status of the accelerator upgrade
DESCRIPTION
Status of the accelerator upgrade. Dec.10 2008 Mika Masuzawa. Contents. Introduction Luminosity goal Strategy Higher currents Smaller b y * Increase x y What we need Components for higher currents R&D Status IR & Lattice design for smaller b y * & larger x y Summary. - PowerPoint PPT PresentationTRANSCRIPT
Status of the accelerator upgrade
Dec.10 2008 Mika Masuzawa
mm 12/10/2008
Contents1. Introduction
– Luminosity goal2. Strategy
– Higher currents– Smaller y
*
– Increase y
3. What we need– Components for higher currents
• R&D Status– IR & Lattice design for smaller y
* & larger y • Summary
mm 12/10/2008
1. Introduction
Luminosity goal
mm 12/10/2008
Luminosity goal
mm 12/10/2008
Target: 5-8 × 1035 cm-2s-1
=30-50 x World Record (KEKB)
mm 12/10/2008
2. Strategy
mm 12/10/2008
Strategy
(1) Increase beam currents•1.7 A (LER) / 1.4 A (HER) → 9.6 A (LER) / 4.1 A (HER)(2) Smaller y
*
•6.5(LER)/5.9(HER) mm→3.0/3.0 mm(3) Increase y
•0.09 (with Crab) → 0.29mm 12/10/2008
Crab cavity
The superconducting cavities will be upgraded to absorb more higher-order mode power up to 50 kW.
The beam pipes and all vacuum components will be replaced with higher-current design.
The state-of-art ARES copper cavities will be upgraded with higher energy storage ratio to support higher current.
SuperKEKBe- 4.1 A
e+ 9.4 A
*y= σz = 3 mm
Will reach 5-8 × 1035 cm-2s-1.
Tunnel already exists.Most of the components (magnets, klystrons,etc) will be re-used.
Comparison of parametersKEKB Design
(A)KEKB
(achieved)KEKB upgrade
(B)Gain Factor
(B/A)
y* (mm) 10 5.9/6.5
(5.9/5.9) 3 3.3
y 0.052 0.056 (0.093) 0.296
Ry 0.885 0.879(1.15) 1.11
y/Ry 0.059 0.063(0.081) 0.267 4.5
Ibeam (H/L) (A) 1.1/2.6 1.45/1.8 (0.95/1.62) 4.1/9.4 3.6
RL 0.845 0.715(0.827) 0.86 1.02
Luminosity (1034 cm-2 s-1) 1 1.71 (1.46) 55 55
z (mm) 4 ~ 7 5(LER)/3(HER)mm 12/10/2008
( ): with crab
Strategy
3. What we need
Components for higher currentsR&D Status
mm 12/10/2008
What we needfor (1) higher beam currents
mm 12/10/2008
a.Vacuum components (pipes/bellows…)b.Modification of the monitors (BPMs,SRMs…)c.Longitudinal bunch-by-bunch FB systemd.More RF cavities and klystronse.Modifications of the RF systems for higher currentsf.New Crab cavities for SuperKEKB
Vacuum components⇨talk by K.Shibata tomorrow
mm 12/10/2008
Beam current increase causes:
Intense Synchrotron Radiation power•27.8 kW/m in LER, twice as high as in KEKB•21.6 kW/m in HER, 4 times as high as in KEKBHigh photon density•Photon density ~1x1019 photons/m/s in average
•Large gas desorption•Gas load ~ 5x10-8 Pa m3/s/m (for h = 1x10-6 molecules/photon)•Average pressure ~ 5x10-7 Pa for S ~ 0.1 m3/s/m•Electron Cloud Instability (ECI) becomes a big issue in positron ring
Heating due to Higher Order Modes (HOM)• For a loss factor of 1 V/pC, loss power ~ 200 kW
a) Vacuum components
Beam ductCopper beam duct with ante-chambers
– Copper is required to withstand intense SR power
Features (compared to simple pipe):– Low SR power density– Low photoelectrons in beam pipe– Low beam impedance– Expensive
mm 12/10/2008
BeamSR
Pump
LER HER
Y.Suetsugu
a) Vacuum components
Some sections of KEKB LER have been replaced by ante-chamber type
Trial model of a copper beam duct with ante-chambers for arc section
The duct is bent with a radius of 16 m
mm 12/10/2008Y.Suetsugu
a) Vacuum components
More on suppressing photoelectronsTiN (Titanium nitride) coating on inner surfaceDecrease secondary electron yield (SEY): Max. SEY ~0.9A test stand for the coating was built in KEK, and applied to a test duct with ante-chambers.
