sri: green power development and energy efficiency
TRANSCRIPT
Social Safeguard Monitoring Report
July 2020
SRI: Green Power Development and Energy
Efficiency Improvement Investment Programme
(Tranche 2)
Prepared by Ceylon Electricity Board for the Asian Development Bank. This social safeguard monitoring report is a document of the borrower. The views expressed
herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and
may be preliminary in nature. Your attention is directed to the “terms of use” section of this website.
In preparing any country program or strategy, financing any project, or by making any designation
of or reference to a particular territory or geographic area in this document, the Asian
Development Bank does not intend to make any judgments as to the legal or other status of any
territory or area.
1
Semi- annual Social Safeguard Progress Report ADB Loan 3483/3484 SRI
Reporting Period {July 01, 2019 to December 31, 2019}
Date {February 15, 2020}
SRI: Green Power Development and Energy Efficiency Improvement Investment Programme
(Tranche 2)
Prepared by the Ceylon Electricity Board for the Asian Development Bank
2
ADB – Asian Development Bank
CCD – Coast Conservation Department
CEA – Central Environment Authority, Government of Sri Lanka
CEB – Ceylon Electricity Board
DC or D/C – Double Circuit
DPR – Detailed Project Report
DSD – Divisional Secretariat Divisions
EA – Executing Agency
EARF – Environmental Assessment and Review Framework
EIA – Environmental Impact Assessment
EMOP – Environmental Monitoring Plan
EMP – Environmental Management Plan
EHV – Extra High Voltage
GHG – Green House Gas
GND – Gram Niladhari Divisions
GOSL – Government of Sri Lanka
GRC – Grievance Redress Committee
GRM – Grievance Redress Mechanism
IA – Implementing Agency
IEE – Initial Environmental Examination
LILO – Line – in- Line- out
MFF – Multi-tranche Financing Facility
MOPE – Ministry of Power and Energy. Government of Sri Lanka
PAA – Project Approving Authority
PCB – Poly Chlorinated Biphenyl
PMU – Project Management Unit
REA – Rapid Environment Assessment
ROW – Right of Way
RP – Resettlement Plan
SC or S/C – Single Circuit
SF6 – Sulphur Hexafluoride
SPS
GPD&EEIIP1-2
–
–
Safeguard Policy Statement
Green Power Development & Energy Efficiency Improvement Investment Programme (Tranche 1) Part 2
3
Table of Contents
1 INTRODUCTION ............................................................................................................................. 4
1.1 Project Background .................................................................................................................. 4
2 PROJECT STATUS ......................................................................................................................... 9
2.1 Present Status of these Transmission Infrastructure Development ........................................... 9
2.2 Project Progress Status and Implementation Schedule ...........................................................12
3 RESETTLEMENT AND COMPENSATION PROGRESS ................................................................18
3.1 Package 1: Lot B ...................................................................... Error! Bookmark not defined.
3.2 Package 2: Lot A ...................................................................... Error! Bookmark not defined.
3.3 Package 2: Lot B1 .................................................................... Error! Bookmark not defined.
3.4 Package 3: Lot A1, Lot A2 and Lot B .......................................................................................18
3.5 Package 04: ...........................................................................................................................18
3.6 Package 05 : ..........................................................................................................................18
4 COMPLAINTS AND GRIEVANCE REDRESS ................................................................................19
4.1 Status of the Grievance Redress Mechanism ..........................................................................19
4.2 Summary of complaint status ..................................................................................................19
5 CONSULTATION AND PARTICIPATION .......................................................................................21
5.1 Public consultation activities ....................................................................................................21
6 CONCLUSION AND FUTURE PLAN .............................................................................................21
6.1 Plans for next monitoring period ................................................ Error! Bookmark not defined.
6.2 Conclusion ..............................................................................................................................23
7 ANNEXES ......................................................................................................................................23
4
1 INTRODUCTION
This document is the Social Safeguards Monitoring Report for the period July 01 2018, through
December 31, 2018 for the Green Power Development and Energy Efficiency Improvement Investment
Programme - Tranche 2. Tranche 2, consists of three components, namely, Transmission infrastructure
enhancement under Package 1, 2 & 3, Efficiency improvement of medium voltage network under
Package 4 & 5 and Demand-side management improvement for energy efficiency under Package 6 & 7.
All the provinces in Sri Lanka excluding Uva Province will be directly benefitted by the implementation of
transmission, distribution and demand side management components of this program.
The total investment cost of the Tranche 2 is USD 260 million. ADB will provide USD 150 million while
AFD will provide USD 30 million as a loan directly to Ceylon Electricity Board (CEB) under a treasury
guarantee. The loan agreement between ADB & CEB was signed on 27th December 2016. The
executing and implementing agency for above packages are Ministry of Power, Energy and Business
Development & Ceylon Electricity Board respectively.
Social Safeguard aspects of each package of the Project is described below.
1.1 Project Background
1.1.1 Package 1: Lot A - Construction of Hambantota 220/132kV Grid Substation & Augmentation
of 132/33 kV Hambantota Grid Substation & Lot B - Construction of New Polpitiya -
Hambantota 220kV Transmission Line – 150km
The Southern Province demonstrates visibly the Sri Lankan government’s efforts to develop regional
economies. The new port and new airport in Hambantota offer significant opportunities in diverse
business areas, including cargo and shipping, tourism and the service sector. No major power plant
developments have been identified in Southern Province until year 2024 and therefore it finds difficulty
to provide quality and reliable power supply from existing 132kV network. Further, when the
Samanalaweva power station is not in operation, the system reliability in southern province area is not
guaranteed under contingency situation.
To mitigate above issue Long Term Transmission Development Plan 2013-2022 has identified 220kV
transmission connection to Hambantota from New Polpitiya. This will operate as a transmission high
way to flow hydro power generated at Mahaweli complex and Laxapana complex to southern load
center and hence facilitate to provide quality and reliable power supply to Southern Province.
5
Construction of New Polpitiya-Hambantota 220kV transmission line and Hambantota 220/132kV Grid
Substation and Augmentation of 132/33 kV Hambantota Grid Substation are a part of this development.
According to the year 2017 transmission network, over loading of Pannipitiya-Panadura 132kV
transmission line and severe voltage drops at Embilipitiya, Hambantota, Matara, Beliatta, Galle,
Deniyaya grid substations can be observed without the proposed New Polpitiya-Hambantota 220kV
transmission line. So, the proposed line is at the highest priority to improve the reliability and voltage
profile of the Southern network.
1.1.2 Package 2: Lot B1 Construction of Mannar – Nadukuda 220kV Transmission Line & Lot A
Construction of Nadukuda 220/33 kV Grid Substation & Augmentation at Mannar 220/33kV
Grid Substation
In the efforts to harness renewable energy in the country, wind has been identified as a source of
significant potential to generate electricity. Studies carried out by both local and international experts
envisaged that 375 MW of wind capacity with 35~45% plant factor could easily be developed in the
Mannar island. Accordingly, the Generation and Transmission planning branch of CEB has planned to
set up a 220/33kV GSS at Nadukuda in the Manna Island and a 220kV transmission line from
Nadukuda to Mannar in order to evacuate the wind power generation in the Mannar Island.
Accordingly, a PMU has been established to construct a 100MW Wind Power plant and a separate
PMU to construct the transmission infrastructure, under the Green Power Development and Energy
Efficiency Improvement Program (Tranche II) which is funded by ADB.
