the risk of lopa and sil classification in the process...

28
The Risk of LOPA and SIL Classification in the process industry Mary Kay O’Connor Process Safety Center International Symposium Beyond Regulatory Compliance, Making Safety Second Nature October 28-29, 2008 Chris Pietersen Safety Solutions Consultants BV [email protected]

Upload: dangxuyen

Post on 25-Feb-2018

216 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

The Risk of LOPA and SIL Classification in the process industry

Mary Kay O’Connor Process Safety Center

International Symposium

Beyond Regulatory Compliance, Making Safety Second NatureOctober 28-29, 2008

Chris PietersenSafety Solutions Consultants BV

[email protected]

Page 2: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

Chris Pietersen

Director SSC (before : TNO SSC)

> TU Delft, Shell (Process Control)> 25 year in safety, TNO senior Research Fellow> Accident investigation (e.g. Bhopal, Mexico LPG)> Member Dutch Advisory Council for Hazardous Material>

Leader Module ‘Industrial Safety’

of official Dutch Safety Education Program

>SSC: Life Cycle Process Safety: Consultant for the Process Industry.

Page 3: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

Process Safety Philosophy

Technical: HAZOP, SIL, LOPA, QRA

OrganisationalSafety Management, Learning from incidents

CultureSafety Culture Assessment (SCM)Behaviour

Page 4: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

International SIL Standards:

IEC 61508/ 61511: Risk Based Approach

-Evaluate the Risk of a (HAZOP derived) scenario- Determine the required Risk reduction magnitude

- Design or Verify the Risk Control Measure- Implement in Safety Management System

Page 5: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

Potential Pitfalls (1)

The quality of the HAZOP study–

Team composition/ experience–

As built drawings–

Project budget/ planning–

Inherent Safety–

Credibility, information of LOC scenario’s for SIL/ LOPA

The risk analysis capability of the team–

Consequence / frequency assessment–

(In) dependencies in causes and control measures

Page 6: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

Potential Pitfalls (2)

The SIL verification:–

Functionality check–

(In) dependencies–

PFD calculations

Safety management of SIL–

Plan, Do, Check, Act approach–

Procedures and Workinstruction

Page 7: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

Buncefield explosion (UK): Overfilling of storage tank (December 2005)

Texas City disaster: Overfilling of distillation tower (March 2005)

Mexico City LPG Disaster : Overfilling a storage sphere (November 1984)

The need for a SIS

The risk of overfilling a vessel Examples from disasters

Page 8: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

Overfilling Tank 912

Buncefield Depot 11 December 2005

>

Filling (from pipeline) with ‘motorfuel’

(550-

890 m3/hr)>

Start filling tank: 19.00 hr, overfilling/release: 5.20 hr>

Explosion: 06.01 hr

>

Automatic Overfill protection system failed (levelswitch): IEC 61511: Reliability of (overfill) protection system

>

Main Problem: Safety Management, no risk based approach.

Page 9: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

Explosion Texas Refinery, 23 March 2005•

Continued overfilling of the raffinate splitter in the isomerisation during start-up (closed outlet)

Opening Relief valves to Blowdown drum and Loss of Containment (200 m3) via ventstack at 36 meter height.

• Explosion and fire, temporary trailers: 15 fatalities/ >170 injured persons

Page 10: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

Texas disaster aspects

Inherent Safety: vent to non-safe location–

Proposed modification not implemented. –

Post disaster reaction industry: SIL protection overfilling!•

IEC 61508: always consider inherent safety first•

Effort to be put at safe design/ controlled system; remaining risk: SIL

HAZOP start-up not performed–

Common practice in industry: only continuous process–

IEC 61508: A systematic Hazard Identification for all Life Cycle

phases is required before the SIL approach is applied.

Page 11: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

Inherent Safety Example

SIL Runaway reaction killing systemVenting to non-safe location

Page 12: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

Level instrumentation bottom splitter (Texas)

–Level transmitter voor Level Control (not functional).–Level indication (control room) via transmitter: failed–High Level Alarm (72%, 2,3 m) : normal functioning–Separate, redundant, hardwired high level alarm (78%, 2,4 m): Failed–Level Sight Glass: not functional (dark residue)–No automatic overfill protection

–IEC 61511 SIL Approach: SIS required–Operator dependence (alarms, sight glass)–Maintenance of safety critical equipment

Texas disaster aspects (2)

Page 13: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

Mexico City LPG depot 19 November 1984 Overfilling storage sphere

Page 14: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

Consequences of overfilling

500 people killed

BLEVE phenomenum

• No HAZOP• No MOC• No Overfill protection

Page 15: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

IEC 61508/ 61511 SIL approach

Perform a systematic hazard identification study–

HAZOP study

Evaluate the risks of the identified hazards :–

Risk matrix, Risk Graph, LOPA

Determine the need for risk reduction :–

Compare with acceptable Risk level

Determine the required SIL of the SIS

Verify the SIL for the SIS

Page 16: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

SeparatorV1

gas

liquid fromUnit 100

liquid fromRecovery unit CV

LC

P-01

LT

liquid

Overfill Example

HAZOP: overfilling can lead to an explosion:1 fatality

Page 17: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

4

W3 W2 W1

C1

C2

C3

C4

a - -

1 a -

2 1 a

2 1 a

3 2 1

3 2 1

4 3 2

na 3

P1

P2

P1

P2

F1

F2

F1

F2

Start

Frequency of occurence?Consequences

?

