Social Monitoring Report Project Number: 37231-043 September 2015 PAK: Punjab Irrigation Agriculture Investment Project Pakpattan Canal and Suleimanki Barrage Improvement Project Loan 2971 Internal Resettlement Monitoring Report Prepared by the Project Management Office (PMO) for Punjab Barrages, Irrigation Department, Punjab for the Asian Development Bank (ADB). The social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Upload: others

Post on 18-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Social Monitoring Report PAK: Punjab Irrigation ... · (Nov, 2014 – Sep, 2015) which involved 33 affected households were completed in April 2015. Phase 2 (Nov, 2015 – Sep, 2016)

Social Monitoring Report

Project Number: 37231-043

September 2015

PAK: Punjab Irrigation Agriculture Investment Project – Pakpattan Canal and Suleimanki Barrage Improvement Project Loan 2971

Internal Resettlement Monitoring Report

Prepared by the Project Management Office (PMO) for Punjab Barrages, Irrigation Department,

Punjab for the Asian Development Bank (ADB).

The social monitoring report is a document of the borrower. The views expressed herein do not

necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 2: Social Monitoring Report PAK: Punjab Irrigation ... · (Nov, 2014 – Sep, 2015) which involved 33 affected households were completed in April 2015. Phase 2 (Nov, 2015 – Sep, 2016)

GOVERNMENT OF THE PUNJAB

IRRIGATION DEPARTMENT

Pakpattan Canal and Suleimanki Barrage

Improvement Project (PCSBIP)

ADB Loan No. 2971-PAK

Internal Resettlement Monitoring Report

For Quarter July - September 2015

PROJECT MANAGEMENT OFFICE (PMO) FOR PUNJAB BARRAGES,

IRRIGATION DEPARTMENT CANAL BANK

MUSTAFABAD, LAHORE

Page 3: Social Monitoring Report PAK: Punjab Irrigation ... · (Nov, 2014 – Sep, 2015) which involved 33 affected households were completed in April 2015. Phase 2 (Nov, 2015 – Sep, 2016)

PCSBIP Internal Resettlement Monitoring Report

1

PMO For Punjab Barrages

Pakpattan Canal and Suleimanki Barrage Improvement Project

(PCSBIP)

Internal Monitoring Report for the Quarter July-September, 2015

1. LAND ACQUISITION AND RESETTLEMENT PLAN (LARP)

ADB approved the updated LARP for Pakpattan canal in July 2014. A total of 80 households

have been affected. Implementation of the LARP has been divided into three phases. Phase 1

(Nov, 2014 – Sep, 2015) which involved 33 affected households were completed in April 2015.

Phase 2 (Nov, 2015 – Sep, 2016) involves 20 households, while Phase 3 (Nov, 2016 – Sep, 2017)

involves 27 households. PMO and PSSC have targeted to complete Phase 2, Phases 2 and 3 by

June 2016. There is no land acquisition at Sulemanki Barrage but temporary land acquisition is

only at Pakpattan Canal. The compensation is related to temporary land acquisition, structures,

trees etc. of the affected families residing at ROW and nearby by vicinity of canals.

Most of the affected households are illegal settlers on the irrigation land and are compensated

for their losses of assets and are provided with relocation allowance and assistance for

vulnerable households. PMO and PSSC have full-time staff that visit the site on regular basis to

interact with the communities and affected households.

LARP Implementation activities for Tranche 3 relates to Pakpattan Canal System. The LARP

cover the impacts due to the rehabilitation and upgrading of Pakpattan canal Upper/ Lower,

Khadir Branch and Pakpattan Islam Link. Internal monitoring is done by the PMO Environment

& Social Unit (ESU) with support from PSSC and internal monitoring reports in the shape of QPR

are being regularly submitted to the Bank, The external monitor for tranche 2 & 3 will be

recruited in the month of November 2015 and he will submit his first external resettlement

monitoring report in the month of January 2016.

Tranche 3 also has an operational grievance redress mechanism that covers all aspects of the

project activities, including resettlement. Concerns and feedback from residents of the 10

nearby villages are noted by the ESU and PSSC. Complaints register is also maintained by PSSC

to record community concerns and there solutions. Most of the concerns received are related

Page 4: Social Monitoring Report PAK: Punjab Irrigation ... · (Nov, 2014 – Sep, 2015) which involved 33 affected households were completed in April 2015. Phase 2 (Nov, 2015 – Sep, 2016)

PCSBIP Internal Resettlement Monitoring Report

2

PMO For Punjab Barrages

to employment with the contractor. According to the contract the contractor is bound to hire

maximum labors from the locals.

