the challenges of converting arrester standards to understandable utility standards michael k....

41
The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Upload: kylie-robbs

Post on 15-Dec-2015

214 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

The Challenges of Converting Arrester Standards to

Understandable Utility Standards

Michael K. Champagne, P.E.Member, IEEE-SPDC

Page 2: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

What are these Challenges?

Page 3: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

1. Personnel are not familiar with arrester ratings and applications

• Newer engineers replacing older experienced engineers (aging and retiring workforce problem)

• Personnel not familiar with / aware of / do not have access to IEEE Standards and Guides.

• Budget limitations do not allow for much training• Surge protection not perceived as important as major

equipment.

Page 4: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

2. Standards for other equipment is more straight forward

• Breakers and switches– Continuous current ratings and voltage ratings are straight

forward– Interrupting ratings have reasoning that with some

explanation, can be understood by a novice• Transformers

– Voltage ratings are straight forward– Power ratings only require a short explanation

Page 5: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

3. Arrester Ratings are not as Straight Forward

Best illustrated by a question from a project manager:

“We are building a 230 kV substation. Why would you install a 192 kV rated arrester? Is this a mistake?”

Page 6: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

It’s not obvious to a novice what arrester ratings mean

• Two voltage ratings: – MCOV– Duty Cycle

• Concept of Insulation coordination• Energy Ratings: Distribution / Intermediate / Station Class • Fault duty rating• Temporary Overvoltage (TOV)• Physical characteristics• Other attributes

Page 7: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Confusion over what an arrester doesCommon Questions are:

• When does it work?• What does it do when it does work?• What happens when it really does work?• How do I know it worked?• What does it do when it does work?• Does it have to “fail” to work?• Do we even need arresters?

Page 8: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Other Sources of Confusion

• Why so many building blocks and what are their effects?• What is meant by failure mode?• What is collateral damage?

Page 9: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

What happens if I don’t get it right?

• Misapplication and it’s effects• Arrester failure• Equipment failure

Page 10: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Who applies arresters?

Utilities:

• Standards Engineers• Design Engineers• Maintenance technicians• Linemen / mechanics

Factories & Other Industry:

• Corporate Engineers• Local Engineers• Maintenance workers

In each case:Does surge protection get enough attention?

Page 11: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

How can these Challenges be Met?

One Approach:Produce an Internal Application Guide

Page 12: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Two Objectives Today

• Explain the rationale of this approach• Provide some examples of what an internal guide includes to

illustrate the need.

Page 13: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Publish an internal application guide with these objectives:

• Identify audience and keep them in mind• Base the guide on IEEE standards, but only address the parts we need => keep

it simple• Address problems experienced in the past• Answer common questions and clear up confusion• Maintain the fewer building blocks approach • Describe special applications to guide’s reader• Publish and teach the guide to all personnel involved• Publish an internal shortcut key to address 90% of applications on our system• Review the guide periodically and update as necessary

Page 14: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Consider our arrester applications

• Where should we apply arresters?– Substations

• What are they designed to protect?– Major Equipment

• What good can they do us => How can they help us?– Prevent equipment outages due to failures– Increase reliability

• Where should we not apply arresters?– Requires development of internal philosophy

• Economical and practical approach– Reduce building blocks

Page 15: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Consider Application Problems of the Past

• Internal (arrester) Failure due to– Temporary overvoltage– Being applied at wrong system voltage

• External (arrester) failure due to– Solid pollution residue on housing– Animals– Improper mechanical forces

• Collateral damage– Failing arrester caused damage nearby equipment

Page 16: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Minimize the building blocks

• Fewer options => less chance of misapplications by those unfamiliar with standards

• Concentrate on the arrester models that solve the most problems• Allow for Special applications• Eliminate models that had a narrow application.• Results in a savings of inventory costs

Page 17: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Results of the New Guide

• Explained using specific examples to introduce arrester concepts to a novice

• Resulted in fewer misapplications• Better equipment protection

Page 18: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Results of the New Guide(Continued)

• Only allow Station Class arresters inside the substation to eliminates confusion. => Zero arrester failures applied ≤ 230 kV since 2004.

• This rule was amended to require the use of energy class H arresters at system voltages up through 230 kV and energy class J arresters at EHV system voltages. This will harmonize with the new C62.11-2012 Test Standard.

• Require one level of MCOV higher than the minimum recommended by IEEE C62.22 for most applications. =>Eliminated TOV damages

• Require only polymer-housed arresters to be used. => Drastic reduction in collateral damage risk.

