the impact of ice

33
The Impact of Ice Nebraska Public Power District 2006-2007

Upload: gil-brady

Post on 03-Jan-2016

18 views

Category:

Documents


1 download

DESCRIPTION

The Impact of Ice. Nebraska Public Power District 2006-2007. Christmas Storm Outcome. 10 transmission lines out – made temporary repairs to 8 – 2 remained out of service 4 telecommunications fibers inoperable – no telecommunications west of Holdrege 2,500 retail customers impacted - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: The Impact of Ice

The Impact of Ice

Nebraska Public Power District

2006-2007

Page 2: The Impact of Ice

2

Christmas Storm Outcome• 10 transmission lines out – made temporary

repairs to 8 – 2 remained out of service

• 4 telecommunications fibers inoperable – no telecommunications west of Holdrege

• 2,500 retail customers impacted

• 21 NPPD technicians assist Dawson PPD

• $1.0 Million in damages (approximate)

Page 3: The Impact of Ice

3

New Year’s Storm TimelineFriday – December 29• Rain, freezing rain, icing, wind

Saturday – December 30• Severe icing conditions and wind • Widespread, extensive damage • Crews respond to numerous outages

Sunday – December 31

• Major effort to assess damage and restore power

Page 4: The Impact of Ice

Back-to-Back Storms

Christmas Storm: New Year’s Storm:

Page 5: The Impact of Ice

5

Normal NPPDTransmission System

Page 6: The Impact of Ice

6

System Condition January 1

Page 7: The Impact of Ice

7

System Condition January 4

Page 8: The Impact of Ice

8

Kearney Area Damage Assessment

53109

2314125

43 54

1

5

2

63

3410

18

1

# #-Wood Structures -Steel Towers # -Shield Wire Miles

52

42

10

Page 9: The Impact of Ice

9

Early Priorities• Kearney

– Lost 4 of 5 transmission feeds– Priority restoration of second feed– Rolling blackouts during initial restoration

• Holdrege– Lost all 3 transmission feeds– Mobile generation located within the community

• Key Messages– Energy conservation– Fragile system– Safety

Page 10: The Impact of Ice

10

System Status – March 2, 2007Initial Current

• Miles assessed 2,650• Customers without power

– NPPD Retail (service restored: 1/6/07) 11,612 0– Wholesale customers 31,000 0

• (service restored: 1/19/07)

• Transmission System (approx, 71% repaired)– Number of line segments out 37 7– Transmission miles out-of-service 1,053 184– Number of substations out 18 0– Miles of conductor down 301 86– Number of structures damaged 1,136 473

• GGS east flow limitation 224 MW 990 MW

• Communities on Mobile Generators 14 0

• More than a dozen public power utilities impacted by storm

• Contractors on site throughout reconstruction260 - 320

*These MW will depend on transmission system status, loading conditions and regional transmission system conditions.

Up to Up to

Page 11: The Impact of Ice

11

FEMA Disaster Declaration FEMA-1674-DR

Page 12: The Impact of Ice

12

Ice on a guy wire

Page 13: The Impact of Ice

13

Engineering Design Criteria

• National Electrical Safety Code 1997– Heavy combined ice and wind loading, ½ inch radial

ice, 40 mph wind, 0°F

• National Electrical Safety Code 2007– Heavy combined ice and wind loading, ½ inch radial

ice, 60 mph wind, 15°F

• New Year’s storm – 2 inch radial ice, winds averaging 21 mph, gusts up

to 40 mph, temperatures hovering around freezing

Page 14: The Impact of Ice

14

Effect of Ice on Power Lines• Typical weight of conductors without ice

– ½ to 1 pound per foot• Weight of lines with ice can increase by

4 - 8 pounds per foot• Weight on structures increased up to 8 -

10 times after ice storm– Example: 115kV structure load went from

3,000 pounds to 26,000 pounds (2-inch radial ice)

Page 15: The Impact of Ice

15

Page 16: The Impact of Ice

16

Size of ice one week after storm

Page 17: The Impact of Ice

The ice mangled 345-kilovolt structures like twist-ties

Page 18: The Impact of Ice

18

More than 40, 345-kilovolt structures were destroyed

Page 19: The Impact of Ice

19

The storm snapped H-frame structures like twigs

Page 20: The Impact of Ice

20

More than 300 miles of line and 1,137 structures were damaged

Page 21: The Impact of Ice

21

Ice on Substation near Holdrege, Neb.

Page 22: The Impact of Ice

Emergency Restoration

Page 23: The Impact of Ice

25

Emergency mobile generation was brought in for 14 communities

Page 24: The Impact of Ice

26

Mutual aid near Elgin, Neb.

Page 25: The Impact of Ice

Day-after-day diligence for more than 30 days. The last community on

emergency generation was

restored line service on Jan. 29, 2007.

Page 26: The Impact of Ice

Reconstruction

Page 27: The Impact of Ice

30

Restore Transmission System• Material procurement and delivery

• Focus on primary reconstruction efforts

• Hire and assign contractors• Parallel efforts (Customer Service Priorities)

• System Network Priorities

• Watch the weather

• Ensure equipment functions

Page 28: The Impact of Ice
Page 29: The Impact of Ice

32

More than 3,000 wood poles ordered.

Page 30: The Impact of Ice

33

Unloading conductor at NPPD’s York Operations Center for 400 + miles of line

Page 31: The Impact of Ice

34

Contractors Reconstructing South of Holdrege, Neb.

Page 32: The Impact of Ice

35

Restoration efforts near Prosser, Neb.

Page 33: The Impact of Ice

36