slide viva-presentation final year diploma building uitm sarawak

76
ENVIRO BUILDERS SDN.BHD (678910-K) CLIENT: Majlis Daerah Samarahan, 94300 Kota Samarahan, Sarawak.

Upload: rayyanhariz

Post on 25-Nov-2015

194 views

Category:

Documents


11 download

DESCRIPTION

To those Final year students GUD LUCK on your last semester as a Diploma Student..:)

TRANSCRIPT

  • ENVIRO BUILDERS SDN.BHD (678910-K)CLIENT:Majlis Daerah Samarahan,94300 Kota Samarahan,Sarawak.

  • INTRODUCTIONTENDERING AND ESTIMANTINGPROJECT PLANNINGPROJECT MANAGEMENTCONCLUSIONINDUSTRIALISED BUILDING SYSTEM

  • COMPANY BACKGROUND

    VisionMissionCorporate InformationCorporate StructureOrganization StructureLogo companyShareholdersFinancial SourceCredit Facilities From Main SupplierList of Previous ProjectList of Current Projects

  • INTRODUCTIONEstablish and incorporated on the 28th February 1997.Provide services in the field of building construction and civil works, particularly on roads, drainage and many more.ENVIRO is symbolize of environment and conscious the type of green building.BUILDERS is symbolize to the person which is build a building with commitment

  • VISION

  • MISSION

  • ORGANISATION STRUCTUREManaging Director Ar. Azizan Hijazi Bin Tan Sri Lukman

    ManagerNur Hasrieza Binti Tan Sri Hassim

    Administration ExecutifSyamril Bin RamliHR ExecutifDg, Ssfura Binti Ag, Kamal Document ControllerPatricia ChristHR AssistantNurul Amira Binti Fazry ClerkJessica TanManagerHerrye Bin Tan Sri JonneyProject MnaagerAzril Fikhry Bin MahmudSite EngineerGhaffar Bin GhazaliSite EngineerMunirah Hayati Binti AliSite SupervisorBakri Bin SafeeSite SupervisorHelmy Bin Saad

    HSE OfficerFakhril Syahri Bin Shafie

    ManagerSr. Norszazlina Binti Dato Ali AbasSenior Quantity SurveyingZafirah Binti AlmyQuantity ServeyingMunirah Binti MahadiAssistant Quantity SurveyingAzhar Bin AhmadManagerMuhammad Faiz Bin Dato OsmanAccountant ExecutifJanet PatrickAccountant ExecutifNatasha Binti MuhammadAccountant AssistantRafiq Bin Duraman

  • LOGO COMPANY

  • ENVIRO BUILDERS SDN BHD (678910-K)Provision of Building Construction (B04) and Civil and Structure Engineering Works (CE21)PKK Reg. No. : 1601 A 1906 0609 (Class C)CIDB No. : 013008123-SL-101345 (Grade G5)

    CORPORATE INFORMATION

  • CORPORATE STRUCTURE

  • SHAREHOLDERS

  • FINANCIAL SOURCES

  • CREDIT FACILITIES FROM MAIN SUPPLIER

    No.Name of SupplierType of MaterialCredit Limit (RM)Payback Period01.Hailek Concrete Sdn BhdReady Mixed Concrete1,500,000.0060 days02.Hsin Ngie Hardware Sdn BhdConcrete1,500,000.0060 days03.Paragon Concrete Sdn. BhdConcrete1,500.000.0060 days04.Sarawak Plywood (m) Sdn BhdPlywood150.000.0060 days05.Perusahaan Tong Tai Sdn BhdSanitary Fittings150.000.0060 days

    06.Syarikat Perniagaan Perindustrian King Hong Sdn Bhd,Steel Bars200,000.0060 days

