the study for update of hoa lac high-tech ...open_jicareport.jica.go.jp/pdf/11868544_01.pdftable...

51
JAPAN INTERNATIONAL COOPERATION AGENCY HOA LAC HIGH-TECH PARK MANAGEMENT BOARD THE STUDY FOR UPDATE OF HOA LAC HIGH-TECH PARK MASTER PLAN IN THE SOCIALIST REPUBLIC OF VIETNAM FINAL REPORT SUPPORTING REPORT, VOLUME I PRE-FEASIBILITY STUDY ON INFRASTRUCTURE DEVELOPMENT November 2007 NIPPON KOEI CO., LTD. PACIFIC CONSULTANTS INTERNATIONAL ALMEC CORPORATION SD JR 07-83 No.

Upload: duongthuy

Post on 26-Apr-2018

214 views

Category:

Documents


1 download

TRANSCRIPT

JAPAN INTERNATIONAL COOPERATION AGENCY HOA LAC HIGH-TECH PARK MANAGEMENT BOARD

THE STUDY FOR UPDATE OF HOA LAC HIGH-TECH PARK

MASTER PLAN IN

THE SOCIALIST REPUBLIC OF VIETNAM

FINAL REPORT

SUPPORTING REPORT, VOLUME I

PRE-FEASIBILITY STUDY ON

INFRASTRUCTURE DEVELOPMENT

November 2007

NIPPON KOEI CO., LTD.

PACIFIC CONSULTANTS INTERNATIONAL

ALMEC CORPORATION SD

JR

07-83

No.

The Study for Update of Hoa Lac High-Tech Park Master Plan Table of Contents

i

TABLE OF CONTENTS Final Report

Supporting Report, Volume I Pre-Feasibility Study on Infrastructure Development

Table of Contents ................................................................................................................................ i

List of Tables and Figures ................................................................................................................. v

Abbreviation List .............................................................................................................................. ix

1. DESCRIPTION OF PROJECT .......................................................................................1-1

1.1 Target and Mission of the Project........................................................................................1-1

1.2 Project Site ..........................................................................................................................1-1

1.3 Land Use Plan and Development Phases ............................................................................1-2

1.4 Planning Criteria .................................................................................................................1-3

1.5 Outline of the Infrastructure Development Plan..................................................................1-4

2. LAND PREPARATION AND DRAINAGE SYSTEM...................................................2-1

2.1 Outline of Original Sector Plan ...........................................................................................2-1

2.2 Present Condition ................................................................................................................2-1

2.2.1 Current Development Progress..............................................................................2-1

2.2.2 Related Project.......................................................................................................2-2

2.3 Update of Sector Plan..........................................................................................................2-2

2.3.1 Sector Development Missions, Strategies and Goals.............................................2-2

2.3.2 Planning Framework..............................................................................................2-3

2.3.3 Sector Development Plan ......................................................................................2-5

2.3.4 Development Issues ...............................................................................................2-5

2.4 Proposed Project List ..........................................................................................................2-6

2.5 Technical Study for Phase-1 Development .........................................................................2-8

2.5.1 Land Preparation Plan............................................................................................2-8

2.5.2 Drainage Plan ........................................................................................................2-8

2.5.3 Project Cost..........................................................................................................2-17

3. ROAD AND TRANSPORTATION SYSTEM.................................................................3-1

3.1 Outline of Original Sector Plan ...........................................................................................3-1

3.2 Present Condition ................................................................................................................3-1

3.2.1 Current Development Progress..............................................................................3-1

3.2.2 Related Project.......................................................................................................3-3

The Study for Update of Hoa Lac High-Tech Park Master Plan Table of Contents

ii

3.3 Update of Sector Plan..........................................................................................................3-4

3.3.1 Sector Development Missions, Strategies and Goals.............................................3-4

3.3.2 Planning Framework..............................................................................................3-6

3.3.3 Sector Development Plan ......................................................................................3-9

3.3.4 Development Issues .............................................................................................3-15

3.4 Proposed Project List ........................................................................................................3-19

3.5 Technical Study for Phase-1 Development .......................................................................3-25

3.5.1 Project Description ..............................................................................................3-25

3.5.2 Interchange Alternatives ......................................................................................3-31

3.5.3 Project Cost..........................................................................................................3-36

4. WATER SUPPLY SYSTEM .............................................................................................4-1

4.1 Outline of Original Sector Plan ...........................................................................................4-1

4.2 Present Condition ................................................................................................................4-2

4.2.1 Current Development Progress..............................................................................4-2

4.2.2 Related Project.......................................................................................................4-3

