    Industry Assessment for

    Solar Energy Market

  • 8/7/2019 Solar Energy Industry Assessment

    2/18

    www.efficientcarbon.wordpress.com

    Phone: +91 [email protected]

    efficientcarbon, All rights reserved

    A basic introduction to theindustry...

    http://www.efficientcarbon.wordpress.com/mailto:[email protected]:[email protected]://www.efficientcarbon.wordpress.com/
  • 8/7/2019 Solar Energy Industry Assessment

    3/18

    www.efficientcarbon.com

    Phone: +91 [email protected]

    efficientcarbon, All rights reserved

    Solar TechnologiesThere are two primary ways of using Solar Energy for different applications

    Solar

    Technologies

    SolarPhotovoltaic

    (SPV)

    PowerGeneration

    Lighting

    Water Pumping

    Solar Thermal

    (CSP)

    Cooking

    Water Heating

    Energy Source Technology Selective Applications

    http://www.efficientcarbon.wordpress.com/mailto:[email protected]:[email protected]://www.efficientcarbon.wordpress.com/
  • 8/7/2019 Solar Energy Industry Assessment

    4/18

    www.efficientcarbon.com

    Phone: +91 [email protected]

    efficientcarbon, All rights reserved

    Industry is pursuing a host of promising

    technologies in Photovoltaics...

    Concentrated

    Photovoltaic

    Ground

    Mounted

    Roof

    Mounted

    Market

    Thin Films

    Amorphous

    Silicon

    Material

    CdTE/

    CIGS Organic

    Crystalline Silicon

    Mono-

    Crystalline

    Multi-

    Crystalline

    Structure

    Setting up a solar PV manufacturing unit can cost around Rs 90 crores for a25MW capacity but the figure can vary depending on govt subsidies, locations,suppliers, etc.,

    http://www.efficientcarbon.wordpress.com/mailto:[email protected]:[email protected]://www.efficientcarbon.wordpress.com/
  • 8/7/2019 Solar Energy Industry Assessment

    5/18

    www.efficientcarbon.com

    Phone: +91 [email protected]

    efficientcarbon, All rights reserved

    ...and in Concentrated Solar Power (CSP)

    Trough Tower Linear Fresnel Dishes

    http://www.efficientcarbon.wordpress.com/mailto:[email protected]:[email protected]://www.efficientcarbon.wordpress.com/
  • 8/7/2019 Solar Energy Industry Assessment

    6/18

  • 8/7/2019 Solar Energy Industry Assessment

    7/18

    www.efficientcarbon.com

    Phone: +91 [email protected]

    efficientcarbon, All rights reserved

    Classifying various applications

    Solar PV System Size

    Small Systems (1MW)

    SystemT

    yp

    e

    Roof topRural Off grid lighting, Urban

    and Residential

    Urban residential,

    Commercial,

    Industrial applications

    Grid Connected Plants

    Ground BasedRural Off grid lighting, Urban

    and Residential

    Village Electrification,

    Industrial applications

    Industrial applications,

    Grid

    connected Plants

    Near ApplicationIrrigation pumps, Public area

    applications

    Cell Towers

    Typical rule of thumb for Solar installations other than at utility scale is Rs. 3 Lakhs fora 1 KW system. This can vary by (+/- ) 25% depending on the margins, sourcing ofpanels, scale, etc.,

    http://www.efficientcarbon.wordpress.com/mailto:[email protected]:[email protected]://www.efficientcarbon.wordpress.com/
  • 8/7/2019 Solar Energy Industry Assessment

    8/18

    www.efficientcarbon.com

    Phone: +91 [email protected]

    efficientcarbon, All rights reserved

    The Indian scenario The entire public policy on Solar for India is dictated by the Jawaharlal

    Nehru National Solar Mission launched in 2009.

    It talks about achieving 20,000MW of energy generation through Solarin three phases:

    1000 MW by 2013

    Additional 3000 MW by 2017

    Finally reach 20,000 MW by 2022

    For this to become a reality, significant investments to the tune of Rs.250 billion are required over the next 2-3 years.

    In January 2011, NVVN (NTPC Vidut Vyapar Nigam Ltd) selected 37companies to set up solar power projects to the tune of 704 MW forphase 1 of JNNSM.

    Rajasthan accounts for 81% or 571MW of the entire capacity above.Rajasthan, Gujarat and AP are now the favoured destinations of projectdevelopers.

    http://www.efficientcarbon.wordpress.com/mailto:[email protected]:[email protected]://www.efficientcarbon.wordpress.com/
  • 8/7/2019 Solar Energy Industry Assessment

    9/18

    www.efficientcarbon.com

    Phone: +91 [email protected]

    efficientcarbon, All rights reserved

    The Indian scenario Prices paid by the grid for such projects typically range from

    18.45/KWH to 10.95/KWH for Photovoltaic generation based onbidding.

    On another scale Rooftop Solar projects, both feeding into the gridtype and off grid type have huge potential.

    Part of JN National Solar Mission with objectives 10 MW Kitty Size as of now

    Individuals 1 KW array size

    Organizations 100 KW array size

    Central Financial assistance of INR 75 per Wp for battery less and

    INR 90 per Wp for battery based systems.