Construction of Nadukuda GSS and Mannar Nadukuda Transmission are the important component of
the project scope of the Green Power Development and Energy Efficiency Improvement Investment
Program (Tranche II). This project component has an estimated cost of 36 MUSD.
Under this project component, it is proposed; (1) to construct 220/33kV Grid Substation (GSS) at
Nadukuda in Mannar island and the augmentation of Mannar GSS. This GSS will be able to absorb
entire 375 MW of wind power. However, at this stage only 2 X 63MVA capacity transformers will be
installed with the provision to install further 4 X 63MVA transformers in the future. (2) to construct a
30km of 220kV transmission line from Nadukuda GSS to the Mannar GSS. The Nadukuda GSS will
interconnect the clusters of wind plants at 33kV level and transmit the power & energy to Mannar Grid
Substation via the 30km long 220kV transmission Line.
6
1.1.3 Package 2: Lot B2 Horana - Padukka 132kV, 25km Transmission Line and 2nd Circuit
Stringing of Habarana - Valachchenai 132 kV Transmission Line
Present Southern Transmission network is mainly fed through New Laxapana Balangoda, Pannipitiya-
Panadura and Samanalawewa-Embilipitiya 132 kV Transmission lines. An outage in one of the circuits
of Pannipitiya-Panadura transmission line or New Laxapana Balangoda transmission line may cause
tripping of other circuit also. This may cause low voltages in the southern network as well. The proposed
Padukka-Horana 132 kV transmission line will provide an additional path of power flow to the Southern
Transmission Network and will improve the reliability of Southern Network. With the proposed Padukka-
Horana 132 kV, loading of existing 132 kV lines is reduced and it reduces the losses of the transmission
network.
At present Valachchenai 61.5 MVA 132/33 kV grid substation is connected to the national grid by two
single circuit 132 kV transmission lines from Habarana grid substation. One transmission line is of Lynx
conductor and built in 1995 and this line can transfer only 88 MVA. The new transmission line is a Zebra
conductor line and is commissioned in 2014 and it can handle up to 145 MVA. The new line is a double
circuit transmission line with only one circuit strung and it connects the Polonnaruwa 63 MVA grid
substation. By 2018, Valachchenai grid substation will handle a capacity of 63 MVA. In case of a tripping
of Habarana-Polonnaruwa section of the new transmission line, the total grid capacity will flow through
the old single circuit transmission line, which will cause to overload and trip the line. In such a case both
Polonnaruwa and Valachchenai grid substations will be isolated from the system. This leads to supply
failure of 20% of North Central province and 17% of Eastern province load. To avoid such a situation
and to improve the quality and reliability of the electricity supply in Eastern and North Central provinces
it is proposed to string the second circuit of the 132 kV zebra transmission line from Habarana grid
substation to Valachchenai grid substation.
1.1.4 Package 3: Lot A1 Construction of Colombo B GSS, Single In & Out connection from
Colombo C-Kolonnawa 132kV 800sqmm Cable & Augmentation of Colombo C &
Kolonnawa GSS
At Present Colombo B is a 33/11kV substation, which feeds Colombo 11 region. The main Harbor of the
country and many other commercial centers are location in this region. According to the statistical data
the anticipated load growth rate of the area is 5.1%. Several major loads are to be added in the near
future and the existing Colombo B Substation cannot cater for the expected demand increase in the
area. In addition, part of the loads connected to Colombo F GS needs to be transferred to Colombo B
GS in order to avoid overloading in future. Further, there are only two 33kV feeders available at
Colombo B GS at present and these feeders are about 50 years old and frequent failures are occurred
in the cables. The 132kV power cables required for the proposed substation will be laid under the
7
Colombo City Electricity Distribution Development Project, hence only the upgrading of substation is
required.
1.1.5 Package 3: Lot A2 Augmentation of Kotugoda,Kolonnawa ,Padukka,Horana,Dehiwala &
Madampe GSS
It has been proposed to Augment Kotugoda, Kolonnawa, Horana, Padukka, Madampe and Dehiwala to
improve the quality and reliability of the electricity supply while avoiding of overloading the grids and
meet the growing electricity demand.
1.1.6 Package 3: Lot B Construction of Biyagama 220/33kV GSS & Augmentation of Biyagama
GSS
According to the demand forecast giving in Long Term transmission development plan 2015-2024, the
existing 220/33KV transformer capacity of Biyagama interbus transformer is not adequate to cater the
growing demand of Biyagama area, Which has a larger BOI Zone. According to the transmission
system studies carried out for the year 2018, 220/33KV winding of the interbus transformer overloads
8% of the contingency rating during night peak loading conditions. Thus, it is important to construct a
new 220/33KV GSS at existing Biyagama switching station premises to cater the growing electricity
demand in Biyagama area.
1.1.7 Package 04 & Package 05: Medium Voltage Sub Projects
The demand for electricity in Sri Lanka is growing at a rate of about 5-6% per annum. The generating
sources and transmission and distribution facilities have to be developed and strengthened in order to
meet this growth in demand.
Medium Voltage Distribution System is the backbone of the power distribution network and it is the
interface between the Transmission network and the LV Distribution network which provide supply to
the consumers. It is therefore essential to reinforce and develop a healthy Distribution System which
has the capability of catering the growing electricity demand of the country while maintaining an
acceptable reliability and quality above the set operational standards and norms.
The MV Development studies are carried out by Distribution Planning Branches of CEB within the
planning horizon of 10 years as a rolling plan in order to forecast future power demand and to formulate
distribution development proposals to ensure reliable and safe electricity distribution at optimal cost.
8
Outcome of the above studies emphasized the urgency of constructing the distribution system facilities
outlined in this project proposal.
Package 04: 33kV Lines & Gantries
Under this project component, it is planned to,
1. Construct 33 kV 23 km (revised 22km) DC Lynx Tower line from Anuradhapura GSS to
Mahailluppallama Gantry
2. Construct 33kV 4 km DC Lynx Tower line from Storefield Gantry to Ethgala Gantry
3. Construct 33kV 8 km 4cct Lynx Tower line from Kappalthurai GSS to Chinabay Gantry.
4. Construct 33kV 11 km (revised 10.5km) DC Lynx Tower lines from Embilipitiya GSS to Weniwelara.
5. Construct 33kV 14 km (revised 11.5km) DC Lynx Tower line from Matugama GSS to Bentota PSS
6. Construct Two Section Single Busbar Gantry at Mahailuppallama
7. Construct Two Section Single Busbar Gantry at Ethgala
8. Construct Two Section Single Busbar Gantry (revised to Double Busbar) at China Bay
9. Construct Two Section Single Busbar Gantry at Weniwelara (revised to Sooriyawawa)
Package 05: Primary Substations
Under this project component (Package 05), it is planned to,
1. Design, Supply and Augmentation of 2x10 MVA Manned Primary Substation to 2x16 MVA GIS
Manned Primary Substation at Ethulkotte
2. Design, Supply and Augmentation of 2x5MVA + 2MVA Unmanned Primary Substation to 2x10 MVA
GIS Manned Primary Substation at Beligaha
3. Design, Supply and Installation of 2x10 MVA GIS Manned Primary Substation at Rattanapitiya
9
2 PROJECT STATUS
2.1 Present Status of these Transmission Infrastructure Development
2.1.1 Package 1
The Green Power Development & Energy Efficiency Improvement Investment Programme (Tranche 2)
Package 1 Transmission Infrastructure Capacity Enhancement Project, consists of following Lots with
the estimated costs:
Package Lot Project Total (MUSD)
1
Lot A Construction of Hambantota 220/132kV Grid Substation & Augmentation of 132/33 kV Hambantota Grid Substation
15.5
Lot B New Polpitiya-Hambantota 220kV, 150km Transmission Line
57.3
The contract details including the contract price of the following two lots under Package 1 are as follows.