2. ADJUSTMENT MADE IN THE COMPENSATION RATE DURING UPDATING OF LARP IN

2014.

The LARP of Pakpattan Canal System was prepared in year 2012 but the LARP was not

implemented during 2012-2013. Later on, the adjustment was made in compensation rates of

land, structures and livelihood assistance during updating the LARP in July 2014. The temporary

land occupation rates in three districts of project area are starting from Rs. 40,000 to Rs. 50,000

per acre. These rates are more than market rates because the average rate of one acre is upto

Rs. 40,000. But under the supervision of PSSC and PMO Punjab Barrages the rates of temporary

land occupations are being provided maximum upto Rs. 50,000 which are already higher side.

The certification from BOR is not required in this regard due to already higher and safer side to

the AFs. Therefore, the matter of 2015 rates does not applicable in these cases.

The rates of 2014 are still applicable because they were at upper most side in 2014. Therefore,

there is no much changes recognized up till now. The adjustment made in compensation is

given in Annex-A

3. EMPLOYMENT OF THE AFFECTED HOUSEHOLDS IN PROJECT RELATED JOBS.

According to the ADB guideline policy, the Contractor is bound to provide employment to local

community living in surroundings of the project area. The Supervision Consultants staff is

getting Employment Status of the local community on monthly basis and fully concerned to

provide unskilled labor employment to the AFs of the project. The status of skilled and unskilled

labor employment for the month of July, August and September 2015 is given in Annex B, C

and D which is 88%, 88% and 80% respectively for unskilled labor for the project area.

Out of 33 affected families, 03 persons were willing to do job with the Contractor at RD No. 62

of Pakpattan Canal Upper for stone stud activity. The name of affected person is Hashim Ali S/O

of Sardar Ali. His 03 sons are doing jobs with the Contractor.

Page 5: Social Monitoring Report PAK: Punjab Irrigation ... · (Nov, 2014 – Sep, 2015) which involved 33 affected households were completed in April 2015. Phase 2 (Nov, 2015 – Sep, 2016)

PCSBIP Internal Resettlement Monitoring Report

3

PMO For Punjab Barrages

Employment opportunities have been offered to all the AFs at the site. Mostly the AFs are

interested to get the employment. But at this stage, the construction work is being executed at

a far away from their homes. Therefore, AFs are waiting to get the work started at the near

places to reduce the transportation cost.

4. RELOCATION OF AFFECTED HOUSEHOLDS AND THEIR CURRENT LIVING

CONDITION.

Total 80 Affected Households (AHs) will be relocated regarding rehabilitation and upgrading of

Pakpattan Canal System. Out of these, 35 AHs are at Pakpattan Canal Upper, 2 AHs at Pakpattan

Canal Lower, 42 AHs at Khadir Branch and only 1 AH is at P.I Link canal.

During First Phase, 33 AHs, 14 at Pakpattan Canal Upper, 2 at Pakpattan Canal Lower, 16 at

Khadir Branch, 1 at P.I Link Canal. Most of the AHs were shopkeepers having the business of

selling edibles and general store items. They are living hand to mouth and difficult to live within

that income because they have no alternative source of income. Their family size is too large to

support with the current resources.

After getting compensation during first phase, the AHs relocated themselves in the nearby land

purchased by their own. Some of them started the same business and other changes their

occupation. Their living conditions are much better now than previous one. They are happy

with the amount of compensation and the way they get the money. The brief detail is given

bellow.

Out of 33 AFs in Phase 1 at 12 construction sites, the construction activity has been started only

on 4 sites, remaining sites are under process and execution will be started soon. The maximum

AFs loctaed at Khadir Branch at RD 40 and their improved living condition before and after is

given below. The remaining AFs have been noted before condition and will be submitted their

after condition when the work will be started on remaining sites because before starting of

work on remaining sites they will be informed one week before, presently they are doing their

business on old locations.

