Approved March 18, 2019 SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL CAPITAL IMPROVEMENT PLAN (CIP) SUBCOMMITTEE THURSDAY, FEBRUARY 7, 2019 KIVA FORUM – CITY HALL 3939 N. DRINKWATER BOULEVARD SCOTTSDALE, AZ 85251 CALL TO ORDER Councilman Phillips called the meeting to order at 8:30 a.m. ROLL CALL PRESENT: Guy Phillips, Councilman Kathy Littlefield, Councilwoman Suzanne Klapp, Councilwoman STAFF: Dave Lipinski, City Engineer Jeff Nichols, City Treasurer Jim Thompson, City Manager Bruce Washburn, City Attorney Judy Doyle, Budget Director Sylvia Dlott, CIP Budget Manager Dave Meinhart, Sr. Transportation Planner Dan Worth, Public Works Director Erin Walsh, Public Information Officer Billy Murphy, Community Services Director Tim Conner, Office of Environmental Initiatives Manager Kroy Ekblaw, Preserve Director 1. APPROVAL OF MEETING MINUTES Regular Meeting of the Council Capital Improvement Plan Subcommittee – January 17, 2019 COUNCILWOMAN KLAPP MOVED TO APPROVE THE REGULAR MEETING MINUTES OF THE COUNCIL CAPITAL IMPROVEMENT PLAN SUBCOMMITTEE OF JANUARY 17, 2019 AS PRESENTED. COUNCILWOMAN LITTLEFIELD SECONDED THE MOTION, WHICH

Upload: others

Post on 30-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Approved March 18, 2019

SUMMARIZED MINUTES

CITY OF SCOTTSDALE COUNCIL CAPITAL IMPROVEMENT PLAN (CIP)

SUBCOMMITTEE

THURSDAY, FEBRUARY 7, 2019

KIVA FORUM – CITY HALL 3939 N. DRINKWATER BOULEVARD

SCOTTSDALE, AZ 85251 CALL TO ORDER Councilman Phillips called the meeting to order at 8:30 a.m. ROLL CALL PRESENT: Guy Phillips, Councilman

Kathy Littlefield, Councilwoman Suzanne Klapp, Councilwoman

STAFF: Dave Lipinski, City Engineer Jeff Nichols, City Treasurer Jim Thompson, City Manager Bruce Washburn, City Attorney Judy Doyle, Budget Director

Sylvia Dlott, CIP Budget Manager Dave Meinhart, Sr. Transportation Planner Dan Worth, Public Works Director Erin Walsh, Public Information Officer Billy Murphy, Community Services Director Tim Conner, Office of Environmental Initiatives Manager Kroy Ekblaw, Preserve Director

1. APPROVAL OF MEETING MINUTES

• Regular Meeting of the Council Capital Improvement Plan Subcommittee – January 17, 2019

COUNCILWOMAN KLAPP MOVED TO APPROVE THE REGULAR MEETING MINUTES OF THE COUNCIL CAPITAL IMPROVEMENT PLAN SUBCOMMITTEE OF JANUARY 17, 2019 AS PRESENTED. COUNCILWOMAN LITTLEFIELD SECONDED THE MOTION, WHICH

Page 2: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Council Capital Improvement Plan (CIP) Subcommittee February 7, 2019 Page 2 of 6 CARRIED 3-0 WITH COUNCILWOMAN LITTLEFIELD, COUNCILWOMAN KLAPP AND COUNCILMAN PHILLIPS VOTING IN THE AFFIRMATIVE WITH NO DISSENTING VOTES.

2. BOND 2019

1. Proposed projects to the community 2. Next steps

a. Public engagement b. Timeline

Dave Lipinski, City Engineer, reviewed that the Subcommittee began with 99 unfunded projects and $529 million in requests. After discussion, changes were made, including moving two projects into the FY 2019/20 CIP. Three projects tied to the Loloma land sale were removed from the unfunded list. The stormwater projects and Downtown underground parking structures were removed from the list. The Pinnacle Peak Park land purchase and expansion was added. Those changes provide a new starting point of 68 projects at $438 million. Nine projects at WestWorld represent $58.5 million in investments. Councilwoman Klapp asked if an alternative funding source is available for the parking. Mr. Lipinski said they have not identified a funding source, which is why the project is on the unfunded list. Councilman Phillips asked whether this includes a series of parking structures or a single structure. Mr. Lipinski said the description includes looking at two different parking structure locations, both to support the downtown area. Councilman Phillips noted that Downtown parking is an issue; there may be red flags if parking projects are removed. He is uncertain whether the public’s main focus would be to include WestWorld projects on the bond. Councilman Phillips added that during the last meeting Councilwoman Klapp had suggested that if the bond amount was low enough, residents might actually be able to see their rates lowered, even as the bond is approved. Councilwoman Klapp said one of her concerns is that they have not seen a WestWorld master plan. Mr. Lipinski said that next week, there will be a work study session to discuss the WestWorld business plan. Councilwoman Klapp said she is concerned about having all the projects on the list until that discussion can take place. Jim Thompson, City Manager, said the challenge is that they will not return to the CIP Subcommittee for discussion until after outreach has begun. As such, he suggested leaving the items on the list. They can always be removed later. If they are not on the list during community engagement, there will be no way to determine support. Project number 54, parking lots in the vicinity of WestWorld, is intended to support special events, which supports not only WestWorld but also the northern portion of the community. Councilwoman Klapp noted that they are eliminating the underground parking structure Downtown without asking for citizen input, however, they are retaining the WestWorld parking and are asking for input in this regard. She questioned whether Downtown parking is being treated differently than parking in WestWorld. Mr. Thompson said they are free to add the Downtown parking back to the list. They also have the option of listing parking as a separate question on the ballot. Hardware and accompanying software are being utilized in the Downtown area to provide parking data. Dan Worth, Public Works Director, clarified that the project on the list for Downtown parking was at two specific locations, both tied to potential future private development. It would involve the City’s purchase of additional City public parking in the underground structure as part of a private

Page 3: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Council Capital Improvement Plan (CIP) Subcommittee February 7, 2019 Page 3 of 6 development project. In both cases, the cost estimates for the parking desired by the developers was way out of line with what the City would pay if building its own structure. The developer of the Museum Square project has moved forward with the design, with the assumption that the City will not be participating. The other is a potential project on Fifth Avenue. The developer’s proposal quotes the City’s portion of the funding so high that it did not seem prudent to participate. Another issue is that it may be several years before the developments move forward. If the City issues bonds to participate in projects that do not happen for a few years, there may be some repercussions. Councilman Phillips said that the public should at least have the ability to review the options. Councilwoman Littlefield concurred. Councilwoman Littlefield stated that every project on a bond for WestWorld must be in compliance with the Master Plan. Mr. Lipinski addressed community centers and neighborhood parks. There was previous discussion regarding the number of community centers and parks and whether they can be conjoined to a single location. Councilwoman Klapp commented that the number of centers is a concern as it relates to expense. She asked about the number and location of existing centers (excluding senior centers). Bill Murphy, Community Services Director, said there are approximately 12 community centers. In September, staff visited the communities in DC Ranch, Grayhawk and Ashler Hills. Staff had put together simple designs on what a neighborhood park and community park would look like. The DC Ranch feedback was that they already have neighborhood parks and no more are needed. The same held true for a community park located in DC Ranch. The initial plan from years ago was for 15 tennis courts and community center. The village ended up adding courts south of the area on the campus of Copper Ridge. It was not felt that 15 additional courts would be needed. When asked, the community said their current facilities are sufficient. At Grayhawk, the Boys & Girls Club had added an additional gymnasium with almost the same square footage as what the City had planned for a community center at Thompson Peak. Community input reflected the desire for an off-leash area. Ashler Hills expressed interest in having pickleball courts and a small community center. The 2015 Master Plan outlined not building community centers any longer for recreation or human services, but in conjunction with the library, so that all three could function together. Councilwoman Klapp noted that while DC Ranch stated they did not need a park; the list includes a project to build a neighborhood park in DC Ranch. Mr. Murphy agreed that the community feedback indicated they did not need it. When approached about a community center, the group that attended the open house stated they had sufficient facilities at this time. Councilwoman Klapp said that based on the input, projects 47 and 64 should not be on the list. Mr. Murphy said that the centers are identified in the 2015 Master Plan. Councilwoman Klapp said if residents do not want a community center at Thompson Peak Park and prefer an off-leash park, it would make sense to change project 62 to reflect the change. Mr. Murphy addressed the Boys & Girls Club at Thompson Peak, noting that the relationship allows the City space to hold meetings. The second gymnasium provides additional space. The site may have an awkward appearance if it includes a 20,000 square foot building next to the two gyms. Councilwoman Klapp stated that in sum, projects 47, 62 and 64 should be removed. Councilman Phillips agreed. Councilwoman Littlefield said she would like to see a dog park in the north and inquired as to the best place to locate it. Mr. Murphy said that based on the feedback received, Thompson Peak is the appropriate location. She recommended removing the community center and instead adding a dog park. Mr. Lipinski clarified that the dog park at this location is on the list.