Page 19: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Results of New Guide(Continued)

• Required a minimum housing height for medium class voltage applications to eliminate some animal outages

• Required a minimum creep distance for medium class voltages to reduce risk of flashover due to environmental contamination.

• Both of these are helping reduce external flashovers in high pollution environments

Page 20: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Examples of material to include in the new Guide

Page 21: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Definitions

• Terminology must be understood to apply concepts.• Not always straight forward

– Surge Arrester– Line Terminal / Ground Terminal– MCOV, Duty Cycle, and the relationship between the two– System Voltage– Temporary Overvoltage (TOV)

• Use and explain the IEEE definitions

Page 22: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Proper spelling

ARRESTOR•Somebody who puts you in jail.•Be carful with spell check.

ARRESTERThis is the version we’re here to learn about today.

Page 23: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Specific ExampleHow to determine proper arrester rating for a given system

voltage?

• Arresters are installed phase-to-ground on the system• System voltages all have maximum limits where they can deviate from

nominal• Must allow for TOV’s specific to our system.

Page 24: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Calculation of Minimum MCOV

305.1 SYS

MCOV

VV

Where VMCOV = Minimum MCOV rating of applied arrester, kVVSYS = Nominal system operating voltage, kV

Utility’s specific application guide requires the use of the next higher entry from Table 1 of ANSI/IEEE C62.11. This is to allow for a longer unanticipated TOV on the system.

Page 25: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Explain the Concept of Insulation Coordination(ABB T&D Book)

Cres

t Vol

tage

(kV)

Time (s)

A

B

Curve A is the demonstrated strength of insulation on a piece of equipment.Curve B is the protective level provided by an arrester.

Curve A is protected by the protective device of Curve B which limits the voltage to a value level less than in insulation strength of Curve A.

Page 26: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Impulse Wave Example(IEEE Std. 4)

T1 = 1.67 x T

T1 = Virtual Front Time

T2 = Virtual Time to Half

Written as T1 / T2 wave

Typical is 8/20 wave

Time (s)

Am

plitu

de (

kV)

T2T

100%

90%

50%

30%

0

O1

Page 27: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Protective Levels

• Chopped Wave Withstand (CWW) 1.2s rise time, crest value of 1.10 x BIL

• BIL = Basic Impulse Insulation Level

• BSL = Basic Switching Insulation Level BSL = 0.83 x BIL

• Front of Wave (FOW) 0.5s rise time and crest is a function of arrester rating

• Lightning Impulse Protective Level (LPL) 8/20 s impulse w/ 1.5, 3, 5, 10, & 20 kA crest

• Switching Impulse Protective Level (SPL) classifying current w/ rise time of 45-60 s

Transformer Insulation Levels Arrester Protective Levels

Sources: IEEE C57.12.90

IEEE C57.12.00 Sources: IEEE C62.22

IEEE C62.11

Page 28: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Transformer Insulation CoordinationPer IEEE Guide (C62.22)

Values for FOW, LPL, & SPL can be obtained from the arrester manufacturer’s catalogue.

PR1 =CWW

FOW1.1 x BIL

FOW> 1.2=

PR2 = BILLPL

> 1.2

PRS =BSLSPL

= 0.83 x BILSPL

> 1.15

Voltage at Protected Equipment

Insulation Withstand Level of Equip.PRx =

Page 29: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Catalogue Data Example

ArresterRating

(kV rms)

ArresterMCOV

(kV rms)

TOV(kV rms)

Front-of-waveProtective

Level(kV Crest)

Maximum Discharge Voltage (kV Crest)8/20 μs Current Wave

    1 sec 10 sec   1.5 kA 3 kA 5 kA 10 kA 20 kA 40 kA

192 152.0 222.5 212.0 482 386 403 417 444 487 544

CWWFOW = 1.1 x BIL

FOW= 1.1 x 825

482 = 1.88 > 1.2

PR2 =BILLPL

= 825487 = 1.69 > 1.2

PR1 =

Page 30: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Catalogue Data Example (Continued)

Switching SurgeProtective Level

(kV crest)

125 A 250 A 500 A 1000 A

344 352 362 375

PRS =BSLSPL

= 0.83 x BILSPL

= 0.83 x 825375

= 1.82 > 1.15

IEEE recommends using a switching surge coordinating current of 500 A for system voltages up to 150 kV, 1000 A up to 325 kV, and 2000 A up to 900 kV.