Package 1: Lot A Package 1: Lot B
Scope Construction of Hambantota 220/132kV Grid Substation & Augmentation of 132/33 kV Hambantota Grid Substation
Construction of New Polpitiya-Hambantota 220kV,150km Transmission Line
Contractor Chint Electric Co., Ltd, China
China National Cable Engineering Corporation, China
Contract Price including change orders
USD 9,221,930.93 +
LKR 436,827,292.26
USD 32,311,798.62 +
LKR 808,290,584.14
Contract Effective Date
December 04, 2018 August 08, 2018
Expected Completion Date
December 02, 2020 January 23, 2021
10
2.1.2 Package 2
The Green Power Development & Energy Efficiency Improvement Investment Programme (Tranche 2)
Package 2 Transmission Infrastructure Capacity Enhancement Project, consists of following Lots with
the estimated costs:
Package Lot Project Total (MUSD)
2 Lot A Construction of Nadukuda 220/33 kV Grid Substation
23.1
Augmentation at Mannar 220/33kV Grid Substation
Lot B1
Mannar - Nadukuda 220kV, 30km transmission line
13.8
Lot B2
Padukka - Horana 132kV, 25km transmission line 7.6
2nd cct strinnging of Habarana-Valachchenai 132kV Transmission Line
The contract details including the contract price of the following two lots under Package 2 are as follows.
Package 2: Lot B1 Package 2: Lot A
Scope Construction of Mannar – Nadukuda 220kV Transmission
Line
Construction of Nadukuda 220/33 kV Grid Substation & Augmentation at Mannar
220/33kV Grid Substation.
Contractor KEC International Limited Siemens Limited, India.
Contract Price including change orders
Contract Amount
LKR 426,309,080.00 +USD 6,477,201.00 Change Order 01
LKR 8,240,000.00 +USD 88,638.00
Change Order 02
LKR 3,955,000.00 +USD 21,518.00
Contract Amount
LKR 932,903,081.57 +USD 11,901,167.32
Change Order 01
LKR 5,660,000.00 + USD 476,988.00
Contract Effective Date
October 04, 2017 March 16, 2018
Expected Completion Date
May 04, 2020
{extension of time has been granted as per the Change
Orders No 01 & No 02}
March 16, 2020
(an EOT requested by the Contractor is under process)
11
Package 2: Lot B2 A Package 2: Lot B2 B
Scope Construction of Horana-Padukka 132 kV, 25km Transmission Line
2nd circuit stringing of Habarana-Valachchenai 132 kV Transmission
Line
Contractor China National Electric Engineering Co., Ltd
China National Electric Engineering Co., Ltd
Contract Price including change orders
Contract Amount
USD 3,788,201.13
Contract Amount
USD 3,208,816.79
Contract Effective Date
To be finalized November 28,2019
Expected Completion Date
To be finalized November 17, 2021
2.1.3 Package 3
The Green Power Development & Energy Efficiency Improvement Investment Programme (Tranche 2)
Package 3 consists of following Lots with the estimated costs:
Package Lot Project Total (MUSD)
3 Lot A1 Construction of Colombo B GSS, Single In & Out connection from Colombo C-Kolonnawa 132kV 800sqmm Cable & Augmentation of Colombo C & Kolonnawa GSS
8.16
Lot A2 Augmentation of Kotugoda, Kolonnawa, Padukka ,Horana, Dehiwala & Madampe GSS
14.25
+ 0.44
Lot B Construction of Biyagama 220/33kV GSS & Augmentation of Biyagama GSS
9.28
The contract details including the contract price of the following three lots under Package 3 are as
follows.
Package 3: Lot A1 Package 3: Lot A 2 Package 3: Lot B
Scope Construction of Colombo B GSS, Single In & Out connection from
Colombo C-Kolonnawa 132kV 800sqmm Cable & Augmentation of
Colombo C & Kolonnawa GSS
Augmentation of Kotugoda,Kolonnawa
,Padukka,Horana,
Dehiwala & Madampe GSS
Construction of Biyagama 220/33kV
GSS & Augmentation of Biyagama GSS
12
Contractor Hyosung Heavy Industries
Cooperation
ABB India Limited.
ABB India Limited.
Contract Price including change orders (Equivalent MLKR)
1,260.8 2,214.2+ 78.77
1434.12
Contract Effective Date
October 15, 2019 October 22, 2018 November 14, 2018
Expected Completion Date
October 14, 2021 October 21, 2020 November 13, 2020
2.1.4 Package 4 and 5
The estimated costs of the Green Power Development & Energy Efficiency Improvement Investment
Programme (Tranche 2) - Package 4 & 5 are as follows.
Package Project Total (MUSD)
4 Construction of 05 Nos. of 33 kV Tower Lines and 04 Nos. of Gantries
14.8
5 Augmentation of 02 Nos. of Primary Substations and Construction of 01 No. of Primary Substation
10.4
The contract details including the contract price of Package 4 are as follows.
Package 4:
Scope Construction of 5 Nos of 33kV Tower lines & 04 Nos of 33kV Gantries
Contractor Ceylex Engineering (Pvt) Ltd
Contract Price including change orders (Equivalent MLKR)
2979.5 MLKR*
Contract Effective Date Dec 03 , 2019
Expected Completion Date Dec 02 , 2021
*selling exchange rate of 3rd May 2018 (Tec. Bid opening date) : 1USD = 159.0357 LKR
13
The contract details including the contract price of Package 5 are as follows.
Package 5:
Scope Construction/Augmentation of 3 Nos of Primary Substations
Contractor Siemens Ltd India consortium with DIMO (pvt) Ltd Sri Lanka
Contract Price including change orders (Equivalent MLKR)
1578.5 MLKR
Contract Effective Date Not yet finalized
Expected Completion Date N/A
*selling exchange rate of 6th Feb 2019(Tec. Bid opening date) : 1USD = 179.9798 LKR
2.2 Project Progress Status and Implementation Schedule
2.2.1 Progress Status of Package 1: Lot A Construction of Hambantota 220/132kV Grid
Substation & Augmentation of 132/33 kV Hambantota Grid Substation
The updated status of project activities during the period of July, 2019 to December, 2019 is given
below for the Grid Substation.
Description Affected Area Status Plan
Lot A
Construction of Hambantota 220/132kV Grid Substation & Augmentation of 132/33kV Hambantota Grid Substation
CEB obtained 3-hectare land from UDA on 30 Years Long Term Lease
Design Works – 58% Completed Sep - 2020
Procurement – 35% Completed Aug - 2020
Civil Work - 19.5% Completed Oct - 2020
2.2.2 Progress Status of the Package 1: Lot B Construction of New Polpitiya-Hambantota
220kV, 150km Transmission Line
The updated status of project activities during the period of July, 2019 to December 2019 is given
below for the transmission line.
