technical basics for grid connection

Upload: hilal-said

Post on 06-Apr-2018

240 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Technical Basics for Grid Connection

    1/73

    David Roberts

    Dulas Ltd, UK

    DULAS

    Grid Connection ofEmbedded Generators

  • 8/3/2019 Technical Basics for Grid Connection

    2/73

    This presentation will:

    Outline the issues concerned with the gridconnection of embedded generators

    Outline the work undertaken in Sri Lanka in theyear 2000 on the grid connection of embeddedgenerators

    DULAS

    Grid Connection of Embedded Generators

  • 8/3/2019 Technical Basics for Grid Connection

    3/73

    What is Embedded Generation?

    Embedded generation describes any generationsystem that is connected to the distributionnetwork. It derives from the generation beingembedded into the distribution network.

    There is no formal definition of what is a distributionsystem and what is therefore an embeddedgenerator.

    Commonly systems up to 33 kV are described as

    distribution systems, where either consumer loadsor lines leading to consumer loads are present.

    DULAS

  • 8/3/2019 Technical Basics for Grid Connection

    4/73

    Why is this a subject requiring attention?

    Distribution networks are primarily designedto distribute power from a centraltransmission system down to consumerloads connected to the distribution system,

    the power flow is one wayWith embedded generation the power flow is

    more complex and may be both ways

    There are plans for the implementation ofincreasing amounts of smaller gridconnected generation systems.

    DULAS

  • 8/3/2019 Technical Basics for Grid Connection

    5/73

    What are the key factors to be considered?

    Grid stability and security Fault Level

    Interconnection Protection

    Islanded Operation Voltage levels Earthing Load flow

    Connection application process Testing and maintenance of protection

    DULAS

  • 8/3/2019 Technical Basics for Grid Connection

    6/73

    Maintenance of grid stability and security are primerequirements for the specification of interconnectionequipment and regulations.

    The grid supply system may be subject to: increasing load demand

    low availability of spinning reserve

    load shedding to maintain system security

    an increasing use of embedded generation

    DULAS

    Grid stability and security

  • 8/3/2019 Technical Basics for Grid Connection

    7/73

    Connection and disconnection of embeddedgeneration may cause grid disturbances whichmay affect grid stability and reliability.

    This is particularly the case if there is the lossof a large amount of embedded generation atone time and embedded generation may be asignificant contribution towards overall

    generation capacity. There is usually no central control over

    embedded generation operationDULAS

    Grid Stability

  • 8/3/2019 Technical Basics for Grid Connection

    8/73

    There will be increasing amounts of embeddedgeneration in Indonesia

    This is likely to lead to an increasingproportion of the grid load being supplied by

    embedded generation.

    The security of supply of the embeddedgeneration will become more significant for the

    security of the grid as a whole.

    DULAS

    Grid Security

  • 8/3/2019 Technical Basics for Grid Connection

    9/73

    The connection of embedded generation willcontribute to the fault levels in the system

    This may require changes to the protectionequipment on the distribution system

    This is usually only a factor when there arelarge sizes or large numbers of embeddedgenerators in one area.

    DULAS

    Fault levels

  • 8/3/2019 Technical Basics for Grid Connection

    10/73

    There is a requirement for some electricalprotection at the point of connection to ensurethat:

    Operation of the generator will not compromise the

    safety of the grid system Deviations in the grid system will not damage the

    generator equipment

    Safety on the distribution system and at the

    generation station is maintained Islanded operation of sections of the distribution

    system is prevented

    DULAS

    Interconnection Protection

  • 8/3/2019 Technical Basics for Grid Connection

    11/73

    Islanded operation is where: a section of the distribution network is separated from

    the rest of the network (islanded) and

    the supply to the separated section is maintained by

    embedded generationThis is potentially dangerous in that there is little

    control on voltage or frequency and theprotection systems of the distribution network

    may not operate due to the limited capacity ofthe embedded generation

    DULAS

    Islanded operation

  • 8/3/2019 Technical Basics for Grid Connection

    12/73

    Embedded generation will cause changes to thevoltage levels in the distribution systemgenerally it will raise the voltage at points alongthe distribution network.