Page 4: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Council Capital Improvement Plan (CIP) Subcommittee February 7, 2019 Page 4 of 6 Councilman Phillips recommended the possibility of adding just one of the projects at Cavalliere Park and Ashler Hills, as they are fairly close. Cavalliere Park is somewhat hidden with only local residents knowing its location. Councilwoman Littlefield stated her understanding that either Carefree or Cave Creek has a community center in the Ashler Hills area that is used by many residents. She encouraged partnership for possible expansion. Mr. Murphy identified it as the Holland Community Center. The City has had discussions with the Center regarding programs offered. The Ashler Hills Center is substantial, however, residents are looking for more recreational outdoor space, such as sports courts, restrooms and grass area. There have not yet been outreach discussions for the Troon area. Councilwoman Klapp suggested the possibility of partnering with Holland Community Center in the future in terms of senior services. This may alleviate the need to build another senior center in northern Scottsdale. Councilwoman Littlefield concurred with the need for a senior center, based on feedback in the community. Mr. Lipinski summarized the CIP Subcommittee’s direction as follows: Remove projects 47, 62 and 64 and take out (as part of public outreach), the Ashler Hills and potentially Cavalliere Park. Public outreach will ask about additional needs in the northern area. Mr. Lipinski addressed the solar projects. From preliminary figures, the rooftop solar projects look to be a 10-plus year payback window. Parasol shade projects for the parking structures are close to a 20-year payback window. In response to a question from Councilman Phillips, Mr. Lipinski confirmed that the work would be completed by a contractor. Councilwoman Klapp said 20-year payback projects are not the best use of the City’s money. Councilwoman Littlefield inquired as to life expectancy. Mr. Lipinski said some of the City’s solar photovoltaic panels have been in use for over 20 years. The City receives a guaranteed period (seven to ten years) where they do not degrade below a certain level. The City is finding that the degradation period is even longer than the estimate. After 15 to 20 years, the supporting equipment needs replacement. The electricity generated is based on a number of factors, such as square footage and obstructions. This is matched against the electrical needs of the buildings. The savings vary; they are reflected in the reduction of the power bill and are generally substantial. Councilman Phillips supported leaving the items on the list to allow the public to provide input. Councilwoman Littlefield concurred. She also suggested the possibility of adding solar at the WestWorld parking lots. Tim Conner, Office of Environmental Initiatives Manager, commented that another project in the WestWorld package includes a shade structure on the arena, which would be another opportunity to install solar. Councilwoman Littlefield suggested pursuing the option. Mr. Lipinski summarized the direction to staff to keep all four solar projects on the list. Mr. Lipinski addressed the powerline undergrounding projects, which are a continuation of the Scottsdale Road streetscape project. Other sections of Scottsdale Road were covered under Bond 2000 to underground powerlines. In terms of creating a facilities district for the undergrounding, the City only owns half the street. The other half is owned by other municipalities. Councilman Phillips said that residents should have the opportunity to decide. Councilwoman Littlefield said she had previously inquired as to a facilities district, noting that several districts have been asked to pay for their undergrounding. The policy should be consistent as a decision of those who live in the vicinity. Councilman Phillips agreed that it is a public amenity. Mr. Worth said that historically, the City has used bond funding to underground significant portions of the 69KV powerlines along Scottsdale Road. Bond funds were used to do the segment from Indian Bend north to Doubletree Ranch, the segment from just north of the canal up to Thompson Peak Parkway, and to do a portion on either side of Thunderbird. These projects fill in the gaps. The rationale in 2000 and the years following was that Scottsdale Road is the main tourist corridor for the City. Councilwoman Klapp agreed to leave the projects on the

Page 5: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Council Capital Improvement Plan (CIP) Subcommittee February 7, 2019 Page 5 of 6 list, however, it may lead to requests from other areas to have their powerlines undergrounded as well. There are many tourist areas besides Scottsdale Road. It is her preference to not include this on the bond list. Councilwoman Littlefield agreed generally, however, she was interested in hearing input from citizens. Councilman Phillips said he would like to see it remain on the list and receive public comment. Mr. Lipinski addressed the purchase of land adjacent to Pinnacle Peak Park to expand the parking lot and do upgrades to the facility. Kroy Ekblaw, Preserve Director, clarified that the funding would not come from Preserve funds. The additional parking will help to avoid future neighborhood conflicts as development increases. Councilwoman Littlefield suggested changing the title in order to avoid confusion regarding Preserve funds. Mr. Lipinski discussed an item not yet included in the list of unfunded projects is the Thompson Peak Parkway Bridge at Reata Wash, which would build the northern bridge. It is on the Unfunded Transportation list. Councilman Phillips expressed support for the project. In response to a question from Councilwoman Klapp, Mr. Lipinski said there is not currently funding through the Transportation Sales Tax (0.20%) available balance list. The idea is that with the new Transportation Sales Tax 2019 (0.10%) in place, this may be funded down the road. Councilwoman Klapp noted that other Transportation projects were removed from the Unfunded Projects list several meetings ago. Mr. Lipinski confirmed that this would be the only Transportation item being added to the list. Councilman Phillips said that all it is under the heading of Transportation, it involves completion of a bridge and as long as it is presented in this fashion, people will be more favorable towards it. In response to a question from Councilwoman Littlefield, Mr. Lipinski said the cost is $6.3 million. Councilwoman Littlefield said she is willing to include it, as there is no other funding source. Erin Walsh, Public Information Officer, discussed next steps in public outreach. Many of the projects have already had public input. The outreach period will be from February 19th through March 12th. Truncated public comment periods actually increase involvement. The comment period would include a website platform with a feedback component. Four to six community meetings are proposed. The timeline allows for the City Council to call an election in April. The goal will be to provide the information to City Council on March 14th or March 19th. Staff proposes a City Council study session on March 26th. The April 2nd City Council meeting could include discussion on how to group projects. In response to a question from Councilwoman Littlefield, Ms. Walsh stated that the timeline would have the bond on the ballot in the fall. Councilman Phillips asked about the possibility of individual members being able to discuss the issue on social media or hold their own meetings. Mr. Washburn said that state law prohibits the use of City resources in an attempt to influence the outcome of an election. As long as individuals are not using City resources, they can advocate for an election, even after the election has been called. The use of the position of City Councilmember is not the use of City resources. However, actions such as using a City office phone for such uses is prohibited. Councilman Phillips suggested that a notice be sent to City Council reviewing these provisions. Councilwoman Littlefield asked why storm drain projects were removed from the list. Mr. Thompson stated that last year, the City increased its storm drain fee. The proposal is to fund as many storm drain projects as possible using this fee. Reata was the only one remaining. There was agreement by the CIP Subcommittee for the proposed timeline.

Page 6: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Council Capital Improvement Plan (CIP) Subcommittee February 7, 2019 Page 6 of 6 Alex McLaren was recognized to offer public comments. He agrees with the public outreach outline. He suggested the possibility grouping questions according to the type of project. In terms of drainage projects, there are concerns regarding moving into the area of a drainage utility. The preparatory steps may not have yet been taken to set up such a utility. Stadium improvements are not included on the list. This is a very important project that needs to be funded. The undergrounding of the powerlines should be left on the list. It is important to note the difference between 69KV lines and 12KV lines. 3. DISCUSSION AND DIRECTION TO STAFF REGARDING MEETING LOGISTICS

(MEETING FREQUENCY, DATES, TIMES AND LOCATION) Discussion ensued regarding upcoming meeting dates and the possibility of grouping like projects together before the first full City Council meeting. There was consensus to meet on March 13th with the first discussion of City Council on March 19th. Councilwoman Littlefield suggested that when preparing the material for City Council, there should be comments included as to why certain items were removed from the list. DIRECTION TO STAFF: To schedule the next meeting on March 13, 2019 to

discuss: 1) feedback from the Community Outreach Sessions; 2) suggestions on how to group projects; and 3) a recommendation to City Council.