4.3 Update of Sector Plan..........................................................................................................4-5

4.3.1 Sector Development Missions, Strategies and Goals.............................................4-5

4.3.2 Planning Framework..............................................................................................4-5

4.3.3 Sector Development Plan ....................................................................................4-10

4.3.4 Development Issues .............................................................................................4-18

4.4 Proposed Project List ........................................................................................................4-18

4.5 Technical Study for Phase-1 Development .......................................................................4-20

4.5.1 Projects to Be Implemented in Phase-1 ...............................................................4-20

4.5.2 Reservoirs, Pump Stations and Elevated Tanks in Phase-1 .................................4-20

4.5.3 Hydraulic Analysis of Water Supply Network.....................................................4-22

4.5.4 Project Cost..........................................................................................................4-27

5. POWER SUPPLY SYSTEM ............................................................................................5-1

5.1 Outline of Original Sector Plan ...........................................................................................5-1

5.2 Present Condition ................................................................................................................5-2

5.3 Update of Sector Plan..........................................................................................................5-4

5.3.1 Sector Development Missions, Strategies and Goals.............................................5-4

5.3.2 Planning Framework..............................................................................................5-6

5.3.3 Sector Development Plan ......................................................................................5-8

5.3.4 Internal Power Sector Development Plan............................................................5-12

5.3.5 Development Issues .............................................................................................5-16

5.4 Proposed Project List ........................................................................................................5-17

The Study for Update of Hoa Lac High-Tech Park Master Plan Table of Contents

iii

5.5 Technical Study for Phase-1 Development .......................................................................5-18

5.5.1 Detail of Each Project Component ......................................................................5-18

5.5.2 Project Cost..........................................................................................................5-19

5.5.3 Recommendations ...............................................................................................5-20

6. SEWERAGE SYSTEM ....................................................................................................6-1

6.1 Outline of Original Sector Plan ...........................................................................................6-1

6.2 Present Condition ................................................................................................................6-3

6.2.1 Current Development Progress..............................................................................6-3

6.2.2 Related Project.......................................................................................................6-4

6.3 Update of Sector Plan..........................................................................................................6-5

6.3.1 Sector Development Missions, Strategies and Goals.............................................6-5

6.3.2 Planning Framework..............................................................................................6-6

6.3.3 Sector Development Plan ......................................................................................6-9

6.3.4 Development Issues .............................................................................................6-14

6.4 Proposed Project List ........................................................................................................6-15

6.5 Technical Study for Phase-1 Development .......................................................................6-16

6.5.1 Projects to Be Implemented in Phase-1 ...............................................................6-16

6.5.2 Specifications for Sewage Treatment Plant .........................................................6-16

6.5.3 Specifications for Pump Stations .........................................................................6-17

6.5.4 Study on Sewer Pipe............................................................................................6-17

6.5.5 Hydraulic Analysis of Sewerage Collection System ...........................................6-18

6.5.6 Project Cost..........................................................................................................6-24

7. COST ESTIMATE ............................................................................................................7-1

8. IMPLEMENTATION SCHEDULE ................................................................................8-1

9. FINANCIAL ANALYSIS..................................................................................................9-1

9.1 Presumption of Financial analysis.......................................................................................9-1

9.2 Assumed Conditions Applied for Financial Analysis..........................................................9-4

9.3 Result of Financial Analysis................................................................................................9-5

9.4 Result of Computation of Financial Viability Indicators.....................................................9-7

Annex 9.1 Financial Viability Indicator Computation (Phase-1) ..........................................9-10

Annex 9.2 Financial Viability Indicator Computation (Phase-1 + Phase-2) .........................9-11

10. ECONOMIC ANALYSIS ...............................................................................................10-1

10.1 Methodology .....................................................................................................................10-1

10.2 Assumed Conditions for Economic Analysis ....................................................................10-1

The Study for Update of Hoa Lac High-Tech Park Master Plan Table of Contents

iv

10.3 Result of Economic Analysis ............................................................................................10-3

10.4 Evaluation of Economic Viability .....................................................................................10-3

Annex 10.1 Economic Analysis (1).........................................................................................10-4

Annex 10.2 Economic Analysis (2).........................................................................................10-5

The Study for Update of Hoa Lac High-Tech Park Master Plan List of Tables and Figures

v

LIST OF TABLES

Table 1.3-1 Description of the Functional Zones .........................................................................1-2

Table 1.3-2 Development Area of Each Zone ..............................................................................1-3

Table 1.4-1 Planning Criteria .......................................................................................................1-4

Table 1.5-1 Outline of Infrastructure............................................................................................1-5