Page 6: Social Monitoring Report PAK: Punjab Irrigation ... · (Nov, 2014 – Sep, 2015) which involved 33 affected households were completed in April 2015. Phase 2 (Nov, 2015 – Sep, 2016)

PCSBIP Internal Resettlement Monitoring Report

4

PMO For Punjab Barrages

Resettlement Cases at RD # 40 of Khadir Branch

Case No. 1

The LARP has improved the living condition of the AFs, before the relocation Mr. Javed Iqbal s/o

Muhammad Ali was doing food seller business and after the relocation he has got his own shop and

started his business.

Before Relocation After Relocation

Case No.2

In case no 2 Mr. Javed Iqbal s/o Bahadur Ali was doing shoemaker occupation and now he has

established his own barber shop near to old location and he is happy with this new business.

Before Relocation After Relocation

Page 7: Social Monitoring Report PAK: Punjab Irrigation ... · (Nov, 2014 – Sep, 2015) which involved 33 affected households were completed in April 2015. Phase 2 (Nov, 2015 – Sep, 2016)

PCSBIP Internal Resettlement Monitoring Report

5

PMO For Punjab Barrages

Case No. 3

The business of Mr. Khalid Hussain s/o Qasim Ali was shopkeeper. After the relocation process, he has

got Riksha and now has established his new business.

Before Relocation After Relocation

Case No. 4

Mr. Khadim Hussain s/o Ghulam Muhammad was not doing any business due to abundant wooden shop

but now he has established his own wooden shop and his source of income is increased due to

relocation.

After Relocation

Case No. 5

Page 8: Social Monitoring Report PAK: Punjab Irrigation ... · (Nov, 2014 – Sep, 2015) which involved 33 affected households were completed in April 2015. Phase 2 (Nov, 2015 – Sep, 2016)

PCSBIP Internal Resettlement Monitoring Report

6

PMO For Punjab Barrages

Mr. Ghulam Rasul s/o Talib Hussain was doing green grocer business. After the relocation process, he

has got his own Riksha and doing business.

Before Relocation After Relocation

Case No. 6

The business of Mr. Muhammad Saeed s/o Manzoor Ahmad was selling food point. He had not his own

home and was living in poor condition, after the relocationn process he has built his own house and

food seller point has been shifted away from old location.

Before Relocation After Relocation

Resettlement Cases at RD 36+000 of PI Link Canal

Case 7

Mr Ramzan s/o Muhammad Sadiq was having a small cycle workshop at the bank of canal. After the

relocation, he has changed and shifted his cycle workshop to some other place having more business.

Page 9: Social Monitoring Report PAK: Punjab Irrigation ... · (Nov, 2014 – Sep, 2015) which involved 33 affected households were completed in April 2015. Phase 2 (Nov, 2015 – Sep, 2016)

PCSBIP Internal Resettlement Monitoring Report

7

PMO For Punjab Barrages

Before Relocation After Relocation

The status of improved living condition of the AFs is given in Annex-E.

The status of Implementation of LARP for PCSBIP/ICB-01as of 30-09-2015 is given as Annex-F

2. Grievance Redressed Mechanism.

On Pakpattan Canal project Contractor has established Grievance Redressal Mechanism on camp site

and each location of work. Mostly complaints arise regarding having employment of the local persons,

sprinkling of water and late payments. At Burewala Camp Site, total 61 cases recorded among them,

Fifty five complaints have been resolved while 6 are pending. The detail is given in Annex-G. At Pakpatan

Camp Site, total 70 complaints recorded and 53 have been resolved while 17 are pending. The pending

cases will be resolved very soon.

Page 10: Social Monitoring Report PAK: Punjab Irrigation ... · (Nov, 2014 – Sep, 2015) which involved 33 affected households were completed in April 2015. Phase 2 (Nov, 2015 – Sep, 2016)

PCSBIP Internal Resettlement Monitoring Report

8

PMO For Punjab Barrages

Adjustment made in Compensation Rates in LARP July, 2014 Annex - A

Sr. No.

Description Unit Unit Rate of LARP 2012

Unit Rate of updated

LARP 2014

Remarks

1 Land Occupation

- Temporary occupation of land for 3 years

Acres 50,000 60,000 The temporary land occupation rates in three districts of project

area are started from Rs. 40,000 to Rs. 50,000 per acre.

These rates are more than market rates because the

average rate of one acre is upto Rs. 40,000. But under the

supervision of PSSC and PMO Punjab Barrages the rates of

temporary land occupations are being provided maximum upto Rs. 50,000 which are already higher side. The certification

from BOR is not required in this regard due to already higher

and safer side to the AFs. Therefore the matter of 2015 rates does not applicable on

these cases.