PUBLIC COMMENT

There were no public comments. ADJOURNMENT With no further business to discuss, being duly moved by Councilwoman Klapp and seconded by Councilwoman Littlefield, the meeting adjourned at 9:50 a.m. AYES: Councilman Phillips, Councilwoman Klapp, Councilwoman Littlefield NAYS: None SUBMITTED BY: eScribers, LLC *Note: These are summary action meeting minutes only. A complete copy of the audio/video recording is available at http://www.scottsdaleaz.gov/council/council-subcommittees/capital-improvement-subcommittee

Page 7: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Item 2

Page 8: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager
Page 9: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager
Page 10: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager
Page 11: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager
Page 12: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager
Page 13: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager
Page 14: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Rank Project TitleUnfunded Amount

Other Sources

Unfunded Running

Total 1 Replace Aging Infrastructure and Improve Public and Event Spaces on Civic Center Plaza 27,317.8 0.0 27,317.8 2 Add Splash Pad and Improve Walkways at McCormick-Stillman Railroad Park 917.2 0.0 28,235.0 3 Build Flood Control Structures to Protect Homes and Businesses in the Reata Wash Flood Plain 27,330.0 27,330.0 55,565.0 4 Renovate WestWorld Horse Barns to Increase Rentable Space 4,703.0 0.0 60,268.0 5 Replace Outdated Emergency Response Equipment for Fire Department 2,057.0 0.0 62,325.0 6 Modernize Computer Equipment Rooms to Protect City Servers 691.6 0.0 63,016.6 7 Replace Emergency Power Source for Public Safety Radio Network 305.2 0.0 63,321.9 8 Upgrade Police Records Management System to Improve Reporting and Analytics 591.2 0.0 63,913.0 9 Upgrade Website Management Software 188.6 39.4 64,101.6

10 Replace the Public Address System at WestWorld 366.1 0.0 64,467.7 11 Install Fiber Optic Infrastructure to Reduce Operating Costs 11,385.6 6,332.4 75,853.3 12 Replace Tennis Court Surface at Indian School Park and Scottsdale Tennis Center 3,497.1 0.0 79,350.4 13 Replace Document Management System to Improve Public Access to Information 674.0 0.0 80,024.4 14 Update Scottsdale's 15-year-old Digital Terrain Model 177.2 0.0 80,201.6 15 Expand Granite Reef Senior Center to Meet Demand for Adult Day Care Center 2,972.2 0.0 83,173.8 16 Replace Obsolete Planning and Permitting Software 2,964.0 0.0 86,137.8 17 Build 200 Space Parking Lot off 75th Street to Serve the City Court and Scottsdale Stadium 1,530.7 0.0 87,668.5 18 Replace the City's Obsolete Training Software 342.0 0.0 88,010.5 19 Obtain a Citywide Data Management and Analytics Solution for Data-Based Decision Making 62.0 0.0 88,072.5 20 Build Roadway and Pedestrian Improvements along 2nd Street from Drinkwater Blvd to Goldwater Blvd 1,845.4 0.0 89,917.9 21 Build Roadway and Pedestrian Improvements along Marshall Way North of Indian School Road 1,800.8 0.0 91,718.7 22 Replace WestWorld Arena Lights to Reduce Operating Costs 1,331.3 0.0 93,050.0 23 Widen 94th Street at WestWorld to Improve Access 1,469.2 0.0 94,519.1 24 Build Roadway and Pedestrian Improvements along Main Street from Scottsdale Road to Brown Avenue 994.2 0.0 95,513.3 25 Build Shade Structure over Arena at WestWorld to Increase Event Revenue 543.5 500.0 96,056.8 26 Expand Via Linda Senior Center to Meet Demand for Senior Services 4,538.6 0.0 100,595.4 27 Build New Swimming Pools and Replace Building at Cactus Pool 31,229.6 0.0 131,825.0 28 Repair Lakes and Irrigation at Vista del Camino Park in the Indian Bend Wash 23,512.8 0.0 155,337.8 29 Renovate Arena at WestWorld to Provide Flexible Event Space 960.3 0.0 156,298.1 30 Install High Efficiency Sports Lighting at 4 Facilities 1,224.3 0.0 157,522.5 31 Replace Aging Buildings that Comprise Paiute Community Center 11,174.2 0.0 168,696.7 32 Replace Deteriorating Vehicle Training Track at the Police and Fire Training Facility 1,919.4 0.0 170,616.1 33 Modernize and Expand the Police and Fire Training Facility 4,227.3 0.0 174,843.4 34 Build a New Fire Station near Hayden Road and the Loop 101 to Improve Response Times 10,470.0 0.0 185,313.4 35 Replace Workstations at 911 Communications Dispatch Center to Accommodate New Technology 638.5 0.0 185,951.9 36 Install Permanent Lighting at WestWorld Parking Lots to Reduce Operating Costs 1,438.3 0.0 187,390.2 37 Indian School Park Field 1 Lighting 696.1 0.0 188,086.3 38 Move Powerlines Underground along Scottsdale Road from Frank Lloyd Wright Blvd to Thunderbird Road 16,095.3 0.0 204,181.5 39 Convert Mountain View Park Tennis Courts to Sand Volleyball Courts to Meet Demand and Increase Revenue 506.1 0.0 204,687.7 40 Move Powerlines Underground along Scottsdale Road from Indian Bend Road to Chaparral Road 14,271.4 0.0 218,959.1 41 Move Powerlines Underground in several areas along Scottsdale Road from Sweetwater Blvd to Double Tree Ranch Road 20,090.2 0.0 239,049.3 42 Renovate and Modernize the Stage 2 Theater at the Scottsdale Center for the Performing Arts 1,200.0 0.0 240,249.3

Unfunded Projects(in thousands)

1

Page 15: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Rank Project TitleUnfunded Amount

Other Sources

Unfunded Running

Total

Unfunded Projects(in thousands)

43 Expand Restrooms in WestWorld North Hall 701.5 0.0 240,950.8 44 Move Powerlines Underground and Build New Streetlight System on Scottsdale Road from Thompson Peak Parkway to Williams Drive 12,140.6 0.0 253,091.4 45 Renovate the Via Linda Police Station to Increase Efficiency 16,600.0 0.0 269,691.4 46 Build New Fire Station at 90th Street and Via Linda to Replace Aging Facility 5,914.0 0.0 275,605.4 47 Build a Community Center in DC Ranch 13,021.6 0.0 288,627.0 48 Install Bullet Proof Glass in Reception Areas of Police Department Facilities 977.3 0.0 289,604.3 49 Provide Free Public WiFi at the Civic Center Plaza 57.2 0.0 289,661.5 50 Implement an Inventory and Asset Control System for City Technology 572.0 0.0 290,233.5 51 Install Solar Systems North Corporation Campus 4,810.3 0.0 295,043.8 52 Install Parasol Solar Shade Structure at City Hall Parking Lot 4,669.4 0.0 299,713.2 53 Install Solar Systems at Civic Center Campus 2,784.5 0.0 302,497.7 54 Build Parking Lots in the Vicinity of WestWorld to Support Special Events 47,000.0 0.0 349,497.7 55 Build a new Fire Department Training Facility 18,258.5 0.0 367,756.2 56 Build a Community Center at Ashler Hills Drive and 74th Way (Whisper Rock) 9,084.7 0.0 376,840.9 57 Renovate the Foothills Police Station to Accommodate Current Staffing Levels 1,024.0 0.0 377,864.9 58 Build a Community Center at Doc Cavalliere Park 10,736.4 0.0 388,601.3 59 Renovate and Expand the Civic Center Jail and Downtown Police Facility to Meet Demand 13,102.5 0.0 401,703.8 60 Build a 17-Acre Neighborhood Park at Ashler Hills Drive and 74th Way (Whisper Rock) 6,097.7 0.0 407,801.5 61 Install Solar Heating System for Eldorado Pool 560.3 0.0 408,361.8 62 Build a Community Center at Thompson Peak Park 9,636.1 0.0 417,997.9 63 Double the Solar Power Generating Capacity at Appaloosa Library 39.7 0.0 418,037.6 64 Build a Neighborhood Park in DC Ranch 6,097.7 0.0 424,135.3 65 Add a Dog Park to Thompson Peak Park 4,637.4 0.0 428,772.6 66 Improve 5th Avenue from Scottsdale Road to Goldwater Boulevard 3,569.9 0.0 432,342.5 67 Replacement of Fire Utility Truck to be used on fire ground activity and response to Hazardous Materials and Technical Rescue incidents 782.6 0.0 433,125.1 68 Purchase land, expand Pinnacle Peak Park parking lot, staff office and restrooms, renovate hiking trail and construct an interpretive trail 5,000.0 0.0 438,125.1