Table 2.1-1 Main Features of JICA M/P and F/S .........................................................................2-1

Table 2.2-1 Main Drainage Facilities of Stage-1..........................................................................2-2

Table 2.3-1 Missions, Strategies and Goals .................................................................................2-3

Table 2.3-2 Drainage Planning Criteria for the Study..................................................................2-5

Table 2.4-1 Project List for Land Preparation and Drainage........................................................2-8

Table 2.5-1 Hydraulic Calculation Sheet ...................................................................................2-12

Table 2.5-2 Project Cost for Land Preparation and Drainage ....................................................2-18

Table 3.1-1 Road Length by Type in the Original Master Plan....................................................3-1

Table 3.3-1 Missions, Strategies and Goals for Road and Transportation Sector ........................3-5

Table 3.3-2 Travel Demand Projection ........................................................................................3-9

Table 3.3-3 Standard Road Density by Land Use Type..............................................................3-14

Table 3.3-4 Summary of the HHTP External Road and Transportation Infrastructure ..............3-18

Table 3.4-1 Project List for Roads .............................................................................................3-20

Table 3.4-2 List of Bridges and Culverts ...................................................................................3-23

Table 3.5-1 Minimum Separation Distance of Utility Lines ......................................................3-26

Table 3.5-2 Project Cost for Road..............................................................................................3-37

Table 4.1-1 Water Demand Projection for HHTP and VNUH in the Original M/P .....................4-1

Table 4.1-2 Daily and Hourly Maximum Water Consumption in the Original M/P ....................4-1

Table 4.1-3 Main Specifications of Facilities in the Original M/P...............................................4-2

Table 4.2-1 Capacity of Da River Water Supply Project..............................................................4-4

Table 4.3-1 Missions, Strategies and Goals for Water Supply Sector ..........................................4-5

Table 4.3-2 Unit Water Demand in HHTP ...................................................................................4-6

Table 4.3-3 Water Demand of HHTP...........................................................................................4-7

Table 4.3-4 Water Demand Projection Sheet of HHTP................................................................4-7

Table 4.3-5 Standard for βmax (Coefficient)..................................................................................4-8

Table 4.3-6 Hourly Maximum Factor by Phase ...........................................................................4-9

Table 4.3-7 Water Quality for Urban Water Supply Systems.......................................................4-9

Table 4.3-8 Comparison of Basic Water Supply Systems ..........................................................4-13

Table 4.3-9 Capacity of the Reservoirs ......................................................................................4-15

Table 4.3-10 Necessary Capacities of the Pump Stations ............................................................4-15

Table 4.3-11 Outline of the Reservoirs and Pump Facilities........................................................4-15

The Study for Update of Hoa Lac High-Tech Park Master Plan List of Tables and Figures

vi

Table 4.3-12 Capacities of Elevated Tanks ..................................................................................4-16

Table 4.4-1 Project List for Water Supply..................................................................................4-19

Table 4.5-1 Projects to Be Implemented in Phase-1 ..................................................................4-20

Table 4.5-2 Project Cost for Water Supply.................................................................................4-28

Table 5.3-1 Missions, Strategies and Goals for Power Supply Sector .........................................5-4

Table 5.3-2 Frequency of Failures on T/L Operated by PC-1 ......................................................5-5

Table 5.3-3 Power Demand Calculation for each Zone ...............................................................5-7

Table 5.4-1 Proposed Power Supply Project (Alternative-1) .....................................................5-17

Table 5.4-2 Proposed Power Supply Project (Alternative-2) .....................................................5-18

Table 5.5-1 Cost Estimate for Phase-1 Development of Power Supply System ........................5-20

Table 5.5-2 Cost Estimate for Phase-2 Development of Power Supply System ........................5-20

Table 5.5-3 Cost Estimate for 220kV Transmission Line and 220/110kV Substation ...............5-20

Table 6.1-1 Projection of Sewage Volume in the Original M/P ...................................................6-1

Table 6.1-2 Main Specifications for Facilities in the Original M/P .............................................6-1

Table 6.1-3 Sewage Treatment Plant Development Plan in the Original M/P .............................6-2

Table 6.2-1 Effluent Standards for Industrial Sewage (TCVN 5945-1995).................................6-5

Table 6.3-1 Missions, Strategies and Goals for Sewerage Sector ................................................6-5

Table 6.3-2 Sewage Volume in HHTP .........................................................................................6-7

Table 6.3-3 Hourly Maximum Sewage ........................................................................................6-7

Table 6.3-4 Effluent Standards for Industrial Sewage (TCVN 5945-2005).................................6-8

