standard note for clw as on 31.12clw.indianrailways.gov.in/works/uploads/file/clw standard... ·...

65

Upload: others

Post on 14-Mar-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate
Page 2: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

STANDARD NOTE FOR PRODUCTION UNIT CLW AS ON 31.12.15

Page 3: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

Contents

1. INTRODUCTION 2. SALIENT FEATURES 3. ORGANISATIONAL CHART 4. PRODUCTION PERFORMANCE 5. DESIGN&DEVELOPMENTINCLUDING TOT 6. QUALITY ASSURANCE 7. MARKETING INCLUDING EXPORT 8. STATUS OF M&P 8A. STEEL FOUNDRY 9. STAFF POSITION 10. UNIT COST OF THE PRODUCT 11. INDUSTRIAL SAFETY 12. FUTURE PLANS 13. OTHER ISSUES

Page 4: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

INTRODUCTION

1

Page 5: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

1. INTRODUCTION :

1.1 The Works and Administrative office of Chittaranjan Locomotive Works (CLW) are located at Chittaranjan, Dist. Burdwan in West Bengal. In addition, a Stores Purchase office in Kolkata and CLW’s inspection cells in New Delhi, Mumbai, Kolkata and Bangalore. 1.2 Chittaranjan Locomotive Works (CLW), is the first industrial gift to free India by the planners of the nation.

The issue of setting up a locomotive building unit continued to be under active consideration of the Central legislature and in the late thirties, a committee consisting of M/s Humphries and Srinivasan was appointed to investigate the possibility of establishing a locomotive manufacturing unit and to consider its economic viability. The initial project at Chandmari, a place near Kanchrapara in the state of West Bengal, could not mature due to partition, which inevitably necessitated a change of site. The present site of Chittaranjan was selected after a fresh survey and Railway Board’s approval was obtained in the year 1947. The locoworks was initially established for production of 120 average sized steam locomotives with the capacity to manufacture 50 spare boilers. Production of steam loco commenced on 26th January, 1950. The first President of India, Dr. Rajendra Prasad dedicated the first steam locomotive to the nation on 1st November, 1950 and on the same day the factory which was called Locomotive Manufacturing Works, was named after the great Patriot, Deshbandhu Chittaranjan Das. Production of Diesel Locomotive was taken up during 1968. After manufacturing 2351 Steam Locomotives of 5 types and 842 Diesel Locomotives of 7 types, production of Steam and Diesel Locos were discontinued from 1971-72 and 1993-94 respectively. CLW is now manufacturing main line Electric Locomotives only. Upto 31.12.15, 5635 Electric Locomotives have been produced of different class (AC/DC, AC, DC & 3- phase).

1.3 CLW has augmented its production capacity for Electric Locos in phases besides absorbing 3-phase technology i.e from 60 to 80 Locomotives, 80 to 100, 100 to 130, 130 to 150 and now up to 280.

1.4 Production of Traction Motors and control equipment commenced in April 1967. In the year 2015-16, upto 31.12.15, 1182 TM were produced.

1.5 Steel Foundry was set up in 1962-63 for production of steel castings for Steam Locomotives produced in CLW. It took up production of castings with the State of the Art technology provided by M/S Rockwell International Corporation, USA in the year 1990-91. Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate by RDSO on 9th August 2012.

1.6 CLW has in house facilities for machining and assembly of wheel sets, fabrication and machining bogies.

The facilities include modern CNG machines, Plasma Cutting machines, Inert Gas Welding etc.

1.7 CLW has an exclusive Centre for Design and Development with CAD/CAM facilities.

1.8 There is a well-established quality assurance/inspection for incoming material and stage inspection and final inspection of the CLW manufactured items.

1.9 CLW has been sanctioned “Creation of additional facilities for enhancement of production capacity” . The major works are:

1.Additional Bay of Loco Fabrication &Loco Assembly Shops. 2.Extension of Traction Motor Shops. 3.Additional Machinery &plant, Tools, jigs &fixture. 4.control Information Management System. 5.Augmentation to various Ancillary Shops. 6. Creation of Rain Water Test facilities.

Page 6: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

1.10 CLW has acquired the ISO-14001 certificate on 26.4.2002 both for its works and township for a neat and clean environment. CLW has been awarded ISO 9001:2008 certificate for Quality Management System and OHSAS 18001:2007 for occupational health and safety management system.

1.11 Chittaranjan is a true example of Environment preservation and consciousness. Its lush green ambience talks

of the efforts of the Administration as well as the residents of the township in the conservation of Environment, as well as using of all the existing natural resources in an eco-friendly manner. The concerted and unending efforts have been rewarded immensely by the World Environment Foundation and the Golden Peacock award for Environment Management 2006 had been conferred on 9th June 2006.

1.12 CLW has complied fully with the provisions of the Industrial Safety Act, 1948. CLW in its safety policy

aims to ensure 100% safety for all workers working in Chittaranjan Locomotive Works. CLW is the proud recipient of the Safety innovation award 2006. The award was conferred on CLW on 6th September, 2006 by the Safety and Quality forum of the Institute of Engineers (India).

1.13 during the year 2015-16, CLW has moved toward complete switchover from Conventional to 3-phase and

CLW started producing only 3-phase locomotives from December 2015 & onwards. 1.14 During the year 2015-16, CLW has completely switched over from GTO technology to IGBT technology.

The 1st WAG-9 class freight loco No.31215 fitted with IGBT based Power Converter has been successfully commissioned on 18th December, 2009. Currently more than 300 locomotives are running with IGBT based Power Converter on Indian Railways.

1.15 The first electric locomotive (WAP-7 type no. 30277) with Head on Generation (HOG) scheme was

flagged off on 30th June ,2010. Up to Dec 15, 9 sets of Siemens, 1 Medha, 1 set of BHEL , have been commissioned on locos. For the first time TFP 7775 with double hotel load winding has been provided in WAP7 loco (30445) having Hotel Load Converter. The modified arrangement not only eliminate need of providing Autotransformer (used earlier to boost 750 V to 960 V) but also will lead to reduction in line to earth voltage from 2.4 kV to 750 V improving the overall reliability of HOG system.

1.16 The first WAP-7 loco no. 30279 was produced with brake rigging of WAG-7 design. Now this is standard

design for all WAP-7 locomotives produced by CLW. Flag-off last conventional loco WAP-4 (Loco No. 25051) 1.17 High Reach Pantograph: Regular provision of one High Reach Pantograph in each locomotive has been

made for the year 2016-17 to facilitate working of these locomotives in Dedicated Freight Corridor. 1.18 Complete VCU Redundancy in WAP-7: Loco No. 30436 (ELS/RPM) has been turned out with feature

of complete VCU redundancy sheet for avoiding necessity of CAB changing in case of failure of processor cards of VCU. This has been implemented first time using two additional I/O/ card in WAP7 locomotives.

1.19 1st set of Indigenous Wheel Disc for WAP-5 locomotives, developed by SAIL has been commissioned in

loco 30083 and dispatched to ELS/BRC during June’15.40 nos. Wheel Disc has been supplied by SAIL, Durgapur to CLW.

Page 7: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

1.20 Multiple Operation of WAG-7 locomotives provided with FDCS, Version-III: Multiple operation of WAG7 locomotives, fitted with Microprocessor based control & fault diagnostic system, Version –III has been successfully commissioned in locomotives 28766 & 28767 and dispatched to ELS/AJJ, in month of Oct’15.

1.21 An automated new paint booth has been commissioned under AP-50 Project. In this paint booth PU

painting is being carried out in a controlled atmosphere. 1.22 Electric Loco Reliability meet in CLW

Electric Loco Reliability Meets were held at Chittaranjan Locomotive Works (CLW) on 27th & 28th April, 2015 and 28th Nov, 2015. Chief Electrical Loco Engineers (CELEs), Sr. Divisional Electrical Engineers (Sr. DEEs) of Zonal Railways, Sr. Officers from RDSO/Lucknow and Railway Board/ New Delhi participated in this meet to discuss reliability issues of the CLW build electric locomotives. special focus was given to 3-phase locomotives provided with latest IGBT Technology.

1.23 First Locomotive of the year 2015-16 inauguarated in CLW

The first electric Locomotive (WAP-7 type, No. 30425) of Chittaranjan Locomotive Wroks (CLW) for the year 2015-16 was flagged off on 30.04.2015 by Shri C.P. Tayal, General Manager/CLW and dedicated it to the service of the nation in a ceremony at inside the shop. Smt Amrita Tayal, President, CLW-WWO along with other members of CLW-WWO, Principal HODs, Senior Officers, members of Staff Council and staff of CLW were present on the occasion.

1.24 CLW gets OHSAS ISO 18001 certification

Chittaranjan Locomotive Works (CLW) got OHSAS – ISO - 18001 certification from certifying agency , MS Certification Services Pvt. Ltd on 05-05-15. The OHSAS represents for Occupational Health & Safety Management Systems for Loco Works and Steel Foundry of CLW. This certification is awarded to CLW for compliance to the Occupational Health & Safety Management Systems during Manufacture and Supply of Electric Locomotives & Spares including those of Steel Foundry .

1.25 Visit of Member Electrical , Railway Board to CLW

Shri Navin Tandon, Member Electrical, Railway Board and Ex-Officio Secretary to Govt. of India visited Chittaranjan Locomotive Works (CLW) on 28th & 29th June, 2015. On 28th June, he inspected CLW railway colony, water filter house, Shailahari hill top, Boat club etc. Shri Tandon also enjoyed the Joy ride on Fairy Princess toy train in Deshbandhu Loco park. Later, in the evening a cultural programme was organised in honour of the visiting guest by CLW Cultural Association in Chittaranjan Club.

Page 8: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

1.26 Distpatch of Last WAG-7 Shell of the year 2015-16

The Last WAG-7 Shell of Chittaranjan Locomotive Works (CLW) for the year 2015-16, was flagged off on 07.08.15 by Shri C.P.Tayal, General Manager/ CLW in a ceremony inside the shop. On the occasion, Principal HODs, Senior Officers, members of Staff Council and staff of different shops of CLW were present.

1.27 Vendor Development Programme in CLW

A State level Vendors’ Development Programme and Buyer Seller Meet was organized in the Chittaranjan Club premises on 23rd November 2015. Shri C. P. Tayal, General Manager inaugurated this Vendors Meet as Chief Guest. The meet was jointly organized by Chittaranjan Locomotive Works (CLW), Ministry of Micro, Small & Medium Enterprises (MSMEs), Govt. of India and National Small Industries Corporation Ltd.,(NSCI)/Durgapur to encourage participation of MSME vendors in procurement process of CLW.

1.28 Visit of Member Electrical, Railway Board to CLW

Shri Navin Tandon, Member Electrical, Railway Board and Ex-Officio Secretary to Govt. of India visited Chittaranjan Locomotive Works (CLW) on 2nd December, 2015. He inspected various shops especially, electric loco testing shop, loco assembly shop of CLW. He also reviewed the Electric loco production in CLW. Shri Tandon, inaugurated the newly built paint booth inside the paint shop. Shri Tandon also flagged-off the last conventional locomotive (Loco No. 25051 WAP-4) built by CLW.

1.29 Visit of Financial Commissioner (Rlys.) , Railway Board to CLW

Shri S.Mookerjee, Financial Commissioner(Rlys.), Railway Board and Ex-Officio Secretary to Govt. of India visited Chittaranjan Locomotive Works (CLW) on 26th -28th December, 2015. On 26th December, 2015 in the evening, a cultural programme was organised in honour of the visiting guest by CLW Cultural Association in Chittaranjan Club.

Page 9: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

SALIENT FEATURES

2

Page 10: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

2. SALIENT FEATURES Salient features of CLW w.r.t the following :

2.1 Total turn over as on 31.12.15 a) For Indian Railways : Rs.2617.48 Crores b) For others : -- Nil Turn over ratio as on 31.12.15: 15% Break up of Turnover as on 31.12.15

Supply of Locos Rs. 2307.01 Crore Components manufactured for stock Rs. 308.24 Crore Supply of Spares for Zonal Railways Rs. 02.23 Crore …………………… TOTAL Rs: 2617.48 Crore

Turn over ratio of Store Deptt./CLW for 2015-16 (up to 31.12.15) Physical : 31.67% 2.2 Total assets : (as on 31.12.15) : Rs 867.14 crores

Fixed assets: (as on 31.12.15) : Rs 480.76 crores a) Township : Rs 33.92 crores b) Workshop with M&P : Rs 446.84 crores

Floating assets (as on 31.12.15 : Rs 386.38 crores a)Stores : Rs 764.86 crores b)WMS : Rs. -397.89 crores c)Misc Adv. : Rs. 19.41 crores

2.3 Sanctioned and on-roll position of staff as on (31.12.15) group of staff wise i.e Group A, Group B,

Group C & Group D. Group Sanctioned Strength On Roll Group A 242

104

Group B 77 Group C 14462 11806 Group D 56 54

Total 14760 12041

2.4 Elec. Power requirement (average maximum demand) : 11MVA 2.5 Electric energy consumption : (in lakh units/year) : 448.53187 Lakh unit (from 1st Apr’2015 to

31st Dec’ 2015.) 2.6 No. of H.T. Sub station: A) 33/11 KV : 01 no.