Total 438,125.1

2

Page 16: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Unfunded Projects

Page 17: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Unfunded Projects Table of Contents (in thousands)

* Project has “Other Funding” Sources Page 1 of 3

Project Rank Project Title

Unfunded Amount

Total Project

Cost Page

Number 1 Replace Aging Infrastructure and Improve Public and Event Spaces on Civic

Center Plaza 27,317.8 27,317.8 1

2 Add Splash Pad and Improve Walkways at McCormick-Stillman Railroad Park 917.2 917.2 1

3 Build Flood Control Structures to Protect Homes and Businesses in the Reata Wash Flood Plain *

27,330.0 54,660.0 1

4 Renovate WestWorld Horse Barns to Increase Rentable Space 4,703.0 4,703.0 1

5 Replace Outdated Emergency Response Equipment for Fire Department 2,057.0 2,057.0 1

6 Modernize Computer Equipment Rooms to Protect City Servers 691.6 691.6 2

7 Replace Emergency Power Source for Public Safety Radio Network 305.2 305.2 2

8 Upgrade Police Records Management System to Improve Reporting and Analytics 591.2 591.2 2

9 Upgrade Website Management Software * 188.6 228.0 2

10 Replace the Public Address System at WestWorld 366.1 366.1 3

11 Install Fiber Optic Infrastructure to Reduce Operating Costs * 11,385.6 17,718.0 3

12 Replace Tennis Court Surface at Indian School Park and Scottsdale Tennis Center

3,497.1 3,497.1 3

13 Replace Document Management System to Improve Public Access to Information 674.0 674.0 3

14 Update Scottsdale's 15-year-old Digital Terrain Model 177.2 177.2 3

15 Expand Granite Reef Senior Center to Meet Demand for Adult Day Care Center 2,972.2 2,972.2 4

16 Replace Obsolete Planning and Permitting Software 2,964.0 2,964.0 4

17 Build 200 Space Parking Lot off 75th Street to Serve the City Court and Scottsdale Stadium

1,530.7 1,530.7 4

18 Replace the City's Obsolete Training Software 342.0 342.0 4

19 Obtain a Citywide Data Management and Analytics Solution for Data-Based Decision Making

62.0 62.0 4

20 Build Roadway and Pedestrian Improvements along 2nd Street from Drinkwater Blvd to Goldwater Blvd

1,845.4 1,845.4 5

21 Build Roadway and Pedestrian Improvements along Marshall Way North of Indian School Road

1,800.8 1,800.8 5

22 Replace WestWorld Arena Lights to Reduce Operating Costs 1,331.3 1,331.3 5

23 Widen 94th Street at WestWorld to Improve Access 1,469.2 1,469.2 5

24 Build Roadway and Pedestrian Improvements along Main Street from Scottsdale Road to Brown Avenue

994.2 994.2 5

25 Build Shade Structure over Arena at WestWorld to Increase Event Revenue* 543.5 1,043.5 6

Page 18: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Unfunded Projects Table of Contents (in thousands)

* Project has “Other Funding” Sources Page 2 of 3

26 Expand Via Linda Senior Center to Meet Demand for Senior Services 4,538.6 4,538.6 6

27 Build New Swimming Pools and Replace Building at Cactus Pool 31,229.6 31,229.6 6

28 Repair Lakes and Irrigation at Vista del Camino Park in the Indian Bend Wash 23,512.8 23,512.8 6

29 Renovate Arena at WestWorld to Provide Flexible Event Space 960.3 960.3 6

30 Install High Efficiency Sports Lighting at 4 Facilities 1,224.3 1,224.3 7

31 Replace Aging Buildings that Comprise Paiute Community Center 11,174.2 11,174.2 7

32 Replace Deteriorating Vehicle Training Track at the Police and Fire Training Facility

1,919.4 1,919.4 7

33 Modernize and Expand the Police and Fire Training Facility 4,227.3 4,227.3 7

34 Build a New Fire Station near Hayden Road and the Loop 101 to Improve Response Times

10,470.0 10,470.0 8

35 Replace Workstations at 911 Communications Dispatch Center to Accommodate New Technology

638.5 638.5 8

36 Install Permanent Lighting at WestWorld Parking Lots to Reduce Operating Costs 1,438.3 1,438.3 8

37 Indian School Park Field 1 Lighting 696.1 696.1 8

38 Move Powerlines Underground along Scottsdale Road from Frank Lloyd Wright Blvd to Thunderbird Road

16,095.3 16,095.3 8

39 Convert Mountain View Park Tennis Courts to Sand Volleyball Courts to Meet Demand and Increase Revenue

506.1 506.1 9

40 Move Powerlines Underground along Scottsdale Road from Indian Bend Road to Chaparral Road

14,271.4 14,271.4 9

41 Move Powerlines Underground in several areas along Scottsdale Road from Sweetwater Blvd to Double Tree Ranch Road

20,090.2 20,090.2 9

42 Renovate and Modernize the Stage 2 Theater at the Scottsdale Center for the Performing Arts

1,200.0 1,200.0 9

43 Expand Restrooms in WestWorld North Hall 701.5 701.5 9

44 Move Powerlines Underground and Build New Streetlight System on Scottsdale Road from Thompson Peak Parkway to Williams Drive

12,140.6 12,140.6 9

45 Renovate the Via Linda Police Station to Increase Efficiency 16,600.0 16,600.0 10

46 Build New Fire Station at 90th Street and Via Linda to Replace Aging Facility 5,914.0 5,914.0 10

47 Build a Community Center in DC Ranch 13,021.6 13,021.6 10

48 Install Bullet Proof Glass in Reception Areas of Police Department Facilities 977.3 977.3 10

49 Provide Free Public WiFi at the Civic Center Plaza 57.2 57.2 10

50 Implement an Inventory and Asset Control System for City Technology 572.0 572.0 11

51 Install Solar Systems North Corporation Campus 4,810.3 4,810.3 11

52 Install Parasol Solar Shade Structure at City Hall Parking Lot 4,669.4 4,669.4 11

53 Install Solar Systems at Civic Center Campus 2,784.5 2,784.5 11

54 Build Parking Lots in the Vicinity of WestWorld to Support Special Events 47,000.0 47,000.0 11

Page 19: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Unfunded Projects Table of Contents (in thousands)

* Project has “Other Funding” Sources Page 3 of 3

55 Build a new Fire Department Training Facility 18,258.5 18,258.5 12

56 Build a Community Center at Ashler Hills Drive and 74th Way (Whisper Rock) 9,084.7 9,084.7 12

57 Renovate the Foothills Police Station to Accommodate Current Staffing Levels 1,024.0 1,024.0 12

58 Build a Community Center at Doc Cavalliere Park 10,736.4 10,736.4 12

59 Renovate and Expand the Civic Center Jail and Downtown Police Facility to Meet Demand

13,102.5 13,102.5 12

60 Build a 17-Acre Neighborhood Park at Ashler Hills Drive and 74th Way (Whisper Rock)

6,097.7 6,097.7 13

61 Install Solar Heating System for Eldorado Pool 560.3 560.3 13

62 Build a Community Center at Thompson Peak Park 9,636.1 9,636.1 13

63 Double the Solar Power Generating Capacity at Appaloosa Library 39.7 39.7 13

64 Build a Neighborhood Park in DC Ranch 6,097.7 6,097.7 13

65 Add a Dog Park to Thompson Peak Park 4,637.4 4,637.4 14

66 Improve 5th Avenue from Scottsdale Road to Goldwater Boulevard 3,569.9 3,569.9 14

67 Replacement of Fire Utility Truck to be used on fire ground activity and response to Hazardous Materials and Technical Rescue incidents

782.6 782.6 14

68 Purchase land, expand Pinnacle Peak Park parking lot, staff office and restrooms, renovate hiking trail and construct an interpretive trail

5,000.0 5,000.0 14

Total: 438,125.1 467,327.0

Page 20: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Unfunded Projects Project Descriptions (in thousands)

Page 1 of 14

Replace Aging Infrastructure and Improve Public and Event Spaces on Civic Center Plaza Rebuild the Scottsdale Civic Center Plaza as the community’s signature special event and public gathering space. As recommended by the Tourism Strategic Plan, Public Spaces Master Plan, the City of Scottsdale General Plan, the Old Town Character Area Plan and public outreach conducted since 2015, the conceptual design would create an “event ready” venue that includes an iconic stage structure. With few regional competitors for large events in an outdoor setting, the new public space would place Scottsdale in a competitive position to attract large-scale events, such as Super Bowl Live, a multi-day event leading up to Super Bowl 2023.