Table 6.3-5 Capacities of Pump Stations....................................................................................6-12

Table 6.3-6 Capacities of Sewage Treatment Plants ..................................................................6-12

Table 6.3-7 Comparison of Treatment Process ..........................................................................6-13

Table 6.3-8 Area of Land for Sewage Treatment Plants ............................................................6-14

Table 6.4-1 Project List for Sewerage........................................................................................6-15

Table 6.5-1 Projects to Be Implemented in Phase-1 ..................................................................6-16

Table 6.5-2 Outline of the Sewage Treatment Plant for Phase-1................................................6-16

Table 6.5-3 Materials of Sewer Pipes in HHTP .........................................................................6-17

Table 6.5-4 Minimum Slope of Sewer Pipe ...............................................................................6-19

Table 6.5-5 Maximum Water Depth...........................................................................................6-19

Table 6.5-6 Project Cost for Sewerage.......................................................................................6-25

Table 7.1-1 Direct Construction Cost...........................................................................................7-1

Table 8.1-1 Implementation Schedule..........................................................................................8-1

Table 9.1-1 Development Schedule of Functional Zones by Phase .............................................9-2

Table 9.1-2 Conditions Applied for Project Cost Estimation .......................................................9-3

Table 9.1-3 Project Cost for Financial Analysis...........................................................................9-3

Table 9.2-1 Assumed Land Lease Charge by Type of Use (Pahse-1) ..........................................9-5

The Study for Update of Hoa Lac High-Tech Park Master Plan List of Tables and Figures

vii

Table 9.3-1 Result of FIRR Computation ....................................................................................9-6

Table 9.3-2 Result of Sensitivity Analysis ...................................................................................9-6

Table 9.3-3 Minimum Land Lease Charge...................................................................................9-7

Table 9.4-1 Recommended Minimum Rate of Land Lease and Management Charge.................9-8

Table 9.4-2 Amount of Government Expenditure........................................................................9-9

Table 10.3-1 Result of Economic Analysis ..................................................................................10-3

LIST OF FIGURES

Figure 1.2-1 Location Map of the HHTP ......................................................................................1-2

Figure 2.3-1 Drainage Basin..........................................................................................................2-4

Figure 2.4-1 Typical Cross Section of Drainage Facility...............................................................2-6

Figure 2.4-2 Drainage System .......................................................................................................2-7

Figure 2.5-1 Rainfall Intensity.......................................................................................................2-9

Figure 2.5-2 Drainage System of Tan Xa Lake Basin .................................................................2-10

Figure 2.5-3 Drainage System of Central Canal Basin................................................................2-10

Figure 2.5-4 Drainage System of South Canal Basin ..................................................................2-11

Figure 3.2-1 Current Road Development (Stage-1 of Phase-1) .....................................................3-2

Figure 3.3-1 Typical Cross Section of Lang-Hoa Lac Highway....................................................3-6

Figure 3.3-2 Proposed UMRT Network.........................................................................................3-8

Figure 3.3-3 HHTP Internal and Zonal Road Development Plan ................................................3-11

Figure 3.3-4 Typical Cross Section of an Internal Road..............................................................3-13

Figure 3.3-5 Typical Cross Section of a Zonal Road...................................................................3-13

Figure 3.3-6 HHTP External Road and Transportation Development Projects ...........................3-16

Figure 3.3-7 Master Plan of Northern Phu Cat Industrial Park ...................................................3-19

Figure 3.4-1 HHTP Internal and Zonal Road Development Plan (Phase-1)................................3-22

Figure 3.4-2 Location of Bridges and Culverts in HHTP ............................................................3-24

Figure 3.5-1 Phase-1 Development Plan for Roads and Land Use..............................................3-27

Figure 3.5-2 Phase-1 Development for Roads on the Topographical Map..................................3-28

Figure 3.5-3 Typical Cross Section with Utilities: Type I Road ..................................................3-29

Figure 3.5-4 Typical Cross Section with Utilities: Type II Road.................................................3-30

Figure 3.5-5 Typical Cross Section with Utilities: Type III Road ...............................................3-30

Figure 3.5-6 Cloverleaf Interchange............................................................................................3-31

Figure 3.5-7 Stack Interchange....................................................................................................3-32

Figure 3.5-8 Roundabout Interchange .........................................................................................3-33

Figure 3.5-9 Trumpet Interchange ...............................................................................................3-34

Figure 3.5-10 Diamond Interchange..............................................................................................3-34

Figure 3.5-11 Partial Cloverleaf Interchange.................................................................................3-35