    This voltage rise must be limited to ensure thatthe supplies to consumers remain withinstatutory and safe working limits

    DULAS

    Voltage Levels

  • 8/3/2019 Technical Basics for Grid Connection

    13/73

    Embedded generators ususally genrate at lowvoltage (400V 3 phase) and require suitableearthing for their safe operation

    The connection points will usually include switch

    gear and transformers which require suitablehigh voltage earthing

    These earthing systems must be separated to

    ensure the safety of the plant in fault conditions

    DULAS

    Earthing

  • 8/3/2019 Technical Basics for Grid Connection

    14/73

    Embedded generators will change the load flow inin the distribution system.

    In some cases power will be fed from thedistribution system into the transmission system

    These changes in load flow may causetransmission and distribution system voltagecontrol and protection devices to operate

    incorrectly.

    DULAS

    Load Flow and Grid System operation

  • 8/3/2019 Technical Basics for Grid Connection

    15/73

    A standard process is required for an embeddedgenerator to:

    Apply for a connection

    Agree the connection requirements,specifications and costs

    Implement and test the connection protection

    Operate and maintain the connection

    protection

    DULAS

    Connection process

  • 8/3/2019 Technical Basics for Grid Connection

    16/73

    The connection protection and earthing needs tobe maintained and tested.

    The distribution system will rely on the operationof the embedded generation protection for safe

    and reliable operation

    Maintenance and testing requirements need to bedefined and implemented

    DULAS

    Testing and Maintenance

  • 8/3/2019 Technical Basics for Grid Connection

    17/73

    DULAS

    Typical connection arrangement

  • 8/3/2019 Technical Basics for Grid Connection

    18/73

    DULAS

    The Sri Lanka Guide to Interconnection

    Of Embedded Generators

    2000The work undertaken in Sri Lanka included:Meetings and discussions with many departments of theCeylon Electricity Board, existing and prospective

    embedded generation companies and consultantsworking in the field of embedded generation.The man outputs were:

    The production of a Guide

    Training courses for CEB and private generationcompany personnel

  • 8/3/2019 Technical Basics for Grid Connection

    19/73

    DULAS

    The Sri Lanka Guide to Interconnection

    Of Embedded Generators

    2000

    The work was undertaken by a consortium of companiesand consultants from Sri Lanka and the UK. The lead

    partners were:Resource Management Associates in Sri LankaDulas Ltd in UK

    The work was funded by the World Bank through the Pre

    Electrification Unit of the CEB

  • 8/3/2019 Technical Basics for Grid Connection

    20/73

    The CEB will need to undertake studies to ascertainthe acceptability and requirements for the connectionof a new embedded generator.

    These studies will require information from the

    proposed generating company.

    The generating company will also require someinformation from the CEB to design suitable protectionarrangements and maybe to modify proposed designs

    to suit particular grid requirements.

    DULAS

    Grid Interconnection of Embedded Generators - SriLanka

    Studies and Information Requirements

  • 8/3/2019 Technical Basics for Grid Connection

    21/73

    DULAS

    Grid Interconnection of Embedded GeneratorsSri Lanka

    Studies to be undertaken by the CEB at the

    time of a connection applicationThe following studies may be conducted by theCEB:

    Stability

    Fault Level Grid protection Voltage levels Earthing Load flow

  • 8/3/2019 Technical Basics for Grid Connection

    22/73

    The affect on local stability of new embedded generationcapacity should be analysed when the capacity of thenew plant exceeds 5MW, or when the total capacity ona single distribution line exceeds 5MW.

    For small generators, typically less than 1MW, therequirement for stability information from theGenerating Company may be waived.

    The Generating Company shall provide a model of the

    AVR of the proposed generators where the capacityexceeds 5MW.

    DULAS

    Stability

    Grid Interconnection of Embedded GeneratorsSri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    23/73

    The cumulative effect of of the embedded generator(s)on the design fault level for the distribution systemshall be assessed by the CEB.

    A study should be undertaken when the cumulative fault

    level reaches 90% of the rating of the associatedswitchgear, or the design fault level.