B) 11/3.3KV : 01no. C) 11/0.4KV : 45 nos. D) 11/0.4KV : 21 nos.- under main shop.

2.7 Stand by power generation capacity(in KW) : 8037.50 KWH(as on 31.12.15) 2.8 Water consumption : 0.157 Lakh Kilo liters per day 2.9 (a)Workshop Land : 10,12,600 Sq.m. (b) Covered area of other service building (in SQM) : 35,241 Sq.m 2.10 Township area : 1,834.441 Hectares. 2.11 (a) Covered area in shops : 4,73,268 Sq.m 2.12 (a) Total staff as on 31.12.15 : 11,860 (b) Total number of staff quarters : 9,346 Nos. 2.13 Hospital (no. of beds) : 197 Nos.

Page 11: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

ORGANISATIONAL CHART

3

Page 12: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

ORGANISATIONAL CHART (UPTO JAG) AS ON 31.12.15) GM

CPO CMO CME Dy.GM CEE Secy. to GM COS FA&CAO CVO CE

Dy.CVO

Dy.CPO(W) SPO/Admn CEE/CLW CEE/LOCO CEE/TM CEE/L&S CEE/PL&I CME/Loco Dy.CE/con-I SPO/WE SPO/Res (DKAE/Con)* SPO/WM APO/G Dy.CME/ELB FA&CAO(P) Sr. EDPM

APO/SF Dy.CEE/M Dy.CME/ELF AWO DyCEE/D&D/Con

CEE/Loco Dy.CEE/EL Dy.CEE/TMM Dy.CEE/D-I Dy.CEE/Insp/SBC FA&CAO/HQ (DKAE)* Dy.CME/ELA Dy.CEE/TMD Dy.CEE/D-II Dy.CEE/I&D/DLI* Dy.CEE/I&D/Mum Dy.FA&CAO(I)

Dy.CME/I&D/HWH* Dy.FA&CAO(II) CQAM Dy.FA&CAO(KOL)

Dy.CEE/D&D/CON CME/Prod/SF CME(Mfg) Dy.CME/Proj/Con/SF* Dy.CME/Mfg PE/Plant/SF Dy.CME/Plant Dy.CME/Plant/SF Dy.CME/MPP/CON* CMM(CRJ) CMM/Kol(M) CMM/Kol(E) Dy.CME/M&P/CON* Dy.CC&M Dy.CMM/HQ* Dy.CMM-III/Kol Dy.CMM/I/Kol Dy.CMM/P Dy.CMM-IV/KOL Dy.CMM/Sys/Con* Dy.CMM/D Addl CMS/A Addl.CMS/ENT Addl.CMS/OPD(V) Addl.CMS/Gynae Sr.DMO/S Addl.CMS/Gynae Addl.CMS(V) Sr.DMO Sr.DMO Sr.DMO(V) Sr.DMO Sr.DMO/Path (CMP)(V) Addl CMS/SPN/SPE Sr.DMO(HU) Sr.DMO Sr.DMO ( CMP)(V) DMO/Anesthesia Sr.DMO/FW-II AddlCMS(Path) Sr.DMO/S Sr.DMO(Neuro) Sr.DDS/Dent Sr.DMO/PHY Sr DMO(CMP)(V) Sr DMO(CMP) Sr DMO(CMP) Sr DMO/EYE V-Vacant

*-WC Post

Page 13: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

PRODUCTION PERFORMANCE

4

Page 14: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

4. PRODUCTION PERFORMANCE

CLW built 2351 Nos. of Steam Locomotives and 842 Nos. of Diesel locomotives before switching over completely to the production of Electric Locomotives. The last Steam Locomotive was built in the year 1971-72. The production of Diesel locomotives continued up-to 31st March 1993 when the last ZDM-5 Narrow Gauge Loco was turned out. Now CLW is involved in the production of Electric Locomotives (Conventional and Three phases) and has produced 5635 Electric locomotives till 31st December 2015 and maintenance spares required by Zonal Railways. The annual out-turn of various types of Locomotives CLW has produced since inception is given in the Annexure-I in two sheets. 4.1 ELECTRIC LOCOMOTIVES :

The production of Electric Locomotives was started in the year 1961. Till 31st December 2015, 5635 nos Electric Locomotives of various classes and traction have been produced as shown in the Annexure-I in two sheets. The present production of electric locomotives consists of:

i) 5000 HP 6-axle freight Loco (WAG-7) with fabricated bogies (High Adhesion) and secondary suspension with axle load of 20.5 Ton suitable for air brake trailing stock

ii) 5000 HP, 6 Axle AC Passenger Traffic Locomotives (WAP-4) fitted with Flexi-coil cast steel

bogies and Axle load of 18.8 Ton hauling Rajdhani Express and other Super Fast trains. iii) 3-phase AC IGBT controlled 6000 HP, 6 Axle freight WAG-9 H (with an Axle load of 22.5

Ton) having energy regeneration features. iv) Passenger version of 3-phase IGBT loco viz. WAP-5 with an axle load of 19.5 ton for hauling

Mail/Express and other Super fast trains having energy regeneration features. v) Passenger version of 3-phase IGBT Loco viz. WAP-7 with an axle load of 20.5ton suitable for

hauling Mail/Express and other super fast trains and having energy regeneration features.

During the year 2015-16 (upto 31/12/15) CLW has manufactured 30 nos. WAP-4, 35 nos.WAG- 7, 99 nos.WAG-9, 09 nos.WAP-5 and 32 nos. WAP-7 Electric Locomotives i.e. total 205 nos. Locomotives (against planned yearly out turn of 250 Electric Locomotives As per JPO-68, Dt. 18.10.2015). CLW has planned to produce 280 nos Electric Locomotives during the year 2016-17(As per JPO-68, dt. 18.10.15).

Page 15: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

4.1.1 Year wise production from 2000-01 to 2015-2016 YEAR

WAP-4 (RAJ)

WAG-7 (HH)

WAP - 5 (TP)

WAP-7 (TPP)

WAG-9 (TG)

Total

2000-01 Target 45 67 2 1 5 120 Actual 50 62 2 1 5 120

2001-02 Target 37 50 - 1 2 90 Actual 34 40 - 2 6 82

2002-03 Target 20 24 4 9 12 69 Actual 28 27 1 6 7 69

2003-04 Target 32 39 - 9 6 86 Actual 32 36 - 9 9 86

2004-05

Target 30 35 - 13 12 90 Actual 32 36 2 9 11 90

2005-06 Target 39 56 4 2 27 128 Actual 40 60 1 4 24 129

2006-07 Target 37 77 1 - 35 150 Actual 37 77 - 1 35 150

2007-08 Target 47 98 3 3 49 200 Actual 47 98 3 3 49 200

2008-09 Target 51 115 4 20 30 220 Actual 51 115 3 20 31 220

2009-10 Target 40 120 5 20 45 230 Actual 40 120 3 18 39 220

2010-11

Target 35 95 15 30 55 230 Actual 40 120 12 18 40 230

2011-12

Target 30 100 15 30 55 230 Actual 44 126 12 19 45 246

2012-13 Target 20 100 15 40 75 250 Actual 37 123 13 40 57 270

2013-14

Target 20 80 30 50 95 275 Actual 27 100 13 31 93 264

2014-15

Target 35 70 07 40 98 250 Actual 35 70 07 40 98 250

2015-16 As per JPO-68, Dt.18.10.15 (As on 31.12.2015)

Target 30 35 17 58 140 280 Actual 30 35 09 32 99 205

Page 16: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

3747

5140 40 44

3727

35 30

77

98

115 120 120 126 123

100

70

35

0 3 3 312 12 13 13 7 9

1 3

20 18 18 19

4031

403235

49

3139 40 45

57

93 98 99

150

200

220 220230

246

270 264250

205

0

50

100

150

200

250

300

2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16upto 31.12.15

(JPO-68 dt.18.10.15)

Year wise Electric Loco production from 2006-07 to 2015-16(As on 31.12.15)

WAP-4

WAG-7

WAP-5

WAP-7

WAG-9

Total

Page 17: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

4.2 TRACTION MOTORS:

4.2.1. Cumulative production of Traction Motors during the year 2015-16 upto 31.12.15 has been 1182 Traction Motors (400 Hitachi & 782 Three Phase). 4.2.2 THREE PHASE TRACTION MOTORS TYPE 6FRA 6068 & 6FXA 7059: 3-Phase Traction Motor type 6FRA 6068 for WAG-9 and WAP-7 Locomotives and 6FXA 7059 for WAP-5 Locomotive are being manufactured indigenously by CLW since 1998-99 and 1999-2000 respectively. Upto Dec-15, CLW has manufactured 5560 nos. 6FRA-6068 and 291 nos. 6FXA-7059. During the current fiscal, a total 782 nos. three-phase Traction Motors (774 nos. 6FRA 6068 and 8 nos. 6FXA 7059) have been manufatured at CLW. These Traction Motors, due to absence of Commutator and commutator peripherals like carbon brushes, brush holders etc, need minimal manitenance and are free from problems associated with DC Traction Motors. 4.2.3 HITACHI TRACTION MOTOR TYPE HS-15250A: Hitachi Traction Motor is one of the most critical and vital equipment in conventional Electric Locomotives type: WAG-7 & WAP-4 under production at CLW. Since 1988-89, CLW has manufactured 15080 nos. of Hitachi TM type: HS-15250A upto 31.12.15. During 2015-16, 400 Hitachi TMs have been manufactured till Dec’15. Year wise production of all type of TMs manufactured at CLW from the year 1969-70 onwards is given in Annexure-II. Following Bar chart shows the production trend of Traction Motor at CLW with emphasis of 3-phase Traction Motors:

YEARWISE PRODUCTION OF TRACTION MOTORS

4.2.4 STATIC EQUIPMENTS: Static equipments are required for manufacture of conventional locomotives (WAG 7/ WAP4). The production of Static Equipment during 2015-16 was 32 loco sets + Rly. Spare demands.

8 4 0 4 8 5 24 44 43 60 42 19 8124 128

205276 321 316

390 373 332

564

844759 774

392 417

726 761896 881

815

1000900 913

676 672

400524 549

9311041

1225 1202 1229

1417

1275

1537 15621450

1182

0

200

400

600

800

1000

1200

1400

1600

1800

03-04 04-05 05-06 06-07 07-08 08-09 09-10 10-11 11-12 12-13 13-14 14-15 15-16 (upto

Dec'15)

6FXA 7059

6 FRA 6068

HS 15250 A

Total

Page 18: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

Details of various items of Static Equipment (Quantity in number) manufactured during the year 2015-16 (upto Dec’15) is shown below:

Item Description

Qty. (No.)

Item Description

Qty. (No.)

Motor Contactor (MC) 50 Reverser (J) 12 Shunting Contactor (SC) 64 Master Controller (MP) 109 Inductive Shunt (SJ) 168 Smoothing Reactor (SL) 68 Traction Braking Switch (CTF-1,2&3) 18

Year wise production of various static equipments from 1972-73 onwards are given in Annexure III 4.2.5 SUPPLY OF SPARES :

The following materials were supplied to zonal Railways as spares during the year 2015-16 (upto Dec’15) against their sanction RSPs/Vetted Indents : Item Description Qty.(No.) Item Description Qty.(No.) Hitachi Traction Motor 102 3 Phase Traction Motor (Co Co) 12 Hitachi Armature 24 3 Phase Traction Motor (Bo Bo) 04 Smoothing Reactor (SL) 09

4.2.6 IMPROVEMENTS TO ENHANCE RELIABILITY: To improve reliability and performance, modifications as listed below have been implemented. 4.2.6.1. 3- PHASE TRACTION MOTOR TYPE 6FRA 6068:

To arrest the problem of uprooting/breakage/skewing of teeth of end punchings of 3-phase TM rotors due to opening of spot welds, the existing spot welded end punchings have been replaced by 5 mm thick solid end punchings as per EN-10025-6:2004 vide RDSO’s letter No. EL/3.2.182 dated 28.02.13.

To arrest the problem of bearing seizure of FAG/Germany make bearings in 3 phase TMs due to weak cage design, the design of FAG make bearings have been got modified with strong cage as well as change of cage material from brass to bronze vide RDSO’s letter No. EL/2.2.13 dated 21.11.2014.