    Off grid applications too hold huge potential because of around1lakh villages without electricity. Need a good model in this area.

    http://www.efficientcarbon.wordpress.com/mailto:[email protected]:[email protected]://www.efficientcarbon.wordpress.com/
  • 8/7/2019 Solar Energy Industry Assessment

    10/18

    www.efficientcarbon.com

    Phone: +91 [email protected]

    efficientcarbon, All rights reserved

    Typical finances of a 1MW PV plant Energy Generation: 1.5 Million KWH/MWp /year

    PPA Rate: Rs. 18.45 / KWH 25 years

    1st year Revenue/MW: Rs 2.76 Cr

    Subsequent 25 years as per module degradation rate

    Capital Cost: Rs.13.5 Cr + Land= Rs.14 cr Appr

    70:30 D/E Ratio assumed Debt component: Rs.11.9 Cr

    Terms 11.5%, 10 years with 1 year moratorium

    Interest 1st year: Rs. 1.37 Cr

    O&M / Misc: 12 Lacs typically

    Margin After Tax: 20%

    General RoE ranges from 18 to 20% based on moratorium, CER, interest,transmission line etc

    http://www.efficientcarbon.wordpress.com/mailto:[email protected]:[email protected]://www.efficientcarbon.wordpress.com/
  • 8/7/2019 Solar Energy Industry Assessment

    11/18

    www.efficientcarbon.com

    Phone: +91 [email protected]

    efficientcarbon, All rights reserved

    Financing the projects

    Institutions are ready to fund projects that show a good returns and that arebacked by sound companies with experience in delivering large projects ontime and satisfactorily.

    Project

    Financing

    Commercial

    Banks

    International

    development

    banks / agencies

    IREDA, NABARD,

    NHB, SIDBI, etc.,Public Markets

    Govt lending /

    subsidies

    Internal reservesPrivate Equity /

    VCs / Angels

    PFC and other FIsFIIs

    http://www.efficientcarbon.wordpress.com/mailto:[email protected]:[email protected]://www.efficientcarbon.wordpress.com/
  • 8/7/2019 Solar Energy Industry Assessment

    12/18

    www.efficientcarbon.com

    Phone: +91 [email protected]

    efficientcarbon, All rights reserved

    Factors for Success through Execution Excellence

    Project Management Knowledge of Indian conditions

    Land acquisition and development EPC Contracting

    Tax / Duty implications

    Cost Control / Local Contracting

    On Time Delivery

    EPC Monitoring Long lead time Items

    Inverter and Cable Trenching

    Handling and Logistics

    Commissioning Plans

    Performance Site Survey and Analysis

    Civil / Structural Design

    Optimized Array Configuration

    Power Output / Monitoring

    http://www.efficientcarbon.wordpress.com/mailto:[email protected]:[email protected]://www.efficientcarbon.wordpress.com/
  • 8/7/2019 Solar Energy Industry Assessment

    13/18

    www.efficientcarbon.com

    Phone: +91 [email protected]

    efficientcarbon, All rights reserved

    The Key Dynamics

    POLICY CUSTOMERS

    EXECUTION EXCELLENCE

    FINANCING

    TECHNOLOGY

    Typically we see good policies, project plans and funding plans given but theexecution on the ground is delayed due to host of issues like land acquisitions,financial planning, technology issues etc.,.

    http://www.efficientcarbon.wordpress.com/mailto:[email protected]:[email protected]://www.efficientcarbon.wordpress.com/
  • 8/7/2019 Solar Energy Industry Assessment

    14/18

    www.efficientcarbon.wordpress.com

    Phone: +91 [email protected]

    efficientcarbon, All rights reserved

    How can we help you in thismarket?EfficientCarbon can provide you with comprehensive research on the SolarIndustry in India and give you its understanding, expertise and contacts tohelp you flourish in this industry. We would start by typically answering thefollowing questions

    http://www.efficientcarbon.wordpress.com/mailto:[email protected]:[email protected]://www.efficientcarbon.wordpress.com/
  • 8/7/2019 Solar Energy Industry Assessment

    15/18

    www.efficientcarbon.com

    Phone: +91 [email protected]

    efficientcarbon, All rights reserved

    Questions to Answer Is this the best time to enter the Solar market in India?

    If so, what is the core business model (mfg, trading, EPC, anciliary, etc.,)

    What should you consider before you make a foray? Capital and Operating Costs

    Locations

    Technology

    Govt Policies

    The National Solar Mission

    Who are the already existing players and what is their might?

    Competition analysis

    Alternate, substitute technologies

    What are the detailed costs and returns?

    Capital costs

    Operational costs

    Financial modelling

    Financing options

    What are the govt policies regulating the solar industry?

    http://www.efficientcarbon.wordpress.com/mailto:[email protected]:[email protected]://www.efficientcarbon.wordpress.com/
  • 8/7/2019 Solar Energy Industry Assessment

    16/18

    www.efficientcarbon.com

    Phone: +91 [email protected]

    efficientcarbon, All rights reserved

    Questions to Answer What should I consider while preparing Pre-Feasibility and Feasibility

    reports?

    What are the product/project development stages? Who and where are the suppliers?

    Raw materials

    International trade policies, etc.,

    What are the entire gamut of opportunities available in the ancillary

    industries supporting the Solar Industry?

    EPC

    Inverters

    Batteries

    Tracking systems

    Lighting,

    Servicing, etc.,

    EfficientCarbon would help you answer these questions through primary andsecondary research and put you in direct presence of collaborators, fundingsources, existing players in the market, to help you make more informeddecisions etc.,

    http://www.efficientcarbon.wordpress.com/mailto:[email protected]:[email protected]://www.efficientcarbon.wordpress.com/
  • 8/7/2019 Solar Energy Industry Assessment

    17/18

  • 8/7/2019 Solar Energy Industry Assessment

    18/18

    www.efficientcarbon.com

    Phone: +91 [email protected]

    efficientcarbon All rights reserved

    Thank You

    "Sustainability is not only absolutely necessary considering the situation our

    planet is in, we as companies are also overdue to take responsibility. We

    can't wait for governments. Companies have to lead the way

    - Jochen Zeitz, CEO, Puma

    http://www.efficientcarbon.wordpress.com/mailto:[email protected]:[email protected]://www.efficientcarbon.wordpress.com/