  • CREDIT FACILITIES FROM MAIN SUPPLIER

    No.Name of SupplierType of MaterialCredit Limit (RM)Payback Period07.Kian Chiong Hardware Sdn BhdMild Steel Bar1,000,000.0060 days08.NSC Production Sdn Bhd. Lot Bricks150,000.0060 days09.CMS Sdn. BhdCement150,000.0060 days10.Asabin Trading Sdn BhdPaints200,000.0060 days11.Han Cheng EnterpriseSandStone200,000.0060 days12.Ceramica Indah Sdn Bhd Tiles 150,000.0060 days

  • LIST OF PREVIOUS PROJECT

    No.Project NameCompletionContract sum (RM)Client1.Office renovation for Celcom (M) Bhd, Jalan semarak.20111,230,000.00Jabatan Kerja Raya Sarawak2.Cadangan Projek Pembinaan, Penaiktarafan dan Pembaikpulihan Sekolah-Sekolah dan Asrama di Negeri Sarawak Bagi Sk Sepiring20104,486,967.60Megah Ceria RekaBena Sdn. Bhd3.Cadangan Perpustakaan Desa di Taman Harmoni, Sri Aman2009136,740.00.00Housing Development Corporation Wisma Sultan Tengah Jalan Sukma

  • LIST OF PREVIOUS PROJECT (CONTD)

    No.Project NameCompletionContract sum (RM)Client4.Cadangan Membina dan Menyiapkan Sebuah Masjid, Jalan Ajibah Abol, 93400 Kuching, Sarawak.20041,440,000.00Jabatan Kerja Raya Daerah Kuching, Sarawak5.Kerja-kerja Membina Dan Menyiapkan Rumah Rehat / Wakaf Jalan Ban Hock, P O Box 547 93700Kuching Sarawak.2003791,322.92Jabatan Kerja Raya Daerah Kuching,Sarawak6.Kerja-kerja Membaikpulih Bangunan JKR 5535( 20 Bay) JKR Sarawak, Ibu Pejabat, Wisma Seberkas, Jln Tun Haji Abang Openg, 93582, Kuching Sarawak, Malaysia2002189,500.00Jabatan Kerja Raya Daerah Kuching, Sarawak

  • LIST OF CURRENT PROJECT

    No.Project NameCompletionContract sum (RM)Client1Proposed 10 units of 3 storey shophouses on Lots 924 & 927 Block 68 Mukah Land District (Phase 3), Mukah 20121,532,000.00Hock Peng Realty Sdn Bhd

  • TENDERING AND ESTIMATINGBUILD UP RATEQUOTATIONTENDER

  • TENDERINGCADANGAN MEMBINA DAN MENYIAPKAN SEBUAH DEWAN SERBAGUNA UNTUK KEGUNAAN MASYARAKAT KOTA SAMARAHAN, SARAWAK

  • TENDER SUMMARY

  • BUILD UP RATESUMMARY OF BUILD UP RATE

  • BUILD UP RATEConcreting WorksReinforcement Bar WorksMild/HighFloor Tiles WorksBrick worksPlastering worksForm worksRoof structureExternal and Internal Painting WorksRoof FinishesInsuranceSite Office and Workers kongsi House

  • ORDER & REQUISITION

  • REQUEST FOR QUOTATION

  • PRICE EVALUATION

  • ACCEPTANCE OF PRICE

  • PROJECT PLANNINGINSURANCESITE LAYOUTS-CURVECPMLABOUR SCHEDULEMATERIAL SCHEDULEMACHINERIES SCHEDULEMETHOD STATEMENTRESOURCES ALLOCATION

  • INSURANCE

  • PERFORMANCE BOND

  • CONTRACTOR ALL RISK

  • PUBLIC LIABILITY INSURANCE POLICY

  • WORKMENs COMPENSATION INSURANCE POLICY

  • SITE LAYOUT

  • WORK PROGRAMMECPMFINANCIAL S-CURVEPHYSICAL S-CURVE

  • FINANCIAL S-CURVE

  • PHYSICAL S-CURVE

  • WEEKLY SCHEDULE

  • METHOD STATEMENTSUMMARY

    Method Statement

    NOELEMENTTOTAL DAYS1PRELIMINERIES33 days2PILING WORKS88 days3WORK BELOW LOWEST FLOOR FINISHES17 days4FRAME7 days5UPPER FLOORS7 days6ROOF54 days7EXTERNAL WALLS11 days8INTERNAL WALL AND PARTITIONS10 days9STAIRCASE19 days10DOORS7 days11WINDOW8 days12FLOOR FINISHES8 days13WALL FINISHES11 days14CEILING FINISHES9 days15SANITARY FITTINGS 4 days16GAMES COURT7 daysGRAND TOTAL 300 DAYS