4.2.6.2 HITACHI TRACTION MOTOR TYPE HS-15250A : To reduce the amount of counter weight in balancing the Armatures, dynamic balancing of Armature stack (before winding) with commutator and correction thereafter has been started. To maintain the specified depth(2 to 2.5mm) of mica undercutting of commutator, the process of

diamond turning before mica undercutting has been started. 4.2.6.3 INNOVATIONS & DEVELOPMENTAL WORK IN T.M . SHOPS :

To gear up for the increased 3-Phase Traction Motor production, a new AC enclosure has been set up for 3-Phase Stator winding with new Stator coil winding fixture.

Induction brazing woirk of 3-Phase Rotor has been strengthened for Scheme-I & II Rotors by installation of a new Induction Brazing machine, thereby increasing the production by 35%.

Production Performance of Manufacturing Shops

Sl No. Name of items 2013-14

2014-15 (upto Dec’14)

2015-16 (upto Dec’15)

Comparison of production of 2014-15 with 2013-14 Excess(+), Less(-)

1. Wheel set assembly 278 L/S 189L/S 212L/S (+) 23L/S

2. Hitachi Magnet Frame 180 nos 117 nos 80 nos (-) 37 Nos

3. Stator 3-phase 459 nos 392 nos 354 nos (-) 38 Nos 4. WAP-7 Head Stock 46.5 L/S 23 L/S 23.5 L/S

Page 19: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

4.3 Production Performance of Steel Foundry : 4.4.1 Production & Despatch of Steel Castings over last five years—

4.4.2 Production of Despatch of FC Bogies over last Five years—

4.4.3 Production & Desp. Of RIC Bogie Castings over last five years—

27362976

27702500

1708

2852

4094

2632

20181587

0

500

1000

1500

2000

2500

3000

3500

4000

4500

2011-12 2012-13 2013-14 2014-15 2015-16 (upto Dec)

Production Despatch

60 66

98112

30

76

95

6756

65

0

20

40

60

80

100

120

2011-12 2012-13 2013-14 2014-15 2015-16(upto Dec)

Production Despatch

47 51

120

54

0

108

4633

14

36

0

20

40

60

80

100

120

140

2011-12 2012-13 2013-14 2014-15 2015-16(upto Dec)

Production Despatch

Page 20: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

Annexure – I

YEARLY OUTTURN OF ELECTRIC LOCOMOTIVES FROM CLW

Year

WCM-5

DC WCG-2

ACMT WAG-1 WAG-4

ACMT (WK) WAM-4B

WAG-5A

ACMT WAP-1,3,4

ACMT WCAM-4

WAG-7

DC WCM-6 WCG-3

ACMT WAM -4

WAG- 9

WAP -5

WAP -7

Grand Total

1961-62 05 5

1962-63 14 14 1963-64 2 2 4 1964-65 27 27 1965-66 32 32 1966-67 57 57 1967-68 50 50 1968-69 28 28 1969-70 31 31 1970-71 3 41 06 50 1971-72 6 40 46 1972-73 14 41 55 1973-74 14 36 50 1974-75 13 1 32 46 1975-76 4 4 46 54 1976-77 3 13 28 44 1977-78 18 41 59 1978-79 5 11 40 56 1979-80 2 6 43 51 1980-81 11 4 54 69 1981-82 17 33 50 1982-83 2 51 53 1983-84 17 21 9 47 1984-85 49 1 50 1985-86 54 54 1986-87 70 1 71 1987-88 65 1 66 1988-89 98 2 100 1989-90 100 5 105 1990-91 102 8 110 1991-92 104 10 1 115 1992-93 108 12 5 125 1993-94 105 15 20 140 1994-95 105 15 30 150 1995-96 61 14 59 1 135 1996-97 25 18 111 1 155 1997-98 28 137 165 1998-99 45 112 8 165 1999-00 60 50 8 1 1 120

Page 21: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

2000-01 50 62 5 2 1 120 2001-02 34 40 6 - 2 82 2002-03 28 27 7 1 6 69 2003-04 32 36 9 - 9 86 2004-05 32 36 11 2 9 90 2005-06 40 60 24 1 4 129 2006-07 37 77 35 - 1 150 2007-08 47 98 49 3 3 200 2008-09 51 115 31 3 20 220 2009-10 40 120 39 3 18 220 2010-11 40 120 40 12 18 230 2011-12 44 126 45 12 19 246 2012-13 37 123 57 13 40 270 2013-14 27 100 93 13 31 264 2014-15 35 70 98 07 40 250 2015-16 30 35 99 9 32 205 TOTAL 21 57 268 54 1067 843 53 1770 02 500 664 82 254 8828

Summary as on 31.12.2015

Steam locos – 2351 nos. Diesel locos – 842 nos.

Electric locos – 5635 nos. Total -- 8828 nos.

Page 22: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

Annexure - II

ANNUAL PRODUCTION OF TRACTION MOTORS AT CLW

Year MG-1580 TAO-659 HS15250A 6FRA6068 6FXA7059 TOTAL 1969-70 92 - - - - 92 1970-71 92 - - - - 92 1971-72 18 129 - - - 147 1972-73 - 75 - - - 75 1973-74 - 195 - - - 195 1974-75 - 255 - - - 255 1975-76 4 349 - - - 353 1976-77 12 233 - - - 245 1977-78 12 425 - - - 437 1978-79 8 425 - - - 433 1979-80 8 385 - - - 393 1980-81 10 432 - - - 442 1981-82 5 430 - - - 435 1982-83 8 420 - - - 428 1983-84 4 361 - - - 365 1984-85 1 305 - - - 306 1985-86 3 325 - - - 328 1986-87 12 440 - - - 452 1987-88 6 380 - - - 386 1988-89 8 350 79 - - 437 1989-90 14 350 - - - 364 1990-91 9 450 21 - - 480 1991-92 5 500 80 - - 585 1992-93 6 500 95 - - 601 1993-94 2 400 250 - - 652 1994-95 - 220 422 - - 642 1995-96 - 92 630 - - 722 1996-97 - 36 701 - - 737 1997-98 - 4 750 - - 754 1998-99 - - 755 6 - 761 1999-00 - - 600 6 4 610 2000-01 - - 528 30 - 558 2001-02 - - 400 36 4 440 2002-03 - - 320 76 14 410 2003-04 - - 392 124 8 524 2004-05 - - 417 128 4 549 2005-06 - - 726 205 - 931 2006-07 - - 761 276 4 1041 2007-08 - - 896 321 8 1225 2008-09 - - 881 316 5 1202 2009-10 - - 815 390 24 1229 2010-11 - - 1000 373 44 1417 2011-12 - - 900 332 43 1275 2012-13 - - 913 564 60 1537 2013-14 - - 676 844 42 1562 2014-15 - - 672 759 19 1450 2015-16 (upto Dec’15)

- - 400 774 8 1182

Total 339 8466 15080 5560 291 29736

Page 23: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

Annexure - III ANNUAL PRODUCTION OF STATIC EQUIPMENTS AT CLW

YEAR

Motor Contactor (MC)

Shunting Contactor (SC)

Electric Magnetic Contactor (EMC)

Breaking ExcitationContactor (C145)

Reverser (J)

Traction Breaking Switch (CTF1,2 & 3)

Master Controller (MP)

Inductive Shunt (SJ)

Smoothing Reactor (SL)

1972-73 125 864 592 -- 123 -- 121 129 46 1973-74 185 754 495 -- 102 -- 94 171 73 1974-75 135 624 449 -- 120 -- 104 103 49 1975-76 257 812 576 -- 104 -- 123 147 70 1976-77 243 816 560 005 101 015 118 183 64 1977-78 348 637 664 023 113 031 147 234 74 1978-79 349 692 628 023 100 019 134 210 75 1979-80 330 838 667 009 092 022 126 231 66 1980-81 412 843 729 001 112 041 146 219 52 1981-82 514 784 709 065 126 124 157 209 90 1982-83 630 885 606 049 118 154 149 175 92 1983-84 776 548 696 112 100 165 140 066 100 1984-85 646 268 740 136 129 191 133 050 80 1985-86 686 480 860 076 125 213 155 039 104 1986-87 598 608 960 062 137 213 167 019 140 1987-88 604 416 1016 075 154 220 168 012 170 1988-89 602 616 830 101 336 167 203 150 210 1989-90 662 1200 920 110 238 282 230 215 220 1990-91 700 1800 960 120 240 345 240 310 240 1991-92 740 2360 1075 105 250 360 250 340 242 1992-93 750 2400 1124 100 295 405 290 390 250 1993-94 906 2718 1216 133 337 409 300 400 280 1994-95 972 2945 1162 157 324 450 320 480 300 1995-96 948 2630 1057 138 316 384 300 404 254 1996-97 868 2752 976 130 276 378 292 450 308 1997-98 980 2268 1105 157 339 439 342 495 340 1998-99 982 3577 983 128 350 453 343 500 321 1999-00 853 2672 932 139 291 339 285 390 260 2000-01 728 2469 952 129 328 408 237 268 224 2001-02 698 1565 549 122 277 390 200 280 210 2002-03 490 1244 740 80 158 340 165 154 164 2003-04 580 1796 1089 171 249 246 200 212 151 2004-05 534 1770 696 141 183 286 178 213 124 2005-06 708 2430 1066 181 256 450 232 322 206 2006-07 810 2500 965 200 268 446 270 375 239 2007-08 1020 2800 1020 222 324 416 275 457 304 2008-09 933 2588 1044 158 272 482 338 362 196 2009-10 480 1560 520 80 160 240 160 232 149 2010-11 480 1560 520 80 160 240 180 271 124 2011-12 480 1560 430 80 156 210 180 259 145 2012-13 480 1560 430 80 140 210 210 231 139 2013-14 408 1155 270 64 109 172 114 211 126 2014-15 105 533 12 38 61 140 200 180 103 2015-16 (upto Dec’15) 50 64 0 0 12 18 109 168 68 Total 25785 65961 33590 3980 8561 10513 8825 10916 7242

Page 24: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

DESIGN & DEVELOPMENT INCLUDING TOT

5

Page 25: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

5. CENTRE FOR DESIGN & DEVELOPMENT

5.1 Development of IGBT Technology based Power Converter for 3-phase Locomotives The present Power Converter is based on GTO technology which has been outdated and being replaced by state of art IGTB technology. Orders have been placed on M/s. BHEL, M/s CGL M/s BTIL & M/s ABB. Status:- BTIL: First loco with IGBT based Traction Converter commissioned in loco 31234 and turned out from CLW on 18.12.09. The loco is homed at ELS/GMO in DHN division. Presently 61 locomotives with BTIL supplied IGBT based traction converters are running. BHEL: First loco with IGBT based Traction Converter commissioned in loco 31248 and turned out from CLW on 04.10.10 homed at ELS/LGD in SC division. Presently 126 locomotives (excluding 15 propulsion system) with BHEL supplied IGBT based traction converters are running. CGL: One set commissioned in loco No. 31412 and dispatched to ELS/GMO in Sept’13. Clearance for the supply of balance sets accorded. 03 locosets under commissioning. ABB: First loco with IGBT based Traction Converter commissioned in loco 31281 and turned out from CLW on 10.02.11 homed at ELS/AQ in NGP division. Presently 93 locomotives with ABB supplied IGBT based traction converters are running.

CLW has switched over to 100% use of IGBT technology from 2016-17 onwards. 5.2 Development of IGBT Technology based Auxiliary Converter for 3-phase Locomotives The Auxiliary Converter presently being used are also GTO technology based which is getting obsolete. In order to adopt the latest IGBT technology, this project has been undertaken. Orders have been placed on M/s. BHEL, M/s CGL, M/s BTIL, M/s Hirect, M/s AAL & M/s ABB. Status:- BHEL: First loco with IGBT based Auxiliary Converter commissioned in loco 31248 and turned out from CLW on 04.10.10 homed at ELS/LGD in SC division. Presently 101 locomotives (excluding 15 propulsion system) with BHEL supplied IGBT based Auxiliary converters are running. AAL: Loco No. 31415 (WAG-9H) dispatched to ELS/TKD on 01.08.2013. clearance for the supply of balance sets accorded. Supply yet to commence. HIRECT: Prototype unit commissioned in Loco no. 31563 dispatched in Dec’14. Supply of balance sets to commence after field trial and RDSO clearance of prototype unit. CGL: prototype unit commissioned in Loco no 30325 and dispatched to ELS/LGD in SC division on 29.10.2012. Presently 149 locomotives with CGL supplied IGBT based Auxiliary converters are running. ABB: Converter commissioned in loco 31351 (WAG-9H) & was turned out from CLW on 31.08.12. Presently 21 locomotives with ABB supplied IGBT based Auxiliary converters are running.