    The CEB may require more detailed information from thegenerator than that specified in Annex 3.

    DULAS

    Fault Level

    Grid Interconnection of Embedded GeneratorsSri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    24/73

    The effect on the distribution system protection ratingsand settings shall be studied if any of the followingapply:

    the proposed generating site maximum short circuitcurrent is greater than 20% of the distribution systemshort circuit current

    the cumulative short circuit current from all embeddedgenerators on a distribution line will exceed 30% of thedistribution system short circuit current

    there will be a net export of power from the distributionsystem to the 132 kV transmission system.

    DULAS

    Protection

    Grid Interconnection of Embedded GeneratorsSri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    25/73

    The nominal voltage at the Point of Supply (POS) shallbe stated by the CEB in the LOI.

    The voltage rise at the POS must be within operationallimits.

    A two stage approach shall be made to studies 1) Exclude load connections

    2) Include load connections

    The stage 2 study is required when the stage 1 study

    indicates a potential problem.

    DULAS

    Voltage Levels

    Grid Interconnection of Embedded GeneratorsSri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    26/73

    The Guide provides information on acceptable earthingpractices and earthing requirements for a variety ofsituations. An Annex on earthing is included to providebackground information on earthing.

    The Generating Company shall provide informationabout the proposed earthing arrangement to the CEB.

    It is the responsibility of the Generating Company toprovide adequate earthing at a generating site.

    The interconnection of generating site and CEB earthsystems should be considered for each site situationwith reference to the Guide.

    DULAS

    Earthing

    Grid Interconnection of Embedded GeneratorsSri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    27/73

    To assess the load flow at the distribution transformer themaximum cumulative generation capacity and theminimum captive load on the distribution line shall becalculated.

    This will indicate if there are conditions under which therewill be an export of power from the distribution line tothe 132 kV transmission system.

    If export is likely to occur the protection at the sub stationwill need to be studied.

    DULAS

    Load Flow

    Grid Interconnection of Embedded GeneratorsSri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    28/73

    The initial information to be provided by the CEB andthe generating company are given in a pro forma inAnnex 3.

    This information exchange is to follow the issue of anLOI.

    The Generating Company shall later provide thefollowing information, prior to acceptance testing:

    the proposed interconnection protectionimplementation

    protection test procedures

    drawings showing the protection arrangements

    DULAS

    Information Requirements

    Grid Interconnection of Embedded GeneratorsSri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    29/73

    Synchronisation

    Synchronisation means the minimisation of thedifference in magnitude, frequency and phase anglebetween the corresponding phases of the generatoroutput and the grid supply prior to the connection ofthe two supplies.

    Synchronisation can be achieved either manually orautomatically, the latter is preferable.

    It is very unlikely that new installations will include onlymanual synchronisation. If manual synchronisation issuggested its safe and reliable operation should beseriously considered and implemented carefully.

    DULAS

    Grid Interconnection of Embedded Generators - Synchronisation of Generators

  • 8/3/2019 Technical Basics for Grid Connection

    30/73

    Synchronisation (2)

    Voltage Fluctuation

    During Synchronisation of a single generator, theinduced voltage fluctuation on the grid should notnormally exceed 3% at the Point of Common

    Coupling,

    The requirements of voltage step and flicker givenin Section 11 should also be met.

    DULAS

    Grid Interconnection of Embedded Generators - Synchronisation of Generators

  • 8/3/2019 Technical Basics for Grid Connection

    31/73

    DULAS

    Grid Interconnection of Embedded Generators - Synchronisation of Generators

    Synchronisation of Synchronous

    Generators Generator output frequency must be the same asthe grid frequency.

    The phase angle between the generator outputand the grid supply must be less than specifiedlimits

    The rate of change in phase angle between thegrid and the generator must be within specifiedlimits

    Then the generator may be connected to the grid

    DULAS

  • 8/3/2019 Technical Basics for Grid Connection

    32/73

    DULAS

    Grid Interconnection of Embedded Generators - Synchronisation of Generators

    DULAS

    Synchronisation Methods for Synchronous

    Generators Control motive power to generator to achieve

    synchronisation.