The Study for Update of Hoa Lac High-Tech Park Master Plan List of Tables and Figures

viii

Figure 4.1-1 Location of Water Purification Plant in the Original M/P.........................................4-2

Figure 4.2-1 Location of Wells and Present Water Supply Network .............................................4-3

Figure 4.2-2 Da River Water Supply Project .................................................................................4-4

Figure 4.3-1 Plan and Longitudinal Section of Pipeline of Da River Water Supply Project .......4-11

Figure 4.3-2 Image of Basic Water Supply System Options........................................................4-12

Figure 4.3-3 Plan of Water Supply Network................................................................................4-17

Figure 4.3-4 Image of Connection with Da River Water Supply Project.....................................4-14

Figure 4.3-5 Present Plan of the Branch for HHTP and PCIZ.....................................................4-18

Figure 4.5-1 Plan and Necessary Area for Reservoirs and Pump Station ....................................4-21

Figure 4.5-2 Plan and Necessary Area for Elevated Tank ...........................................................4-21

Figure 4.5-3 Necessary Water Pressure at the Elevated Tanks ....................................................4-22

Figure 5.1-1 22kV Power Supply system for HHTP .....................................................................5-1

Figure 5.2-1 Present Regional Power Supply Network System for HHTP ...................................5-2

Figure 5.2-2 Location of the Substation, Transformers and Present Power Distribution

Network.....................................................................................................................5-3

Figure 5.3-1 HHTP Power Supply Network Scheme Excluding National Power Grid

(Alternative-1).........................................................................................................5-10

Figure 5.3-2 HHTP Power Supply Network Scheme Excluding National Power Grid

(Alternative-2).........................................................................................................5-11

Figure 5.3-3 HHTP Power Supply Network Scheme Including National Power Grid................5-12

Figure 5.3-4 Internal Power Supply System Configuration.........................................................5-14

Figure 5.3-5 Plan of Power Distribution Network.......................................................................5-15

Figure 6.1-1 Collection System and Location of Sewage Treatment Plant

in the Original M/P ...................................................................................................6-2

Figure 6.2-1 Present Sewerage Network .......................................................................................6-3

Figure 6.3-1 Plan of Sewerage System........................................................................................6-10

Figure 6.3-2 Plan of Catchments .................................................................................................6-11

Figure 6.3-3 Diagram of Sewage Collection System...................................................................6-11

Figure 6.3-4 Location of Sewage Treatment Plants.....................................................................6-13

Figure 6.5-1 Methods to Cross the Rivers and Lakes ..................................................................6-18

The Study for Update of Hoa Lac High-Tech Park Master Plan List of Abbreviations

ix

ABBREVIATIONS

BOT Build Operation Transfer DONRE Department of Natural Resources and Environment EIA Environmental Impact Assessment EN Exchange of Notes EVN Electricity of Vietnam FDI Foreign Direct Investment FPT Financing and Promoting Technology Corporation FS Feasibility Study GDP Gross Domestic Product HAIDEP The Comprehensive Urban Development Programme in Hanoi Capital City HBI Hoa Lac Business Incubator HHTP Hoa Lac High-Tech Park JBIC Japan Bank for International Cooperation JETRO Japan External Trade Organization JICA Japan International Cooperation Agency L/A Loan Agreement MARD Ministry of Agriculture and Rural Development MOC Ministry of Construction MOF Ministry of Finance MOI Ministry of Industry MONRE Ministry of Natural Resources and Environment MPT Ministry of Post and Telecommunication MOST Ministry of Science and Technology MOT Ministry of Trade MOU Memorandum of Understanding MP Master Plan MPI Ministry of Planning and Investment NCST National Center for Science and Technology OECD Organization for Economic Cooperation and Development RAP Resettlement Action Plan R&D Research & Development SAPROF Special Assistance for Project Formation TCVN Tieu Chuan Vietnam VINASHIN Vietnam Shipbuilding Industry Corporation VINACONEX Vietnam Construction and Import Export Corporation VITEC Vietnam Information Technology Examination & Training Support Center

The Study for Update of the Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

1-1

1. DESCRIPTION OF THE PROJECT

1.1 Target and Mission of the Project

Hoa Lac High-Tech Park (hereinafter called as HHTP or Project) is a high-tech city development project in Ha Tay Province accumulating national research institutes, educational and training organizations and high-tech industries in its compound, and HHTP is expected to achieve the following target.

“To provide and sustain a level and competitive playing field aimed at promoting science and technology, the innovations of which will be promoted extensively throughout the country, thereby stimulating the development of high-tech industries to help attain the envisioned socioeconomic development of Vietnam.”