⇨Decrease of electrons at high current region was demonstrated.
mm 12/10/2008
~4 m
90 mm
Electron numbers
Y.Suetsugu
a) Vacuum components
And more on suppressing photoelectronsClearing Electrode A possible measure even inside of magnet An electrode with a low beam impedance was developed and tested with beam (in the presence of wiggler magnetic field of B = 0.77 T). Thin structure Electrons decreased to ~1/100 by applying + 300V.
mm 12/10/2008
Clearing electrode for test
Elec
tron
Cur
rent
[A]
Applied voltage [V]
Vr = 1.0 kVB = 0.77 T
V elec
[V]
I e [A]
1585 bunches(Bs ~ 6 ns)~1600 mA
Velec = 0 V
-500 V
+500 V
1 x 10-5
1 x 10-6
1 x 10-7
1 x 10-8
1 x 10-9
CollectorsY.Suetsugu
a) Vacuum components
Drift space
In wiggler magnet
And more on suppressing photoelectrons
Grooved Surface: being tested with the beam now.• Another possible measure in magnets• Decrease effective SEY structurally
TiN~50 nm
SS + TiN coating
M. Pivi
mm 12/10/2008Y.Suetsugu et.al
a) Vacuum components
Grooved surface currently tested
mm 12/10/2008
a) Vacuum components
For lower impedance: RF shielding Comb-type RF shield Features (compared to finger type):
Low beam impedance High thermal strength Applicable to complex aperture Little flexibility (offset)
Effect of RF shielding was demonstrated in KEKB. Finger-type as an option
If more flexibility is required.
Without cooling fan
Comb-type RF-shield
Temperature of bellows
a) Vacuum components
mm 12/10/2008Y.Suetsugu
More for lower impedance: Bellows and gate valves
Comb-type RF shield is adaptable to a complicated aperture of beam duct with antechambers.
Bellows Gate valve
Y.Suetsugu et.al
a) Vacuum components
mm 12/10/2008
And more for lower impedance: Movable maskBig impedance sources in the ring•Planning to use “stealth” type (Ver.6)–Low beam impedance•Present Ver.4 ~ 1V/pC ( 90 mm) 200 kW power loss–Loss factor decreases to ~1/10 ( 90 mm).•Manageable by conventional HOM absorber
Loss factor
Bunch length [mm]
Loss
fact
or [V
/pC]
Ver.4
Ver.6
a) Vacuum components
mm 12/10/2008Y.Suetsugu
And more for lower impedance: movable mask
• Trial models were installed and tested with beam.– Principle was proved experimentally.
• Temperature rise of bellows decreased to 1/2 ~ 1/3.– But, could not withstand a high intensity beam yet.
• Start with Ver.4 ?– While beam current is low.
Head of Ver.6 (trial model)
Temperature of bellows near masks
Beam
HeadSupport
Y.Suetsugu et.al
a) Vacuum components
mm 12/10/2008
Movable mask (beam test)• Principle was proved experimentally.• Improvement for high-current is currently underway
Temperatures of bellows Temperatures of SiC cooling water
Old type
New type
Old type
New type
Y.Suetsugu et.al
a) Vacuum components
mm 12/10/2008
And more for lower impedance:Connection flange
MO-type flange, which can makes very smooth inner surface low impedance
SUS flange
Copper alloy flange (under test)
Flange and gasket (copper)
Y.Suetsugu et.al
a) Vacuum components
mm 12/10/2008
Remaining Vacuum Issues• Optimization of beam duct shape
– CSR (Coherent Synchrotron Radiation) problem have a great effect on the luminosity.
• Deformation of beam duct by heating– Displacement gauge for every BPM?
(50)
Larger aperture OR Smaller aperture
Low impedance Cure for CSR(ex, resistive wall) (Low cost?)Effective pumping
(90)?