CLW has switched over to 100% use of IGBT technology from 2016-17 onwards.

5.3 Development of Open Platform Control System for Vehicle Control with TCN compatibility The control system used in 3-phase loco based on MICAS-S2, which is proprietary of BT. CLW has taken up a project to develop control system hardware and software based on published IEC standards viz. IEC-61375 TCN. CLW has placed P.O. on M/s. BHEL for 3 sets & M/s. Stesalit for 02 sets. Status:- BHEL: 1st loco set commissioned in Loco No. 31295 (WAG-9) LGD since Oct.’11. The loco is running under ELS LGD since Oct.’2011. Remaining 02 sets commissioned on loco Nos. 31367 & 31399.

Page 26: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

5.4 Indigenous development of TCN compliant vehicle control system through C-DAC. This project has been undertaken through C-DAC for development of TCN compatible vehicle control system which will ensure compatibility between open standard equipments of different makes. MoU is for developing 02 sets of TCN compliant vehicle control system. Firms have shown interest in EOI for transfer of technology from C-DAC. Status:

Commissioning has been completed in loco No. 31356 (WAG-9H). Loco dispatched to ELS/TKD. Performance is satisfactory.

2nd unit commissioned on loco No. 30429 and dispatched to ELS/BIA. Tripartite Agreement for Transfer of Technology of TCN complaint vehicle control system signed between

CGL and BHEL with C-DAC/CLW.

5.5 Development of modular and Universal Aux. Converter for Locos & EMUs with C-DAC

This project shall result in development of a modular universal auxiliary converter for railway rolling stock. C-DAC/TVC is executing the project. MoU is for developing 07 prototypes of 130 kVA of modular and Universal Aux. Converter. Status:

Prototype has been received at CLW. Full load test completed in loco no. 31356 (WAG-9H). Test results evaluated by C-DAC.

C-DAC to advise CLW for the installation of 01 locoset after necessary validations. 5.6 Development of Wireless remote control for control of slave locomotives on a train.

This project has been taken up as per RSP provision. The project shall help develop wireless communication amongst locomotives in a train formation leading to better adhesion and other operational advantages. 2 sets of this system have been ordered on M/s ARC Bangalore for 3-phase locomotives. Status:

The prototype has been installed in loco nos. 31282 (WAG-9) & 31284 (WAG-9). Loco has been put into commercial service w.e.f. 18.05.2012.

2nd set has been installed on loco No. 31525 & 31526 and dispatched to ELS/TATA . Final field being carried out in association with RDSO and shed.

5.7 Development of Hotel load Converter This is for utilizing OHE power for supply of hotel load of coaches through HOG Scheme by providing Hotel Load converter in the locomotive. Order placed on AAL, Siemens, BHEL, ABB and Medha. Status: Siemens:

Hotel load converter fitted in 30277 (WAP-7) and dispatched to GZB on 30.06.2010. Commercial service of the loco started on 21.02.2011.

Presently 09 Locomotives with Siemens supplied Hotel Load Converter are in service. 11 more sets have been received at CLW. Under installation at CLW.

BHEL: 1st set commissioned on Loco no 30426 and dispatched to ELS/RPN in Aug,15.

AAL: Prototype unit received. RDSO to clarify for remaining test to be carried out on the converter.

Page 27: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

ABB: Type test conducted jointly by CLW & RDSO from 04.02.2014 to 14.02.2014 and again from 17th to 23rd November 2014 after modification of test setup for electrical tests. RDSO to issue type test clearance. MEDHA:

Loco No. 30375 (WAP-7) dispatched to ELS/GZB. Field trial conducted successfully on NDLS –Kalka Shatabdi in presence of RDSO representatives. Second set received in March 2016. Under installation on locomotive.

5.8 Development of Alternate Drive Gear Assembly for WAP5 AC Electric Locos (160 Kmph). This project will address the reliability issues of the presently used Hurth coupling by way of improved design of the transmission system. P.O. of 5 loco sets (20 Nos.) of new type of Drive Gear system placed on M/s Arihant Electricals. Status: One loco set commissioned in Loco No. 30056 (WAP-5). Loco sent to ELS/Vadodara on 15.11.2012. Presently 04 locomotives with M/s Arihant Electricals supplied Drive Gear system suitable for 160 kmph are

running. Expression of interest (EOI) for development of Alternate Gear Drive System for WAP-5 locomotive

uploaded on CLW website. 5.9 Development of Alternate Drive Gear Assembly for WAP5 AC Electric Locos (200 Kmph). This project will address the reliability issues of the presently used Hurth coupling by way of improved design of the transmission system. P.O. of 2 loco sets (08 Nos.) of new type of Drive Gear system placed on M/s Arihant Electricals. Status:

Prototype unit commissioned on loco no. 30086. Loco dispatched to ELS/GZB in Oct’15. Balance set to be supplied after successful field trial.

5.10 Indigenous development of propulsion system IGBT based 3-phase propulsion system consists of traction converter, auxiliary converter, and control electronics (Vehicle control unit). Orders have been placed on M/s BHEL, M/s MEDHA, M/s AAL, M/s ABB & M/s SIEMENS. Status:

BHEL: 1st loco set installed on Loco no. 31347 (WAG-9) dispatched to ELS/LGD on 11.07.2012. 14 more locomotives have been commissioned and running in field.

MEDHA: 1st set installed on Loco No. 31427 (WAP-7) dispatched to ELS/LGD on 31.10.2013. Presently 28 locomotives with M/s Medha supplied propulsion system are running.

Page 28: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

QUALITY ASSURANCE

6

Page 29: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

6 QUALITY ASSURANCE

6.1 QUALITY OBJECTIVES: 6.1.1 Inspection of locomotives and its components in the Inspection Shops to be done 100% on the basis of Work

Instruction and their related Design, Drawings, Specifications and relevant Standards to meet Quality requirement on continuing basis.

6.1.2 Inspection within fortnight from date of receipt of call letter for inspection of Purchase Items.

6.1.3 5% of total Inspection of Outstation Venders or minimum 5 numbers of Inspection offered per month are to be

personally inspected by the Outstation Officer in-charge. (N.B. SL. No. 6.1.2 & 6.1.3 above are applicable only for Out Side Inspection Wings of CLW i.e.

Dy.CEE/I&D/NDLS, Dy.CEE/I&D/Mumbai, Dy.CEE/I&D/Bangalore & Dy.CME/I&D/HWH) 6.2 OTHER OBJECTIVES:

6.2.1 Constant endeavor for Quality improvement of the products at all stages of manufacturing which are turned

out from different shops of CLW. 6.2.2 To carry out inspection of various assembly and sub-assembly at TM Shops, Static Equipment Shops, HMS,

LMS, Loco Fabrication & Assembly Shops and also Steel Foundry Shops. 6.2.3 To certify the Material Movement Slip for movement of products conforming to the drawings/WI/Specification

from one shop to other and consequently clearing Job Cards related to that product.

6.2.4 To prepare Loco Inspection Certificates and sent the same to User Railways. As per previous year’s commitment, 100% Scanned Inspection Data are used to make the Soft Copy of Loco Inspection Certificates of locomotive to be produced in the financial year 2014-2015 onwards.

6.3 ACHIEVEMENTS:

6.3.1 Inspection Check points have been introduced in bending radius of Compressor Lugs of three phase loco to

reduce the cracks generations at Lugs. 6.3.2 On trial basis the camber of 15mm in place of earlier 10mm has been introduced for roof girder/channel to

minimize the gap between roof and girder which were causing roof leakage. 6.3.3 Tail lamp bracket has been ensured to be fitted after introducing new check points and repeated NC arisen. 6.3.4 Safety sealing of Traction Motors at the loco underframe have been provided by constant booking and

monitoring to ensure safety. 6.3.5 Fitment of Leather Bellow in place of Rubber Bellow has been mostly ensured by repetitive booking and

constant monitoring to ensure durability and flexibility.

6.3.6 100% NDT test implemented on different types of Axle and Wheels for better quality control. 6.3.7 To overcome the bearing cease problem during MSU fitment in three phase locomotives, new check points at

X-clearance and D-clearance have been introduced on Wheel Set Assembly. 6.3.8 To improve the performance of power transmission drive in Traction Motors, proper matching of the gear with

pinion has been ensured by colour coating procedure. . 6.3.9 To improve the quality of Flexi-coil Bogie rectification is restricted up to the R-2 stage of Radiography Test.

Page 30: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

6.3.10 On the basis of customer feedback received in the past, fresh inspection check points have been introduced in the fitment of the following items during shell fabrication for quality improvement.

a) Floor Ventilation Ducting and Machine Room Entrance Door on shell of WAP 5 locos. b) Under Slung Compressor and Battery Box Stools on WAP-4 Shell at USD Stage.

c) Compressor Leg at USD Stage on both WAG-9 & WAP-7 locos. d) CBC on all types of locos. 6.3.11 Keeping in view the recently received customer complaint on welding joint failure of WAG-9 loco,100% DP Test has been introduced for the four joints between Cross Box and Transformer rod pillar mounting base of Central Under-frame.

6.3.12 The huge back log (due to change in format of loco ICs and other unavoidable reason) of preparation of Loco Inspection Certificate and issue the same to user shed have been almost up dated by clearing record 1016

numbers of loco ICs in the last eighteen months (w.e.f. 1st July 2013 to 31st January 2016). 6.3.13. Recently in spite of acute shortage of Staff and Supervisors in various Inspection Shops as well as in Loco

IC Cell, upgradation of Loco Inspection Certificate in to 100% soft copy along with reduction of back log as state above have been achieved.

6.4 METALLURGICAL & CHEMICAL LABORATORY

Metallurgical & Chemical Laboratory under control of Dy. CC & M and assisted by 01 Sr. Scale & 03 Jr. Scale officers are responsible for quality assurance of Electric Loco components and miscellaneous mechanical items by conducting metallurgical, chemical and non-destructive test of casting, forging & fabricated components as well as physical-chemical test of non-metals, rubber items, paints & oil & lubricants. It consists of three units i.e. main Lab., NDT Lab, loco works and Steel Foundry.

The M & C Laboratory ensures quality control of inputs and finished products of Steel Foundry including

stage wise process control. The M&C wing of Steel Foundry ensures quality control of castings like CO – CO Bogie, FC bogie, Bolster, Casnub bogie, Suspension tube etc. It also ensures quality control of different raw material of Steel Foundry like Ferro – manganese, Silico – Manganese, Ferro-silicon, Ferro - molly, iron ore, silica sand, core binders, bentonite power etc. It also ensures quality control of furnace consumables like basic lining bricks, high alumina bricks, ladle bricks etc.

NDT Lab./SF arranges radiography of various casting to ensure casting quality as per specification. Main activities of M&C organization is as under:-

i) Chemical analysis of Ferrous & non-ferrous alloys using spectrometer. ii) Review of specification from time to time for quality improvement. iii) Internal & external ISO: 9001 & ISO: 14001, OHSAS-18001 audit as per ISO requirements. iv) All Lab. IMTE’s calibration in time both in Main Lab & SF. v) Testing of Loco items as per Loco production target to meet the requirement. vi) Testing of water samples and controlling various parameters of drinking water requirements.

Metallurgical & Chemical Lab conducts metallurgical investigations of in-service failures of components of

CLW built Locomotives. It maintains liaison with RDSO, BIS & other Non-Railway institutions on M&C matters.

Page 31: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

6.5 PERFORMANCE w.e.f. 01-01-2014 to 31.12.2014 and 1.1.15 to 31.12.15 6.5.1 METALLURGICAL & CHEMICAL LAB/LOCO: (Upto Dec ’15)

Sl.

No. Name of Lab.

No. of Sample Tested Nos. of Tests No. of Sample

Accepted % of Rejection

2013 2014 2015 2013 2014 2015 2013 2014 2015 2013 2014 2015

1. Metallurgical/ Mechanical Lab.

3135 3480 2995 6637 7116 6084 3040 3406 2928 3.15 2.12 2.24

2. Chemical Lab. 3421 3125 2481 19489 18220 13574 3392 3054 2461 0.93 2.27 0.81

3. Filter House Lab.

2014 2020 3058 16895 16821 14285 2014 2020 3058 Nil Nil Nil

4. Rubber , DMC, I. M. & Lubricant

257 221 166 354 445 728 235 208 152 8.56 5.88 8.43

TOTAL

8827 8846 8700 43375 42602 34671 8681 8688 8599 - - -

6.5.2 NDT LABORATORY (LOCO):

Sl. No. Name of Lab.

