schedule - planning for schedule development

Upload: perwaiz

Post on 07-Apr-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/6/2019 Schedule - Planning for Schedule Development

    1/38

    Scheduling With

    the Masters

    Schedule Design Planning forSchedule Development

    Chris Carson, PSPCorporate Director of Project Controls

    Alpha Corporation

    [email protected]

  • 8/6/2019 Schedule - Planning for Schedule Development

    2/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    2

    Scheduling With

    the Masters

    Schedule Design

    Why design a schedule? A schedule meets the criteria for a project in itself A schedule is a guideline or plan for a project A schedule provides a a methodical approach for a projectKeeps the schedule development on track Prevents rework due to late understanding of needs Allows buy-in from end users prior to DevelopmentMakes the schedule development session much moremeaningfulDocuments the assumptions and intention of the schedule

    For reviewer and approverFor future referenceTo facilitate changes in schedulersPlace to capture Lessons Learned

  • 8/6/2019 Schedule - Planning for Schedule Development

    3/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    3

    Scheduling With

    the Masters

    Schedule Design

    Scope of Design vs. Development

    Design Conceptualizing the schedulePlanningStarting with the end in mindProviding concept of final productCreating organizational structure to fulfill the concept

    Development - Building the scheduleInput activitiesInput logic

    Input durationsReview for design complianceReview for CPM methodology best practicesQuality control

  • 8/6/2019 Schedule - Planning for Schedule Development

    4/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    4

    Scheduling With

    the Masters

    Schedule Design - Background Design vs. Development How PMI & PMBOK handles it?

    PMBOK identifies six Project Time Managementprocesses, usually defined as part of the project

    lifecycle, Section 2.1 of PMBOK. Activity Definition. Activity Sequencing. Activity Resource Estimating. Activity Duration Estimating. Schedule Development. Schedule Control.

    These processes are preceded by a planning effort bythe project management team, which is part of PMBOKsDevelop Project Management Plan, PMBOK Section 4.3(which sets the format and establishes criteria for

    developing the project schedule). These processes are documented in what PMBOK calls aSchedule Management Plan, which is contained in theproject management plan, in the introduction to Section4.3, Project Integration Management.

  • 8/6/2019 Schedule - Planning for Schedule Development

    5/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    5

    Scheduling With

    the Masters

    Schedule Design - Background PMBOK Process Inputs.

    The inputs for the different Time Management Processes arelisted as:

    Activity list. Product description. Mandatory dependencies. Discretionary dependencies. External dependencies. Resource requirements. Resource capabilities. Historical information. Identified risks. Constraints. Assumptions.

    All of these items, along with the Schedule Management Plan,are part of Schedule Design, but PMBOK does not offer cleardefinition and delineation of Schedule Design.

    The Time Management Processes do not include ScheduleDesign.

  • 8/6/2019 Schedule - Planning for Schedule Development

    6/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    6

    Scheduling With

    the Masters

    Schedule Design - Background

    Design vs. Development whyemphasize the distinction? Design tends to be ignored in favor of jumping

    right into development.

    Many schedulers elect to begin creating activitiesinstead of Designing.Work is subsequently repetitive, with lots ofpotential for rework.

    Results tend to be disorganized. Avoid planning mistakes and problems.

  • 8/6/2019 Schedule - Planning for Schedule Development

    7/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    7

    Scheduling With

    the Masters

    Schedule Design

    Avoid planning mistakes and problems

  • 8/6/2019 Schedule - Planning for Schedule Development

    8/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    8

    Scheduling With

    the Masters

    Schedule Design Lack of Good Area Definition preventing activity

    closeout:

    Areas are so broadly defined

    that activities sit at nearly complete for large parts of the project.

    Hinders productivity analysis, good cost loading,accurate as- built dates.

  • 8/6/2019 Schedule - Planning for Schedule Development

    9/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    9

    Scheduling With

    the Masters

    Schedule Design Inconsistency in level of detail throughout

    trades:

    Some trades are heavily developed while others are left with summary-level activities only.

