ID Task N am e DUR Start 0 P ro gram D escrip tion 450 d 3/1/08 1 Milestones 0 d 3/1/08 2 Build 1 CD R 0 d 3/1/08 3 SDRLs 135 d 3/3/08 4 S001 - Initial S ubm ittal 35 d 3/3/08 5 S001 -Deliver 30 DP T B uild 1.0 PD R 40 d 4/21/08 6 S014 -DeliverQ uality Plan 60 DAC 60 d 6/17/08 7 System E ngineering 25 d 9/11/08 8 System E ngineering R equired Capabilities 25 d 9/11/08 9 DocumentRequirements 25 d 9/11/08 10 Allocate Prelim CIDS Requirem ents to Build 1. 10 d 9/11/08 11 Finalize Allocation ofC IDS R equirem ents forB 15 d 9/25/08 12 Softw are Developm ent 140 d 10/16/08 13 Softw are Developm entRequired Capabilities 85 d 10/16/08 14 Functionality1 85 d 10/16/08 15 HR Revise D raftS halls P ostIR R Build 1.0 40 d 10/16/08 16 HR Validate ActivityD iagram s 40 d 12/15/08 17 HR Review Requirem ents Docum ents (SRS /IRS 5 d 2/18/09 18 TechnicalOperations 55 d 2/25/09 19 TechnicalLeadership & Support 55 d 2/25/09 20 SE Supportto D evelopm entP rocesses 30 d 2/25/09 21 Prepare for& SupportBuild 1.0 CDR 25 d 4/8/09 22 Integration and Test 130 d 5/13/09 23 Integration 25 d 5/13/09 24 Perform Integration 10 d 5/13/09 25 Resolve S PRs P ost 15 d 5/28/09 3/1/08 3/1/08 Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec J 2009 2

Upload: ferris-ross

Post on 02-Jan-2016

10 views

Category:

Documents


0 download

DESCRIPTION

- PowerPoint PPT Presentation

TRANSCRIPT

Page 1: schedule

ID Task Name DUR Start

0 Program Description 450 d 3/1/081 Milestones 0 d 3/1/08

2 Build 1 CDR 0 d 3/1/08

3 SDRLs 135 d 3/3/08

4 S001 - Initial Submittal 35 d 3/3/08

5 S001 - Deliver 30 DPT Build 1.0 PDR 40 d 4/21/08

6 S014 - Deliver Quality Plan 60 DAC 60 d 6/17/08

7 System Engineering 25 d 9/11/08

8 System Engineering Required Capabilities 25 d 9/11/08

9 Document Requirements 25 d 9/11/08

10 Allocate Prelim CIDS Requirements to Build 1.0 10 d 9/11/08

11 Finalize Allocation of CIDS Requirements for Build 1.015 d 9/25/08

12 Software Development 140 d 10/16/08

13 Software Development Required Capabilities 85 d 10/16/08

14 Functionality 1 85 d 10/16/08

15 HR Revise Draft Shalls Post IRR Build 1.0 40 d 10/16/08

16 HR Validate Activity Diagrams 40 d 12/15/08

17 HR Review Requirements Documents (SRS/IRS) 5 d 2/18/09

18 Technical Operations 55 d 2/25/09

19 Technical Leadership & Support 55 d 2/25/09

20 SE Support to Development Processes 30 d 2/25/09

21 Prepare for & Support Build 1.0 CDR 25 d 4/8/09

22 Integration and Test 130 d 5/13/09

23 Integration 25 d 5/13/09

24 Perform Integration 10 d 5/13/09

25 Resolve SPRs Post 15 d 5/28/09

3/1/08

3/1/08

MarAprMayJunJulAugSepOctNovDecJanFebMarAprMayJunJulAugSepOctNovDecJan2008 2009 2010