No. of Sample Tested Nos. of Location/

Component Tested Nos. of

Component Accepted % of Rejection

2013 2014 2015 2013 2014 2015 2013 2014 2015 2013 2014 2015

1. Ultrasonic Testing 9786 8785 8173 27744 26129 25770 9513 8720 8045 2.78 0.73 1.57

2. M P T 5517 4864 4546 15315 12257 12393 5510 4864 4546 0.12 Nil -

3. Radiographic Test 166 359 267 166 359 166 Nil 294 238 - 18.38 10.9

4. Misc. 1709 1207 1326 3114 3374 3897 1696 1207 1323 0.76 Nil 0.23 TOTAL

17178 15215 14312 46339 42119 42226 16719 15085 14152 - - -

6.5.3 METALLURGICAL & CHEMICAL LABORATORY /STEEL FOUNDRY: CHEMICAL LABORATORIES:

Sl. No. Name of Lab. No. of Sample Tested Nos. of Tests

2013 2014 2015 2013 2014 2015

1. Chemical Lab. 2773 3024 2035 16770 16898 7322

2. Chemical Misc. 135 149 39 949 972 192

TOTAL 2908 3173 2074 17719 17870 7514

Page 32: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

6.5.4 FIELD LABORATORY/S. F. :

Sample Test Physical & Radiographic Tests

Sl. No. Name of Test No. of Tests Name of Test

No. of Tests

2013 2014 2015 2013 2014 2015 1.

Zircon Wash 39 66 70 Tensile Strength 1250 1318 451

2. Green Sand 5689 5726 4131 Microstructure 505 525 303 3. Permeability 983 972 1644 Charpy 0 0 0 4. No-bake Sand 958 992 5294 Hardness 985 926 6242

5. Silica Sand 76 78 2046 Radiography Exposures 11119 11478 8770

Total 7745 7834 13185 Total 13859 14247 12766

Page 33: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

Marketing including export ( Supply of spares to Zonal Railways )

7

Page 34: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

7.Supply of spares

7.1 LIAISON & SERVICES WING:

Electric Loco Sheds and POH/Repair shops over Indian Railways are engaged in maintenance of Locomotives. The Liaison and Service (L&S) Wing of CLW is to perform the task of meeting the requirements of Capital spares allotted by Railway Board & Railways’ own needs of Spares for maintenance. Broadly Liaison and service wing performs the following functions.

7.2 FUNCTIONS:

Consolidating the demands in the form of Requisitions/indents from Railways and RSP Sanctions for purchased and Shop manufactured including imported items.

Co-ordination with Stores department for the procurement of such spares and to issue work orders for the shop manufactured item.

Supplying spares to the railways through stores/shops taking as per demand and availability and to maintain accountal of such supplies.

7.3 SPARES TO RAILWAYS: The supply of spares to various user Railways is one of the most important function of L&S wing. All-out

efforts are made to fulfill the demands of Capital spares as well as the requirement of spares by the Railways. In the year 2015-16 spares worth Rs 8283.63 lakhs (as on 31.12.15) were supplied to the Railways. The break up of the same may be seen at Annexure -B.

Page 35: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

CLW / CHITTARANJAN

SUPPLY OF SPARES TO ZONAL RAILWAYS AGAINST RLY BOARD’S RSP & REQUITIONS OF ZONAL RAILWAYS IN DECEMBER 2015 ANNEXURE- A (All Costs are in Rs. Lakh) Sl. Item description QUANTITY SUPPLIED DURING DECEMBER 2015 Tota

l qty. Total

cost of supply

CR B/ Req

ECoR B/ Req

ECR B/ Req

ER B/ Req

NCR B/ Req

NR B/ Req

SCR B/ Req

SECR B/ Req

SER B/ Req

SR B/ Req

WCR B/ Req

WR B/ Req.

Other ZR

1. TM for G-9/P-7 (3Ф) 2. TM for P-5 (3Ф) 3. Stator of TM for G-9 (3Ф) 4. Rotor of TM for G-9 (3Ф) 5. Rewind Stator (3Ф) 6. Transformer of G-9 (3Ф) 1 1 107.17 7. Transformer of P-5 /P-7(3Ф) 8. Auxiliary Converter (3Ф) 9. Central Electronics (3Ф) 10. Traction Converter (3Ф) 1 1 233.01 11. Speed Sensor (3Ф) 12. Master Controller (3Ф) 13. O.C.B. Unit (3Ф) 2 2 5.75 14. HB-1/HB-2 (3Ф) 15. E-70 Brake System (3Ф) 16. Access tool System (3Ф) 17. Trade Brake Arrangt. (3Ф) 18. Driver’s Display Unit (3Ф) 10 2 12 47.45 19. TM (Hitachi) 6 2 14 22 688.33 20. TM (H)-Armature 21. Transformer 5400 KVA 22. Static Converter 2 2 43.76 23. Vigilance Control Device 24. High Speed Pantograph 2 2 4 4.88 25. Oil free Compressor 2 2 27.52 26. VCB 2 2 5.71 27. DBR (Roof Mounted) 28. DBR (Vertical) 29. RSI 2 2 32.31 30. Tap Changer 1 1 29.09 31. MP Based FDCS 2 1 3 34.45 32. DI/DU Relay 33. Smoothing Reactor (SL-30) 34. Reverser-J 35. C.T.F 36. E.M.C. 37. Motor Contactor 36 36 13.54 38. Shunting Contactor 24 24 48 8.02 39. Master Controller 40. C-145 5 5 1.95 41. Inductive Shunt (SJ) 42. Co-Co Bogie Machined

WAG-7 2 2 16.11 WAP-4 WAG-5 WAP-5 WAP-7 WAG-9

Page 36: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

(2)

Contd……

Sl. Item description QUANTITY SUPPLIED DURING DECEMBER 2015 Total qty.

Total cost of supply

CR B/ Req

ECoR B/ Req

ECR B/ Req

ER B/ Req

NCR B/ Req

NR B/ Req

SCR B/ Req

SECR B/ Req

SER B/ Req

SR B/ Req

WCR B/ Req

WR B/ Req.

Other ZR

43. Bogie with Brake Rigging WAG-7 1 1 9.51 WAP-4 WAG-5 WAP-5 WAP-7 WAG-9

44. Wheel & Axle Assly. WAG-7 WAP-4 WAG-5 WAP-5 WAP-7 WAG-9

45. Al. Gear Case WAP-5 46. Cast Bolster 47. Fabricated Bolster 48. Imported Rubber Bush

Cost of Misc. items in Rs. Lakh 36.28 2.45 41.45 26.01 45.54 23.30 17.87 13.89 146.40 70.84 424.03 Total cost of Rs. Lakh 609.34 2.45 158.27 135.22 100.78 25.74 17.87 451.93 146.40 84.59 1732.59

Page 37: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

CLW / CHITTARANJAN

SUPPLY OF SPARES TO ZONAL RAILWAYS AGAINST RLY BOARD’S RSP & REQUITIONS OF ZONAL RAILWAYS IN APRIL 2015 TO DECEMBER 2016 ANNEXURE- B (All Costs are in Rs. Lakh) Sl. Item description QUANTITY SUPPLIED UPTO DECEMBER 2015 Tota

l qty. Total

cost of supply

CR B/ Req

ECoR B/ Req

ECR B/ Req

ER B/ Req

NCR B/ Req

NR B/ Req

SCR B/ Req

SECR B/ Req

SER B/ Req

SR B/ Req

WCR B/ Req

WR B/ Req.

Other ZR

1. TM for G-9/P-7 (3Ф) 1 3 6 2 12 266.33 2. TM for P-5 (3Ф) 4 4 95.51 3. Stator of TM for G-9 (3Ф) 4. Rotor of TM for G-9 (3Ф) 5. Rewind Stator (3Ф) 6. Transformer of G-9 (3Ф) 1 1 1 1 4 422.27 7. Transformer of P-5 /P-7(3Ф) 1 1 2 249.06 8. Auxiliary Converter (3Ф) 1 1 2 97.62 9. Central Electronics (3Ф) 2 2 46.78 10. Traction Converter (3Ф) 1 1 233.01 11. Speed Sensor (3Ф) 12. Master Controller (3Ф) 13. O.C.B. Unit (3Ф) 4 2 2 3 5 4 20 80.70 14. HB-1/HB-2 (3Ф) 15. E-70 Brake System (3Ф) 1 2 3 100.38 16. Access tool System (3Ф) 17. Trade Brake Arrangt. (3Ф) 18. Driver’s Display Unit (3Ф) 10 4 6 2 8 4 34 131.51 19. TM (Hitachi) 8 2 2 12 4 9 7 4 2 44 8 102 2738.28 20. TM (H)-Armature 3 6 6 9 24 234.76 21. Transformer 5400 KVA 22. Static Converter 2 1 3 65.64 23. Vigilance Control Device 24. High Speed Pantograph 2 2 4 2 2 12 22.61 25. Oil free Compressor 2 2 27.54 26. VCB 2 2 5.71 27. DBR (Roof Mounted) 28. DBR (Vertical) 6 3 9 76.62 29. RSI 3 3 48.37 30. Tap Changer 1 1 2 58.18 31. MP Based FDCS 6 19 1 10 14 50 551.89 32. DI/DU Relay 33. Smoothing Reactor (SL-30) 5 4 8 95.76 34. Reverser-J 20 30 20 10 13 93 166.01 35. C.T.F 25 45 40 30 140 228.38 36. E.M.C. 50 20 30 100 19.28 37. Motor Contactor 24 36 50 30 140 52.58 38. Shunting Contactor 24 24 20 60 128 20.18 39. Master Controller 40. C-145 5 20 25 9.73 41. Inductive Shunt (SJ) 42. Co-Co Bogie Machined

WAG-7 2 2 16.11 WAP-4 WAG-5 2 2 24.44 WAP-5 WAP-7 WAG-9

Page 38: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

(2)

Contd……

Sl. Item description QUANTITY SUPPLIED UPTO DECEMBER 2015 Total qty.

Total cost of supply

CR B/ Req

ECoR B/ Req

ECR B/ Req

ER B/ Req

NCR B/ Req

NR B/ Req

SCR B/ Req

SECR B/ Req

SER B/ Req

SR B/ Req

WCR B/ Req

WR B/ Req.

Other ZR

43. Bogie with Brake Rigging WAG-7 1 1 2 19.02 WAP-4 WAG-5 WAP-5 WAP-7 WAG-9

44. Wheel & Axle Assly. WAG-7 WAP-4 WAG-5 WAP-5 WAP-7 6 6 94.38 WAG-9

45. Al. Gear Case WAP-5 46. Cast Bolster 47. Fabricated Bolster 4 4 15.46 48. Imported Rubber Bush

Cost of Misc. items in Rs. Lakh 268.82 2.45 79.06 223.73 130.00 99.33 89.87 9.59 332.66 610.78 123.26 1967.55 Total cost of Rs. Lakh 1034.39 371.11 720.59 893.98 310.05 672.18 354.29 31.47 2274.12 712.70 373.06 525.28 10.41 8283.63

Page 39: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

STATUS OF M&P

8

Page 40: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

8. MACHINARY AND PLANT

Manufacturing, M&P Maintenance, Transport, Machinery & Plant Procurement

Manufacturing group of shops consists of Heavy machine shop, Wheel shop, Light machine shop, Smithy & Forge shop, Heat Treatment shop and Tool Room. Millwright and Electrical Maintenance shops look after maintenance of all M&Ps of loco works, power supply and distribution inside loco works. MPP cell deals with planning and process for procurement & commissioning of machines sanctioned by Rly.Board & GM/CLW under M&P Plan Head-4100 & 4200. It also looks after TPT shop including Road and Industrial vehicle maintenance work and shunting work.

Manufacturing shops: (i) Wheel Shop: Wheel shop manufactures wheel sets for loco production as well as spares to Zonal Railways.

Presently wheel sets for WAP4, WAP5, WAP7, WAG7 and WAG9 locos are manufactured. (ii) Heavy Machine shop: Heavy machine shop undertake machining of components for loco production as

well as meeting the spares required for zonal railways such as suspension tube, 3-ph stators for WAG9 & WAP5 locos, Hitachi Magnet Frame, Equalizer & Compensating beams etc.

Machining work of Steel Castings from Steel Foundry like centre pivots of WAP4, CBC Coupler are also done in

HMS. (iii) Smithy & Forge shop: SFS undertakes fabrication of Head Stock of WAP7 loco, forging of small components of

loco assembly, assembly of casnub bogie as and when required. (iv) Light Machine Shop: Light Machine Shop manufactures small components like bushes, traction motor blower

holding plates etc. to meet requirement of loco production as well as spares required for zonal railways. (v) Tool Room: Tool room supplies tooling, gauges, jigs & fixtures for production requirements of various shops. It

also carries out calibration of various gauges, fixtures, instruments etc to meet the ISO requirements. (vi) Heat Treatment Shop: Heat Treatment Shop undertakes heat treatment of WAP7/WAG9 bogies manufactured in

Loco Shop and other items e.g. Magnet Frame, Equalizer, Compensating Beams etc. manufactured in Heavy Machine Shop.