Description Affected Area
Status Plan
Lot B : Construction of New Polpitiya Hambantota 220kV, 150km
150 km
Width of RoW 35m
1. Design & survey works have been completed to 92% December 2020
2. Material Procurement is in progress and 60% is completed.
May 2020
3. Progress of construction is 12% Jan 2021
14
Transmission Line
Construction of tower foundations was started in June, 2019 and 95 nos. have been completed by end of this reporting period.
2.2.3 Progress Status of Package 2: Lot A Construction of Nadukuda 220/33 kV Grid Substation
& Augmentation at Mannar 220/33kV Grid Substation
The updated status of project activities during the period of July, 2019 to December 2019 is
given below for the Grid Substation.
Description Affected Area
Status Plan
2A
Construction of Nadukuda 220/33 kV Grid Substation & Augmentation at Mannar 220/33kV Grid Substation
7Acre Land is belongs to CEB
1. Designs works were completed up to 90% Mar 2020
2. Equipment Procurement are in progress Mar 2020
3 Engineers accommodation Completed & Control Room Building is in progress
Mar 2020
4. Equipment Erection March 2020
Note: Refer Annex 1 for detail schedule
2.2.4 Progress Status of the Package 2: Lot B1 Construction of Mannar – Nadukuda 220kV
Transmission Line
The updated status of project activities during the period of July, 2019 to December 2019 is
given below for the Transmission Line.
Description Affected Area
Status Plan
2B1
Mannar - Nadukuda 220kV, 30km transmission line
30km of
Width of 35 m
1. Profile & Tower designs were completed. October 2018
2. 95% of Equipment Procurement is completed Mar 2020
3. Erection of towers are in progress 76 completed
Mar 2020
4. 80 foundations were completed Mar 2020
Note: Refer Annex 2 for detail schedule
2.2.5 Progress Status of Package 2: Lot B2 Padukka-Horana 132kV,25km Transmission Line
and 2nd Circuit Stringing of Habarana-Valachchenai 132 kV Transmission Line
The updated status of project activities during the period of July, 2019 to December 2019 is
given below for the Transmission Line.
15
Description Affected Area
Status Plan
2B2 A
Construction of Horana-Padukka 132kV,25km Transmission Line
25km
Width of RoW
27m
1. 10% Advance payment was released and LC was established
2B2 B
2nd circuit stringing of Habarana-Valachchenai 132 kV,100km Transmission Line
-
1. 10% Advance payment was released and LC was established
2. Commencement date for the 2nd circuit stringing of Habarana-Valachchenai 132 kV Transmission Line was established on Nov 28, 2019.
3. Design works are in progress. May 2020
2.2.6 Progress Status of Package 3: Lot A1, Lot A2 and Lot B
The updated status of project activities during the period of July, 2019 to December 2019 is
given below.
Description Affected Area
Status Plan
3A1 : Construction of Colombo B GSS, Single In & Out connection from Colombo C-Kolonnawa 132kV 800sqmm Cable & Augmentation of Colombo C & Kolonnawa GSS
These are within CEB’s premises.
Design And Engineering – 1%
Feb 2021
Procurement and Delivery –0 %
April 2021
Civil Works –3 % October 2021
Physical Progress -4% October 2021
3A2: Augmentation of Kotugoda, Kolonnawa,Padukka, Horana, Dehiwala & Madampe GSS
These are within CEB’s premises.
Design And Engineering – 85.31%
Feb 2020
Procurement and Delivery – 51.44%
May 2020
Civil Works – 23.37% Dec 2020
Physical Progress -34.04%
October 2020
3B: Construction of Biyagama 220/33kV GSS & Augmentation of Biyagama GSS
These are within CEB’s premises.
Design And Engineering - 86.05%
January 2020
Procurement and Delivery –50.15%
April 2020
Civil Works – 12.2% November
16
Switchyard cut and filling completed. Cable trench excavation & concrete wall works in progress. Control Room Building excavation & shoring works is in progress.
2020
Physical progress – 31%
2.2.7 Progress Status of Package 04: 33kV Lines & Gantries
Progress summary of the contract is as follows:
Contract was effective from 03rd Dec. 2019
Description Affected area Status Plan
1. i)33 kV 22 km DC Lynx Tower line from Anuradhapura GSS to Mahailluppallama Gantry
ii) Two Section Single Busbar Gantry at Mahailuppallama
22km, 15m RoW
0.039 ha of government owned land to be used
Design progress : 85.0 %
Procurement process : 10.5 %
Civil work : 5.0 %
Installation : 0.0 %
April 2020 Feb 2021 Jan 2021
Aug 2021
2. i)33kV 4 km DC Lynx Tower line from Storefield Gantry to Ethgala Gantry
ii) Two Section Single Busbar Gantry at Ethgala
4 km, 15m RoW
0.042 ha of private owned land was purchased.
Design progress : 59.5 %
Procurement process : 10.5 %
Civil work : 0.0 %
Installation : 0.0 %
April 2020 Feb 2021 Dec 2020 July 2021
3. i)33kV 8 km 4cct Lynx Tower line from Kappalthurai GSS to Chinabay Gantry.
ii) Two Section Double Busbar Gantry at China Bay
8 km, 15m RoW
0.03 ha of government owned (Sri Lanka Port Authority)
Design progress : 59.5 %
Procurement process : 10.5 %
Civil work : 0.0 %
Installation : 0.0 %
April 2020 Feb 2021 Nov 2020 May 2021
4. i)33kV 10.5 km DC Lynx Tower lines from Embilipitiya GSS to Weniwelara Gantry
ii) Two Section Single Busbar Gantry at Sooriyawawa
10.5km, 15m RoW
0.05 ha of government owned land to be
Design progress : 59.5 %
Procurement process : 10.5 %
Civil work : 0.0 %
Installation : 0.0 %
April 2020 Feb 2021 April 2021 Sep 2021
17
used
5. 33kV 11.5 km DC Lynx Tower line from Matugama GSS to Bentota PSS
11.5km, 15m RoW
Design progress : 0.0 %
Procurement process : 10.5 %
Civil work : 0.0 %
Installation : 0.0 %
April 2020 Feb 2021 Nov 2020 May 2021
Total Summary
Activity Progress (% completion)
Design progress (weightage – 15%) 26.64 %
Procurement process (weightage – 20%) 10.50 %
Civil work (weightage – 30%) 2.00 %
Installation (weightage – 35%) 0.00 %
Total Progress 6.70 %
2.2.8 Progress Status of Package 05: Primary Substations
Progress summary of the contract is as follows:
Acceptance letter was send on 14th Nov 2019 to Siemens Ltd India consortium with DIMO (pvt) Ltd Sri Lanka. Contract Agreement yet to be signed.
Progress Status of the Land acquisition for the Package 5; Primary substations is as follows,
Description Affected area
Status Plan
1. Augmentation of PSS at Ethulkotte
Existing land area of 0.067 ha
Land acquisition not required. Augmentation to be done at the same land where the existing PSS.
Construction shall be started after contract agreement signing.
2. Augmentation of PSS at Beligaha
Existing land area of 0.127 ha
Land acquisition not required. Augmentation to be done at the same land where the existing PSS.
Construction shall be started after contract agreement signing.
3. Construction of PSS at Rattanapitiya
0.1161 ha to be acquired
Section 38 (a) of Land acquisition act was published on 02nd Aug. 2019 ( No 2134/57 – 2019)
Ownership of the Land was handed over to CEB on 05th September 2019.