Y.Suetsugu et.al
a) Vacuum components
mm 12/10/2008
Modification of the monitors :Beam Position Monitors
• Use same front-end electronics.
• New button electrodes◆ New connector design for
improved reliability.◆ 12 mm →6 mm diameter Signal power same as at
present, at higher beam currents, to match dynamic range of existing front-end electronics.
M. Tejima et al.
b) Modification of the monitors
mm 12/10/2008
Modification of the monitors:Beam Size Monitors
•Chamber redesign for high current.•Source bending radius for synchrotron radiation monitors increases 3x to reduce mirror heating at high currents.
•Reduces beam image distortion at high currents. Also increases visible light flux.
•Development of x-ray monitor also being pursued based on x-ray astronomy technique of Coded Aperture Imaging for high-bandwidth/high-speed readout with low beam current dependence.
•Optics testing and detector development being carried out in collaboration with Cornell (CesrTA ILC damping ring study machine group) and U. Hawaii (Belle detector group).•Collaboration with other machines and between physics and accelerator groups.
1-D URA Mask for Coded ApertureImaging
J.Flanagan et.al
b) Modification of the monitors
mm 12/10/2008
Bunch-by-bunch Feed back system
mm 12/10/2008
Transverse feedback similar to present design →Target damping time 0.2ms-Detection frequency 2.0→2.5 GHz.-Transverse kicker needs work to handle higher currents-Improved cooling, supports for kicker plates.
Longitudinal feedback to handle ARES HOM & 0/ mode instability→Target damping time 1ms-Use DANE-type (low-Q cavity) kicker.
Digital FIR and memory board to be replaced by new Gboard.-Low noise, high speed (1.5 GHz), with custom filtering functions possible.-Extensive beam diagnostics.
A prototype of the new bunch-by-bunch feedback system (G-board / Gproto) has been developed as a result of collaboration between SLAC, KEK and INFN, and successfully tested at KEKB, KEK ATF, KEK PF, SLAC and DANE.
c) Bunch-by-bunch FB system
RF systemsNeed RF systems which can store high beam currents and handle shorter bunches.
ARES (normal-conducting cavity) for LER ARES + SCC (Single-cell Superconducting cavity) for HER
Adopt the same RF frequency as KEKB and use the existing RF system as much as possible, with improvements as necessary to meet the requirements for SuperKEKB.
→Construction cost is greatly reduced.→Technical uncertainties are relatively small.
d & e ) RF system for higher currents
mm 12/10/2008Akai et.al
The ARES CavityPassive stabilization with huge stored energy.Eliminate unnecessary modes by coupling of 3
cavities.Higher order mode dampers and absorbers.No need for longitudinal bunch-by-bunch
feedback.No transverse instability arises from the cavities.
Storage
Resonant
Acceleration
Accelerator Resonantly-coupled Energy Storage
T. Kageyama, et al
d & e ) RF system for higher currents
mm 12/10/2008
High power RF R&D
Y. Takeuchi, T. Kageyama, et al
d & e ) RF system for higher currents
mm 12/10/2008
◆ Higher HOM powerUpgrade of HOM damper
◆ Higher input RF power400 kW/cavity -> 800 kW/cavityR&D of input coupler using new test-stand.
Superconducting CavitySuperKEKB challenges:The expected power load to the HOMabsorber is 50 kW/cavity at 4.1 A,(even) with a larger beam pipe of 220 mmφ.HOM damper upgrade may be needed.
S. Mitsunobu, et al
d & e ) RF system for higher currents
mm 12/10/2008
mm 12/10/2008
Crab cavity with 10 A beam• The original cavity is designed for 1-2 A beam
– Simple structure, suitable for SC → High kick voltage is obtained by one cavity.
– Sufficient damping of parasitic modes.– Not necessarily optimized for a 10 A beam.
• Possible problems at 10 A– Large HOM power (200 kW)
• Loss factor is not very small, because the radius of coaxial beam pipe can not be widely opened.
• Additional loss factor comes from the absorber on wide beam pipe.
– Much heavier damping of HOM’s may be needed, particularly for horizontal polarization of transverse modes (large x at crab).