(vii)Motorised Wheel Set Assembly: 52 Loco sets, tested Motirized wheel set assembly have been supplied up to

December’2015. It has helped the Bogie shop immensely in production of motorized bogie. Performance of Manufacturing Shop is furnished in Annexure-‘A’

Page 41: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

BRIEF REGARDING PLANT MAINTENANCE ORGANISATION(LOCO WORKS) CLW has more than 1800 M&Ps including 118 Nos. Cranes in Loco Works, out of which 50% of M&Ps are

overaged. The breakdown as well as preventive maintenance of M&Ps is carried out by the Plant Maintenance Organisation consisting of Millwright Shop (MTS-56) and Electrical Repair Shop(Shop-59). Plant Maintenance Organisation deals with repairing, reconditioning, re-engineering, retro-fitment of machineries and plant & electrical maintenance of lighting inside shops. Installation of new small machineries and plants, condemnation & uprooting of old M&Ps are also carried out by the Maintenance Shops-56 & 59.

8.2 SPECIAL WORK DONE (In maintaining health of M&Ps) 1. Bristol Crane No. 3854(26/E/03) was under long breakdown due to driving CT Wheel shaft bearing, Idle CT

Wheel Bearing & Plummer block found damaged. The same were replaced and fitted in the crane. Other related repairing work has also been done in the crane.

2. CNC Pipe Bending M/c No. 16/5611/31 is a critical machine. The machine has been reported under breakdown due to problem in main hydraulic pump. There was no spare available with MTS Stores. However, In-house Maintenance staff tried their level best and rectified the pump.

3. Two Nos. ESAB make Oxy cutting Machine were under long breakdown due to problem in scanner control card. The cards were repaired in house by Maintenance Wing of CLW and fitted in the machine.

4. HMT CNC Chucker Machine No. 20/0685/03 was reported defective due to mis-alignment of turret assembly. Plant Maintenance Wing investigate the defects thoroughly and due to their sincere and hard work, the alignment of the turret assembly restored.

5. 3 Phase Power supply for Oil Filtration Plant etc. and 12 Nos. Architechrural Column light have been provided in proposed Transformer Section at Bay-0 of Shop-19.

6. TC Milling Machine No. 08/2597/01 was under long breakdown due to Z axis drive defect. The problem was rectified in house by CNC/ERS staff and the machine was handed over to production on 28.08.15.

7. New Elgamil Universal Milling M/c No. 08/2594/01 for production of suspension tube went under breakdown due to cutter locking device fault. Air driven Hydro-pneumatic pump of the machine was not working. Pump seal kit of the machine was replaced and assembled after modifying the pump housing.

8. Wire DSL for EOT Cranes supply has been converted into Shrouded DSL in Shop-12, 17, 26 and 19(Bay-3). 9. Health checkup of 45 over aged EOT Cranes completed through outside agency (approved by Chief Inspector

of Safety/WB). 10. Testing and certification of Cranes (111 nos.), Chains (194 nos.), Hoists (66 nos.) and Pressure Vessels (56

nos.) completed through outside agency (approved by Chief Inspector of Safety/WB). 11. Commissioning of Energy efficient LED light as Bridge light of EOT Cranes for 04 cranes in Mfg. Shops and

01 Crane in AIF Go down has been made. Illumination of Pneumatic Test Shed at Saloon siding has also been done.

12. 1 No. Fire affected EOT Crane(4A) of Capacity 5T of Shop-19 complete repairing, rewiring done through outside agency and put in service.

13. Repairing and re-commissioning of Loco Lifting Jack at Bay-2 of Shop-19 has been done. 14. Mechanical Foot Brake of 8 Nos. Jessop make Crane has been done. 15. Renovation of Crane 0B of Shop-19 has been done

8.3 UPTIME AVAILABILITY OF CRITICAL MACHINES The availability of 80 critical machines in Loco Works has been 97.48%% during the year 2015-16 upto December, 15 as against the target of 92%. 8.3.1 CONDEMNATION OF M&Ps

During the year 2015-16 (upto 31st Dec 15), 36 nos. of machines have been condemned.

Page 42: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

Annexure ‘A’ 8.4 Production Performance of manufacturing shop

Sl No. Name of items 2013-14

2014-15 (upto Dec’14)

2015-16 (upto Dec’15)

Comparison of production of 2014-15 with 2013-14 Excess(+), Less(-)

1. Wheel set assembly 278 L/S 189L/S 212L/S (+) 23L/S 2. Hitachi Magnet Frame 180 nos 117 nos 80 nos (-) 37 Nos

3. Stator 3-phase 459 nos 392 nos 354 nos (-) 38 Nos

4. WAP-7 Head Stock 46.5 L/S 23 L/S 23.5 L/S

Page 43: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

8.5 STATUS OF MPP & M&P SECTION. 1. PLAN HEAD: 4100 (i) INDENTS PLACED DURING THE YEAR 2015-16 -( Position as on 31.12.15 )

( From April’2015 to

Dec’2015 )

COS COFMOW TOTAL

09 03 12

(ii) MACHINES FOR WHICH P.O. DUE (Position as on 31.12.15)

No. of Machines for which P.O. due Total COS COFMOW

20 15 05

(iii) P.O. PLACED DURING THE YEAR 2015-16 ( Position as on 31.12.15)

COS COFMOW TOTAL 08 01 09

2. PLAN HEAD: 4200 (i) INDENTS PLACED DURING THE YEAR 2015-16 ( Up to Dec’15 )

( From April’2014 to Dec’2015 )

COS COFMOW TOTAL Nil Nil Nil

(ii) MACHINES FOR WHICH P.O. DUE (Position as on 31.12.15)

No. of Machines for which P.O. due Total COS COFMOW

03 03 Nil

(iii) P.O. PLACED DURING THE YEAR 2015-16 ( Up to Dec’15 ) :-

(From April’2014 to Dec’2015)

COS COFMOW TOTAL 01 Nil 01

Page 44: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

(iv ) PROGRESS OF WORKS (M&P) PH-4200 :- ( As on 31.12.15 )

Dscription M/cs. Sancd.

Dro pped

Recd.

M/cs. Under proc.

Proc. Agency Indent Due P.O. due

P.O. placed Dely. Due. COF COS

50 Loco Proj.

2007-08

11 04 05 02 Nil 01 NIL 01 Nil COF COS COF COS COF COS

NIL Nil Nil 01 Nil Nil

200 Loco Proj. 2007-08

30 05 20 05 02 03 03 Nil 02

COF COS COF COS COF COS

Nil 03 Nil Nil 02 Nil

275 Loco Proj. 2010-11

18 03 07 08 02 06 06 02 Nil

COF COS COF COS COF COS

02 04 Nil 02 Nil Nil

TOTAL 59 12 32 14 04 10 02 07 Nil 03 02 Nil 3. Progress of works by M&P Deptt. during the year 2015-16

(Position from April’15 to Dec’15 during the year 2015-16 ) Particulars M&Ps

Received M&Ps

Under commissioning M&Ps

Commissioned. M&P Programme items sanctioned by Rly.Board

02 Nos 04 Nos 02 Nos

GM’s Out of turn items sanctioned by GM/CLW

09 Nos 04 Nos 07 Nos

Project items ( 200 Loco Project & 50 Loco Project & 275 Loco Project . )

01 Nos 03 Nos 02 Nos

Total 12 Nos 11 Nos 11 Nos 4. Machines under Installation & Commissioning – 11 Nos Nos. (As on 31.12.15 ) i) Plan Head – 4100 ( M&P Prog. items) - 04 Nos. SN

M&P Ref.

Description of machine Received on

Suppliers name Consignee

1 M&P 05-06

High speed continuous Sand Mixer with Sand Reclamation plant-01 no Cost 2.8cr

July,11 M/s. Ferro Crafts, Asansol, P.O no.05/2007/ 7004/ 89450 dt.21.06.10.

Dy.CME/ Plant/SF

2 M&P 09-10

Electric Arc furnace, Cost 6.16 crores,

15.03.13 M/s. Megatherm Electronics, Kolkata, P.O no. 05/ 2009/ 7003/91381 dtd.10.08.11

Dy.CME/ Proj/ SF

3 M&P 13-14

CNC Vertical Turret Lathe. (Swing dia. 1400 mm), PO Cost – 1.57 Cr. DRF

15.09.15 M/s. HYT Engg. Co. Pvt. Ltd., New Delhi, OP – 2309 dated – 10.09.14.

Dy.CME/ Mfg

4 M&P 11-12

Portable Radial Drilling Machine, DRF Qty.01 no., cost 35,99,958.

28.12.15 M/s. Energy Machine Tools, Jamnagar, COFMOW/ IR/ S-4757/P-I/OP-2219 Dt. 04.01.14.

Dy.CME/ELF

Page 45: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

(ii) GM’s Out of Turn Items :- 04 Sl. N

M&P Ref

Description, of Machine Recd. on Suppliers Name Consignee

1 GM OT 09-10

Capacitor Bank , 220K.VAR, CAP 27.25 lakhs

24.06.15 M/s. Voyager, Kolkata. PO no. 05/2009/7107/ 05230 dated – 24.04.2015

Dy.CME/P/SF

2 GM OT 13-14

Dimmer Stat Variable Auto Transformer Set 200 KVA , (Qty. – 02 Nos.) DRF 7.45 Lakhs each.

24.09.15 M/s. Deswetch Engineers, Thane, P.O.No.05/2014/ 7112/05560 dated – 18.06.15

Dy.CME/ELB

3 GM OT 12-13

Magnetic Particle Inspection Equipment (Qty. – 01 No.) CAP, 27.25 Lakhs

16.10.15 M/s. K. Electronics, Gujrat, P.O.No.05/2014/7107/05093 dated – 17.04.15

Dy. CC& M

4 GM OT 12-13

Induction Heater , DRF, PO cost 4,12,189

24.10.15 M/s. Unitech Instruments, Thane, PO no. 05/2014/7108/ 04938 dated –17.02.15

Dy.CEE/TMM

(iii) Plan Head – 4200 (Project Items) : 03 Nos Sl. N

Sanction Case No.

Description, Qty. & PO Cost

Recd. on Supplier, PO/AT No. Consignee & Location

1 275 Loco MT/AP/275/08

Axle Turning M/C for Shaft , Cost 1.69 crores

30.03.13 M/s. Askar Microns, Mysore, OP-2130 Dt. 23.04.12

Dy.CEE/TMM

2 PH 42, 275 Loco

MT/AP/275/18

EOT crane 5T 34.77 lakhs.

PO Cost - 2469472/-

26.09.14 M/s. Saico Cranes Pvt. Ltd, Nashik, OP-2235/13

Dy.CME(ELA

3 200 Loco Project

MT/AP – 200/19 COF

15Ton EOT crane (Qty. – 01 No.) PO Cost - 45.91 lakh

17.11.15 M/s. Krane Mfg., OP – 2231 dated – 09.06.14.

Dy.CME/ELF

8.6 Machines Commissioned – 11Nos. (Position from April’15 to Dec’15 during the year 2015-16) M&P Programme Items :-

Sl No

Item No. & Yr. of san.

Description, Qty. & P.O cost

MT / No Supplier’s Name/A.T / PO no. Consignee

1 M&P 10-11

Horizontal Boring m/c. Cost 2.35 crore

MT / 2096

M/s. Geeta Machine Tools, Jamnagar, G-619 dated- 30.01.12

Dy.CME / Mfg.

2 M&P 07-08

Plasma Cutting m/c.-01 no., Cost 1.42 crores,

MT/ 1904

M/s. Pro- Arc Welding & Cutting System (P) Ltd., Pune, 05/2007/7040/89488 dt.19.08.10

Dy.CME/ ELF, shop-17 (oxy-cut)

Page 46: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

GM’s Out of Turn Item :- Sl No

Item No. & Yr. of san.

Description, Qty. & P.O cost

MT / No Supplier & A.T / PO no. Consignee

1. GM OT 12-13

Portable Colour Doppler, m/c., 13.17 lakhs, WMS

MT/ 2156

M/s. Sigma Medical System, Kol., P.O no. 05/ 2014/ 7104/05105 dated-25.03.15

CMO/ KGH

2. GM OT 06-07

Profile Gas Cutting m/c. 02 nos, Cost 28.76 Lakhs.

MT/ 1828

M/s. Associated Industries & Trading Co., Kol, P.O. no. 05/2007/ 7072/71807 dt.21.01.09.