Unfunded Amount: 27,317.8 Total Project Cost: 27,317.8

Add Splash Pad and Improve Walkways at McCormick-Stillman Railroad Park Add a splash pad and Improve walkways at McCormick-Stillman Railroad Park to implement the park’s master plan to boost attendance and revenues. The splash pad will boost park attendance and revenues from May through August when both numbers drop off. McCormick-Stillman Railroad Park is Scottsdale's signature park and generates approximately $1.5 million of revenue annually.

Unfunded Amount: 917.2 Total Project Cost: 917.2

Build Flood Control Structures to Protect Homes and Businesses in the Reata Wash Flood Plain Building drainage systems to divert storm flows along Reata Wash from Pinnacle Peak Road to existing retention basins at WestWorld could alleviate temporary road closures and other disruptions caused by seasonal storms and provide 100-year flood protection for 4,600 structures in the area, which could save a typical mortgage holder several hundred dollars per year on flood insurance premiums.

Unfunded Amount: 27,330.0 Other Sources: 27,330.0 Total Project Cost: 54,660.0

Renovate WestWorld Horse Barns to Increase Rentable Space These revenue-generating facilities are a key part of any horse show held at WestWorld. Built in the 1980s, the barns require renovation to remain useful and rentable.

Unfunded Amount: 4,703.0 Total Project Cost: 4,703.0

Replace Outdated Emergency Response Equipment for Fire Department Replace aging specialty public safety fire equipment that has reached or exceeded its manufacturer's useful life or needs replacement due to breakage. This equipment includes patient heart monitors known as Cardiac Monitors and Defibrillators, patient heart defibrillators known as Automatic External Defibrillators (AED), Thermal Imaging Cameras (TIC), fire fighter self-contained breathing apparatus (SCBA) units, extrication equipment and ballistic vests.

Unfunded Amount: 2,057.0 Total Project Cost: 2,057.0

Page 21: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Unfunded Projects Project Descriptions (in thousands)

Page 2 of 14

Modernize Computer Equipment Rooms to Protect City Servers Replace the battery backup power and the large cooling units that support the City’s primary data center, which has reached the end of its life cycle. Battery Backup power allows the data center to remain operational during various weather or power provider events that can cause power disruptions throughout each year. The data center supports the primary data network, phone, and server computing environments that run all of the applications and communications equipment required for the city to operate and supports all eServices for the citizens of Scottsdale.

Unfunded Amount: 691.6 Total Project Cost: 691.6

Replace Emergency Power Source for Public Safety Radio Network Replace the batteries in Uninterrupted Power Supplies (UPS) at Public Safety Radio Sites. The batteries were installed in 2010 and have an average life of 7 years. The batteries are used when there is a commercial power interruption and provide the critical link between commercial power and generator power. If the batteries are not replaced, the UPS units would not be functional, and the public safety radio system would be vulnerable to a commercial power outage. This means that the Police and Fire radios might not transmit critical and time sensitive information.

Unfunded Amount: 305.2 Total Project Cost: 305.2

Upgrade Police Records Management System to Improve Reporting and Analytics Replace the existing Police Department Computer Aided Dispatch (CAD) and Records Management System (RMS) to create a web-based platform designed to interface with new applications and improve reporting and analytics capabilities. The current suite of systems will not be supported by the vendor after FY 2018/19. A new CAD allows computer-controlled emergency vehicle dispatching, vehicle status, incident reporting, and management information. A Records Management System is an agency-wide system that provides for the storage, retrieval, retention, manipulation, archiving and viewing of information, records, documents, or files pertaining to law enforcement operations.

Unfunded Amount: 591.2 Total Project Cost: 591.2

Upgrade Website Management Software The software used to build and maintain the city’s public service websites, including ScottsdaleAZ.gov, ScottsdaleLibrary.org, and ChooseScottsdale.com was purchased in 2006 and is no longer regularly updated by the vendor. A new web content management platform is required to meet accessibility standards and provide a modern customer service experience for residents who access city services and information online.

Unfunded Amount: 188.6 Other Sources: 39.4 Total Project Cost: 228.0

Page 22: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Unfunded Projects Project Descriptions (in thousands)

Page 3 of 14

Replace the Public Address System at WestWorld Replace the outdated Public Address System at WestWorld. The current Public Address System utilized for 95 percent of all events held at WestWorld and is included as part of the base rental. The current system uses outdated technology and is experiencing frequent issues and expensive repairs, which will continue to escalate until a new system is purchased.

Unfunded Amount: 366.1 Total Project Cost: 366.1

Install Fiber Optic Infrastructure to Reduce Operating Costs Install city-owned fiber throughout the City to meet increasing need for network bandwidth to conduct business operations and reduce the dependency on leased-lines from telecommunications providers that require ongoing operating costs. The majority of the remote city sites require network bandwidth increases to meet either citizen or city employee needs including Community Centers, Parks, Libraries, Fire Stations, and other community-use or city employee-based locations.

Unfunded Amount: 11,385.6 Other Sources: 6,332.4 Total Project Cost: 17,718.0

Replace Tennis Court Surface at Indian School Park and Scottsdale Tennis Center Replace old asphalt tennis courts at Indian School Park and Scottsdale Ranch Tennis Center with post-tension concrete -- a modern system that will dramatically increase the life of the courts and reduce ongoing maintenance and operating costs. These improvements will save an estimated $3 million to $4 million in maintenance and repair costs over the 30-year life of the concrete courts.

Unfunded Amount: 3,497.1 Total Project Cost: 3,497.1

Replace Document Management System to Improve Public Access to Information The City of Scottsdale has millions of public records in electronic format. Maintaining those documents in compliance with federal, state and local laws and ensuring they are accessible quickly and efficiently requires an electronic document management system. The city’s current system is 15 years old and increasingly difficult and expensive to maintain and expand. A new system will provide a modern and cost-effective solution that best serves the needs of the organization and the public.

Unfunded Amount: 674.0 Total Project Cost: 674.0

Update Scottsdale's 15-year-old Digital Terrain Model Key city services including fire, parks, police, solid waste and water rely on location data contained in the city’s geographic information system. The heart of that system is the digital terrain model - a three-dimensional elevation map of the city upon which buildings, streets, waterlines and other city infrastructure is placed. As the surface of Scottsdale changes with development and redevelopment, the accuracy of our digital terrain model, now 15 years old, continuously degrades. Updating this model is required to maintain the fidelity of data and accuracy of information the city relies on to provide service and make data-based decisions.

Unfunded Amount: 177.2 Total Project Cost: 177.2

Page 23: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Unfunded Projects Project Descriptions (in thousands)

Page 4 of 14

Expand Granite Reef Senior Center to Meet Demand for Adult Day Care Center Add a 7,600 square foot expansion to Granite Reef Senior Center to meet the growing demand for senior services, including an Adult Day Care Center. The new space would offer fee-based adult day care services during the day, for which there is an increasing demand and no service provides in South Scottsdale. Fee-based leisure education classes would be held in the evenings.

Unfunded Amount: 2,972.2 Total Project Cost: 2,972.2

Replace Obsolete Planning and Permitting Software Purchase a fully integrated web-based Community Development System (CDS) to increase efficiency and enhance the customer experience for Planning & Zoning, Long Range Planning, Environmental Initiatives, Plan Review for Building & Engineering, Stormwater Management, One Stop Shop permitting, the Records department, Inspections, Building & Engineering, and Code Enforcement. The new system will allow customers an intuitive, user-friendly interface to submit cases, construction plans, re-submittals, and other documents at the One Stop Shop which collects over $20 million in revenue annually.

Unfunded Amount: 2,964.0 Total Project Cost: 2,964.0

Build 200 Space Parking Lot off 75th Street to Serve the City Court and Scottsdale Stadium This project would add 180–200 new parking spaces on 75th Street for the public visiting the City Court and Scottsdale Stadium and improve stadium access for emergency vehicles, solid waste trucks and other services. The new parking would address the daily parking needs at the city court and reduce spillover parking in adjacent neighborhoods during Spring Training games and other large stadium events.

Unfunded Amount: 1,530.7 Total Project Cost: 1,530.7

Replace the City's Obsolete Training Software The city’s web-based training system, used by employees across the organization to maintain and improve key job skills, is no longer supported by the vendor. A new system is required to provide for the ongoing training needs of city employees, comply with documentation and tracking requirements and Arizona public records law.