The HHTP has six missions to accomplish this target as below;

1) Provide a high-grade environment for living as well as other activities for its residents and visitors that are integrated with adjoining areas and communities.

2) Provide an attractive and competitive location that will help create new value added in science and technology innovations mainly by state research institutes

3) Attract international eminent high-tech industries by ensuring desirable investment climate and venue for fair competition which will be realized through state-of the-art infrastructures and superlative management methods.

4) Provide an attractive and competitive location that will nurture young talents who will, in turn, teach the next generation of S&T leaders and innovators through higher education of a global standard.

5) Provide a central place that will popularize science and technology to the nation to contribute the sustainable development.

6) Provide an appropriate venue to strengthen the competitiveness of industries, education, and R&D institutes through the principle of synergy.

1.2 Project Site

The HHTP is located in Thach That district, Ha Tay Province, about 30 km west of the capital city, Hanoi. The HHTP is connected with Hanoi with Lang-Hoa Lach highway which will be expanded to 6 lanes from the existing 2 lanes by 2009. The location map of the HHTP is shown below;

The Study for Update of the Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

1-2

Figure 1.2-1 Location Map of the HHTP

Source: JICA Study Team

1.3 Land Use Plan and Development Phases

The total development area of HHTP is 1,610 ha and consists of the following 14 zones.

Table 1.3-1 Description of the Functional Zones

Zones Candidate Facilities Software Park Software firms

Research and Development Zone State research Institute, High-tech enterprise laboratories

High-tech Industrial Zone Factories of high-tech manufacturers, Bonded warehouse for import and export procedure

Education and Training Zone University, Technical Training School, Vocational School, and Dormitory

Center of High-tech City High-tech transaction and services function

Residential Zone Wealth residential environment and facilities for staff and employees working in the Park Dwellings

Housing Complex Flats for employees working in the Park with necessary living facilities

Mixed Use Zone Commercial and Business Facilities, Residential Facilities)

Amusement Zone Sports, health and recreational facilities

Amenity Zone Recreation and social facility with includes residential area for executives

Infrastructure Zone Roads, water treatment plant and other utility service facilities

Lake and Buffer Zone Preserved area as a core for eco-friendly environmental

The project is planned to be developed in two phases targeting its completion of construction work at 2012 for Phase-1 and 2020 for Phase-2, respectively. The land area to be developed in each phase is tabulated in the following Table;

NH-5

NH-18

Noi Bai Airport

HANOI

HA TAYProvince

KEY MAPNORTHERN VIETNAM

Lang - Hoa Lac Highway

HHTP RR-3

N

10 km

RR3

Missing Link to

Hai Phong

to

Cai

The Study for Update of the Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

1-3

Table 1.3-2 Development Area of Each Zone

Updated MP (ha) Land Use Category Phase-1 Phase-2 Total

1 Software Park 45 30 752 Research and Development Zone 70 75 1453 High-Tech Industrial Zone 140 200 3404 Education and Training Zone 55 40 955 Center of High-Tech City 40 10 506 Mixed Use Zone 75 25 1007 Residential Zone 15 35 509 Housing Complex 0 20 2010 Reserved Area 0 180 18011 Amenity Zone 100 10 11012 Amusement Zone 20 40 6013 Infrastructure 110 135 24514 Lake and Buffer Zone 140 0 140 Total 810 800 1,610

1.4 Planning Criteria

Planning criteria of each functional zone is defined; i) to create the eco-friendly atmosphere, ii) to keep good living environmental, iii) to originate international level working space for the scientist and technologist, moreover iv) to estimate infrastructure demand. The criteria consists of; i) floor area, ii) population (daytime and residents), iii) maximum building coverage ratio, iv) maximum floor area ratio, v) maximum number of stories. The criteria determined for every zone is shown in the Table 1.4-1 below.

The Study for Update of the Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

1-4

Table 1.4-1 Planning Criteria

Area Total Floor Area Area Total Floor Area(ha) *2 (ha) *2 Daytime *3 (ha) *1 (ha) *2 Daytime *3

1 Software Park 45 25 2,250 75 42 3,750

2 Research and Development Zone 70 39 4,200 145 81 7,800

a. Research and Development 70 39 4,200 130 73 7,800

b. High Class Residential 0 0 15 8 0

3 High-tech Industrial Zone 140 98 14,000 340 238 34,000

4 Education and Training Zone 55 58 22,000 95 100 38,000

5 Center of High-tech City 40 140 10,000 50 175 12,500

6 Mixed Use Zone 75 158 11,250 100 210 15,000

7 Residential Zone 15 16 0 50 53 0

8 Housing Complex 0 0 0 20 42 0

9 Reserved Area 0 0 0 180 126 18,000

10 Amenity Zone 100 0 200 110 6 200

a. Golf Course 100 0.1 200 100 0.1 200

b. High Class Residential 0 0 0 10 6 0

11 Amusement Zone 20 0.1 2,000 60 0.4 6,000

12 Infrastructure 110 245

13 Lake and Buffer Zone 140 140

Total 810 534 65,900 1,610 1,073 135,250

Remarks:

