Page 1: the Sinop project

Technical Meeting on Topical Issues in the Development of Nuclear Power Infrastructure

Mehmet BİÇER EUAS Deputy General Manager

3-6 February 2015

IAEA Headquarter, Vienna, Avustria

1

Page 2: the Sinop project

SİNOP NUCLEAR POWER PLANT PROJECT AND PERSPECTIVE OF EUAS

About EUAS

Sinop Nuclear Power Plant Project

Cooperation with Japan

Stages of the Sinop Project

EUAS Role in Sinop NPP Project

Reactor Technology of Sinop NPP

Technical Feasibility Study

Challenges

Content

2

Page 3: the Sinop project

Installed Capacity and Electricity Generation

3

Page 4: the Sinop project

Thermal Power Plants

4

Page 5: the Sinop project

Hydroelectrical Power Plants

5

Page 6: the Sinop project

Sinop Nuclear Power Plant Project

EUAS was commissioned in July 2012 by MENR for taking site licensing and performing all studies related with the site evaluation in the Sinop site.

EUAS will perform the required site evaluation studies and the prepared reports will be submitted to TAEK in order to have SITE LICENSING.

6

Page 7: the Sinop project

Cooperation with Japan

IGA was signed on May 03, 2013 between Turkish and Japanese Governments.

IGA ratification by Turkish Parliament.

After ratification, JAPCO and EUAS will establish Project Company.

HGA will be signed Project Company and MENR.

7

Page 8: the Sinop project

Cooperation with Japan (cont.)

According to IGA, Sinop NPP will be constructed and operated by Project Company to be establish by Project Sponsors (JAPCO and EUAS).

Japanese Consortium (JAPCO) EUAS

& 8

Page 9: the Sinop project

Cooperation with Japan (cont.)

JAPCO and EUAS are conducting jointly feasibility study for site and economic viability of the adoption of ATMEA1 in Sinop. Hence, Development Teams in below issues have been established among Sponsors.

Development Teams :

- Finance - Tax & Incentive - Legal - Regulatory/Licensing - FS Technical - QA & Control - Fuel - HR Management - O&M - Communication - EPC - Localization and Tec. Transfer - Economic impact assessment - Project Risk & Insurance - Decommissioning & Fuel Spent/Rad. Waste

9

Page 10: the Sinop project

Date Action

7 July 2012 EUAS was commissioned by MENR

22 August 2012 EUAS has been recognized as “Owner” by TAEK

26 September 2012 Protocol EUAS & TÜBİTAK MAM

3 May 2013 IGA Turkey & Japan

28 May 2013 Non-Disclosure Agreement (JapCo-EÜAŞ)

10 July 2013 Momerandum of Understanding (MoU)

(JapCo-EÜAŞ)

5 December 2013 JAPC Cooporation Agreement

26 June 2014 Protocol (JapCo-EÜAŞ)

30 June 2014 Amendment of Momerandum of Understanding(MoU)

Sinop NPP- EUAS Fundamentals

10

Page 11: the Sinop project

Stages of the Sinop Project

11

Page 12: the Sinop project

EUAS’s Role in Sinop NPP Project

Participation in the negotiations coordinated by MENR. Planing to hold 49 % share in Project Company Currently recognized as Owner of Sinop NPP by TAEK. Presently carrying out site studies. Additionally, apart from Sinop NPP Project EUAS also assigned for the evaluation of third NPP site.

12

Page 13: the Sinop project

Reactor Technology of Sinop NPP

Cooperation between GDF Suez (France), Itochu and Mitsubishi (Japan) for ATMEA1- (New Generation) NPP Technology

Mixture of APWR, Tomari-3, N4, EPR, KONVOI power plant technologies

Mid Size Gen III+ PWR

4 Units each of apprx. 1100 MW

13

Page 14: the Sinop project

Technical FS Content For Licence Application

DATE EVENT

07.07.2012 Application of EUAS to TAEK for recognision as “Founder Company”

22.08.2012 Recognision of EUAS as “Founder Company” by TAEK

28.05 2013 Start of Technical FS

05.09.2013 Notification of TAEK about the start of TUBITAK studies on shore – off shore in Sinop

site.

TUBITAK, EUAS and JAPC (off shore) Submission of Quality Documents

24.09.2013 TAEK informs EÜAŞ to start “Site Studies” on 5th of October for taking “Site License”

05.10.2013 Start of “Off Shore” Studies

31.10.2013 Completion of Off Shore Studies by JAPC

July 2014 EIA (Environmental Impact Assessment)

July 2014 LIDAR (Light Detection And Ranging)

August 2014 On shore investigations

Summer 2014 Off shore investigations

December 2015 Completion of Technical FS

•For license application to TAEK , Technical FS should be completed. • Expectation with Technical FS : Suitability of the Site and Feasibility of Project 14

Page 15: the Sinop project

15

Historical and Pre-instrumental period earthquake catalogues were created in and around Project Site. 23 seismological monitoring stations network and 13 GPS measurement network were established in July 2013. Geophysical and geomorphological studies were performed in May 2014-August 2014. Around Sinop Peninsula, the measurement work of oceanographic parameters were completed by TUBİTAK Marmara R/V vessel owned by TUBİTAK MAM

Research Project Intended to the Parameters of Field Assessment

Page 16: the Sinop project

JAPC Studies

Off-shore studies of JAPC

Acquiring the data from off-shore

at Sinop site, the works

completed on 5-31 October 2013,

in order to determine the fault of

sea and its characteristic.