2 Residential Structures

- i) Pacca structure Sq. ft. 720 840

- ii) Semi-pacca structures - Sq. ft. 525 600

- 5 nos.

- iii) Katcha/ thached shed - Sq. ft. 310 360

- 6 nos.

iv) Boundary walls - 6 nos.

Sq. ft. 310 120

3 Commercial Structures (shops/ kiosks)

- i) Semi-pacca structures (shops) - 4 nos.

Sq. ft. 525 600

- ii) Katcha structures/ sheds - 11 nos.

Sq. ft. 310 360

iii) Kiosks/ phatta Nos. 5,000 5,000

4 Community Structures

- Hand Pumps Nos. 10,000 10,000

Electric Motor - 15,000

5 Livelihood Assistance

-

i) Business interruption allowance (for 3 months based on the oficial wage rate at Rs. 9,000 per month).

Nos. 27,000 31,500

Page 11: Social Monitoring Report PAK: Punjab Irrigation ... · (Nov, 2014 – Sep, 2015) which involved 33 affected households were completed in April 2015. Phase 2 (Nov, 2015 – Sep, 2016)

PCSBIP Internal Resettlement Monitoring Report

9

PMO For Punjab Barrages

-

ii) Livelihood assistance to Boatmen (for 3 months based on official wage rate at Rs. 9,000 per month.

Nos. 27,000 31,500

-

iii) Shifting/ transport assistance allowance (Rs.5,000) - 7 DPs of residential structures and 7 boatmen for sifting.

Nos. 5,000 5,000

iv) Severe impact allowance

- 10,500

v) Vulnerability allowance (cash allowance for 3 months based on the Officail Wage Rate Rs. 9000 per month as fixed).

Nos. 27,000 31,500

Page 12: Social Monitoring Report PAK: Punjab Irrigation ... · (Nov, 2014 – Sep, 2015) which involved 33 affected households were completed in April 2015. Phase 2 (Nov, 2015 – Sep, 2016)

PCSBIP Internal Resettlement Monitoring Report

10

PMO For Punjab Barrages

Pakpattan Canal and Suleimanki Barrage Improvement Project (PCSBIP)

Employment Status for the Month of July, 2015 Annex - B

Sr.

No.

Project

Area

Sinohydro-NEL Sub-Contractor Total

Remarks Skilled

Un-

Skilled Total Skilled

Un-

Skilled Total Skilled

Un-

Skilled Total

1 Pakpattan

18 4 22 35 5 40 53 9 62

During Phase

1 out of 33

AFs, the

contractor

has

employed 3

memebers

of AFs. They

are serving

with the

contractors

from Jully

01, 2015.

2 Vehari

- 4 4 - 5 5 - 9 9

3 Burewala

10 5 15 35 10 45 45 15 60

4 Arifwala

4 4 4 4

5 Qubula

6 Total

28 17 45 70 20 90 98 37 135

7 % age

65% 88%

8

Other

from

Project

Area

8 8 45 5 50 53 5 58

9 % age

35% 12%

10 Total

36 17 53 115 25 140 151 42 193

Note : Local Labor utilized :88%

Out of 33 Afs, 3 AF were employed since July 2015 and still working.

The type of employment of AFs related to non-skilled labour.

Page 13: Social Monitoring Report PAK: Punjab Irrigation ... · (Nov, 2014 – Sep, 2015) which involved 33 affected households were completed in April 2015. Phase 2 (Nov, 2015 – Sep, 2016)

PCSBIP Internal Resettlement Monitoring Report

11

PMO For Punjab Barrages

Pakpattan Canal and Suleimanki Barrage Improvement Project (PCSBIP)

Annex -C

Employment Status for the Month of August, 2015

Sr.

No. Project Area

Sinohydro-NEL Sub-Contractor Total

Remarks

Skilled Un-

Skilled Total Skilled

Un-

Skilled Total Skilled

Un-

Skilled Total

1 Pakpattan 18 4 22 35 5 40 53 9 62

During Phase 1

out of 33 AFs,

the contractor

has employed 3

memebers of

AFs. They are

serving with

the contractors

from Jully 01,

2015 to

onward.