    Usually indicated with Synchroscope lights or

    indicator. Problems of controlling large rotatingmasses and motive power

    Control of the load on the generator to achievesynchronisation. This is usually done with anElectronic Load Control (ELC) system

    Requires a dump load, it provides very smooth anaccurate synchronisation.

  • 8/3/2019 Technical Basics for Grid Connection

    33/73

    DULAS

    Grid Interconnection of Embedded Generators - Synchronisation of Generators

    DULAS

    Synch Check relays

    A synch check relay must be used to check thatthe synchronisation of the generator and the grid iswithin the specified limits

    The relay must operate on at least two, andpreferably all three phases to ensure phaserotation is correct

  • 8/3/2019 Technical Basics for Grid Connection

    34/73

    DULAS

    Grid Interconnection of Embedded Generators- Synchronisation of Generators

    DULAS

    Synchronisation limits

    The limits specified in the Guide for allowingsynchronisation are:

    Phase angle +/- 20 degrees

    Maximum voltage difference 7% Maximum slip frequency 0.44 %

  • 8/3/2019 Technical Basics for Grid Connection

    35/73

    Synchronisation of Induction Generators

    Two main methods of synchronisation:

    Use of electronic soft start unit to motor the generatorup to synchronous speed

    Mechanically drive the generator up to synchronous

    speed.

    Once at, or slightly above, synchronous speed thegenerator may be connected to the grid.

    DULAS

    Grid Interconnection of Embedded Generators - -Synchronisation of Generators

  • 8/3/2019 Technical Basics for Grid Connection

    36/73

    Synchronisation of Induction Generators (2)

    Inrush Current

    There will be a large inrush current when the generatoris connected. This current is building up the field in the

    generator.The inrush current may be reduced by adding seriesresistance for a short time after connection.

    A large inrush current will cause problems to the local

    grid, which must provide the current

    DULAS

    Grid Interconnection of Embedded Generators Synchronisation of Generators

  • 8/3/2019 Technical Basics for Grid Connection

    37/73

    The addition of embedded generation may change therequirements for grid protection.

    There will be a fault level contribution from theembedded generator, though this is usually small.

    It is important that grid system protection will operatewhen required.

    If a grid sub station becomes a net exporter of powerto the 132kV system the operation of voltage control

    and distance protection systems will require study andmodification.

    DULAS

    Grid Interconnection of Embedded GeneratorsSri Lanka

    Grid protection

  • 8/3/2019 Technical Basics for Grid Connection

    38/73

    The hazards created during islanded operation are:

    Unearthed operation of the distribution system

    Lower fault levels

    Out of synchronisation reclosure

    Voltage levels outside statutory limits

    Reduction in quality of supply

    Risk to maintenance personnel

    DULAS

    Grid Interconnection of Embedded Generators - Sri Lanka

    Hazards of Islanding

  • 8/3/2019 Technical Basics for Grid Connection

    39/73

    Due to the hazards listed the operation of an islandedsituation is to be avoided.

    There may be an advantage to consumers, andgenerating companies, to allow islanded operation in

    the maintenance of supply when a line has beendisconnected. This advantage is small and thehazards outweigh the advantages.

    DULAS

    Grid Interconnection of Embedded Generators - Sri Lanka

    Islanding

  • 8/3/2019 Technical Basics for Grid Connection

    40/73

    The onset of an islanded situation will be accompaniedby a disturbance in the grid.

    The detection of islanded operation relies of thedetection of this disturbance.

    The disturbance may take the form of:

    a change in voltage or frequency

    a single shift in voltage vector

    a change in reactive power flow

    DULAS

    Grid Interconnection of Embedded Generators - Sri Lanka

    Detection of Islanded operation

  • 8/3/2019 Technical Basics for Grid Connection

    41/73

    A prime consideration in the development of thedetection and protection requirements is to minimisethe potential for multiple tripping of embeddedgenerators due to grid disturbances or faults onadjacent lines which may not require a generator to be

    disconnected.