Unfunded Amount: 342.0 Total Project Cost: 342.0

Obtain a Citywide Data Management and Analytics Solution for Data-Based Decision Making Identify and purchase a software system to store and analyze vast amounts of data generated across the organization so this information can power data-based decision making. The goal is to improve service to residents, identify potential problems and increase the efficiency of city operations by combining disparate data sets into actionable intelligence.

Unfunded Amount: 62.0 Total Project Cost: 62.0

Page 24: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Unfunded Projects Project Descriptions (in thousands)

Page 5 of 14

Build Roadway and Pedestrian Improvements along 2nd Street from Drinkwater Blvd to Goldwater Blvd Widen and repair sidewalks, add bike lanes, new landscaping and pedestrian lighting, and build two pocket parks to help create a better pedestrian experience in this portion of Old Town Scottsdale per the Main Street Streetscape and Pedestrian Design plan.

Unfunded Amount: 1,845.4 Total Project Cost: 1,845.4

Build Roadway and Pedestrian Improvements along Marshall Way North of Indian School Road Narrow the traffic lanes and widen sidewalks, add bike lanes, new landscaping and pedestrian lighting and add at least two pocket parks to improve the pedestrian experience in this portion of Old Town Scottsdale. The focus of this project is the section of Marshall Way from Indian School Road north to 5th Avenue; Marshall Way has long been envisioned as a major pedestrian corridor connecting the northern and southern ends of Goldwater Boulevard. This project implements recommendations of a handful of planning efforts including the Tourism Strategic Plan, Downtown 2.0, the Public Spaces Master Plan, and the Economic Development Strategic Plan as well as the City of Scottsdale General Plan 2001 and the Old Town Scottsdale Character Area Plan.

Unfunded Amount: 1,800.8 Total Project Cost: 1,800.8

Replace WestWorld Arena Lights to Reduce Operating Costs Replace lights at several arenas to reduce operating costs, replace outdated technology and reduce light spillage to adjacent communities. The lighting at WestWorld is over 35 years old and uses outdated technology. A new LED system will provide focused lighting within the arenas eliminating light trespass and glare, provide HD TV broadcast quality light levels, and instant-on with no warm-up delay and have an operating impact savings of $24,000.

Unfunded Amount: 1,331.3 Total Project Cost: 1,331.3

Widen 94th Street at WestWorld to Improve Access Widen 94th Street from WestWorld Drive to Bahia Drive to include a sidewalk, curbing, gutter, and streetlights to improve access and reduce safety hazards. This is one of the main entrances into WestWorld, and a thoroughfare for many of the 800,000+ attendees to WestWorld events. Temporary light towers, currently used for guest safety, are expensive to operate and generate complaints and would no longer be needed with the new streetlight system.

Unfunded Amount: 1,469.2 Total Project Cost: 1,469.2

Build Roadway and Pedestrian Improvements along Main Street from Scottsdale Road to Brown Avenue Design and build streetscape and pedestrian improvements from Scottsdale Road east to Brown Avenue in Historic Old Town. Main Street has long been envisioned as a major east/west pedestrian corridor; this project would create a better pedestrian experience via improved sidewalks, lighting and landscaping and two pocket parks. This project implements recommendations of a handful of planning efforts including the Tourism Strategic Plan, Downtown 2.0, the Public Spaces Master Plan, and the Economic Development Strategic Plan as well as the City of Scottsdale General Plan 2001 and the Old Town Scottsdale Character Area Plan.

Unfunded Amount: 994.2 Total Project Cost: 994.2

Page 25: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Unfunded Projects Project Descriptions (in thousands)

Page 6 of 14

Build Shade Structure over Arena at WestWorld to Increase Event Revenue Build a shade structure over an existing arena at WestWorld to increase event revenue and extend the arena’s use in the warmer months. The additional covered area would increase revenue by $28,000 a year.

Unfunded Amount: 543.5 Other Sources: 500.0 Total Project Cost: 1,043.5

Expand Via Linda Senior Center to Meet Demand for Senior Services Expand the Via Linda Senior Center by approximately 7,800 to address the increasing demand for services and leisure education classes. Demand for adult services and leisure education offerings is increasing, will continue to increase, as census figures show that 42 percent of Scottsdale population is over the age of 50.

Unfunded Amount: 4,538.6 Total Project Cost: 4,538.6

Build New Swimming Pools and Replace Building at Cactus Pool Renovate aging swimming pool and buildings at Cactus Aquatic Center to meet increasing demand and increase revenue. The current pool and building have many limitations including pool leakage, dated restrooms and showers, limited ADA access and security concerns and limited possibilities for improvement. Cactus Pool hosts 144,000 guests annually and is the only City aquatics facility that can host swimming and diving competitions. The renovated facility is projects to increase revenue by $125,000 annually.

Unfunded Amount: 31,229.6 Total Project Cost: 31,229.6

Repair Lakes and Irrigation at Vista del Camino Park in the Indian Bend Wash Repair Failing Lakes and Irrigation from McKellips Road to Thomas Road in the Indian Bend Wash. The lake system is showing signs of aging and failure due to punctures in the lake liner, erosion of the lake edges and leaks in the spillway system. The irrigation systems are outdated, undersized and perform inadequately. Updating materials and technologies will lower annual operating cost, enhance water conservation and quality, resolve lake edge erosion and allow more effective use of park open space areas.

Unfunded Amount: 23,512.8 Total Project Cost: 23,512.8

Renovate Arena at WestWorld to Provide Flexible Event Space Arena 8 at WestWorld lacks flexibility and is therefore of limited use for many events. Relocating light towers and adding power and box connections would provide the needed flexibility and increase the rentable, useful space at WestWorld.

Unfunded Amount: 960.3 Total Project Cost: 960.3

Page 26: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Unfunded Projects Project Descriptions (in thousands)

Page 7 of 14

Install High Efficiency Sports Lighting at 4 Facilities Replace, upgrade or install new lighting systems for sports fields at Laguna and Pima schools, Horizon Park and at two currently unlit fields at Scottsdale Sports Complex to meet increased demand and current sports lighting standards, and to minimize light spillage in adjacent neighborhoods. The newly lit fields at Scottsdale Sports Complex would generate approximately $10,000 per year in additional revenue and offset any utility costs associated with the new lights. Additionally, these lights will eliminate the annual need to use diesel generators for lighting in some areas of the Phoenix Open and reduce light spillage into the surrounding area.

Unfunded Amount: 1,224.3 Total Project Cost: 1,224.3

Replace Aging Buildings that Comprise Paiute Community Center Build a new 22,700 square foot facility to replace the existing buildings that comprise Paiute Neighborhood Center. The existing buildings have fallen into a state of disrepair and are costing the city approximately $144,000 per year in maintenance costs. The new facility has a projected increase of $25,000 in annual Leisure Education revenue.

Unfunded Amount: 11,174.2 Total Project Cost: 11,174.2

Replace Deteriorating Vehicle Training Track at the Police and Fire Training Facility Replace the Deteriorated Vehicle Training Track at the Police and Fire Training Facility to accommodate the weight of Fire Department Vehicles and Equipment. The current track was developed prior to the City having a municipal Fire Department and was designed for use by light duty vehicles, such as motorcycles and automobiles. With the formation of the Scottsdale Fire Department, the track is being utilized by larger and heavier equipment than the track was designed to handle. The track has excessive damage and constant repairs are needed resulting in training delays for police, fire, and municipal departments.

Unfunded Amount: 1,919.4 Total Project Cost: 1,919.4

Modernize and Expand the Police and Fire Training Facility Build a stand-alone 5,000 square foot, two story training structure, a 2,000 square foot live fire shoot house and renovate current ballistic range to accommodate 15 shooting lanes. The new training facility will accommodate the size of the police and fire departments and maintain pace with technological and legal changes within the law enforcement community. The current facility is over 20 years old, undersized, does not meet the national training curriculum standards and limits the type of training police officers and personnel can receive creating a safety issue.

Unfunded Amount: 4,227.3 Total Project Cost: 4,227.3

Page 27: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Unfunded Projects Project Descriptions (in thousands)

Page 8 of 14

Build a New Fire Station near Hayden Road and the Loop 101 to Improve Response Times Design and construct a new 12,000 square foot fire station northwest of the Airpark near the 101 and Hayden Road to improve response times. The response times from this station are significantly impacted by its location and explosive growth for residential and commercial properties in the area. As a result, both stations 609 and 611 have a response time that exceeds the goal of 4 minutes. By moving the station closer to the geographic center of the area it serves and improving access, the response times for emergency services will improve significantly.