2 Vehari - 4 4 - 5 5 - 9 9

3 Burewala 12 5 17 35 10 45 47 15 62

4 Arifwala - 4 4 - - - - 4 4

5 Qubula - - - - - - - - -

6 Total 30 17 47 70 20 90 100 37 137

7 % age - - - - - - 66% 88% -

8

Other from

Project Area 6 - 6 45 5 50 51 5 100

9 % age - - - - - - 34% 12% -

10 Total 36 17 53 115 25 140 151 42 237

Local Labor utilized :88% Note:Out of 33 Afs, 3 AF were employed since July 2015 and still working. The type of employment of AFs related to non-

Page 14: Social Monitoring Report PAK: Punjab Irrigation ... · (Nov, 2014 – Sep, 2015) which involved 33 affected households were completed in April 2015. Phase 2 (Nov, 2015 – Sep, 2016)

PCSBIP Internal Resettlement Monitoring Report

12

PMO For Punjab Barrages

Pakpattan Canal and Suleimanki Barrage Improvement Project (PCSBIP) Annex -D

Employment Status for the Month of September, 2015

Sr.

No. Project Area

Sinohydro-NEL Sub-Contractor Total

Remarks

Skilled Un-

Skilled Total Skilled

Un-

Skilled Total Skilled

Un-

Skilled Total

1 Pakpattan 55 25 80 85 35 120 140 60 200

During Phase 1

out of 33 Afs,

the contractor

has employed 3

memebers of

AFs. They are

serving with

the contractors

from Jully 01,

2015 to

onward.

2 Vehari 7 3 10 15 - 15 22 3 25

3 Burewala 51 19 70 55 35 90 106 54 160

4 Arifwala 20 - 20 - 25 25 20 25 45

5 Qubula 10 - 10 - - - 10 - 10

6 Total 143 47 190 155 95 250 298 142 440

7 % age - - - - - - 84% 80% -

8

Other from

Project Area 55 35 90 - - - 55 35 90

9 % age - - - - - - 16% 20% -

10 Total 198 82 280 155 95 250 353 177 530

Local Labor utilized :80% Note: Out of 33 Afs, 3 AF were employed since July 2015 and still working. The type of employment of AFs related to non-skilled labour.

Page 15: Social Monitoring Report PAK: Punjab Irrigation ... · (Nov, 2014 – Sep, 2015) which involved 33 affected households were completed in April 2015. Phase 2 (Nov, 2015 – Sep, 2016)

PCSBIP Internal Resettlement Monitoring Report

13

PMO For Punjab Barrages

Status of Improved Living Condition of the AFs Annex E

Sr.

No Location

Case

No. Before After Remarks

1

RD No. 40 Khadir

Branch

Case

No. 1 Unsettled Shop Settled Shop Javed Iqbal S/O Muhammad Ali

2

RD No. 40 Khadir

Branch

Case

No. 2

Shoemaker

unsettled

Settled Barber

Shop Javed Iqbal S/O Bahadur Ali

3

RD No. 40 Khadir

Branch

Case

No. 3

Shoemaker

unsettled

Settled Barber

Shop Khadim Hussain S/O Qasim Ali

4

RD No. 40 Khadir

Branch

Case

No. 4 - Motor cycle Riksha

khadim Hussain S/O Ghulam

Muhammad

5

RD No. 40 Khadir

Branch

Case

No. 5 Gree Grocer Motor cycle Riksha Ghulam Rasool S/O Talib Hussain

6

RD No. 40 Khadir

Branch

Case

No. 6 -

Own house + food

seller point

Muhammad Saeed S/O Major

Akeel

7

RD+36+000 PI Link

Court

Case

No. 7

Small cycle

workshop

Better cycle

workshop Mr. Rizwan S/O Muhammad Sadiq

Page 16: Social Monitoring Report PAK: Punjab Irrigation ... · (Nov, 2014 – Sep, 2015) which involved 33 affected households were completed in April 2015. Phase 2 (Nov, 2015 – Sep, 2016)

PCSBIP Internal Resettlement Monitoring Report

14

PMO For Punjab Barrages

Status of Implementation of LARP for PCSBIP/ICB-01 as of 30-09-2015 Annex-F

Sr.

No. Contract No.

Status of

preparation,

vetting and

approval of

RP

Compensation

Due Implementation

%

Implementation Remarks

1

Tranch-3,

Pakpattan

Canal and

Suleimanki

Barrage

Improvement

Project

PCSBIP/ICB-

01

Draft LARP

of Pakpattan

Canal

system was

prepared in

2012 later

on LARP was

revised and

updated in

July, 2014.