Daytime Resident(person/ha) (person/ha)

1 Software Park 502 Research and Development Zone

a. Research and Development 60b. High Class Residential 100

3 High-Tech Industrial Zone 1004 Education and Training Zone 400 3005 Center of High-tech City 250 506 Mixed Use Zone 150 2007 Residential Zone 3008 Housing Complex 4009 Reserved Area 100

10 Amenity Zonea. Golf Course 2b. High Class Residential 100

11 Amusement Zone 100

*1 Area of Phase-2 is accumulation of Phase-1 and 2.*2 Site Area x Average Floor-Area Ratio (Maximum Floor-Area Rat*3 Total Floor Area x Daytime population Density per Hectare*4 Total Floor Area x Resident population Density per Hectare

40 80 3

Including Visitors and staff

Average 500m2 x 5P/hh

Remarks

Average 200m2 x 5P/hh

Average 100m2 x 5P/hh

Applied "hi-tech industry"

Incl. students and staff

Including visitors

Average 500m2 x 5P/hh

Max. Floor-Area Ratio Max. No. of Storey Population Density

Including visitors

(%) (%) (Number of floor)

Development Floor Area & Population

Basic Indicator

Phase-1 Phase-2Population Population

Max. Bldg Coverage Ratio

30 80 5

30 80 5

40 100 335 150 570 500 10 (Extra height 30)80 300 8

3

50 150 460 300 1240

5 1 3

100 3

1 0.2 240 80

Residents *4

0

0

15,000

4,500

0

0

0

19,500

Residents *4

1,500

1,500

28,500

8,750

20,000

15,000

8,000

1,000

1,000

82,750

1.5 Outline of the Infrastructure Development Plan

The public entity organized for the development and operation of HHTP that is Hoa Lac High-tech Park Management Board (hereinafter referred to as the HHTP-MB) is planned to furnish all necessary common infrastructures such as internal road, drainage, water supply system, sewerage system and power distribution system. While, the infrastructure inside the functional zones except for research and development zone will be developed by the private development company (hereinafter referred to as the HHTP-DC) selected by and contracted with the HHTP-MB.

This Pre-feasibility study covers common infrastructures to be developed by HHTP-MB and outline of the facilities are as follows;

The Study for Update of the Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

1-5

Table 1.5-1 Outline of Infrastructure

Phase-1 Phase-2 Item Phase-1 Phase-21. Road a. type I 4.2 km - b. type II 7.0 km 2.0 km c. type III 8.0 km 1.4 km d. bridge 12 units 2 units2. Drainage 46.7 km 13.7 km3. Water pipelines 16.7 km 0.9 km4. Sewer lines a. sewer lines 25.3 km 6.1 km b. pumping station 6 units 8 units5. Power cables 126.7 km 152.6 km6. Telecommunications conduit 46.7 km 13.7 km1. Water reservoir 1 unit 2 unit2. Pumping facilities 1 unit 2 unit3. Elevated water tank 7 units 3 units1.Sub-Station (110/35/22kV) 1 unit

(2x 63 MVA)1 unit(3x 63 MVA)

2.Ring Main Unit 30 units 18 unitsSewerage 13,600 m3/day 48,400 m3/day Construction of Waste Water Treatment Plant 1 unit

(8,500m3/day)2 units(25,500m3/day & 9,000m3/day)

Sector Demand Required Infrastructure

33,858 PCURoad andInfrastructure

197 MVA

73,875 PCU

64,500 m3/day

Power Supply 60 MVA

Water Supply 19,300 m3/day

As for land preparation (or land leveling work), HHTP-MB will at least responsible for Research and Development Zone, and land preparation for other zones will be carried out by HHTP-DC in principle. However, some land preparation work other than Research and Development Zone could be carried out by HHTP-MB in parallel with construction of common infrastructures in order to ensure to maintain the implementation schedule.

In this Pre-feasibility study, all the land preparation work is assumed to be carried out by HHTP-MB, thus included in the scope of study. While, other development work which will be carried out by HHTP-DC is not covered by this study.