  • RESOURCES ALLOCATION

    No.Name of SupplierType of MaterialAddressTel & Fax No.01.Hailek Concrete Sdn BhdReady Mixed ConcreteNo. 188, Jln Chong Jin Chong,93250 Kuching, SarawakTel : 082-6 87 910Fax : 082-687 91102.Hsin Ngie Hardware Sdn BhdConcrete157H, Jalan Satok, 93400 Kuching, P.O Box 756, 93716 Kuching, SarawakTel : 082-256329/ 082-415106Fax : 082-42663203.Paragon Concrete Sdn. BhdConcreteLot 957, Block 224,41/2 Mile Batu Kawa,93250 Kuching, Sarawak.Tel : 082-683000Fax : 082-683866

  • RESOURCES ALLOCATION

    No.Name of SupplierType of MaterialAddressTel & Fax No.04.Sarawak Plywood (M) Sdn BhdPlywoodRH Plaza, 1st Floor, Lot 5400, Block 16, Lorong Lapangan Terbang 1, Kuching 93250 SarawakTel : 082-451 789 Fax : 082-461 30005.Perusahaan Tong Tai Sdn BhdSanitary Fittings1305 Jln Kemajuan Pending Industrial Estate 93450 Kuching, Sarawak.Tel : 082-34855706.Syarikat Perniagaan Perindustrian King Hong Sdn Bhd, Steel BarLots 1059 & 1462, block 7 MTLD, demak laut industrial park, 93050 kuching. Sarawak MalaysiaTel: 082 433388 Fax: 082 433389

  • RESOURCES ALLOCATION

    No.Name of SupplierType of MaterialAddressTel & Fax No.07.Kian Chiong Hardware Sdn BhdMild Steel BarLot 22A, No. 1B, Angching Lorong, Kuching.Tel: 082-248394Fax: 082- 42924608.NSC Production Sdn Bhd. Lot BricksLot 1315, Jalan Muara Tuang, 93700, Kota Samarahan, Sarawak.Tel: 082-628990Fax:082-62889909.Kim Poh bricks Works,BricksNo. 871 Jln kuching-serian, Batu 24, 94200 Siburan Sarawak.Tel : 082-86862610.CMS Sdn. BhdCementLot 5895, Pending Industrial Estate, Jalan Kilang Simen, P O Box 2000, Kuching 93740, SarawakTel : 082-332111Fax : 082-334537

  • RESOURCES ALLOCATION

    No.Name of SupplierType of MaterialAddressTel & Fax No.11.Jee Foh Multi Supply Co No. 39 Gambir Road, 93000 KuchingPaint Lot 1315, Jalan Muara Tuang, 93700, Kota Samarahan, Sarawak.Tel:082-241460 Fax:082-23318912.Asabin Trading Sdn Bhd, PaintsNo. 871 Jln kuching-serian, Batu 24, 94200 Siburan Sarawak.Tel : 082-251231Fax : 082-42113113.Kim Shien Trading Sdn Bhd Sand No. 137 Lot 437 Block 220 Batu 4 1/2 Jalan Perissen Kuching, Sarawak 93250 Malaysia Tel : 082-573842Fax: 082-573842