Construction shall be started after contract agreement signing.
18
3 RESETTLEMENT AND COMPENSATION PROGRESS
3.1 Package 1: Lot B Construction of New Polpitiya-Hambantota 220kV, 150km Transmission
Line
Compensation payment for tree cutting is in progress and started in Deraniyagala, Rathnapura,
Balangoda, Imbulpe, Waligepola, Embilipitiya, Sewanagala, Sooriyawawa and Hambantota Divisional
Secretariats. The details of beneficiaries are listed & attached as Annex 1B-2. Further, no resettlement
is required for this project.
3.2 Package 2: Lot A Construction of Nadukuda 220/33 kV Grid Substation & Augmentation at
Mannar 220/33kV Grid Substation
7-acre private land has been purchased for this construction by CEB. Further no resettlement required for this project.
3.3 Package 2: Lot B1 Construction of Mannar – Nadukuda 220kV Transmission Line
The compensation for the wayleaves has been paid for almost all the effected parties. The details of
beneficiaries are listed. Further no resettlement required for this project.
3.4 Package 2 Lot B2 A
Compensation process is being in progress and no resettlement is required for this project.
3.5 Package 2 Lot B2 B
Compensation or resettlement is not required for this project as this was done in stage 01 of this project.
3.6 Package 3: Lot A1, Lot A2 and Lot B
As the project is carried out in CEB Grid Substations , no resettlement or compensation is required.
3.7 Package 04: 33kV Lines & Gantries
Way leave compensation was started from June 2018 onwards. The details of the beneficiaries from
01st July 2019 to 31st December 2019 are listed & attached as Annexure 3.
3.8 Package 05: Primary Substations
No resettlement / compensation for the reporting period.
19
4 COMPLAINTS AND GRIEVANCE REDRESS
CEB adopted a project specific Grievance Redress Mechanism (GRM) having suitable grievance
redress procedure to receive and facilitate resolution of affected peoples’ concerns, complaints, and
grievances about the social and environmental performance at subproject level. The GRM aims to
provide a time-bound and transparent mechanism to voice and resolve social and environmental
concerns linked to the project.
4.1 Status of the Grievance Redress Mechanism
4.1.1 Package 1: Lot B Construction of New Polpitiya-Hambantota 220kV, 150km Transmission
Line
All public grievances under this project has been considered at the Grievance Redress Meetings
conducted by the relevant Divisional Secretaries with the participation of project engineers from CEB
with the affected parties. In these meetings and site visits, public grievances are considered and
addressed.
4.1.2 Package 2: Lot B1 Construction of Mannar – Nadukuda 220kV Transmission Line
All public grievances under this project has been considered at the Grievance Redress Meeting held at
the District Secretary office handled by the Grievance Redress committee comprising Additional District
Secretary, Divisional Secretary Mannar & Project Engineer from CEB with the participation of the
affected parties. In this meeting all public grievances have been considered and resolved. Further,
based on the result the compensation has been paid by CEB.
During this period, NO Grievance have been recorded.
4.1.3 Package 2: Lot B2 A Construction of Horana- Padukka 132kV Transmission Line
All public grievances under this project has been considered at the Grievance Redress Meetings
conducted by the relevant Grama Niladhari officers with the participation of project engineers from CEB
with the affected parties. In these meetings and site visits, public grievances are considered and
addressed. Further meetings with Divisional Secretaries will be conducted in future.
4.1.4 Package 1: Lot B Construction of New Polpitiya-Hambantota 220kV, 150km Transmission
Line
Issues discussed Response DS Division
Villages requested to shift the line away at
Adavikanda area to avoid line traversing from
Line was shifted complying to the
villagers’ requirement.
Kuruwita
20
the middle of their lands
Villages requested to shift the line away at
Wilpita to protect water feeding area to the
downside villages
Transmission line was shifted to
avoid this water feeding area
accepting people’s need
Balangoda
Villages requested to shift the line to protect
their cultivation at Udagangoda
Transmission line was shifted
complying to their request
Waligepola
A technical issue was identified at the existing
132kV line crossing at Rathkarawwa
Line was shifted to a technically
and socially feasible route
Embilipitiya
Road Development Authority has requested to
avoid their reservation for Sooriyawewa
Highway interchange in constructing the
transmission line
CEB will shift the line in complying
to their request and is in progress
Sooriyawawa
Some adjacent land owners at Siripagama
request to shift the line to alternative routes
Under discussion with participation
of Divisional Secretary
Rathnapura
Some adjacent land owners at
Wijinathkumbura request to shift the line to
alternative routes
Under discussion with participation
of Divisional Secretary
Balangoda
A and owner objection at Deraniyagala Line route was deviated after
consultation of Divisional
Secretary, Deraniyagala
Deraniyagala
4.1.5 Package 2: Lot B1 Construction of Mannar – Nadukuda 220kV Transmission Line
Issues discussed Response
Public requested to shift the line away to Konnayan
Kudiyiruppu
Transmission line has been shifted away
to the particular village
Agriculture people requested to reduce the no of
towers in Korakulam tank
CEB will only install one tower at
Korakulam tank
Land owner requested to shift one tower away from his
land near Korakulam
Transmission line has been shifted away
to the particular land
4.1.6 Package 2: Lot B2 Construction of Horana – Padukka 132kV Transmission Line
Issues discussed Response DS Division
Public at Sri Rathana road (AP7-AP9)
requested to shift the line away.
The request was forwarded to
Divisional Secretary Homagama
Homagama
Land owner at requested to shift the line from The request to be forwarded to the Ingiriya
21
her land at AP 40 Divisional Secretary Ingiriya
The land owner requested to shift the line to
the border of the land at AP21-AP22
The request to be forwarded to the
Divisional Secretary Padukka
Padukka
4.1.7 Package 03: Grid Substations
No complains and grievances received yet.
4.1.8 Package 04: 33 kV Lines & Gantries
No grievances/objections received for the reporting period.
4.1.9 Package 05 : Primary Substations
No complains and grievances received yet.
5 CONSULTATION AND PARTICIPATION
5.1 Public consultation activities
5.1.1 Package 2: Lot B1 Construction of Mannar – Nadukuda 220kV Transmission Line
No public consultations were held for the reporting period.
6 CONCLUSION AND FUTURE PLAN
6.1 Plans for next monitoring period
6.1.1 Package 1: Lot A Construction of Hambantota 220/132kV Grid Substation & Augmentation
of 132/33 kV Hambantota Grid Substation
10% of the physical progress is expected.
6.1.2 Package 1: Lot B Construction of New Polpitiya-Hambantota 220kV, 150km Transmission
Line
65% of the physical progress is expected.
70% completion of compensation for tree cutting is projected.
6.1.3 Package 2: Lot B1 Construction of Mannar – Nadukuda 220kV Transmission Line
92% of the physical progress has to be completed.
22
6.1.4 Package 2: Lot A Construction of Nadukuda 220/33 kV Grid Substation & Augmentation at
Mannar 220/33kV Grid Substation
63% of the physical progress has to be completed including Control room building & Major civil works
6.1.5 Package 2: Lot B2 A Construction of Padukka-Horana 132kV,25km Transmission Line
Planning to mobilize in site and start preliminary survey works.
6.1.6 Package 2: Lot B2 B 2nd Circuit Stringing of Habarana-Valachchenai 132 kV Transmission
Line
Planning to conclude design works and initiate procurement of materials.