  • 8/6/2019 Schedule - Planning for Schedule Development

    10/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    10

    Scheduling With

    the Masters

    Schedule Design

    Documentation and use of Schedule Design

    Create a book or binderUse the highest level of checklist outline items as tabsUse the book as basis for schedule submittaldocumentation

    Keep the book current during projectUse the book for handoff between schedulersShare a copy of the book with superintendent/PM

    TimingMust be done prior to Schedule Development

  • 8/6/2019 Schedule - Planning for Schedule Development

    11/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    11

    Scheduling With

    the Masters

    Schedule Design Checklist

    Project Description

    Reference DocumentsContractProject DrawingsSpecifications

    Scheduling SpecificationNotice to Proceed or Release Letter Any Owner produced master scheduleLiquidated Damages schedule Area Designation PlanSequencing planEstimate & quantity surveys/bills of materials

  • 8/6/2019 Schedule - Planning for Schedule Development

    12/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    12

    Scheduling With

    the Masters

    Schedule Design Checklist -Schedule Specification General Contents.

  • 8/6/2019 Schedule - Planning for Schedule Development

    13/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    13

    Scheduling With

    the Masters

    Schedule Design Checklist

    Team Players

    Organizational Chart (OBS)Who are Schedule Users?

    Who has InputWho Updates

    Who Checks for AccuracyWho ReviewsWho approves

    Identify Responsibility Assignment Matrix (RAM)

  • 8/6/2019 Schedule - Planning for Schedule Development

    14/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc. 14

    Scheduling With

    the Masters

    Schedule Design ChecklistOrganizational Breakdown Structure.

    From: DOE Training EVM Tutorial WBSby Booze-Allen-Hamilton

  • 8/6/2019 Schedule - Planning for Schedule Development

    15/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc. 15

    Scheduling With

    the Masters

    Schedule Design

    RAM Example (based on PMBOK RACI Chart)

  • 8/6/2019 Schedule - Planning for Schedule Development

    16/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc. 16

    Scheduling With

    the Masters

    Schedule Design Checklist

    Software Identification

    Specific softwareRequired minimum and versions allowedEnterprise specific issues

    Users identified

    Schedules used for import or data sourceLevels of access Validation processFor master schedules, establish data dates

  • 8/6/2019 Schedule - Planning for Schedule Development

    17/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc. 17

    Scheduling With

    the Masters

    Schedule Design Checklist

    Work ProductWhat the Schedule can be used for (purpose)Reports Generated from the Schedule

    Who receives reportsList of reportsSamples of reports

    Glossary/Lexicon of ambiguous termsSchedule Outline

    Key Activities being trackedClient Milestones

    Long Lead ItemsWBS StructureOther Contracts on Project

  • 8/6/2019 Schedule - Planning for Schedule Development

    18/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc. 18

    Scheduling With

    the Masters

    Schedule Design

    Reporting

  • 8/6/2019 Schedule - Planning for Schedule Development

    19/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc. 19

    Scheduling With

    the Masters

    Schedule Design Checklist

    Work Package Development.

    By Contract. As assigned by Client.

    VI. Work Packages

    Division 2 and 5 Specifications require the following Work Packages:

    Superstructure Waterproofing Corrosion Protection of Structural Steelwork Movements and Tolerances Specification for Structural Steel Structural Steel Superstructure Cast in Place Concrete

  • 8/6/2019 Schedule - Planning for Schedule Development

    20/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc. 20

    Scheduling With

    the Masters

    Schedule Design Checklist

    Level of Detail

    Determine approach:Bottom-up (starting with detailed activities)Top-down (starting with summary schedule)Both (prepare Top-down, then Bottom-up)

    Identify frequency of updatesEstablish smallest activity duration range

  • 8/6/2019 Schedule - Planning for Schedule Development

    21/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    21

    Scheduling With

    the Masters

    Schedule Design Checklist

    Codes DictionaryFor tracking and monitoring work:

    Work PhaseStructure AreaFloor or Station

    Location.For Project Management:

    ResponsibilityWork ShiftsCosts

    ResourceSpecificationChange management

  • 8/6/2019 Schedule - Planning for Schedule Development

    22/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    22

    Scheduling With

    the Masters

    Schedule Design ChecklistCalendars

    Establish number neededDefine calendars and application

    Costs & ResourcesEstimate & correlation to cost loadingBill of Quantities & use in resourcesResource Crew descriptions