17

Page 17: the Sinop project

On-Shore studies of JAPC

JAPC was started to field studies as of 2014, August 11 to define active faults for research of geological, geophysical and geotechnical on land and the concerned studies was completed on 2014, November 28.

17

Page 18: the Sinop project

Owner Engineering

Tractabel Engineering is an owner engineer in feasibility studies. A framework Agreement was signed on September 15, 2014. Tasks of Owner Engineer in the content of Technical Feasibility; o Determine the deficiency and evaluate the existing field studies o Constitute technical specifications regaring work package o Perform the procedure of selection of contractor to be served in

cooperation with Project Parties. o Audit of service in accordince with technical specification o Establishment of the work program and monitoring o Preparation of technical reports in the required subject

18

Page 19: the Sinop project

LIDAR

To obtain high resolution topography

on Sinop NPP site LIDAR and geomorphological study contract was signed on 26 June 2014.

LIDAR data collection was carried out in November 2014 and it is planned to finalize survey at the end of April 2015.

19

Page 20: the Sinop project

Bathymetry

Within the scope of seafloor topography and technical specifications to determine the available bathymetric discontinuities the contract was signed on 20 November 2014.

The collection of data studies on Black Sea was started on 21 January 2015 and it is planned to finalize survey on 26 May 2015.

20

Page 21: the Sinop project

Seismic Hazard Analysis (SHA)

• Development of DSHA (Deterministic Seismic Hazard Analysis) and PSHA

(Probablistic Seismic Hazard Analysis) will be conducted through SSHAC (Senior

Seismic Hazard Assessment Committee) approach.

• The process will be carried out in coordination with Tractebel Engineering, JAPC

and participation of independent experts.

• SSHAC process will address :

Fault displacement hazard

Probabilistic approach

Deterministic approach

• SSHAC Level-2 will be for The Ground Motion Characterization and The Site

Response. SSHAC Level-3 will be for The Seismic Source Characterization. First

SSHAC preparatory meeting was performed on 9-10 December 2014.

21

Page 22: the Sinop project

Environmental Impact Assessment Studies (EIA)

The contract for EIA was signed at the end of June 2014

The scope of studies;

• meteorology,

• radiology,

• terrestrial and marine,

• hydrology,

• socio-economic,

• air quality.

22

Page 23: the Sinop project

Health, Safety, Security & Environment (HSSE)

A contract was signed on July 2014

Related to HSSE activeties, all site surveys (JACP’s surveys, EIA Company and all subcontructors studies, etc.) are under control of the consulting company.

23

Page 24: the Sinop project

Public Relations

Consulting company selectedfor PR activities.

For Sinop NPP, Communication Plan will be formed by the C. Company

Stakeholder list will be defined.

Some surveys with the stakeholder will be perfomed.

Sinop NPP Project will be introduced locally as a Project Company, if need.

Frequently asked questions (Master Q&A documentation) will be established.

Participation in all related seminar, congre, conference, summit etc.

24

Page 25: the Sinop project

Economic Impact Assessment (EcIA)

EcIA will be used to quantify the benefits of the Project It will include:

An Overview of the Turkish economy, industry, human resources with respect to the field nuclear power industry Analysis of the effects of the Sinop NPP Project Assessment of the capabilities of industries and companies

It will provide a basis for Four Plan; 1. Localization Plan 2. Human Resources Development Plan 3. Technology Transfer Plan 4. Social Responsibility, Public Acceptance and Public

Awareness Plan

25

Page 26: the Sinop project

Future Feasibility Studies

Volcanic Hazard Assessment 2015

Determining Of İnitial Site Characteristic 2015

Geotechnical Investigations 2015

Establishment Of The Project Company 2015

Determination Of The Final Site Characteristics 2016

Additional Land Work 2015

Process Of Seismic Hazard Analysis 2015-2016

Preparation Of Draft Site Report 2015

26

Page 27: the Sinop project

Challenges

Experienced Human Resources in nuclear (basically feasibility studies, operation&maintenance) Capabilities in operating NPP. Dealing with some of the issues that EUAS has never faced before such as Shareholders Agreement Long term training in particular field (external human induced hazards, lidar and batımetry, site surveys)

27

Page 28: the Sinop project