6.1.7 Package 3: Lot A1 Construction of Colombo B GSS, Single In & Out connection from
Colombo C-Kolonnawa 132kV 800sqmm Cable & Augmentation of Colombo C &
Kolonnawa GSS
Completion of 30% of the physical progress.
6.1.8 Package 3: Lot A2 Augmentation of Kotugoda,Kolonnawa ,Padukka,Horana,Dehiwala &
Madampe GSS
Completion of 88.76% of the physical progress.
6.1.9 Package 3: Lot B Construction of Biyagama 220/33kV GSS & Augmentation of Biyagama
GSS
Completion of 84.75% of the physical progress.
6.1.10 Package 4: 33 kV Lines & Gantries
46 % of overall physical progress is expected.
6.1.11 Package 5: Primary Substation
Contract commencement
Preliminary work, soil testing & Design work is expected to be completed within the next
reporting period.
23
6.2 Conclusion
Package 1: Lot B Construction of New Polpitiya-Hambantota 220kV, 150km Transmission Line
The project management team is of the view that the social concerns are well addressed and all
the stakeholders related on this regard are working together to complete the project successfully.
Further, the project management team is highly concerned about the site activities affected to
public associated to the transmission line and always carefully monitors construction works to
minimize if any. Further, the team is closely monitoring the job opportunities for the local people
living in the area and it is created openings by tree cutting, soil testing activities, survey activities,
concrete redymix supplying, foundation constructions, security services, driving light/heavy
vehicles and machinery, and etc either through the CEB or contractor. At the moment, about 100
people are involving on these opportunities and it is expected that this number will get increased
with future activities.
Package 2: Lot B1 Construction of Mannar – Nadukuda 220kV Transmission Line
The project management team is closely monitoring the job opportunities for the local peoples
living in Mannar region, so far more than 25 labours has been given job opportunities through the
contractor/ CEB for the construction works, clearing the site, laying boundary stones, and survey
helping from the local area.
Package 2: Lot B2 A Construction of Padukka-Horana 132kV,25km Transmission Line
Project management team is of the view that social concerns should be well addressed and
proper compensation has to be given affected parties, even considering the devaluation of their
land value.
Package 2: Lot B2 B 2nd Circuit Stringing of Habarana-Valachchenai 132 kV Transmission Line
Project management team is highly concerned about stringing works which is to be carried out in
hot line condition across some wild life area and expects support of Department of wild life and
Department of forest conservation to complete the project successfully.
7 ANNEXES
Annex 1 : Project Construction Schedule Package 2: Lot A Construction of Nadukuda 220/33 kV
Grid Substation & Augmentation at Mannar 220/33kV Grid Substation
Annex 2: Project Construction Schedule Package 2: Lot B1 Construction of Mannar – Nadukuda
220kV Transmission Line
24
Annex 3 - Details of the beneficiaries Package 4.
Annex 4 - Safeguard Due Diligence on ADB project (SRI) 47037-005
CLIENT : CEYLON ELECTRICITY BOARD, SRI LANKA CONTRACTOR : KEC INTERNATIONAL LTD.
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
QTY UNIT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY
A MOBILISATIONB SURVEY WORKS1 Route Alignment 30 Km
2 Detail Survey & Profile 30 Km
3 Check Survey & Pegging Out 30 KmC ENGINEERING & DESIGN1 Coductor 1 No.
2 Earthwire 1 No.
3 OPGW 1 No.
4 Insulator 1 No.
5 Hardware Fittings 1 No.
6 Tower Design 5 No.
7 Earthing Materials 1 No.
8 Tower Accessories 1 No.
9 Testing of Suspension Tower 1 No.
10 Testing of Angle Tower 1 No.
11 Soil Investigation 90 No
12 Foundation Design 90 NoC MANUFACTURING AND DELIVERY1 Conductor 384 Km
2 Earthwire 32 Km
3 Stubs & Towers 90 No
4 Insulator 18896 No.
5 OPGW & Fittings 30 Km
6 Hardware Fittings 90 Sets
7 Earthing Material 90 Sets
8 Tower Accessories 90 Sets
CONTRACT COMMENCEMENT DATE : 19th Oct'2017 REVISED COMPLETION DATE : 04th May'202
CONSTRUCTION OF MANNAR TO NADIKUDA 220KV D/C TRANSMISSION LINE UNDER GREEN POWER DEVELOPMENT NAD ENERGY EFFICIENCY IMPROVEMENT INVESTMENT PROGRAMME (TRANCHE‐2) PACKAGE 2 (LOT B1)
CONSTRUCTION SCHEDULE
YEAR ‐ 2019Sl No ActivityMonths YEAR ‐ 2017 YEAR ‐ 2018 YEAR'20
CLIENT : CEYLON ELECTRICITY BOARD, SRI LANKA CONTRACTOR : KEC INTERNATIONAL LTD.
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
QTY UNIT OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY
CONTRACT COMMENCEMENT DATE : 19th Oct'2017 REVISED COMPLETION DATE : 04th May'202
CONSTRUCTION OF MANNAR TO NADIKUDA 220KV D/C TRANSMISSION LINE UNDER GREEN POWER DEVELOPMENT NAD ENERGY EFFICIENCY IMPROVEMENT INVESTMENT PROGRAMME (TRANCHE‐2) PACKAGE 2 (LOT B1)
CONSTRUCTION SCHEDULE
YEAR ‐ 2019Sl No ActivityMonths YEAR ‐ 2017 YEAR ‐ 2018 YEAR'20
D CONSTRUCTION1 Tower Foundation & Earthing 66 No2 Tower Foundation & Earthing(Vankalai) 24 No2 Tower Erection 66 No
2 Tower Erection (Vankalai) 24 No
3 Stringing of Conductor & Earthwire 30 Km4 Stringing of OPGW 30 Km
5 Tower Accessories 90 No
6 Final Checking 90 NoE TESTING AND COMMISSIONINGF T.C.C
ID Task Name
1 CEB - 220/33kV GIS Substation at Nadukuda and Augmentation of 220kV AIS Substation at Mannar
2 Project 1: 220/33kV GIS SUBSTATION AT NADUKUDA
3 Handing Over of Encumbrance free Site with Access Road
4 Site Studies
15 Providing Services
18 Substation Engineering
93 Equipments: Design, Engineering, Procurement & Supply
230 Civil Works
289 Installation
304 Testing & Comissioning
315 Final Commissioning & Handover
316 Project 2 : AUGMENTATION OF 220kV AIS SUBSTATION AT MANNAR
317 Existing Substation Drawings and Details of Mannar SS from Customer
318 Handing over of Encumbrance free Site with Access Road
319 Engineering
369 Equipments Supply
483 Civil
501 INSTALLATION ,TESTING & COMMISSIONING
Mar 16 '18 Mar 14 '20
Mar 16 '18 Mar 14 '20
Mar 17 '18 Mar 17 '18
Feb 27 '20 Mar 14 '20
Mar 16 '18 Feb 15 '20
Mar 16 '18 Apr 19 '18
Mar 19 '18 Mar 19 '18
1/14 2/4 2/25 3/18 4/8 4/29 5/20 6/10 7/1 7/22 8/12 9/2 9/23 10/14 11/4 11/25 12/16 1/6 1/27 2/17 3/10 3/31 4/21 5/12 6/2 6/23 7/14 8/4 8/25 9/15 10/6 10/27 11/17 12/8 12/29 1/19 2/9 3/1 3/22 4/12 5January 11 March 1 April 21 June 11 August 1 September 21 November 11 January 1 February 21 April 11 June 1 July 21 September 11 November 1 December 21 February 11 April 1
Normal
Milestone
Summary
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Manual Progress
SIEMENS CEB - 220/33kV GIS Substation at Nadukuda and Extn. of 220kV AIS at Mannar, Sri Lanka
SUNDAY IS CONSIDERED AS NON WORKING DAY IN SCHEDULE. Page 1 of 1
Date: Tue 9/18/18
21,106,571.00
Log
Month
Acct.