    This multiple tripping is known as Common Cause orCommon Mode tripping.

    DULAS

    Common Cause Tripping

    Grid Interconnection of Embedded Generators - Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    42/73

    The protection types and settings specified in the Guide

    are designed to avoid Common Cause tripping.

    For larger generating sites (>5MW) inter tripping fromthe grid sub station, and possibly distribution breakers,should be used to ensure a generator is disconnected

    when an islanded condition occurs. For sites < 5MW Loss of Mains (LoM) protection may

    be used to detect an islanded condition anddisconnect the generator. For these smaller generating

    sites the remaining small possibility of common causetripping is considered acceptable.

    DULAS

    Avoiding Common Cause TrippingGrid Interconnection of Embedded Generators - Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    43/73

    All sites require under / over voltage and under / overfrequency protection

    Other Loss of Mains protection may be provided by:

    Rate of Change of Frequency (ROCOF)

    Voltage Vector Shift

    Reverse VAR

    Other novel techniques

    DULAS

    Loss of Mains Protection

    Grid Interconnection of Embedded Generators - Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    44/73

    Voltage

    The voltage of all three phases shall be monitored.

    The limits for operation are:

    for HV connection +/- 10%

    for LV connection +/- 14%

    The relay should have a time delay to avoidspurious trips due to remote faults.

    The maximum total tripping time shall be 0.5seconds

    DULAS

    Islanding Detection and Protection (1)

    Grid Interconnection of Embedded Generators - Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    45/73

    Frequency

    The frequency of the supply shall be monitored, thiscan be single phase.

    The limits for operation are:

    +4%, -6% (i.e. 52Hz to 47Hz)

    There is no requirement for a time delay.

    The maximum total tripping time shall be 0.5seconds

    The low frequency limit may be reduced to 46Hz,this may require additional generator frequencyprotection.

    DULAS

    Islanding Detection and Protection (1)

    Grid Interconnection of Embedded Generators - Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    46/73

    Rate of Change of Frequency (ROCOF)

    True ROCOF detects the islanded condition

    rather than the onset of islanding.

    Some ROCOF relays may also be sensitive to an

    initial change in voltage vector.

    The limits of operation are:

    2.5 Hz/second. This high level is specified toensure minimum spurious tripping.

    There is no requirement for a time delay.

    The maximum total tripping time shall be 0.5seconds

    DULAS

    Loss of Mains Protection (1)

    Grid Interconnection of Embedded Generators - Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    47/73

    Voltage Vector Shift

    Voltage vector shift detects the onset on anislanded condition.

    It is susceptible to spurious tripping due to grid

    distrurbances

    The limits of operation are:

    6 degrees in a half cycle.

    This may be de-sensitised to up to 12 degrees.

    There is no requirement for a time delay.

    The maximum total tripping time shall be 0.5seconds

    DULAS

    Loss of Mains Protection (2)

    Grid Interconnection of Embedded Generators - Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    48/73

    Reverse VAR

    Reverse VAR relays detect the flow of reactivepower from the generator to the grid. This willoccur when during an islanded condition of a

    single generator. Generators must have stable power factor control

    to use reverse VAR protection.

    The limits of operation are to be agreed between

    the generating company and the CEB. Typically 1-5% of the magnitude of maximum kW export.

    A time delay of up to 5 seconds may be required.

    DULAS

    Loss of Mains Protection (3)

    Grid Interconnection of Embedded Generators - Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    49/73

    Intertripping

    Intertripping is a direct means of islandingprotection. It can provide a reliable method oftripping isanded generators without any common

    cause problems. A trip signal is sent from the circuit breaker or

    recloer responsible for the islanding.

    The reliability is dependant upon the security of the

    trip signal communication method. Reliabilityshould be assessed for each particular site. A failsafe method of communication should be used.

    DULAS

    Loss of Mains Protection (4)

    Grid Interconnection of Embedded Generators - Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    50/73

    Fault Thrower

    This is a special application of a fault thrower.

    The fault thrower would be installed at the sourcesub station and would operate following the

    opening of the source circuit breaker.