    Equipment descriptionsHow actual production will be monitoredEarned Value Management System

    Narrative Basis & Assumptions

    Procedure Used to create the ScheduleDefinitions/lexiconDescription of sequence of work per structure

  • 8/6/2019 Schedule - Planning for Schedule Development

    23/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    23

    Scheduling With

    the Masters

    Schedule Design Checklist

    Example of Calendar Section:

    Calendars are defined as follows: Calendar 1 24 hours a day, 7 days a week. Calendar 2 24 hours a day, only Fridays off. (This is the Default

    Calendar.)

    Calendar 3 Night Shift, only Fridays off. Calendar 4 Night Shift, 24 hours a day, 7 days a week. Please note that 01140/1.9.a. requires that the Contractor notify the

    Client regarding multiple shifts, etc. This has been accomplishedby using Day and Night sift calendars as well as by incorporatingmultiple crew codes into the Program. (For more on Crews, pleaserefer to the Resources section of this report.)

  • 8/6/2019 Schedule - Planning for Schedule Development

    24/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    24

    Scheduling With

    the Masters

    Schedule Design ChecklistExample of Lexicon

    General Notes Regarding this Report: Program, Programme, and Baseline CPM, and Schedule all

    have the same definition and are used interchangeably. Snagging and Punch-out have the same definition and are

    used interchangeably. Fixed and Rough-in have roughly the same definition. For

    clarification purposes, Fixed has been used in this Program.

    Conventional concrete is defined as post-tension poured-in-place concrete.

    Wild Air is defined as a stage in construction, for which thebuilding is closed in by perimeter walls and ventilation hasstarted. (Ventilation only, not complete environmental controls or

    functioning air conditioning.) This term is used in lieu ofenvironmental controls, or drying in as wet weather is not areal factor in Dubai.

    Raft construction consists of the foundation including but notlimited to piles, grade beams, footers, and slab-on-grade.

  • 8/6/2019 Schedule - Planning for Schedule Development

    25/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    25

    Scheduling With

    the Masters

    Schedule Design

    Narrative Basis

  • 8/6/2019 Schedule - Planning for Schedule Development

    26/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    26

    Scheduling With

    the Masters

    Schedule Design Checklist

    Risks & ConstructabilityBrainstorming of issues

    Known problems (threats)Provisional ItemsPredicted ProblemsLessons LearnedOutside influencesSite condition concernsOpportunities

    Develop Risk Management PlanInitial process during baseline schedule developmentProcess for use during updates

  • 8/6/2019 Schedule - Planning for Schedule Development

    27/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    27

    Scheduling With

    the Masters

    Schedule DesignRisk Management Plan Based on PMBOK

  • 8/6/2019 Schedule - Planning for Schedule Development

    28/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    28

    Scheduling With

    the Masters

    Schedule Design Checklist

    Weather planningExpected adverse weatherIdentify source or specification requirementIdentify methodologyIdentify accounting method for actual weather

  • 8/6/2019 Schedule - Planning for Schedule Development

    29/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    29

    Scheduling With

    the Masters

    Schedule Design ChecklistTime Contingencies

    AmountsSpecific trade (from risk management plan)Specific contractor contingencyHow carriedUse historical data for reference

    Time Performance Ratio

    0.0

    2.0

    4.0

    6.0

    8.0

    10.0

    12.0

    A d m i n

    S i t e w

    o r k

    C o n c r

    e t e

    M a s o n

    r y M e

    t a l s

    C a r p e

    n t r y

    R o o f i n

    g

    D o o r s

    / W i n d

    o w s

    F i n i s h

    e s

    E q u i p

    m e n t

    F u r n i s

    h i n g s

    E l e v a t

    o r s

    M e c h a

    n i c a l

    E l e c t r i

    c a l

    Type of Work

    T P R

  • 8/6/2019 Schedule - Planning for Schedule Development

    30/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    30

    Scheduling With

    the Masters

    Request forUpdate Data

    Collect AdminProgress Data

    Collect FieldProgress Data

    Identify ContractChanges

    StatusSchedule

    UpdateSchedule

    Compare toBaseline

    Verify AllData

    Request forUpdate Data

    Collect AdminProgress Data

    Collect FieldProgress Data

    Identify ContractChanges

    StatusSchedule

    UpdateSchedule

    Compare toBaseline

    Verify AllData

    Schedule Design Checklist

    Establish Update processFrequencyData request and transmission ValidationProcess flowchart