Date
Document No Document Remarks Dr Amount Cr Amount Running
9 9/11/19 12: 977.00/PSO/19/0213 466344 PS-ONLINE Being Payment of Way Leaves.
(Mahaweli Authority)790,000.00 0.00 21,896,571.00
10 10/30/19 977.00/PSO/19/0237 466362 PS-ONLINE BEING PAYMENT OF WAY LEAVE. 254,000.00 0.00 22,140,571.00
1,044,000.00 0.00
22,140,571.00
Cost Center Ledger Card - from July to December /2019Cost Centre : / PD-PMU OF MEDIUM VOLTAGE NETWORK EFFICIENCY IMPRV PRJ-MVNEIP
Gl Code : 977.00-E7830 - WAY LEAVES Opening Balance : 01/ 7/2019
Cheque
No
Closing Balance : 31 /12/2019
Ceylon Electricity Board, Sri Lanka December 2019
Safeguard Due Diligence on ADB project (SRI) 47037-005:
Green Power Development and Energy Efficiency Improvement Investment Program –Tranche 2 Transmission Line component:
New Polpitiya-Hambantota 220kV Transmission Development Distribution component: Construction of a new 8km 33kV distribution line from Kappalthurai GSS to Chinabay Gantry, Construction of Gantry at Chinabay, Construction of a new 11km 33kV distribution line from Embilipitiya GSS to Weniwelara and Construction of Gantry at Weniwelara. Prepared By: Ceylon Electricity Board, Sri Lanka
NOTES Prepared by Ceylon Electricity Board for Asian Development Bank (ADB). This due diligence is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or another status of any territory or area.
Introduction: The “Sri Lanka Green Power Development and Energy Efficiency Improvement Investment Program” is being implemented with a loan from the Asian Development Bank (ADB). The objective of the loan is to achieve increased adequacy and efficiency of the power system. The funding is structured in two tranches. The project components of the tranche two are Transmission Infrastructure Enhancement, Medium Voltage Network Efficiency Improvement and Demand Side Management (DSM) pilot project in the Aweriwatte/Katunayake area in the Western Province. The Medium Voltage Network Efficiency Improvement component comprises the construction of 33kV distribution tower lines, Gantries, primary substations and augmentation of 33kV substations. This Due Diligence Report (DDR) is for the following transmission and distribution development sub-projects of the tranche-2 of the investment program, as CEB has proposed several deviations in the distribution line route and changes at the locations of the gantries.
1. Transmission Development Component: Construction of new 220kV double circuit, 144km, 2xZebra Polpitiya-Hambantota Transmission Line Development
2. Distribution Development (Under the Medium Voltage Network Efficiency
Improvement Component) a. Construction of a new 33kV, 8km 4cct Lynx tower line from Kappalthurai GSS to
China bay gantry b. Construction of a new 33kV gantry at China Bay c. Construction of a new 33kV, 11 km DC Lynx tower lines from Embilipitiya GSS to
Weniwel-ara gantry d. Construction of a new 33kV gantry at Weniwel-ara
CEB proposes deviations to the transmission and distribution line routes and the locations of gantries. The objective of the DDR is to ascertain whether such deviations fall within the scope of subproject RAPs and also to ensure that the agreed social safeguard requirements in the RAPs are fully followed/implemented before moving forward about those sub-projects.
a. Construction of new 220kV double circuit, 144km, 2xZebra Polpitiya-Hambantota transmission line
As per the initial design prepared by CEB, the line was 144km long with 543 towers that traverse mostly through private lands. During the detail design stage, CEB changed the line route at 06 locations to meet some technical requirements and because of the requests of landowners and villagers. The detail list of the changes are in Table 1.
Table 1: Details of the Line Route Deviations Proposed for the Polpitiya-Hambanthota transmission Line
No. DS Division Tower
points
the
deviation
made
Length of
Deviated
line
Cause of the deviation
1 Deraniyagala AP19 –
AP21
0.6 km The landowners objected placing of towers on
their land and way leave according to the
original design.
2 Kuruwita AP39 –
AP41
1 km The villagers requested to shift the line to
avoid the line traversing through their lands.
3 Balangoda AP100 –
AP104
3.5 km The villagers requested to shift the line to
protect their common vegetation and the
reservoir, which serves as the water source for
cultivation.
4 Waligepola AP109 –
AP111
1.4 km The landowners requested to shift the line to
protect their home gardens and paddy
cultivation.
5 Embilipitiya AP134 –
AP135A
1.8 km Line route shifted to a technically suitable
location to cross the existing 132kV line
6 Sooriyawawa AP173 –
AP176
3.2 km To avoid the reservation of the Sooriyawewa
Highway interchange as per the request made
by the Road Development Authority.
Source: Information collected from the office files b. Construction of new 33kV, 8km 4cct Lynx Tower line from Kappalthurai GSS to China
bay Gantry CEB originally planned to construct an 8km distribution tower line from the Kappalthurai GSS to the distribution point at China Bay. The line designed with 28 towers and 20 m of line corridor (RoW). The line was to traverse mostly through the vacant state land and proposed the last 3.7km of the line to traverse through the land belong to the Lanka Indian Oil Company (LIOC) to connect with the distribution point through a new gantry in the CEB-owned land.
However, CEB failed to secure the required permissions from the LIOC to use the land section that falls under the LIOC compound. The CEB proposed a line re-routing to tackle this issue. The alternate route proposed for this section is 4.2 km in length and, it traverses through the land reserved for Sri Lanka Port Authority (SLPA), and CEB has secured the consent from the SLPA for this purpose.
c. Construction of New 33kV Gantry at China bay:
A gantry construction had proposed on the CEB land at the existing distribution point next to the LIOC compound to connect the proposed 33kV Kappalthurai to the China Bay line (Described above in section b). CEB proposes to shift the location of the gantry to match the proposed re-routing of the Kappalthurai-China bay line, as described above (in section b). The land identified for the construction of the gantry belongs to the SLPA, and CEB has obtained consent from the SLPA for this purpose already. d. Construction of gantry at Weniwel-ara A gantry was proposed to construct in Weniwel-ara to connect the proposed 33kV line from Empilipitiya Grid Sub Station (GSS). Now, CEB proposes to shift this gantry to Sooriyawewa as the grid substation construction proposed at Sooriyawewa under the transmission project is cancelled due to the changes made in the provincial level development plan of CEB.