No.

of

Afs.

Amount

Due

Total

AFs

paid

Amount

paid

AFs

paid

Amount

Paid

Status of

Civil

work

award

Out of 33,

payment

has been

made to

29 AFs

Which is

88%. The

Payment

of Phase 2

and 3 in

under

process

that will

be

completed

within due

periods.

Phase 1

(Nov 2014

to Sep 2015)

33 3.58 29 3.162 88% 88% Awarded

for

Phase 1

Phase 2

(Nov 2015

to Sep 2016)

20

Phase 3

(Nov 2016

to Sep 2017)

27

Total 80 3.58 29 3.16 88% 88%

Page 17: Social Monitoring Report PAK: Punjab Irrigation ... · (Nov, 2014 – Sep, 2015) which involved 33 affected households were completed in April 2015. Phase 2 (Nov, 2015 – Sep, 2016)

PCSBIP Internal Resettlement Monitoring Report

15

PMO For Punjab Barrages

Status of Settlement of Complaints Annex-G

Sr

#

Date Complainant Location Sort of Complain Status

01 03-07-14 M. Deen Camp Burewala Leveling issue of land hired for

camp after completion of

project

Pending

02 05-07-14 Abdul Kareem Camp Burewala Dust Issue because of machinery

working

Resolved

03 08-07-14 Jamal Camp Burewala Road Blockage issue /material

transfer to camp

Resolved

04 10-07-14 Ahtasham Camp

Pakpattan

Noise of machinery creates

disturbance

Resolved

05 11-07-14 Nasir Camp Burewala No proper construction waste

disposal

Resolved

06 17-08-14 AsmatUllah Camp Burewala Labor making noise & disturbing

nearby locals

Resolved

07 14-07-14 Naeem Camp

Pakpattan

Construction material dumped

on main road

Resolved

08 12-08-14 Asif Camp Burewala Heavy Machinery blocks the

road

Resolved

09 14-08-14 Ibrahim Camp Burewala Labor use to walk through the

local people fields

Resolved

10 17-07-

2014

Zaman Camp

Pakpattan

Provide Safety Shoes to labour Resolved

11 18-07-14 AmanUllah Camp

Pakpattan

Construct the boundary wall of

camp in order to avoid any

disturbance to local people

Resolved

12 19-07-14 Rasheed Camp

Pakpattan

Provide medical facilities at

camp

Resolved

13 20-07-14 Zahid Camp

Pakpattan

Provide Lunch and dinner on

time

Resolved

14 20-07-14 Shabir Camp

Pakpattan

Road Blockage issue /material

transfer to camp

Resolved

15 03-09-14 Khursheed Camp

Pakpattan

Workshop of camp creates noise

pollution

Resolved

16 14-09-14 LatifKabariya Camp

Pakpattan

Leveling issue of land hired for

camp

Resolved

17 28-09-14 Bashir Camp

Pakpattan

No proper construction waste

disposal

Resolved

18 29-09-14 Younis RD 13 Khadir

Branch

Dust Pollution creating

breathing problem

Resolved

19 03-09-14 Rafique RD 399 PC

Upper

Dust issue because of diversion

construction

Resolved

20 30-09-14 Yasir RD 17 Khadir

Branch

Traffic not managed properly Resolved

Page 18: Social Monitoring Report PAK: Punjab Irrigation ... · (Nov, 2014 – Sep, 2015) which involved 33 affected households were completed in April 2015. Phase 2 (Nov, 2015 – Sep, 2016)

PCSBIP Internal Resettlement Monitoring Report

16

PMO For Punjab Barrages

21 01-10-14 Ansar RD 399 PC

Upper

No proper parking for

machinery at site

Resolved

22 04-10-14 Akram RD 449 PC

Upper

Request to borrow material

from private land

Resolved

23 3-10-14 Wajid Ali RD 20 Khadir

Branch

Leveling issue of borrow area Resolved

24 07-10-14 Ghafoor RD 470 PC

Upper

Enhance the width of new

proposed bridge

Resolved

25 07-10-14 Waheed RD 05 Khadir

Branch

Provide dust masks to staff

workers

Resolved

26 11-10-14 Liaqat Ali RD 399 PC

Upper

Pay the rent of private land used

for diversion

Resolved

27 22-10-14 Babar RD 476 PC

Upper

Dust issue because of diversion

construction

Resolved

28 16-10-14 Usman Camp

Pakpattan

Paramedical staff does not

reach on time at dispensary.