Dy.CME/ ELF,

3. GM OT 11-12

Ophthalmic combined A and B Scan with video printer. PO Cost-

9.05 lakh

MT/ 2141

M/s.Shri Hari International, Kolkata, PO No. 05/2012/7108/04411 dtd.17.10.14

CMO / KGH

4. GM OT 13-14

Defibrillator cum AED Machine, Cost

3.42 lakh WMS

MT/ 2172

M/s. Sigma Medical, Kolkata, PO No.05/2015/ 7102/05764 dated- 17.07.15

CMO/ KGH

5. GM OT 12-13

Portable Hydraulic Press, (100T) CAP, PO cost – 25.54 lakh

MT/ 2159

M/s. Jain Trading Co., Kolkata, PO no. 05/2014/ 7109/04713 dated – 22.01.15

Dy.CME/ Mfg.

6. GM OT 13-14

3 - D Optical Coherence Tomography with fundus photography Eombo instrument. WMS 29,98,000

MT/ 2170

M/s. Shri Hari International, Kolkata, P.O no.05/2014/7110/ 05846 dated-20.08.15

CMO/ KGH

7. GM OT 13-14

3 Ø Variable Voltage Transformer (Qty. – 01 no.) , 4,47 lakh,

MT/ 2176

M/s. Deswetch Engineers, PO no.05/2015/7103/ 05763 dated – 17.07.15

Dy.CEE/ TMM

Project Items under PH-42

Sl No

Item No. & Yr. of san.

Description, Qty. & P.O cost

MT / No Supplier& A.T / PO no. Consignee

1. 200 Loco Project

50 Ton EOT Crane (Qty. – 03 Nos.) PO Cost – 3.24 Cr.

MT/AP –200/05 COF

M/s. SAICO Engineers, Nasik, OP – 2229

Dy.CME/ ELF

2. 50 Loco Project

Paint Booth, 7.4679 Cr.

MT/AP -50/48

M/s. Global Engineers, New Delhi, OP-2020 Dt. 15.09.11

Dyt.CME/ ELA

8.7 Important M&Ps yet to be supplied upto SL No.

Item No. & year of sanction

Description Estimate No.

Supplier name & AT/PO No.

DP Status

1 1293 M&P 13-14

Double ended Facing, Centering, and Drilling Machine Qty. 01

MT/2166

M/s. Geeta Machine Tools

30.01.16 PO Placed. Delivery Due.

2 1262 M&P 13-14

Induction Brazing Equipment Qty. 01

MT/2165

M/s. EFD 31.03.16 PO Placed. Delivery Due.

Page 47: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

8.8 Transport Shop :- 8.8.1 Transport Shop maintains all road vehicles consisting of passenger vehicles like cars, jeeps, mini buses etc. for movement of officials and industrial vehicles like forklifts, dumpers, tractors, platform trucks/ Lister Trucks for movement of material inside and outside the shops. Shunting of rolling stocks is also the responsibility of Transport Shop. Availability of Material handling equipments (as on 31.12.15):-

FLT : 32 Nos. PLT : 26 Nos. Tractor : 02 Nos. Truck: 07 Nos., Tripper- 03 Nos. Bus: 02 Nos. Shunting Locos : 03 Nos. Sky Lifter : 05 Nos.

Passenger Vehicles : 23 Nos. - Maintained through in-house and outside agencies. 8.8.2 Performance of TPT-57 Shop

Availability particulars of FLT, PLT, Trucks & Shunting Locos :-

Sl.No.

Particulars Target Achievement During the year 15-16

( Up to Dec’15 ) 1. Availability of vehicles & material handling

equipments & passenger vehicle 95% 91 %

2. Shunting Loco Availability 100% 100%

Page 48: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

STEEL FOUNDRY

8A

Page 49: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

8A.1 OVERVIEW

Location of the Factory: P.O. & P.S. : Chittaranjan Dist : Burdwan, Pin – 713331 The Factory is located at Chittaranjan, Dist: Burdwan, West Bengal, approx. 305 km. from Kolkata. The location is well connected by road and rail from Howrah Station. Chittaranjan Locomotive Works, Steel Foundry, a unit of Ministry of Railway is set up for supplying Steel casting products of locomotives. It has two Arc furnace of 15T and 7T capacity. The 7T Furnace is being replaced by a 10T Arc Furnace, CLW follows stringent quality processes, duly certified with

ISO : ISO 9001::2008, ISO 14001:: 2004, ISO 18001 certified, Total Area of the Plant : 45 acres (182108.70 sq. m.) Covered Area : 12.4 Acres (50181.064 sq. m.) Product : Steel casting for rolling stocks

8A.2 IMPORTANT MILESTONES

ISO-9002 CERTIFICATE- In August 1996 Steel Foundry was awarded with the ISO-9002 Certificate for its Quality Standards.

ISO-9001:: 2008 CERTIFICATE- In October 2009 Steel Foundry was awarded with the ISO-9001 Certificate for its Quality Standards.

ISO-14001 CERTIFICATE- Steel Foundry was accredited with Environment Management System (EMS 14001:: 2004) in the year 2006 with the objective to regularly educate the staff, encouraging them to preserve the environment and conserve the environment as well as utilizing all the existing natural resources in a eco-friendly manner.

CLASS-A CERTIFICATE- Steel Foundry/CLW has been certified as CLASS-‘A’ FOUNDRY by RDSO on 9th August 2012 vide RDSO Vendor No. 419.

LOCO COUPLER- Production of Loco Coupler for Electric Loco has been started from August 2012 vide RDSO Vendor No. 419.

E- TYPE COUPLER- Production of E-type Coupler for Diesel Loco has been started from May 2013 vide RDSO Vendor No. 419.

GM BOGIE- Product is under development against the order of 40 Nos. of GM Bogie, 4th. Sample has been cast in month of Aug’15 and marking process has been done and it is waiting for Mechanical and Chemical clearance by RDSO.

H- TYPE TIGHT LOCK COUPLER- Order for 40 nos. of H-type tight lock Coupler has been

received from DLW/Varanasi. Pattern & Core Boxes received. Already two sample castings have been cast. Marking is okay. Gauging is under process. Procurement of assembly materials and gauging tools is under process.

Page 50: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

BLC BOGIE- It is under project. An order of 63 nos. of BLC Wagon Bogie has been received from Rly. Brd. The pattern and Core Boxes has been inspected at firm premises. The sample production will be will be started shortly after mounting the pattern on match plate by firm at SF/CLW.

8A.3 PRODUCT RANGE

8A.3.1 STEEL CASTINGS:

Loco-items—

Flexi coil Bogie for WAP-4 loco. Flexi coil Bolster for WAP-4 loco. Co-Co Bogie BG for WAG-5 & WDM-2 Loco. Suspension Tube for Hitachi TM. Suspension Tube for 3phase TM. Rotor Clamp for Hitachi TM. Commutator Spider for Hitachi TM. Centre Pivot for WAP-4 loco. Ballast Blocks for WAG-9 loco. Ballast Block for IGBT loco. Ballast Weights for WAG-7 loco. Loco Couplers for Electric loco (Assly. with Yoke, Knuckle also) Striker Castings for Electric loco. ‘E’ type Couplers for Diesel loco

Wagon Items—

Casnub Bogie for BOXNHL wagons Casnub Bolster for 22HS/BOXNHL wagons Casnub Side Frame 22HS/BOXNHL wagons. Bogie Centre Pivot Top 22HS/BOXNHL wagons Bogie Centre Pivot Bottom 22HS/BOXNHL wagons

C.B.Coupler Items (Wagon) — Knuckle for CB Coupler. Coupler Body for CB Coupler. Yoke for CB Coupler. Striker Castings for CB Coupler.

Spares for Zonal Railways— Suspension Tube for WDM-3D loco. Wheels for Tower Car. Wheels for Power Car Wheels for Narrow Gauge Coaches. Wheels for Narrow Gauge loco. Wheels for Kalka. Wheels for Gwalior.

8A.3.2 DEVELOPMENT OF NEW STEEL CASTING ITEMS:

(a) DEVELOPED & SUPPLIED REQUIRED TO RAILWAYS-

CB Coupler for Electric Locomotives Striker Casting for Electric Locomotives ‘E’ type Coupler for Diesel loco Striker Casting Wagon

Page 51: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

(b) UNDER DEVELOPMENT- Casnub Side Frame & Bolster for BLC Wagon ‘H’-type Coupler for Diesel Loco

(c) SAMPLE CASTING MADE-

GM bogie for DLW made WDG4 loco Clevis for Coupler items N.G. Wheel for N.F. Rly. N. G. Wheel for Kalka. N. G. Wheel for Gwalior.

8A.3.2 FABRICATED ITEMS for LOCO:

Side Sill Casnub Dummy Bogie(TG/TPP) Conversion of HH Dummy Bogie into TP Dummy Bogie

8A.4 QUALITY:

Steel Foundry/CLW, despite following Green Sand moulding system, is endeavoring to contain the rejection level within 3%. Rejection percentage for the last 5 years is produced below which show that they are contained within the targeted limit.

8A.4.1 QUALITY ASSURANCE MEASURES: (a) Switching over to Metal Patterns/Core-boxes-

With an objective to eliminate the casting defects owing to over-aged wooden patterns/core-boxes, induction of metallic patterns/core-boxes has been introduced. In this regard, Hitachi Suspension Tube, Knuckle, Coupler Body etc. for locos & wagons, metallic patterns and core boxes have been procured from out agencies. The quality of the relevant castings pertaining to dimension and surface finish has been improved.

(b) Mechanization of Foundry Process— Steel Foundry/CLW is in the process to adopt the Synthetic Sand Moulding System to

overcome the casting defects like- sand inclusion, poor surface finish, blow holes etc. being induced by the existing Green Sand Moulding Practice.

(c) Other Steps— In addition, following actions are being taken to improve upon quality/reduction in rejections—

Periodical checking of patterns & core boxes on quarterly basis.

Years Total Cast

(in MT)

Rejection

(in MT)

Target Rejection

Percentage

2011-12 2736 56 3 % 2.05 %

2012-13 2976 64 3 % 2.15 %

2013-14 2770 52 3 % 1.88 %

2014-15 2500 55 3% 2.20%

2015-16(Up to Dec) 1708 47 3% 2.75 %

Page 52: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

Use of exothermic sleeves to eliminate chances of shrinkage and cavities & to increase yield%.

Use of branded Zircon based mould washes to improve surface finish. Use of pouring ponds and tiles of high refractoriness in metal flow areas. Strict control over carbon boiling during melting to avoid pouring of gassy metals. Use of quick lime has been introduced to bring down phosphorous content of melt. Strict control on heat cycle during heat treatment of castings to achieve prescribed physical

properties. 100% load testing of Bogies & Bolsters to improve reliability in service.

8A.5 PRODUCTIVITY: Load Lifted per Direct Worker— The Allowed Time Discharged per Direct Worker per Month for the last 5 years has been as follows:

Years 2011-12 2012-13 2013-14 2014-15 2015-16 (Up to Dec)

AT Discharged 246 hrs. 253 hrs. 255 hrs. 232.56 hrs. 216.47

8A.5 PLANT & SAFETY: 8A.5.1Action taken to ensure Safety 2015-16

a) OHSAS -18001::2007 Audit conducted on 20.04.2015 and Auditor satisfied over the documentation of SF.

b) Fire Hydrant pressure of Steel Foundry checked by the staff of SSE (W)/WS-II on 13.05.15 and found satisfactory.

c) West Bengal Pollution Control Board / Asansol visited on 27.05.15 and conducted Stack Emission test of GADI furnace. The report received on 10-07-2015 and found Particulate matter 0.54 mg-Nm3 Which is within limit, kept in our record.

d) Work order issued to M/S. Indicative Consultant India for Work Environment monitoring which will indicate the position of air pollution, status of illumination level and noise level.

e) All documents required for modification of Steel Foundry Plant Lay out is submitted to Inspector of Factories/Asansol on 27-07-15 for approval of chief Inspector of Factories/Kolkata.

f) External Auditor conducted Audit of Steel foundry on 12-08-2015 and there is no adverse report/comments.

g) Compliance report submitted to Sr. Environmental Engineer, circle office/Kakinada, against memo no: 1142/WPBA/NOC(1909)/11 Dtd. 18-05-2015 on 15-07-2015 and again chased on 26-08-2015 about their opinion.

h) NOC for consent to establish for 10 Ton EAF (Meghatherm) in SF obtained from Sr. Environmental Engineer, circle office/Kankinara, West Bengal dated 23.09.2015.

i) Work Environment monitoring carried out by Inspector of Factories, West Bengal approved agency M/S Indicative Consultant India from 30.09.2015 to 01.10.2015, which includes Ambient, work Zone, Illumination and Sound level measurement in Steel Foundry.

j) “ON SITE EMERGENCY PLAN” has been prepared and copy submitted to I.O.F/Asansol for kind perusal on 29-10-2015.

k) Safety Audit of Steel Foundry by external agency conducted on 19-11-2015 to 20-11-2015.

l) I.O.F/Asansol visited Steel Foundry on 11-12-2015 to witness Hydrostatic test of Pressure Vessels.

m) Statutory Fire Extinguishers checked and revalidated by RPF/Fire which was due.