Figure 1: The Original and Proposed Deviations of Distribution Line Route and Gantry Location of Kappalthurai to Lot D-5 and
D-6 Components of the Project
Initially, the gantry was proposed to construct on private land (0.03Ha) at Weniwel-ara, and CEB wanted to acquire the land from the owner, who is a woman. As per the latest change proposed by CEB, the land for constructing the gantry is in Sooriyawewa and belongs to the Board of Investment (BoI). CEB has obtained the consent of the BoI for this purpose already.
e. Construction of New, 33kV, Empilipitiya to Weniwelara Distribution Line
The 33kV DC Weniwelara distribution line was originally planned to originate from the Emplipitiya GSS and to end at the gantry proposed to construct at Weniwelara. This 11km long line was estimated to construct with 40 towers (each with 36sqm footings) and a 20m line corridor (RoW). Because of the shifting of the gantry to Sooriyawewa as described above (in section d), the distribution line from Empilipitiya to be traversed up to Sooriyawewa, which will make the line to 21km in length. Accordingly, the CEB proposes to construct a 9.5km section of this line as per the original design and proposes a new extension for the rest (11.5km) of the line. CEB has completed tendering the construction of the initial 9.5km of this distribution line and the financing arrangement for the newly proposed extension (11.5km) is yet to be finalized.
DUE DILIGENCE ON LAND ACQUISITION AND RESETTLEMENT The draft Resettlement Action Plan (RAP), prepared in 2016, describes the impacts of the sub-projects and mitigation measures as per the original design of those sub-projects. The scope of the sub-projects, the scope of land acquisition, social impacts and mitigation measure,
Figure 2: The Empilipitiya GSS to Weniwalara Distribution Line, Weniwalara Gantry and Newly Proposed Gantry at
Sooriyawewa
entitlement matrix, operational structure, Grievance Redress Mechanism (GRM) and socioeconomic profile of the project impact area were outlined in the RAP along with other required sections of a RAP.
i) New 220kV double circuit, 144km, 2xZebra Polpitiya-Hambantota Transmission Line Development
The proposed deviations in this line have increased the length of the transmission line by 1.9km, and the number of affected households were increased by 05. However, the impacts considered as significant by the villagers and landowners have been avoided and the increase in the number of affected households is mainly due to the deviation proposed to avoid expressway reservation, which is unavoidable. Even though the deviated line for this expressway section traverses through paddy lands, banana lands and lands with perennial trees like coconut and mango trees, no trees will be removed within the line corridor by adjusting the height of the towers. CEB will take further actions to reduce the impacts. CEB is in the process of paying cash compensation to the people affected by the transmission tower line. No structures are found to be affected by this transmission line, and crops and tree losses are the only impacts identified. CEB follows the Entitlement Matrix of the original RAP, and it provides sufficient guidance to mitigate subproject impacts. ii) New 33kV, 8km 4cct Lynx Tower line from Kappalthurai GSS to China bay Gantry
As per the original RAP, based on the original design of the distribution line, the distribution line
was to traverse through state land and the land belongs to LIOC. There were no settlements or
structures found within the distribution line corridor. However, the proposed line route change
adversely impacts on 03 households that are located within SLPA land. These 03 households
are non-titled landholders. The number of towers that will be placed on their land is yet to be
finalized, and that will be done after the detail design is completed. However, the initial estimate
is that one tower will be built on the land that is being occupied by each non-titled landholder.
CEB will make an effort to reduce the number of towers on these lands and to use stripes of un-
occupied state lands that belong to SLPA on the premises. The maximum space required to
place a tower is 36sqm, which is very small.
CEB obtained the consent of those three households for the project and will follow the process
and Entitlement Matrix of the original RAP (draft) to compensate them. The land for the tower
footings and the wayleave will not be acquired, but the losses caused to the trees to be
compensated at their replacement cost. Accordingly, the proposed deviation causes temporary
impacts to three households and the next update on the RAP (Draft) will describe the impacts
that have been caused by this line route change.
iii) New 33kV gantry at China bay:
As per the original RAP (draft), the land for constructing the gantry belongs to CEB, and no land acquisition is therefore required. The land identified for constructing the gantry as per the proposed deviation belongs to SLPA, and this 0.025Ha land is free from all encumbrances. CEB obtained clearance from SLPA to use this land for this purpose. Accordingly, this subproject does not require any land acquisition or resettlement.
iv) Weniwel-ara Gantry As per the original design, it was proposed to acquire 0.03ha of land from a woman-headed household in Weniwelara. The land (0.05Ha) identified for shifting the gantry to Sooriyawewa is vacant land that belongs to the BoI. The consent of the BoI has been already received for this purpose. Accordingly, this sub-component will not require land acquisition or resettlement. However, the RAP will be updated to include this scenario accordingly. v) New, 33kV, Empilipitiya to Weniwelara distribution tower line CEB has stopped wayleave clearance of the 1.5 km corridor and informed the people about the discontinuation of this line section. Neither compensation process nor the physical works of wayleave clearances started in this section. Paying compensation for the impacts caused by the wayleave and the tower footings is in progress for the 9.5km section as per the original design. CEB follows the approved RAP in paying compensation. The 11.5km extension the CEB proposes now is traversing mostly through private lands which mostly are paddy lands. Even though the financing source for this extension not being finalized yet, CEB has already initiated the wayleave clearance process, issuing the “D Notice.” The construction of the originally proposed distribution line section (9.5km) and the gantry at Sooriyawewa can’t be functioning without the proposed 11.5km extension. Therefore, even though the financing source for this extension is yet to be finalized, CEB has followed the local regulatory framework and social safeguard requirements of the ADB to deal with land acquisition. The initial site investigation made by CEB confirms that the extension (11.5km) will not cause any land acquisition or physical and economic displacement, and the nature of impacts will mainly be limited to loss of crops, perennial trees, and few restrictions on land use within the 15m line corridor. Even though the original RAP (draft) is included with the inventory of losses (IOL) of the line as per the original design, it has to be updated with the IOL for the 11.5km extension the CEB proposes now.
FINDINGS Construction of gantries will not entail land acquisition and resettlement because the lands on which they will be built belongs to the state institutions such as SLPA and BoI. No private land users are found on the land. The minor changes introduced to the Polpitiya-Hambanthota transmission line are to reduce the project impacts on the people and the environment. The Kappalthurai to Chinabay distribution line will run through the land belongs to the state, and such lands are allocated to state institutions such as SLPA. As a result, the need for land acquisition does not arise. Private land users in three land lots are squatters on SLPA land. They are not entitled to get any compensation for land. However, they will be compensated for land development on the plots. The inventory of losses survey has been carried out by CEB,
and the entitlement matrix prescribed in the original RAP is found adequate for compensating these impacts. The process of wayleave clearance and paying compensation for the distribution line section proposed originally from Empilipitiya is progressing well following the RAP (Draft). The IOL survey and socioeconomic survey has to be completed and their finding to be included in the RAP During the next update (December 2019 Version) for the newly proposed extension (11.5km) of Empilipitiya-Sooriyawewa distribution line. CONCLUSION AND RECOMMENDATIONS Project components cause temporary impacts on APs. Such impacts are mainly limited to the 15m corridor of the distribution line. The impacts are: restriction on land use and losing perennial trees within the line corridor. The entitlement matrix in the approved RAP is adequate for mitigating and compensating these impacts, and the RAP will be updated (2019, December version) to reflect the changes in the number of APs and land requirements. During the construction phase, contractors may cause temporary disturbances to the people in the area. Such disturbance may occur when excavating tower footings and mobilizing heavy machinery and equipment to the construction sites. CEB will address such disturbances through civil works contracts. The civil works contracts will require contractors to negotiate and reach a mutual agreement with the owners/users of any land before it is used temporarily for the installation/rehabilitation activities.