• A new crab cavity has been designed, which can be used at 10 A.
f) Crab cavity for higher currents
3. What we need
IR & lattice design for smaller y
*
& larger y
mm 12/10/2008
IR (Interaction Region)
mm 12/10/2008
Issues Causes Possible cures
Physical aperture Lower * Injection beam quality (Damping ring)
Dynamic aperture Lower * Injection beam quality (Damping ring)Move the IR magnets closer to IP⇨needs stronger magnets Local correction at the IR straight section in HER
Detector background Higher beam current Optimization of mask, IP beam duct shape etc. talk by M.Iwasaki⇨
Heating of components Higher beam current & shorter bunch length
Optimization of the IP beam duct, cooling systems etc.
For smaller *
Higher luminosity smaller ⇨ * causes issues such as
IR layout
•Crossing angle: 22 30 mrad⇨•Move final focus quadrupoles closer to IP for lower beta functions at IP.•Preserve current machine-detector boundary.•QCS and solenoid compensation magnets overlap in SuperKEKB.
mm 12/10/2008
For smaller *
mm 12/10/2008
IR-overviewpresent design
(based on the LoI)
QCSL(QCSL center from IP = 0.969 m)KEKB=1.6 m
QCSR (QCSR center from IP = 1.163 m)KEKB=1.92 m
ESR
ESL
IP
The cryostats were designed with keeping the KEKB boundary conditions with Belle detector.
N.Ohuchi
For smaller *
mm 12/10/2008
Cross section of QCSR
•6 layer coils (3-double pane cake coils)•Inner coil radius : 90.0 mm•Outer coil radius : 116.8 mm•Cable size : 1.1 mm 4.1 mm1.1 mm 7.0 mm (KEKB)•Number of turns : 271 in one pole1st layer = 38, 2nd layer = 393rd layer = 46, 4th layer = 475th layer = 50, 6th layer = 51•Field gradient : 40.124 T/m•Magnet current : 1186.7 A•Magnetic length : 0.299m (R), 0.358m (L)•Inductance : 69.98 mH (R), 83.79 mH (L)•Stored energy : 49.3 kJ (R), 59.0 kJ (L)•Operation temperature : 4.5 K•Operation point w.r.t. SC limit : 75% (R), 74% (L)
N.Ohuchi
IR magnets (QCS) : DesignFor smaller *
IR magnets (QCS R&D) : Field measurement results
mm 12/10/2008
Field gradient at 1186.7A
G=40.05 T/m was obtained (Design G=40.124T/m)MultipolesData at r=48mm•a3= -0.86 units, b3= 0.91 units
•a4= -1.27 units, b4= 0.40 units
•a5= 0.11 units, b5= -0.80 units
•a6= -0.55 units, b6= -0.00 units ( I units = 10-4 × b
2 )
Design at Rref = 50 mm
•b6=0.12, b10=-0.04, b14=0.12
N.Ohuchi
For smaller *
IR magnets (QC1&QC2) : R&D on coil winding
mm 12/10/2008
Coil winding on a cone shaped bobbinR&D work required for a winding tool
N.Ohuchi
For smaller *
mm 12/10/2008
IP
4 layer structure Integrated field gradient = 17.445T field gradient = 98.9 T/m needed for new IR ⇦ Length = 336mm Cable ( the same type as QCS R&D 4.05mm×1.16mm ) Current = 2610A Max field inside the magnet = 8.8T ( corresponds to 10T iron bore magnet )
N.Ohuchi
QCS @ 1.9 K (design)IR magnets (QCS) : 1.9K version for new optics
For smaller *
mm 12/10/2008
IR magnets (QCS) : 1.9K version for new optics to do list
1. IR design has to be fixed.
2. Design of Super-QC23. Design of compensation solenoids4. Optimization of QCS, QC2 and compensation solenoid
under the combined operation
5. Design of cryostats for 1.9K operation!
N.Ohuchi
For smaller *
Local chromaticity correction for widening dynamic aperture
KEKB Design Report
Effects of local correction- widen dynamic aperture- weaken synchro-betatron resonance
KEKB: local correction only in LER
KEKB upgrade:local correction also indownstream of HER
⇨ New magnets need to be designedand made/measured/installed.