Unfunded Amount: 10,470.0 Total Project Cost: 10,470.0

Replace Workstations at 911 Communications Dispatch Center to Accommodate New Technology The workstations used by Scottsdale’s 911 emergency dispatch operators are 10-15 years old and nearing the end of their service life. This project would install new workstations that include modern video monitors, telephones, radios and ergonomic features in addition to improving the acoustics and flooring throughout the dispatch center.

Unfunded Amount: 638.5 Total Project Cost: 638.5

Install Permanent Lighting at WestWorld Parking Lots to Reduce Operating Costs Install permanent lighting for gravel parking lots K & M at WestWorld which are utilized for parking during WestWorld events. These parking lots are used by over 800,000+ people annually and are currently lit with temporary light towers to ensure public safety. The temporary light towers are noisy, create glares impacting WestWorld's neighbors to the north, and are costly due to their diesel generators. Permanent lights will reduce operating costs, improve the event experience at WestWorld and increase the ability to attract new events.

Unfunded Amount: 1,438.3 Total Project Cost: 1,438.3

Indian School Park Field 1 Lighting Replace the sub-standard light towers on Field 1 at Indian School Park to expand operating hours and increase revenue. The new lightning will be more energy efficient, comes with a 25-year maintenance-free guarantee, and reduces light spillage into the surrounding neighborhood by 50 percent.

Unfunded Amount: 696.1 Total Project Cost: 696.1

Move Powerlines Underground along Scottsdale Road from Frank Lloyd Wright Blvd to Thunderbird Road Underground existing above grade dry utilities including overhead power, cable TV, telephone, fiber optics and intelligent transportation systems and replace street lights currently mounted on power existing power poles on Scottsdale Road from Frank Lloyd Wright Boulevard to Thunderbird Road.

Unfunded Amount: 16,095.3 Total Project Cost: 16,095.3

Page 28: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Unfunded Projects Project Descriptions (in thousands)

Page 9 of 14

Convert Mountain View Park Tennis Courts to Sand Volleyball Courts to Meet Demand and Increase Revenue Convert 2 tennis courts at Mountain View Park to 4 sand volleyball courts to meet demand and increase revenue. Demand for volleyball courts has increased to coincide with increased participation throughout Scottsdale schools. The new volleyball courts will be rented to teams and individuals and have a projected revenue of $45,000 annually.

Unfunded Amount: 506.1 Total Project Cost: 506.1

Move Powerlines Underground along Scottsdale Road from Indian Bend Road to Chaparral Road Underground existing above grade dry utilities including overhead power, cable TV, telephone, fiber optics and intelligent transportation systems and replace street lights currently mounted on power existing power poles on Scottsdale Road from Indian bend Road to Chaparral Road.

Unfunded Amount: 14,271.4 Total Project Cost: 14,271.4

Move Powerlines Underground in several areas along Scottsdale Road from Sweetwater Blvd to Double Tree Ranch Road Underground existing above grade dry utilities including overhead power, cable TV, telephone, fiber optics and intelligent transportation systems and replace street lights currently mounted on power existing power poles on Scottsdale Road from Sweetwater Boulevard to Doubletree Ranch Road.

Unfunded Amount: 20,090.2 Total Project Cost: 20,090.2

Renovate and Modernize the Stage 2 Theater at the Scottsdale Center for the Performing Arts Design and renovate the Stage 2 Theater at Scottsdale Center for the Performing Arts. This smaller theater is an integral part of Scottsdale Arts’ commitment to provide artistic and cultural programming for the community, however, the 42-year-old theater needs a complete physical renovation and technical modernization. The result would create a flexible performance space and greatly enhance the number of bookings and attendance of the theater.

Unfunded Amount: 1,200.0 Total Project Cost: 1,200.0

Expand Restrooms in WestWorld North Hall Enlarge the restrooms in north vestibule of the North Hall of the Tony Nelssen Events Center at WestWorld to meet demand during large events.

Unfunded Amount: 701.5 Total Project Cost: 701.5

Move Powerlines Underground and Build New Streetlight System on Scottsdale Road from Thompson Peak Parkway to Williams Drive Underground existing above grade dry utilities including overhead power, cable TV, telephone, fiber optics and intelligent transportation systems and replace street lights currently mounted on power existing power poles on Scottsdale Road from Thompson Peak Parkway to Williams Drive.

Unfunded Amount: 12,140.6 Total Project Cost: 12,140.6

Page 29: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Unfunded Projects Project Descriptions (in thousands)

Page 10 of 14

Renovate the Via Linda Police Station to Increase Efficiency Reconfigure the Via Linda Police Station to Increase Efficiency. Several areas in the current building are undersized for current staffing levels and are not usable in their current condition. The renovation will create increased efficiency throughout the department and maximize service delivery to our citizens.

Unfunded Amount: 16,600.0 Total Project Cost: 16,600.0

Build New Fire Station at 90th Street and Via Linda to Replace Aging Facility Build a new fire station at 90th Street and Via Linda to replace aging facility. The current station was built in 1988 and has been modified several times, but does meet many baseline requirements of the Scottsdale Fire Department. The new station will include crew quarters and facilities, office space, Occupational Safety and Health Administration (OSHA) Certified decontamination area, safety gear storage, a double apparatus bay and public parking space with entrance.

Unfunded Amount: 5,914.0 Total Project Cost: 5,914.0

Build a Community Center in DC Ranch Build a 12,000 square foot community center to include rooms available for reservation, after-school programs and a wide variety of leisure education programs serving all age groups at Thompson Peak Parkway and Desert Camp Drive.

Unfunded Amount: 13,021.6 Total Project Cost: 13,021.6

Install Bullet Proof Glass in Reception Areas of Police Department Facilities Install approximately 420 square feet of ballistic rated glass in reception areas of the police facilities to improve safety. Over the past year the number of incidences of individuals shooting at or inside public buildings has climbed to an alarming number and the police department is most vulnerable in the areas that have direct public access.

Unfunded Amount: 977.3 Total Project Cost: 977.3

Provide Free Public WiFi at the Civic Center Plaza Provide free public WiFi on Civic Center Plaza in order to remain a competitive events venue. The Civic Center area is a gathering point for citizens and visitors alike and a venue for the city to host world-class festivals, concerts, performances, etc. Free public WiFi is a service patrons commonly expect and is becoming the norm at other venues in the valley.

Unfunded Amount: 57.2 Total Project Cost: 57.2

Page 30: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Unfunded Projects Project Descriptions (in thousands)

Page 11 of 14

Implement an Inventory and Asset Control System for City Technology Implement a citywide RFID (Radio Frequency IDentification) inventory system for all technology items which integrates with the Asset Tracking System. This newer technology would greatly improve the time, accuracy and efficiency of the annual technology inventory and recover approximately two months of staff time to focus on other projects.

Unfunded Amount: 572.0 Total Project Cost: 572.0

Install Solar Systems North Corporation Campus Install photovoltaic (PV) solar systems on 80 percent of the existing covered parking and 30 percent of the roofs of the North Corporation Yard building, PD-3 building and two water resources buildings. Additionally, install two electric vehicle dual charging stations. This project will increase the city’s solar generating capacity and reduce the energy cost of the North Campus by approximately $240,380 per year. Increased energy efficiency in public facilities and increased renewable energy production are goals in the current General Plan.

Unfunded Amount: 4,810.3 Total Project Cost: 4,810.3

Install Parasol Solar Shade Structure at City Hall Parking Lot Install a photovoltaic (PV) Parasol system over the City Hall parking lot and install 2 electric vehicle dual-charging stations. This project will increase the city's solar generating capacity, will create a shaded public space for events, and reduce the energy cost at the Civic Center Campus by approximately $130,526 per year. Increased energy efficiency in public facilities and increased renewable energy production are goals in the current General Plan.

Unfunded Amount: 4,669.4 Total Project Cost: 4,669.4

Install Solar Systems at Civic Center Campus Install a photovoltaic (PV) solar systems on a portion of the roof of City Hall, One Civic Center and the Civic Center Library, and install two electric vehicle dual-charging stations. This project will increase the solar generating capacity and reduce the energy cost of the Civic Center Campus by approximately $143,869 per year. Increased energy efficiency in public facilities and increased renewable energy production are goals in the current General Plan.

Unfunded Amount: 2,784.5 Total Project Cost: 2,784.5

Build Parking Lots in the Vicinity of WestWorld to Support Special Events Build a variety of parking solutions to support large scale events at WestWorld including the reconstruction of recreational fields and paving of gravel lots. WestWorld currently utilizes a number of temporary parking lots on Arizona State Land that will become unavailable as the land is sold.

