  at  the  corners  and  any  joins  or  overlaps  were  heat  welded  together  to  create  a  seal.  Finally,  the  shrink  wrap  sheeIng  was  heat  shrunk  ‘drum  Ight’.  Each  pod  required  100  to  200  square  metres  of  shrink  wrap  sheeIng.  

�2

Rhino  Shrink  Wrap  installaCon  team  

‘Workshops  in  the  sky’  

Page 3: Scaffold Shrink Wrapping Case study : Queen Elizabeth Olympic Park

30  January  2015

Project benefits from shrink wrap

• SheeIng  cut  and  sealed  around  protrusions  (like  roof  trusses)  whilst  maintaining  containment.  

• Heat  shrunk  ‘drum  Ight’  -­‐  very  resistant  to  damage  from  high  winds.  

• VersaIle  -­‐  can  be  cut  and  resealed  for  crane  access  and  remain  weather  Ight.  Zipped  access  doors  maintain  factory  like  environment.  

• Smart  &  professional  appearance  for  a  high  profile  project.  

• Quick  to  remove  aLer  use  &  100%  recyclable.  

Challenges

1. Welding  contractors  required  new  roof  components  to  be  welded  to  the  exisIng  roof  structure.  These  needed  to  be  craned  into  posiIon,  inside  the  sheeted  area,  aLer  the  area  had  been  shot  blasted.  However,  the  Rhino  team  were  able  to  cut  an  opening  in  the  roof  (or  on  the  lower  and  smaller  pods  -­‐  the  sides)  to  allow  the  components  to  be  craned  through  and  then  seal  back  up  by  taping  and  welding.  

2. Working  simultaneously  on  mulIple  locaIons  within  a  large  construcIon  site  was  challenging.  Our  teams  met  each  morning  for  a  briefing  so  that  every  team  member  knew  what  they  were  doing  and  working  Ime  was  maximised.  

3. There  were  changes  in  the  schedule  of  work  from  the  client  which  required  us  to  be  highly  flexible  in  our  approach.  Where  necessary  our  teams  worked  weekends  to  meet  revised  schedules.  

Lessons

The  scaffolding  and  encapsulaIon  of  the  168  ‘workshops  in  the  sky’  was  finished  ahead  of  schedule.  Although  a  very  challenging  3  month  project,  with  much  Ime  away  from  home,  our  teams  learned  the  importance  of  effecIve  communicaIon  for  safety  and  efficiency  on  large  sites  and  were  proud  to  play  a  small  part  in  making  this  exciIng  and  innovaIve  project  a  success.

�3

Further  informaCon;  

T.  +44  (0)1477  532222  

E.  [email protected]  

W.  www.rhinoshrinkwrap.com  

Queen  Elizabeth  Olympic  Park,  London  

Shrink  wrap  moulded  Cghtly  around  scaffolding  and  sealed  around  protrusions