Lattice Design
mm 12/10/2008
For smaller *
Dynamic aperture
Lattice DesignTravelling focus
mm 12/10/2008
We would like to have z ~ y*
Bunch length limitation due to CSRLER bunch z=5mm (not 3mm) when y
*=3mm⇨z > y*
Hourglass effect is not negligible.
⇨A possible cure is to use the travel focusing
Beam size changes along Z
Smaller *
Larger z
Hourglass effect
Travelling focus
mm 12/10/2008
Evaluation by Koiso-san
Needs a pair of sextupole magnets at both sides of the crab cavityANDTwo crab cavities each ring…
More evaluation of the effect on the luminosity will be studied.(how much do we gain by this scheme??Awfully expensive!)
Smaller *
Recovering from the hourglass effect
Lattice Designfor higher y
KEKB KEKB upgrade
y (max) with crab from b-b simulation
0.15 0.296
x* [m] 0.9 0.2
x (LER/HER) [nm] 18/24 12/13
y/x [%]1 0.5
x (LER/HER) 0.506/0.510 0.505/0.505Improving the performance with crab crossing is a mustBeam-beam parameter, beam lifetime ⇨ Injecter upgrade⇨presentation by Funakoshi-san on KEKB status
Other efforts for higher y areLower x
*, smaller x, y, smaller coupling ,,,,⇨Better magnet alignment⇨More auxiliary coils for optics diagnostics and correction
mm 12/10/2008
For higher y
Injecter upgradeSimultaneous (pulse-by-pulse) injection of KEKB LER/HER/PF
Phase I : Construction of a new beam transport which bypasses the energy compression system (ECS).
Phase II : Fast beam switch between KEKB e- and PF e- by a pulsed bend.
Phase III : Fast beam switch between KEKB e-, PF e- and KEKB e+ by an e+ target with a hole and pulsed steerings.
e- Gun (A1 Gun; for KEKB and e- Gun (A1 Gun; for KEKB and PFPF))
e- Gun (CT Gun; for PF-Ae- Gun (CT Gun; for PF-ARR ))
#3 Switchyard
KEKB/ KEKB/ ARAR
PFPF
pulsed BendECS
Crystal tungsten target5 mm
Hole: 3 mm
4.5 mm
Phase I and II have been completed. Beam study for Phase III is underway. Phase III will be started in this autumn.
Simultaneous injection of e- and e+ is desirable in view of thermal stability of components and an ability of the operation with shorter beam lifetime.
(M. Satoh, KEKB review committee 2007)Positron Target
mm 12/10/2008
Injecter upgrade
HER / 12.5HzPF / 5Hz
N.Iida
On Dec.8, 2008First pulse-by-pulse injection to PF & KEKB HER!
mm 12/10/2008
Injecter upgradeSimultaneous injection of KEKB LER/HER/PF
Injecter upgrade
mm 12/10/2008
2004 data
Measurement data were used as alignment errors and simulation was done by Ohnishi.No need for leveling the tunnel but local ups and downs better be corrected.We also found that the magnets are rotated, horizontal position moved and so on…
Tunnel level Magnet level
KEKB tunnel continues to sink and magnets follow the tunnel
Better magnet alignmentFor higher y
Summary
mm 12/10/2008
Accelerator componentsR&D work of the accelerator components (vacuum, monitors and etc) is ongoing. Some have been tested with the beam.
IR optics IR optics is being re-designed with x=20 cm⇨Koiso-san’s talk on the new IR optics parallel session tomorrow.
IR magnetsQCS R&D version has been made and its magnetic field has been measured.IR magnets (QCS,QC1 and QC2) will all be superconducting.Evaluation of QCS at 1.9K shows a possibility of higher field gradient which is needed for the new IR optics with smaller x.⇨New cryostat for 1.9K needs to be designed.
Summary
mm 12/10/2008
Lattice designBunch length of HER 3 mm/LER 5 mm (due to CSR) is the current choice.Hourglass effect will degrade the luminosity. ⇨Travelling focus?Effect of travelling focus needs to be examined.
Better alignmentMagnet rotation/level measurement data have been taken and machine performance is simulated.Realignment (smoothing locally) will be needed though a leveling of the entire tunnel may not be necessary.
We are making steady progress toward 5-8 × 1035 cm-2s-1.
mm 12/10/2008
Contribution is welcome.