Page 53: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

8A.6 Machinery & Plant—

i. Synthetic Sand Moulding Plant of 10 MT capacities — Civil foundation work has been completed. Erecting work will be started by firm after joint inspection.

ii. Megatherm 10T Direct Arc Furnace — Complete material received. Civil work is under progress. PDC- May. 2016. A. Supplier : M/s Megatherm Electronics Pvt. Ltd. B. P.O. No. : 05/2009/7003/91381 dated 10-08-2011. C. P. O Cost : ` 6,16,45,113.00 D. Present Status as on 31.12.2015 :

i. Transformer Room :Completed. (All components are placed) ii. Cooling Tower :Civil work in water complex of 10T EAF is completed

(except Motor Pump Area) within 08.01.2015. Placement of components is not done. Pipe line work not started.

iii. Fume Extraction System Civil Work is completed within 08.01.2015. Placement of components is not done.

iv. Furnace Area Civil Foundation work started on 14.11.2014. Foundation work is under process.

v. Pipe Line Work Water pipe line from Furnace to Cooling Tower is not started.

Page 54: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

STAFF POSITION

9

Page 55: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

9. STAFF BREAK UP

STAFF BREAK UP DEPARTMENT WISE Gr. C & D (AS ON 31.12.15)

DEPARTMENT SANCTIONED STRENGTH

STAFF ON ROLL VACANCY

ACCOUNTS GROUP –C 532 362 170 GROUP –D 01 01 NIL Total 533 363 170 ADMINISTRATION GROUP –C 829 683 146 GROUP –D 10 10 NIL Total 839 693 146 CIVIL GROUP –C 829 713 116 GROUP –D 34 34 NIL Total 863 747 116 ELECTRICAL GROUP –C 3116 2551 565 GROUP –D 02 02 NIL Total 3118 2553 565 MECHANICAL

GROUP –C 6689 5764 925 GROUP –D 07 07 NIL Total 6696 5771 925 MEDICAL GROUP –C 616 377 239 GROUP –D NIL NIL NIL Total 616 377 239 PERSONNEL GROUP –C 299 283 16 GROUP –D NIL NIL NIL Total 299 283 16 RPF GROUP –C 533 386 147 GROUP –D Nil Nil Nil Total 533 386 147 S & T GROUP –C 53 48 05

GROUP –D NIL NIL NIL Total 53 48 05 STORES GROUP –C 966 639 327 GROUP –D 02 NIL 02 Total 968 639 329 TOTAL GROUP - C 14462 11806 2656

GROUP - D 56 54 02 GRAND TOTAL 14518 11860 2658

Page 56: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

UNIT COST OF THE PRODUCT

10

Page 57: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

10. UNIT COST OF THE PRODUCTS (Figures in thousands of Rs.)

a. Financial Year 2012-13 Type of Loco

Direct Labour

Direct Materials

Over heads

Total(ex. Pro. Chgs.)

Pro. Charges

Total(in pro.charges)

ED Total (in.ED)

WAP - 4 4098 53558 11744 69400 1041 70441 1400 718411

WAG-7 5001 50068 14031 69100 1036 70136 1400 71536 WAG-9 5529 110536 19335 135400 1963 137363 2800 140163 WAP-7 5529 113279 19292 138100 2002 140102 2800 142902 WAP-5 5529 115461 19310 140300 2035 142335 2800 145135

b. Financial Year 2013 – 14

Type of Loco

Direct Labour

Direct Materials

Over heads

Total(ex. Pro. Chgs.)

Pro. Charges

Total(in pro. charges)

ED Total (including ED)

WAP-4 3914 52800 11886 68600 1029 69629 1400 71029

WAG-7 4413 51856 12331 68600 1029 69629 1400 71029

WAG-9 5642 101094 18064 124800 1810 126610 2800 129410

WAP-7 5225 104136 16039 125400 1881 127281 2800 130081

WAP-5 5310 112428 16462 134200 2013 136213 2800 139013

c. Financial Year 2014-15

Type of Loco

Direct Labour

Direct Materials

Over heads

Total(ex. Pro. Chgs.)

Pro. Charges

Total(in pro.charges)

ED Total (in.ED)

WAP - 4 4347 52800 14853 72000 1800 73800 1400 75200 WAG-7 4901 51856 15543 72300 1843 74143 1400 75543 WAG-9 6265 101094 23241 130600 1959 132559 2800 135359 WAP-7 5802 104136 21062 131000 1965 132965 2800 135765 WAP-5 5896 112428 21476 139800 2097 141897 2800 144697 d. Financial Year 2015-16 (upto 31.12.15)

Type of Loco

Direct Labour

Direct Materials

Over heads

Total(ex. Pro. Chgs.)

Pro. Charges

Total(in pro.charges)

ED Total (in.ED)

WAP - 4 4315 60539 12746 77600 1400 79000 1940 80940 WAG-7 3898 56476 11526 17900 1400 73300 1790 75090 WAG-9 3920 100207 11873 116600 2800 119400 1749 121149 WAP-7 4778 101405 14817 121000 2800 123800 1815 125615 WAP-5 6490 104059 19451 130000 2800 132800 1950 134750

Page 58: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

INDUSTRIAL SAFETY

11

Page 59: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

11. SAFETY ORGANISATION

11.1 Safety Officer & Safety Inspectors regularly check the safety aspect in the shop floor such as use of Personal Protective Equipment, proper use of Material Handling Equipment, unsafe working practices etc. They also conduct safety inspections, investigations of accidents and recommended remedial measures. They also formulate plans for motivating staff for safety consciousness, use of safety equipment and compliance of statutory act and regulations. To monitor Occupational Health Hazards, periodical Medical Check-up is done by Medical Department as per statutory regulation. Safety department in co-ordination with Medical Department frames the programme and maintain the records of the tests. It also maintains liaison with State Pollution Control Board. Environmental Engineers of WBPCB from Asansol & Kolkata regularly visits Steel Foundry/ CLW/Chittaranjan. Safety department with the help of approved agencies of WBPCB conducts regular tests of air and sound to provide proper work environment.

11.2 Measures taken for Improvement:

i. All Shops and work sides are regularly inspected for “Plant Safety Inspection”. All plants using flammable substances like acetylene and LPG etc. are inspected regularly and plant maintenance/operation units follow fire proof working procedures for safe operation and maintenance of these plants. Contractors engaged for maintenance of acetylene/oxygen/LPG plants are monitored regularly by Safety Units. Fire Prevention measures - like use of Flash back arrestor in acetylene cylinder and declaration of fire prone area as “NO SMOKING ZONE”, rigorous training of staff by fire inspectors, demonstration of fire- fighting equipment at the work sites, regularly re-filling/repair of fire extinguishers and being followed for vulnerable zones. All accident/dangerous occurrences are investigated and remedial measures are suggested to prevent recurrence of such incidents.

ii. Regular check is conducted at shop floor regarding use of Personal Protective Equipments like Safety

Shoes, Goggles, Helmet, Nose mask etc. Staffs are continuously motivated to wear PPEs and also apprised of the adverse consequences associated with non use of such equipments.

iii. A proper vigil is regularly maintained to determine whether all critical equipments like Crane, chain,

Pressure Vessel etc. are tested as per Statutory Rules by the agencies approved by the State Inspectorate of factories. Do’s and Don’ts for safe operation of crane has been circulated to concerned shops.

iv. Crane Drivers, Riggers, staffs engaged for Spray Painting, Electroplating, Battery Charging, Foundry work,

operation and signaling to the cranes etc. are given regular medical check up to assess their vision, chest, lung function etc. in compliance with the statutory obligation.

v. Safety calendars, posters, retro-reflective boards containing safety slogans procured by safety deptt. are

displayed at shop floor for safety awareness among the workers. As per the relevant provision of Factory Rules’1958, Safety and Health Policy of CLW has been prepared duly signed by the CME and occupier and displayed the same in various locations through laminated boards. Staff are regularly counseled by the Chief Safety Inspectors / Safety Inspectors to adopt safe practices while they are at work.

vi. Fume Extraction System has been installed in shop no 26. The system is effective to extract the welding

fumes arising out of welding operation thus maintaining upgraded environmental standard in the shop floor as well as to prevent the workers from being afflicted with any irreversible diseases by inhalation of the fumes.

vii. The safety action plan pertaining to various operations being carried out inside the factory premises has

been chalked out and the same has already been distributed to all stake holders to ensure strict compliance of the same to user in safe practice while performing the respective job .

Page 60: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

viii. Work-shop on safety are being held in collaboration with TTC where demonstration is made by Safety Deptt. with the aid of audio-visual mode based on the video footages filmed during the working hours to admonish the staff about the various processes of un-safe act and also an inter-active session is conducted in the work-shop to en-courage participation by the workers .

ix. Plant Safety Audit and Work Area Monitoring have been conducted by the expert agency approved by the

Inspector of Factories in different areas inside the Factory premises. The deficiencies found in course of the above work have been pointed out and the same have been brought to the notice of concerned authorities to make necessary rectification.

x. Organizing safety awareness week has been introduced from the year 2014 in which safety skits are

conducted by various drama units of CLW bringing out the unsafe practices and their severe consequences. Eminent dignitaries are invited to make valuable contribution and make way out to eliminate unsafe conditions engulfed in the factory premises.

xi. In the first phase, factory lay out in respect of ELA & ELF group of shops has been prepared by the

outside recognized agency duly approved by the CIF, WB. The process of preparing factory lay out in respect of the remaining part of the factory including all the new constructions is under process.

Accident Statistics of CLW during the following periods 2011,2012, 2013, 2014, 2015 Sl no. Year No. of Accident Type of Injury

Fatal Serious Minor 1 2011 06 - 06 - 2 2012 07 - 07 - 3 2013 10 01 07 02 4 2014 10 01 06 03 5 2015 03 - 03 -

Page 61: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

FUTURE PLANS

12

Page 62: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

12. Future Plan

1. Commissioning of IGBT based propulsion system on 66 locomotives. Procurement of

60 sets under process.

2. Development of composite converter for WAP-5 locomotives.

3. Commissioning of Hotel Load Converter on 60 L/Sets.

4. Proliferation of technology developed by C-DAC for TCN VCU and commissioning of

TCN VCU on 50 locomotives.

5. Procurement and commissioning of DPWCS on 15 sets of WAG-9H locomotives.

6. Regular fitment of Cab AC from August, 2016. Prototype clearance of 02 firms under

issue from RDSO & 01 firm completed. Purchase under for 380 locomotives placed.

7. Fitment of water closet in 05 locomotives. Expression of Interest called.

8. Provision of crew-voice recording in 05 locomotives. Expression of Interest called.

9. Development of Dual Mode Locomotive having provision for electrical, diesel and

battery operated modes for different operational requirement over IR.

Page 63: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

OTHER ISSUES

13

Page 64: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate

13. Other issues

Up to 31st Dec’15 CLW has turned out 205 locos. Amongst 205 Locos CLW has turned out

140 nos 3 phase locos. The 3 phase locomotives are the future of Indian Railway transportation system.

These locomotives are capable of hauling long distance freight and passenger trains at high

Speed with its capacity. The manufactures of three phase loco equipment have stepped up their Production to meet the enchased requirements. The assistance from Board in this regard is highly appreciated.

Chittaranjan Locomotive Works had been sanctioned “Creation of additional facilities forenhancement of production capacity up to 275 locomotives per year under AP275 project.

To meet the increase in demands of electric locomotives and to cope up with the freight and passengers traffic on electricfied routes over Indian Railways, CLW has taken up a project named AP-275 for augmentation of production capacity from 200 to 275 locomotives per year. Extension of main bay and additional berthing space for the locomotives are already completed.

The foundation for setting up an Electric Locomotive Assembly and Ancillary Unit(ELAAU) of CLW had been laid during 2010. The production of High horse power locomotives of the order of 9000 HP to 12000HP would be carried out in this unit and mainly the locomotives will be utilised for Western dedicated freight corridor. The work for setting up of Electric Locomotive Assembly & ancillary Unit (ELAAU) at Dankuni is expected to turn out in the month of March 2016.

Page 65: STANDARD NOTE FOR CLW AS ON 31.12clw.indianrailways.gov.in/works/uploads/File/CLW Standard... · 2019-10-17 · Steel Foundry/CLW has been accredited with CLASS- ‘A’ FOUNDRY certificate