  • 8/6/2019 Schedule - Planning for Schedule Development

    31/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    31

    Scheduling With

    the Masters

    Schedule Design Checklist

    Change Management processNotification requirementsMethodology allowedProcess flowchart

  • 8/6/2019 Schedule - Planning for Schedule Development

    32/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    32

    Scheduling With

    the Masters

    Request forUpdate Data

    Collect AdminProgress Data

    Collect FieldProgress Data

    Identify ContractChanges

    StatusSchedule

    UpdateSchedule

    Compare toBaseline

    PublishUpdatedSchedule

    Critical PathDelay?

    Identify PreviousPeriod

    Critical Path

    No

    Yes

    Verify AllData

    Identify ChangesTo Critical Path

    Identify CausalDelay Activities

    QuantifyDelays

    ResearchDocuments ForDriving Delays

    AssessResponsibility

    For Delays

    AnyConcurrent

    Delays?

    Verify SingleSource DelayResponsibility

    Is theOwner

    ResponsibleFor Delay?

    No

    No

    Discuss Delay &Mitigation withSubcontractor

    PerformConcurrent Delay

    Analysis

    Yes

    Yes

    Discuss Delay& MitigationWith Owner

    Prepare DelayAnalysis

    & Change Order

    Is theOwner

    ResponsibleFor Delay?

    No

    Yes

    Is aSubcontractorResponsibleFor Delay?

    Prepare

    RecoverySchedule

    No

    Yes

    Prop osed Sc hed ule UpdateWith Chang e Manag em ent

    ResolveSubcontractorContributions

  • 8/6/2019 Schedule - Planning for Schedule Development

    33/38

  • 8/6/2019 Schedule - Planning for Schedule Development

    34/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    34

    Scheduling With

    the Masters

    Schedule Design Checklist

    18. Dispute resolution process1. Review program for claims avoidance

    1. Reinforce planning for claims avoidance2. Identify specific program for claims avoidance during

    schedule updates and change management

    2. Identify steps if change management process fails orstalls

    3. Follow specifications4. Provide time frames for stages in process5. Provide process description or flow chart

  • 8/6/2019 Schedule - Planning for Schedule Development

    35/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    35

    Scheduling With

    the Masters

    Schedule Design

    Conclusion For success in Schedule Development,

    Schedule Design should be a completelydifferent process

    Process done prior to Development Process and results documented Documentation done in formal Schedule

    Design Book Book used to provide continuity between

    schedulers or project managers

  • 8/6/2019 Schedule - Planning for Schedule Development

    36/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    36

    Scheduling With

    the Masters

    Schedule Design Resources

    See Lance Stephensons Schedule BasisMemorandum paper, also addresses schedule levels

    See AACEis Total Cost Management See PMBOK for Risk Management process

    Recommendations Get involved with the CoS SEI Project developing Best

    Practices and Guidelines for Scheduling Get involved with AACEi and the Recommended

    Practices development Get involved with CMAA in the Time Management

    development

  • 8/6/2019 Schedule - Planning for Schedule Development

    37/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    37

    Scheduling With

    the Masters

    Schedule DesignQuestions?

    Recommendations?

    War Stories?

    Gripes?

  • 8/6/2019 Schedule - Planning for Schedule Development

    38/38

    PMI College of SchedulingPMI is a registered trade and service mark of the Project Management Institute, Inc.

    38

    Scheduling With

    the MastersChris Carson, PSP

    Corporate Director of Project Controls Alpha Corporation

    101 West Main Street, Suite 715Norfolk, VA 23510

    757-533-9368 Office757-342-5524 Mobile

    [email protected]

    Schedule Design Planning for

    Schedule Development