Page 31: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Resistively-Grounded TransformerConcern in on the secondary of the transformer

• Neutral bushing (Xo) voltage shifts during phase-to-ground faults

• Produces over voltage on un-faulted phases during phase-to-ground faults

• Requires an arrester with higher MCOV

• Do NOT depend on TOV curve of arrester for this application.

Page 32: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Why not depend on the TOV curve?Because it’s not necessary.

Solidly Grounded• Apply a 12 kV, 10.2 kV MCOV arrester• PR1 = 3.36

• PR2 = 2.98

• PRS = 3.51

Resistively Grounded• Apply an 18 kV, 15.3 kV MCOV arrester• PR1 = 2.25

• PR2 = 1.99

• PRS = 2.34

•Both cases assume 110 kV BIL on the secondary winding of the transformer.•Even by increasing the arrester MCOV rating by two steps, the protective ratios are still well above the IEEE recommended value.

Page 33: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Transformer High Voltage Side Fault When DG is present

Scenario:• DG is present on low voltage side of

transformer• Ground Fault on HV bus• HV bus cleared either by local

breakers or remote end breakers.• Backup relaying may take up to 20

cycles to trip the LV BKR.Question:• Will our standard arrester withstand

TOV caused by the delta winding on the isolated bus?

Page 34: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Analyze the DG Scenario

• Standard arrester applied at 230 kV is a 192 kV (duty cycle) 152 kV MCOV• When the fault occurs and the bus is cleared from the high side, voltage

on un-faulted phases rises to 230 kV phase-to-ground. This is 1.5 per unit MCOV.

• It was determined that that BACK UP relaying would take 20 cycles to clear the LV breaker.

• This would exceed the TOV curve of the arrester.

Page 35: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

What are these Challenges?

1.6

1.5

1.4

1.3

1.2

0.01 1.00.1

`

Max Time Duration in seconds

Volta

ge p

er u

nit M

COV

20 cycles = 1/3 second. Yes the arrester’s TOV curve is exceeded and it will fail.

TOV Curve

10.0

Page 36: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

So which arrester do we apply?

• Would an arrester with an MCOV higher than the anticipated TOV work in this case?

• No, because the discharge voltages would be too high to coordinate with the BIL of the transformer?

• Therefore, we have to select an arrester with low enough discharge voltages to protect our transformer, but still be able to withstand the TOV.

Page 37: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Determine the proper MCOV

• From the TOV curve, we know that at 20 cycles, the previous arrester can withstand 1.45 x MCOV for 20 cycles.

• Use that as a starting point:

MCOV ’ > TOV1.45

= 158.6 kV

The next available size arrester is a 198 kV, 160 kV MCOV model.

Page 38: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Will it work?

• TOV: It will withstand 234.2 kV for 1 sec.Prev.

Ratio• FOW = 508 kV PR1 = 1.78 (1.88)

• LPL = 512 kV PR2 = 1.61 (1.69)

• SPL = 395 kV PRS = 1.73 (1.82)

Page 39: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Do we need arresters at transmission line terminals in substations?

SUBS

TATI

ON

BU

S

BREAKER

ARRESTER

• Lightning Flash may contain many strokes• Arresters must be located on the line side

of the breaker• Mandatory at EHV, should be considered

at lower voltages• Should be based on

-Economics-Importance of substation-MTBF of breaker’s voltage class-Presence of automatic tripping schemes in areas around EHV switch yards

Page 40: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

ConclusionA company-specific guide is necessary to explain and

solve arrester standards challenges that are specific to your system.

• Specific Explanations -> less confusion• Fewer building block -> fewer mistakes• Specific application examples -> fewer misapplications

Page 41: The Challenges of Converting Arrester Standards to Understandable Utility Standards Michael K. Champagne, P.E. Member, IEEE-SPDC

Bibliography[1] IEEE Std. 4-2013, IEEE Standard for High Voltage Testing Techniques. [2] IEEE Std. C57.12.00-2010, IEEE Standard for General Requirements for Liquid-Immersed Distribution, Power, and

Regulating Transformers. [3] IEEE Std. C57.12.90, IEEE Standard Test Code for Liquid-Immersed Distribution, Power, and Regulating Transformers. [4] IEEE Std. C62.11-2012, Standard for Metal-Oxide Surge Arresters for AC Power Circuits (>1 kV). [5] IEEE Std. C62.22-2009, IEEE Guide for the Application of Metal-Oxide Surge Arresters for Alternating-Current Systems

(>1 kV). [6] Central Station Engineers of the Westinghouse Electric Corporation, Electrical Transmission and Distribution

Reference Book, re-published by ABB.