the highs & lows
Embed Size (px)
TRANSCRIPT

The Highs & Lows
Materials Falling
Lessons Learned

Work at Height Workshop
• Held on 9th October 2009 due to several problems with scaffolding on Blackfriars & Farringdon
• Materials/tools falling from height
• Attended by members of the Blackfriars & Farringdon project teams
• Encourage knowledge and best practise sharing across Station & Civils projects

9th June & 12th July 2009 (Blackfriars Bridge)
What Happened
1. Scaffold base plate fell from Blackfriars bridge and struck a passenger
boat. No persons injured and no damage to boat
2. Report of an object falling from the bridge, hitting a passing boat and
bouncing into the river Thames.
No persons injured and no damage to boat

Base Plate / Bolt
Investigation Identified
Scaffold base plate fell from underside of
bridge, possibly through opening in crash
deck. Other openings (areas of weaknesses)
in scaffolding

Base Plate / Bolt
Actions as a Result of Incident1. Purge of the bridge and scaffolds to identify ‘hotspots’ gaps
closed in areas of weakness on scaffolding
2. Bridge housekeeping, edge and side protection and scaffold in the
regular monitoring regime
3. Tally system for access to authorised personnel only
4. Bridge scaffolding inspected on a weekly basis by the
construction team and the Port of London Authority
Photographs of remedial work follow………….

Bolt / Base Plate
Remedial workEnclosed walkway
including roof and
full height sides
“Brick guards” and
netlon to support and
reinforce sheeting

Bolt Base / Plate
Remedial work
Plywood infill decking to
eliminate gaps. Expanding
foam also used to plug
gaps

29th June 2009(Blackfriars – Hopton Street)
What HappenedThe scaffolders dropped a hammer through the boards onto the floor
underneath.
Investigation Identified
Birdcage scaffold wider than original so extended outside original scaffold
structure. Not close boarded or fitted, loose equipment fell down gap.

29th June 2009(Blackfriars – Hopton Street)
Actions as a Result of Incident
Scaffolding boarded out with no gaps

22nd September 2009(Farringdon – Cardinal Tower)
What Happened
Scaffold spanner became dislodged from scaffolders belt.
No persons injured, no damage occurred.
Area where
scaffolder was
situated
Position of
spanner
Podium roof where spanner
believed to have bounced
Final
landing
point of
spanner

22nd September 2009(Farringdon – Cardinal Tower)
Investigation Identified
• Deviation to scaffold design
• Failure to review the WPP and recognise that by re-sequencing the scaffold erection
works introduced a new risk
Actions as a Result of Incident
• Tethered tools
• Combisafe netting introduced during scaffolding construction
• Fully boarded lifts during scaffolding construction
See following slides…….

Farringdon – Cardinal Tower
Spanner
Tethered tools
used by scaffolders

Farringdon – Cardinal Tower
Spanner
Plywood infill decking to
eliminate gaps
Combisafe netting to prevent
debris/tools falling in work and
pedestrian areas during
construction

Best Practice Examples
• Documentation
– WPP review if in use for 8 weeks - check risks & methodology still relevant
– WPP compliance and safe working practice checks on site during tours/inspections
– Engagement of workforce/site supervisors in writing WPP and defining work sequence and methodology

Best Practice Examples
• Checks on site
– Regular temporary works inspections to ensure design compliance
– Daily/twice daily inspections of netting and screens during works/demolition activities
– Use of 16ft scaffold tubes over 21ft tubes, and rope tethered during installation

Best Practice Examples
• Physical Controls– Lanyarded (tethered) tools
– Fall arrest netting during scaffold construction
– Netting over specified walkways
– “Brick guard” type mesh used to reinforce lower areas of debris netting/dust sheeting
– Full boarded lifts as the scaffolding is constructed
– Plywood decking on top of scaffold boards - prevent debris falling in gaps
– Double encasement/bagging of materials when accessing the scaffold i.e. need 5 bolts, take 5 bolts not a box of 40
– Lookout on scaffolding (in a similar way to a lookout on the railway)
– Use of expanding foam to block ALL gaps in scaffold decking
– Restricted access – tally system

Have we learned?
3rd November (Borough Viaduct)
What Happened
A socket wrench was dropped from the 2nd level
scaffolding to the road below.
No injuries or damage, Exclusion Zone in place.
Investigation currently underway to identify issues
and actions required.

Borough High Street
Lack of protection for members of public
Socket wrench dropped from 2nd level, landed in exclusion zone
See next slide for depth of exlusion zone that was operational when incident occurred

Borough High Street
Exclusion Zone