    Operation would be delayed to allow generatorrelays to operate if sufficient load imbalance exists.

    It is only effective for generators connected

    between the source breaker and the first autorecloser.

    DULAS

    Loss of Mains Protection (5)

    Grid Interconnection of Embedded Generators - Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    51/73

    Other novel techniques

    The Guide does not preclude the use of noveltechniques that may be developed to achieve adependable and reliable loss of mains function.

    An example is the use of sensitive ROCOF blocked byvoltage vector shift to prevent operation during generalgrid instability.

    DULAS

    Loss of Mains Protection (6)

    Grid Interconnection of Embedded Generators - Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    52/73

    Detection of islanding will not be possible in allsituations, for example a perfect load / generatorbalance may exist.

    Secondary protection may be used such as:

    dead line or synch check on auto reclosingdevices

    Neutral Voltage Displacement (NVD)

    NVD is a dependable means of satisfying safety

    requirements and mitigating the risks of islandedoperation.

    Details on NVD protection are given in the Guide.

    DULAS

    Islanding Network Protection

    Grid Interconnection of Embedded Generators - Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    53/73

    The type and size of generator connection isclassified into five cases and the protectionrequirements defined for each case.

    The factors that define which case applies are:

    Generation site capacity

    Generator type

    Ratio of minimum captive load and maximumcapacity

    Capacity and interconnection protection of othergenerators on the same distribution line and substation.

    DULAS

    Interconnection Protection Requirements

    Grid Interconnection of Embedded Generators - Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    54/73

    DULAS

    Interconnection Protection Requirements Summary

    Case 1 Case 2 Case 3 Case 4 Case 5

    Generator type All All See case

    3descripti

    on

    All See case 5

    description

    Self commutated

    static inverters

    Minimum captive

    loadL L L L

    Maximum

    cumulative export

    capacity

    0.8 x L

    Max site export

    capacity

    < 5

    MW

    < 5 MW < 5

    MW

    > 5 Mw

    Under and over

    voltage protection

    Under and over

    frequency protection *

    Vector shift

    protection *

    ROCOF protection

    *True ROCOF

    protection*

    NVD protection *(1)

    Intertripping * * * *Other requirements * * * * *

    Grid Interconnection of Embedded Generators - Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    55/73

    All types of Generator The maximum cumulative export capacity is less

    than half the minimum distribution line (orcaptive) load

    the maximum export capacity is less than 5MW.Protection Required

    Under and over voltage

    Under and over frequency

    Optional:

    Three phase vector shift, subject to generatorpreference

    DULAS

    Interconnection Protection, Case 1

    Grid Interconnection of Embedded Generators - Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    56/73

    All types of generator

    The maximum cumulative export capacity is lessthan 0.8 times the minimum captive load, and

    the maximum export capacity is less than 5MW.

    Protection Required:

    Under and over voltage

    Under and over frequency

    3 phase vector shift

    Optional: True RoCoF may be used as well as vector shift

    DULAS

    Interconnection Protection, Case 2

    Grid Interconnection of Embedded Generators - Sri Lanka

    id i f b dd d i k

  • 8/3/2019 Technical Basics for Grid Connection

    57/73

    All types of generator except mains excited generatorsdefined in Case 5.

    The maximum cumulative generation export capacityis greater than 0.8 times the minimum captive load,

    such that load/generator balance is possible, and the maximum export capacity is less than 5 MW.

    Protection Required:

    Under and over voltage

    Under and over frequency

    3 phase vector shift, or true ROCOF

    NVD

    Dead line check

    DULAS

    Interconnection Protection, Case 3

    Grid Interconnection of Embedded Generators - Sri Lanka

    G id I i f E b dd d G S i L k

  • 8/3/2019 Technical Basics for Grid Connection

    58/73

    Alternative ProtectionAs a replacement for the combination of Vector shift

    and NVD any one of the following may be used:

    Intertripping

    Fault thrower

    Reverse VAR, where applicable

    NVD is not required when the maximum exportcapacity is less than 1MW if the cumulative exportcapacity on a line is less than 0.8 times theminimum captive load.