29 27-10-14 Kashif RD 499 PC

Upper

Dust issue because of diversion

construction

Resolved

30 25-10-14 Umer Khalil RD 13 Khadir

Branch

Labor is creating disturbance for

local community by shouting

and making a laugh

Resolved

31 04-11-

2014

BushraBibi Camp Burewala Start a free diabetes checkup

free camp

Pending

32 12-12-14 San Ullah RD 449 PC

Upper

Labor interfering with local

vegetation

Resolved

33 23-12-14 Jala Din RD 470 PC

Upper

Dust issue because of diversion

construction

Resolved

34 13-11-14 Toqueer RD 26 Khadir

Branch

Don’t look at our houses by using Total Station

Resolved

35 03-01-15 Fateh

Muhammad

RD 449 PC

Upper

Local people are feeling

disturbance due to rough

language of local labors

Resolved

36 14-01-15 Nusrat Begum Camp

Pakpattan

Free Medicines have ended Resolved

37 19-01-15 Noor Ahmad RD 34 PC Upper Give me amount of

Resettlement Cases

Pending

38 28-02-15 Barkat Ali Camp

Pakpattan

Build a complete boundary wall

at front

Resolved

39 03-04-15 Yousaf RD 470 PC

Upper

To save a big mature shady tree

(bohar)

Resolved

40 03-03-15 M. Tufail RD 34 PC Upper When we will receive the

cheque of resettlement case

Pending

41 01-14-15 Jamshaid RD 476 PC

Upper

Dust issue because of diversion

construction

Resolved

42 04-09-15 Haider RD 354 PC

Upper

A lot of trees in diversion will it

out

Contact the forest department

Resolved

Page 19: Social Monitoring Report PAK: Punjab Irrigation ... · (Nov, 2014 – Sep, 2015) which involved 33 affected households were completed in April 2015. Phase 2 (Nov, 2015 – Sep, 2016)

PCSBIP Internal Resettlement Monitoring Report

17

PMO For Punjab Barrages

for tree cutting

43 1-04-15 M. Ashiq RD 34 PC-Upper When we will receive the

cheque of resettlement case

Pending

44 07-09-15 Akbar Khan RD 384 PC

Upper

Change the diversion design so

that to save his private land

No Solution

45 03-05-15 Riaz Ahmad RD 240 Khadir

Branch

Dust issue because of diversion

construction

Resolved

46 11-09-15 SaqibHussain RD 354 PC

Upper

Local labor eats fruits from

nearby fields without

permission

Resolved

47 22-09-15 Safdar RD 406 PC

Upper

Request to borrow land from

private land

Resolved

48 11-06-15 Shafique RD 286 Khadir

Branch

Install sign boards at road side Resolved

49 27-10-15 Khan Zaman RD 406 PC

Upper

Local labor eats fruits from

nearby fields without

permission

Resolved

50 27-07-15 Salman RD 275 Khadir

Branch

Local people are feeling

disturbance due to rough

language of local labors

Resolved

51 04-10-15 IrfanSaleem RD 406 PC

Upper

Local Labor quarrel with local

people because of fishing

Resolved

52 21-08-15 Zafar Khan RD 62 PC Upper Trucks creating disturbance in

flow of traffic

Resolved

53 12-10-15 Nouman Ali RD 406 PC

Upper

Cut two trees creating

hindrance in diversion cutting

Not

Required

54 23-10-15 Naveed RD 354 PC

Upper

Construct a small water channel

along with diversion

Resolved

55 17-09-15 Farooq Ahmad RD 216 PC

Upper

A lot of trees in diversion will it

out

Contact the forest department

for tree cutting

56 07-10-15 TajDeen RD 354 PC

Upper

Disturbing private land during

diversion construction

Resolved

57 11-10-15 Sajid Ali RD 354 PC

Upper

Dust issue creating problem to

local farmers

Resolved

58 02-10-15 Ali Raza RD 286 PC

Upper

Local labor disturbs the fields of

farmers using short cuts

59 22-10-15 SughranBibi Camp Burewala Provide free hepatitis medicine Pending

60 27-10-15 NasreenBegaum Camp Burewala Guards at gate not behaving

good

Resolved

61 12-10-15 Ramzan Camp

Pakpattan

Floor Cleaner not properly doing

cleaning.

Resolved