  • RESOURCES ALLOCATION

    No.Name of SupplierType of MaterialAddressTel & Fax No.14.Han Cheng EnterpriseSandStoneNo. 2503, Jalan Stapok Utama, Kuching 93250,Sarawak.Tel : 016-8882033Fax : 082- 68170915.Ceramica Indah Sdn Bhd Tiles 4 1/2 Mile Kong Ping Road Off Penrissen Road Kuching, Sarawak 93250 MalaysiaTel: 082-451567 Fax: 082-452135

  • PROJECT MANAGEMENT

  • SITE ORGANISATION STRUCTURE

  • SITE SAFETY IMPLEMENTATION

  • EMERGENCY RESPONSE PLAN

  • PERSONAL PROTECTION EQUIPMENT

  • SAFETY SIGNBOARDS

  • TOOL BOX MEETING

  • HAZARD IDENTIFICATION, RISK ASSESSMENT AND RISK CONTROL (HIRARC)

  • SITE CONTROL SYSTEM

  • TIME CONTROLCPMWORK CARDTIME CONTROL

  • CPM Arrange of the planning work more than properly WORK CARD/RECORD Record of the working days for each worker.

  • COST CONTROL

    Material on siteSupervise materials flow on site operations from delivery process to implementing process carefully.

    Maintenance of machinery and plant on siteMaintenance instead of repairing

    Facilities on siteEnsure facilities on site are maximally utilized

  • LABOUR CONTROL Incentive given to the labourAllowance and sufficient overtimeSafety and welfare of labourArrange all labour to be several teamsDivide among the labour to be a several timeIncrease the productivity on siteWell payment recordHave salary record which is known as a Contractor CardManagement knows the status of the payment

  • MATERIAL CONTROL

  • MACHINERY AND PLANT CONTROL

  • QUALITY CONTROL

  • DAILY WORK REPORT

  • PROGRESS WORK

  • FINANCIAL S-CURVE

  • PHYSICAL S-CURVE

  • PROGRESS CLAIM & PAYMENT

  • PROGRESS CLAIM FROM MAY - OCT

    Item CertificatesDatedInterim ClaimRetention SumCertificated AmtCumulativeRMRMRMRM1Perakuan Bayaran Interim No. 110/6/2013RM150,619.357,530.97143,088.38143,088.382Perakuan Bayaran Interim No. 212/7/2013RM49,059.702,452.9946,606.72189,695.103Perakuan Bayaran Interim No. 39/8/2013RM21,483.551,074.1820,409.37210,104.474Perakuan Bayaran Interim No. 413/9/2013RM144,415.887,220.79137,195.09347,299.565Perakuan Bayaran Interim No. 511/10/2013RM139,275.776,963.79132,311.98479,611.546Perakuan Bayaran Interim No. 68/11/2013RM163,632.548,181.63155,450.91635,062.45TOTALRM668,486.79RM33,424.34RM635,062.45RM2,004,861.49

  • SUMMARY OF SUB-CONTRACTOR PAYMENTPILING WORKSSHOREFIELD SDN. BHD

    Cert. NoClaim DateValue of Works(RM)Retention Sum 5% (RM)Certificated Value(RM)Cumulative15/6/201354,593.25 2,729.66 51,863.59 51,863.5925/7/201377,290.25 3,864.51 73,425.74 125,289.3335/8/20139,232.00 461.60 8,770.40 134,059.73TOTAL141,115.507,055.77134,059.73134,059.73

  • EXTENSION OF TIME(EOT)CPM EOT

    JustificationDurationDelay due the late of submission drawing for cut off pile- Clause 43 (f)12 daysDelay due late the issuance of the new structural drawings- Clause 43 (f)25 days

  • EXTENSION OF TIME(EOT)

  • INDUSTRIALISED BUILDING SYSTEM

  • INDUSTRIALISED BUILDING SYSTEM

  • INDUSTRIALISED BUILDING SYSTEM

  • INDUSTRIALISED BUILDING SYSTEM

  • INDUSTRIALISED BUILDING SYSTEM

  • INDUSTRIALISED BUILDING SYSTEM

  • CONCLUSION

  • Q & A SESSION

    ***