    DULAS

    Interconnection Protection, Case 3 (2)

    Grid Interconnection of Embedded Generators - Sri Lanka

    G id I t ti f E b dd d G t S i L k

  • 8/3/2019 Technical Basics for Grid Connection

    59/73

    All types of generator The maximum export capacity of an Embedded

    Generation site is greater than 5 MW.

    It is preferred that the Embedded Generator is

    connected directly to the primary bus rather thanteed into an HV distribution feeder.

    Protection Required

    Under and over voltage

    Under and over frequency Intertripping from primary bus intake

    Parallel earthing or NVD protection

    DULAS

    Interconnection Protection, Case 4

    Grid Interconnection of Embedded Generators - Sri Lanka

    G id I t ti f E b dd d G t S i L k

  • 8/3/2019 Technical Basics for Grid Connection

    60/73

    If the Embedded Generator is teed into a distributionfeeder, the following is also required:

    Intertripping from the feeder breaker or

    Fault throwing or

    Reverse VAR protection where applicable.Generators larger than 5 MW will be encouraged to

    obtain more secure connections. For largegenerators remote from the primary bus, adequate

    security may only be achieved by double circuitconnection to the primary bus.

    DULAS

    Interconnection Protection, Case 4 (2)

    Grid Interconnection of Embedded Generators - Sri Lanka

    Grid Interconnection of Embedded Generators Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    61/73

    Mains excited asynchronous (induction) generator withlocal power factor correction less than the reactivepower demand, or a line commutated inverter.

    The CEB network/circuit capacitance is not sufficient

    to self excite the generator. The maximum cumulative connected generation

    export capacity is greater than 0.8 times the minimumcaptive load. No synchronous generation or self-

    excited generation are connected.

    DULAS

    Interconnection Protection, Case 5

    Grid Interconnection of Embedded Generators - Sri Lanka

    Grid Interconnection of Embedded Generators Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    62/73

    Protection Required Under and over voltage

    Under and over frequency

    3-phase vector shift

    The total generation connected to a primary substationusing the vector shift method for loss of mainsprotection shall not exceed 20MW.

    DULAS

    Interconnection Protection, Case 5 (2)

    Grid Interconnection of Embedded Generators - Sri Lanka

    Grid Interconnection of Embedded Generators Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    63/73

    Some wind turbines and photovoltaic system invertersare examples of this type of generator.

    The general requirements are covered with

    synchronous machines in cases 1-4.

    However inverters commonly include proprietaryprotection methods, including ROCOF.

    It is the responsibility of the Generating Company to

    demonstrate that the protection meets theacceptable levels of dependability and reliability.

    DULAS

    Interconnection Protection,Self Commutated Static Inverters

    Grid Interconnection of Embedded Generators - Sri Lanka

    Grid Interconnection of Embedded Generators Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    64/73

    It is the responsibility of the Generating Company to

    organise, agree procedures with the CEB andundertake protection equipment testing.

    Prior to testing, the Generating Company will certifythat:

    the earthing system conforms to the provisions inthis Guide and other relevant standards.

    the design and implementation of the protectionsystem complies with the requirements of the

    Guide, and any protection specified in the PPA. the generating system is safe to operate and

    complies with all the relevant requirements forelectrical installations.

    DULAS

    Test and Acceptance ProceduresGrid Interconnection of Embedded Generators - Sri Lanka

    Grid Interconnection of Embedded Generators - Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    65/73

    It is the responsibility of the Generating Companyrepresentative to provide and complete the test forms.

    Testing is to be witnessed by the CEB representative.The CEB representative is to certify by signature thatthe protection tests were witnessed as successful.

    The CEB may provide staff and/or equipment to theGenerating Company to enable tests to be

    undertaken.

    A standard form to be completed during testing isincluded in Annex 5 of the Guide

    DULAS

    Test and Acceptance Procedures (2)Grid Interconnection of Embedded Generators - Sri Lanka

    Grid Interconnection of Embedded Generators - Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    66/73

    The required grid connection protection is to be testedprior to acceptance of new generation plant forconnection to the grid. Short term connection may beallowed to set up and test the protection equipment.