Unfunded Amount: 47,000.0 Total Project Cost: 47,000.0

Page 31: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Unfunded Projects Project Descriptions (in thousands)

Page 12 of 14

Build a new Fire Department Training Facility The Scottsdale Fire Department requires a modern training facility to meet staff requirements and ensure department personnel are best prepared to handle the full range of medical and emergency response needs in the community. The current training complex, located on the grounds of the Tom Hontz Fire-Police Training Facility, is a hodgepodge of various buildings and resources including a prefabricated training tower and building, converted mobile storage units and a portable classroom building that is at the end of its useful life. This project would remove these outdated elements, design and build a new training complex on the current site to provide Scottsdale’s fire and emergency medical responders with a learning and training environment worthy of our staff and the community.

Unfunded Amount: 18,258.5 Total Project Cost: 18,258.5

Build a Community Center at Ashler Hills Drive and 74th Way (Whisper Rock) Build a new 18,000 square feet community center at Ashler Hills Drive and 74th Way to provide space for after school and adult programs as well as for citizens to rent for meetings and functions.

Unfunded Amount: 9,084.7 Total Project Cost: 9,084.7

Renovate the Foothills Police Station to Accommodate Current Staffing Levels The original design of the Foothills Police Station was based on 60 percent of the current staffing levels - modifications are required to account for the increased occupancy, workload and provide more efficient use of the space. This project would expand and modernize the facility to accommodate the staff who work there and add a community meeting room available for meetings by and with residents.

Unfunded Amount: 1,024.0 Total Project Cost: 1,024.0

Build a Community Center at Doc Cavaliere Park Build a new 20,000 square feet community center to provide space for city after school and adult programs as well as for citizens to rent for meetings and functions. This project includes development of a small retention basin, and associated parking spaces.

Unfunded Amount: 10,736.4 Total Project Cost: 10,736.4

Renovate and Expand the Civic Center Jail and Downtown Police Facility to Meet Demand These facilities were built in 1971 and no longer provide appropriate working environments for staff or holding environments for prisoners. The layout and infrastructure of the jail (including cell doors, booking and intake areas) is severely outdated and creates potentially unsafe conditions. The police station is the smallest of Scottsdale’s four patrol stations, and no longer appropriately accommodates current patrol operations or the specialty units (K-9, Bike Unit, High Enforcement Arrest Team) stationed there. This project would add approximately 7,800 square feet to the jail, including two additional cells, new intake and release points, supervisor offices, and attorney/client interview rooms. The police station would be enlarged and modernized to meet current needs and the entire facility will be brought up to standards of the Americans with Disabilities Act.

Unfunded Amount: 13,102.5 Total Project Cost: 13,102.5

Page 32: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Unfunded Projects Project Descriptions (in thousands)

Page 13 of 14

Build a 17-Acre Neighborhood Park at Ashler Hills Drive and 74th Way (Whisper Rock) Build a 17-acre neighborhood park to include a turf area for unscheduled recreation activities, multi-use lighted sports courts, a playground for ages 2 - 5, a restroom building and lighted parking area at Ashler Hills Drive and 74th Way.

Unfunded Amount: 6,097.7 Total Project Cost: 6,097.7

Install Solar Heating System for Eldorado Pool Install a ground mounted solar pool hot water heating system at Eldorado Pool to reduce energy costs for heating the pool during the shoulder seasons and winter months. The project is estimated to save approximately $70,000 per year in energy costs.

Unfunded Amount: 560.3 Total Project Cost: 560.3

Build a Community Center at Thompson Peak Park Build a 20,000 square-foot community center and associated parking at Thompson Peak Parkway and Desert Camp Drive. The new facility will offer after school and leisure education programs and space for community groups to hold meetings. It is anticipated that the facility would generate approximately $355,000 annually through room rentals, after-school programs and Leisure Education offerings.

Unfunded Amount: 9,636.1 Total Project Cost: 9,636.1

Double the Solar Power Generating Capacity at Appaloosa Library Install equipment to double solar electricity generating capacity at Appaloosa Library. The existing solar system was planned for additional generating capacity, but due to budget constraints, only a portion of the system was installed. Conduits and mounting racks for the additional panels are already in place. Increased energy efficiency in public facilities and increased renewable energy production are goals in the current General Plan.

Unfunded Amount: 39.7 Total Project Cost: 39.7

Build a Neighborhood Park in DC Ranch Build a 17-acre neighborhood park to include a turf area for unscheduled recreation activities, multi-use lighted sports courts, a playground for ages 2 - 5, a restroom building and lighted parking area at Thompson Peak Parkway and Desert Camp Drive. This project anticipates a revenue increase of approximately $5,000 annually through rental of the fields.

Unfunded Amount: 6,097.7 Total Project Cost: 6,097.7

Page 33: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Unfunded Projects Project Descriptions (in thousands)

Page 14 of 14

Add a Dog Park to Thompson Peak Park Build a three-and-a-half-acre Dog Park consisting of three fenced and gated areas, a footbridge connecting the new space to existing amenities and an additional parking area with space for 100 cars at Thompson Peak Park.

Unfunded Amount: 4,637.4 Total Project Cost: 4,637.4

Improve 5th Avenue from Scottsdale Road to Goldwater Boulevard Modify the size of traffic lanes, widen sidewalks, add bike lanes, improve street landscaping elements, and replace and improve street and pedestrian lighting on 5th Avenue from Scottsdale Road to Goldwater Boulevard.

Unfunded Amount: 3,569.9 Total Project Cost: 3,569.9

Replacement of Fire Utility Truck to be used on fire ground activity and response to Hazardous Materials and Technical Rescue incidents Replace the fire department’s only utility truck that went out of service in 2010 once it could not meet safety requirements. The city has not had funding to replace the unit and currently relies on automatic aid partners to provide a response vehicle to support fire ground activity and response to Hazardous Materials and Technical Rescue incidents. Response into most of Scottsdale can be a long 30-45 minutes. Acquisition of a utility truck will improve the reliability of a timely response to working incidents in Scottsdale.

Unfunded Amount: 782.6 Total Project Cost: 782.6

Expand Pinnacle Peak Park parking lot, staff office and restrooms, renovate hiking trail and construct an interpretive trail. Acquire two to three acres of land from the State of Arizona for major expansion of existing parking lot. Expand staff office and restrooms to better service increasing volume of visitors. Renovate portions of the hiking trail and construct an interpretive trail. The project was originally going to be funded by Preservation Sales Tax. It was recently determined that the project does not meet the requirement of that funding source. As a result, the project will need a new funding source in order to be completed.

Unfunded Amount: 5,000.0 Total Project Cost: 5,000.0

Page 34: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

Item 4

Page 35: SUMMARIZED MINUTES CITY OF SCOTTSDALE COUNCIL … · Jim Thompson, City Manager . Bruce Washburn, City Attorney . Judy Doyle, Budget Director . Sylvia Dlott, CIP Budget Manager

S M T W T F S S M T W T F S

1 2 3 4 5 1 2

6 7 8 9 10 11 12 3 4 5 6 7 8 9

13 14 15 16 17 18 19 10 11 12 13 14 15 16

20 21 22 23 24 25 26 17 18 19 20 21 22 23

27 28 29 30 31 24 25 26 27 28

S M T W T F S S M T W T F S

1 2 1 2 3 4 5 6

3 4 5 6 7 8 9 7 8 9 10 11 12 13

10 11 12 13 14 15 16 14 15 16 17 18 19 20

17 18 19 20 21 22 23 21 22 23 24 25 26 27

24 25 26 27 28 29 30 28 29 30

31

S M T W T F S S M T W T F S

1 2 3 4 1

5 6 7 8 9 10 11 2 3 4 5 6 7 8

12 13 14 15 16 17 18 9 10 11 12 13 14 15

19 20 21 22 23 24 25 16 17 18 19 20 21 22

26 27 28 29 30 31 23 24 25 26 27 28 29

30

Key

Subcommittee Meetings

City Council Meetings

Optional City Council Meetings

No meetings will be scheduled

Notes City Council Meetings

24-Jan Kiva Forum reserved for PD Award Ceremony 19-Mar CIP Subcommittee Recommendations

23-Jan Alternate date 14-May Tentative Budget Adoption

25-Jan Alternate date 11-Jun Final Budget Adoption

21-Feb Council Event

20-Feb Alternate date

22-Feb Alternate date