section - 04_06 construction schedule

Upload: sm-moniruzzaman

Post on 04-Jun-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 Section - 04_06 Construction Schedule

    1/3

    Year

    Month Sep-Oct Nov-Dec Jan-Feb Mar-Apr May-Jun Jul-Aug Sep-Oct Nov-Dec Jan-Feb Mar-Apr May-Jun Jul-Aug Sep-Oct Nov-Dec Jan-Feb Mar-Apr May-Jun Jul-Aug

    Cumulative months 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36

    Total working days * * * * * * * * * * * * * * * * * *

    Construction Activity

    A. Mobilization

    1. Camp facilities2. Site Office, Laboratory

    3. Setting out, surveying

    B. Earthworks

    1. Cut & fill Bidder to show two monthly progress

    2. Embankment fill in barchart form and note down

    3. Improved subgrade corresponding progress in percentage.

    C. Aggregate Pavement

    1. Sub-base course

    2. Lower base course3. Upper base course

    D. Bituminous Pavement

    1. Binder course

    2. Wearing course

    E. Box Culvert

    1. Diversion, demolish, etc.

    2. Concrete & reinforceing

    F. Bridge Works

    1. Piling

    2. Sub-structure

    3. PC Girder

    4. Deck, railing, etc.

    G.Miscellanious Works

    1. Drainage & protection

    2. Road appurtenants

    3. Road sign & markings

    4. Other items of Work

    Total Progress during the

    period (% in weightage)

    Cumulative Total Progress

    o ontract mount

    Form CON - 3.1 : WORK PROGRAMME FOR WHOLE WORKS

    2006 2007 2008 2009

    Remarks

  • 8/13/2019 Section - 04_06 Construction Schedule

    2/3

    Sep-Oct Nov-Dec Jan-Feb Mar-Apr May-Jun Jul-Aug Sep-Oct Nov-Dec Jan-Feb Mar-Apr May-Jun Jul-Aug Sep-Oct Nov-Dec Jan-Feb Mar-Apr May-Jun Jul-Aug

    2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36

    Material Unit

    A. Camp, Site Office, Laboratory

    1. Bricks Nos.

    2. Cement Ton

    3. Sand m

    4. M S reinforcement Ton

    B. Earthworks

    1. Fill materials m Bidder to show two monthly quantities

    2. ISG materials m of different materials to be used.C. Aggregate Pavement

    1. Bricks Nos.

    2. Stone aggregate m

    3. Sand m

    D. Bituminous Pavement

    1. Stone aggregate m

    2. Coarse sand/Fine aggregate m

    3. Sand m

    4. Bitumen Ton

    E. Box Culvert & Bridge Works

    1. Stone aggregate m

    2. Reinforcing Steel Ton

    3. H T Strand / Wire Ton

    4. Cement Ton

    Remarks

    Form CON - 3.3 : MATERIALS FLOW CHART FOR WHOLE WORKS

    2006 2007 2008 2009Year

    Month

    Cumulative months

  • 8/13/2019 Section - 04_06 Construction Schedule

    3/3

    Sep-Oct Nov-Dec Jan-Feb Mar-Apr May-Jun Jul-Aug Sep-Oct Nov-Dec Jan-Feb Mar-Apr May-Jun Jul-Aug Sep-Oct Nov-Dec Jan-Feb Mar-Apr May-Jun Jul-Aug

    2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36

    1. Stone Crusher S.C

    2. Brick Crusher B.C

    3. Asphalt Plant A.P

    4. Paver Machine P.M

    5. Bitumen Distributor B.D

    6. Wheel Loader W.L

    7. Excavator Ex.

    8. Bulldozer B.D

    9. Motor Grader M.G Bidder to indicate item-wise expected quantities to be tackled per work front

    10. Tandem Roller T.R per day (or state no. of days). Also indicate combination of equipment per work front

    11. Vibratory Roller V.R (say 5 Dump Truck + 1 Motoer Crader + 1 Wheel Loader + 1 Vibratory Roller).

    12. Steel Wheel Roller S.R

    13. Tire Roller R.R

    14. Water Bowser W.B

    15. Dump Truck D.T

    16. Cargo Truck C.T

    17. Air Compressor A.C

    18. Generator Ge

    19. Concrete Batching Plant C.B

    20. Mixer Machine M.M

    21. Mixer Truck M.T

    22. Concrete Vibrator C.V

    23. Bored Pile Equipment B.P

    24. Low Bed Trailer L.T

    25. Water Pump W.P

    26. Wet Mixing Plant W.M

    Remarks

    Form CON - 3.4 : DEPLOYMENT OF EQUIPMENT / PLANT TO MEET THE PROGRAMME

    2006 2007 2008 2009Year

    Month

    Cumulative months