    Retesting at intervals of no greater than three years or:

    Following any significant change in generation orprotection equipment.

    Following any maintenance or repair, whichinvolved the disconnection or rearrangement of any

    protection equipment.

    DULAS

    Test and Acceptance Procedures (3)Grid Interconnection of Embedded Generators Sri Lanka

    Grid Interconnection of Embedded Generators - Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    67/73

    DULAS

    Thank you for attention

    Any Comments or Questions?

    Grid Interconnection of Embedded Generators Sri Lanka

    Grid Interconnection of Embedded Generators Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    68/73

    DULAS

    Information to be provided by the CEB

    This information shall include the planned (or prospective) fault levels

    expected by the CEB in 10 years from the time of connection

    application.

    Maximum fault levels (for equipment selection and earthing

    design):

    Network design symmetrical fault level (kA or MVA)Peak asymmetrical fault level at half cycle (kA)

    3-phase symmetrical fault level at half cycle (MVA or kA)

    X/R ratio for 3 phase symmetrical fault

    1-phase to earth fault level (kA) (neglecting earth system

    resistances)

    X/R ratio for 1-phase to earth fault (neglecting earth system

    resistances)

    Grid Interconnection of Embedded Generators Sri Lanka

    Grid Interconnection of Embedded Generators Sri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    69/73

    DULAS

    Information to be provided by the CEB (2)

    Minimum fault levels (for protection design):3-phase steady state symmetrical fault level (MVA or kA)

    X/R ratio for 3 phase symmetrical fault

    1-phase to earth fault level (kA) (Neglecting earth system

    resistances)

    X/R ratio for 1-phase to earth fault (neglecting earth system

    resistances)

    Grid Interconnection of Embedded Generators Sri Lanka

    Grid Interconnection of Embedded GeneratorsSri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    70/73

    DULAS

    Information from the Generating Company(1)Synchronous Generators with a capacity above 500 kW

    Site Name

    Location ...Site Reference Number ....

    Generating Company Name.

    Contact

    Point of Supply (location) .

    Maximum export capacity

    Maximum import capacity ...

    Power factor operating range ..

    Generator (for each synchronous generator):

    Terminal voltage (kV) ..

    Machine rating (MVA) .

    Stator resistance (pu) tolerance % .Sub-transient reactance (pu) . tolerance % .

    Transient reactance (pu) . tolerance % .

    Synchronous reactance (pu) . tolerance % .

    Sub-transient time constant (ms) ... tolerance(ms) .

    Transient time constant (ms) . tolerance (ms) .

    Grid Interconnection of Embedded GeneratorsSri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    71/73

    DULAS

    Information from the Generating Company(2)

    Synchronous Generators with a capacity above 500 kW

    Generator (for each synchronous generator):Terminal voltage (kV) ..

    Machine rating (MVA) .

    Stator resistance (pu) tolerance % .

    Sub-transient reactance (pu) . tolerance % .

    Transient reactance (pu) .. tolerance % .

    Synchronous reactance (pu) .. tolerance % .

    Sub-transient time constant (ms). tolerance(ms) .

    Transient time constant (ms) . tolerance(ms) .

    Grid Interconnection of Embedded GeneratorsSri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    72/73

    DULAS

    Information from the Generating Company(3)

    Transformer (for each generator transformer);

    Rating (MVA) ..

    Reactance (pu) .. tolerance % .

    Resistance (pu) .. tolerance % .

    Voltage Ratio .. vector group .

    Cable or Line between the Generator and Point of

    Common Coupling where this cabling distance

    exceeds 50 metres

    Voltage (V) ..

    Reactance (Ohm) Resistance (Ohm)

    Grid Interconnection of Embedded GeneratorsSri Lanka

  • 8/3/2019 Technical Basics for Grid Connection

    73/73

    DULAS

    Information from the Generating Company(4)

    Where a total generating capacity is less than 500 kW

    there is a reduced requirement for information from the

    Generating Company.

    This information requirement is listed on page A3:4

    Where Induction, or Asynchronous, generators are

    proposed the same information should be provided

    where relevant to the induction type generator.