People present?

Escape possible?

Risk reduction for overfill scenario: Result SIL 1

•Team requirements• Company Risk Policy

Page 18: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

LT1XV-

01 SeparatorV1

gas

liquid fromUnit 100

Liquidfrom

Recovery unitCV-

02

L

C2

P-01

high level signal

LT2

clos

e

stop

liquid

Proposed Overfill protection system

4 verification requirements:

• Functionality• Independence of Control• Architectural constraints• Probabilistic requirement

Page 19: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

Often limited to Probabilistic requirement

Failure frequency verification for SIL 1: PFD < 10-1

(PFD=Probability of Failure on Demand)

PFDSIS

= PFDSens

+ PFDIs

+ PFDPLC

+ PFDvalve + PFDpumpPFD ≈

½

λDU

·T

λ

= failure frequency/ hrT= Proof test interval

PLC I

I

Page 20: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

Level transmitter

DU

= 6,0

10-7

/ hSource: SintefIsolator

DU

= 1,5

10-7

/ hSource: ExidaMCC relais

DU

= 2,0

10-7

/ hSource:

SintefSolenoid valve

DU

= 9,0

10-7

/ hSource: SintefValve+ actuator

DU

= 2,1

10-6

/ hSource: Exida PLC

PFD = 5,0

10-3

Source: TÜV Prooftest interval T

4 yearResult: PFDSIS

= 7,8

10-2

PFD < 10-1; Conclusion: SIL 1 probabilistic requirement fulfilled.

PFD calculation

Remarks:• Only one of the four verification requirements • Only if failure rate field data are collected over the lifecycle• Often narrowed to ‘calculations’

Page 21: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

The Hitchhiker's Guide to the Galaxy (Douglas Adams)

Calculate The Ultimate Answer to The Great Question of Life, the Universe, and Everything.

Answer after seven and a half million years' work :

Computer: answer is correct : may be you never actually know what the question is!

Page 22: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

Failure level control LC-1: Failure (LOC) V7

PSV

7

PSV

1

LC

LC‐1

LCV‐1

HP

Separator

V1

HV‐1

Condensate

Vessel V710 barg

60 barg

• Design pressure V7: 10 bar

• Pressure V7 on loss of level V1: 60 bar

Causes:• IC1: Failure of leveltransmitter• IC2: Opening of manual valve HV-1

•Possible Protection Layers, IPL’s):• Relief valve at V7: PSV-7• Low level alarm of LC-1•

Operator training/ procedure: action after alarm

LOPA aspect: IPL?

Page 23: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

Frequency correction:- Presence of the risk(Ptr): 1,0- exposure (Pp): 1,0- Ignition (Pi): 1,0- Vulnerability human: 1,0 Total: 0,8* 10-3/yrIC2: Operator error:

Frequency: 0,8 /yr

PSV: 0,01 Operator: 0,1

IC1: failure LC control:Frequency: 0,1 /yr

Frequency correction:- Presence of the risk(Ptr): 1,0- exposure (Pp): 0,5- Ignition (Pi): 1,0- Vulnerability human: 1,0 Total: 0,5* 10-3/yr

PSV: 0,01

Failure V7 (LOC)

Total:

1,3* 10-3/yr

LOPA results

Is operator an IPL?

?

Page 24: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

Determining SIL with LOPA

LOC frequency: 1,3 * 10-3

/yr•

Consequences: 5 fatalities •

Acceptation criterium: 10-6

/yr

Required PFD of a SIS:PFDSIS

= 10-6/ 1,3 * 10-3= 0,8* 10-3

(PFDSIS

= 10-6/ 0,85 * 10-3= 1,2* 10-3

with operator IPL)

Result: PFD < 10-3 SIL 3(Result: PFD < 10-2 SIL 2 with operator IPL)

Operator should generally not be seen as an IPL!

Page 25: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

Before and after

Page 26: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

Furnace

Page 27: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

Explosion in furnace, 2003

3 people died•

HAZOP/ SIL Classification/ -verification: OK•

The Safety System was wrongly still in override during the start

up of the furnace.

SIL standard not fully implemented: Plan, Do, Check, Act in Safety Management System was lacking.

11th Stamicarbon

Ureum

Symposium 19 –

22 May, 2008, Noordwijk

Page 28: The Risk of LOPA and SIL Classification in the process ...psc.tamu.edu/files/symposia/2008/symposium-program/2008... · The Risk of LOPA and SIL Classification in the process industry

The SIL concept (including the use of LOPA) is often narrowed down to SIL Classification and PFD calculations.

It is a danger that the SIL/ LOPA approach becomes the objective

in itself, instead of a means to reach high safety levels.

The following main problem areas haven been considered:–

The tendency to go for safety systems instead of more inherent safety–

The quality of the HAZOP/ SIL/ LOPA team–

The unjustified over dependency of operators in safety systems–

The too large emphasis on PFD calculations, losing the real meaning behind it.–

The lack of implementation of HAZOP/ SIL/ LOPA in the companies Safety Management System.

Overall:The risk exists that our safety standards and risk analysis methods are

becoming counterproductive. The effectiveness for safety should be be monitored continuously.

Summary/ Conclusions