The Study for Update of Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

2-1

2. LAND PREPARATION AND DRAINAGE SYSTEM

2.1 Outline of Original Sector Plan

(1) Land Preparation

Land grading elevations were determined so as to minimize land preparation cost and avoid flooding from the Tich River in the original JICA Master Plan (M/P) and Feasibility Study (F/S). Land for the R&D and Industrial Zones was planned to be safe from a 100 year probable flood and the arterial road was planned to be safe from a 10 year probable flood. Design elevations were set to be at least 10.0 m above MSL (mean sea level) for the R&D and Industrial Zones and 8.5 m for the arterial roads.

The ground elevation of parts of the industrial park in the southeast of the HHTP and New town in the northwest are lower than 10.0 m. Land grading volume was estimated at around one (1) million m3 for filling of those areas.

(2) Drainage Plan

According to the original JICA M/P and F/S, the drainage system covers an area of 920 ha, which is divided into six drainage zones according to the land uses. Each zone was to be provided with a drainage network made of concrete U-channel and Hume concrete pipe (HCP) along the road in Phase-1. The main features of the drainage facilities are summarized below:

Table 2.1-1 Main Features of JICA M/P and F/S

Target year of completion 2005 Target area 920 ha Design storm runoff 5-year probable Runoff calculation Rational Method Runoff coefficient 0.8 for developed areas Drainage conduit Concrete U-channel

Hume pipe Hydraulic design Manning’s Formula Drainage Facility for Phase-1 Retention Pond: Total 64 ha

U-channel: 600 – 1000mm width x 27 km Hume pipe: 400 – 2200mmDia x 6 km

Source: Master Plan on the Hoa Lack High-tech Park Project (JICA)

2.2 Present Condition

2.2.1 Current Development Progress

After the JICA M/P and F/S, the development plan was reviewed for the Construction of the Road and its facilities under Stage-1 of Phase-1 by HHTP-MB. A total of 200 ha of the whole of the HHTP area is being developed gradually by VINACONEX. Although some companies have already moved into the HHTP and started operations, the land preparation work is still on going and is scheduled to be completed by 2008.

The Study for Update of Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

2-2

A total of 31.5 ha of the land for stage-1 has already been prepared, and the existing grading level was constructed as set out in the road development plan.

However, the drainage system is not in faithful accordance with the JICA M/P. Existing main drainage facilities are summarized below.

Table 2.2-1 Main Drainage Facilities of Stage-1

Target year 2008 Target area 200 ha Design storm runoff 5-year probable of 70.4 mm/hr Runoff calculation Rational Method Runoff coefficient 0.7 for developed areas

0.3-0.5 for green area Drainage conduit Box culvert

Hume pipe Hydraulic design Manning’s Formula Drainage facility for Stage-1 of Phase-1

Box culvert: 600 – 1400mm width x 8 km Hume pipe: 600 – 2000mmDia x 18 km

Source: Construction of the Road and its facilities under Stage-1 of Phase-1

Existing Drainage Facilities

2.2.2 Related Projects

As noted in the above section, the drainage plan was reviewed by HHTP-MB and partially constructed for the area of 200 ha as Stage-1 of Phase-1. There is no other related land preparation or drainage projects in the HHTP area.

2.3 Update of Sector Plan

2.3.1 Sector Development Missions, Strategies and Goals

Although land preparation has been partially advanced by VINACONEX, the land preparation plan should be updated based on the road and land use development plan of this study.

The Study for Update of Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

2-3

As noted in the above section and the road development plan of Chapter 8, the following three reasons show that the revision of land preparation and drainage plan are necessary; 1) Proposed road alignment and land use have been revised from the JICA M/P in this study, 2) Drainage facilities have been partially installed by the HHTP-MB without reference to the JICA M/P, 3) Catchment basins of each drainage facility will be modified based on the proposed road and land use development plan in this study.

Mission, strategy and goals for land preparation and the drainage plan are set forth as stated below:

Table 2.3-1 Missions, Strategies and Goals

Land Preparation Drainage Plan Mission To develop land where industry

and housing can be developed To enhance investment activities without any interruption throughout the year To complete a systematic drainage network covering the entire HHTP area

Strategies To be able to access the developed area smoothly without any difficulty To prepare the land in conjunction with the drainage plan To be consider the existing elevations of the roads

To minimize inundation areas by constructing proper drainage facilities To install a drainage network in conjunction with the road development plan To reinforce the O&M system of HHTP

Goals To prepare the land by filling and cutting by 2020

To install drainage facilities in the developed area by 2020

2.3.2 Planning Framework

(1) General criteria for Land Preparation

The elevations of the existing roads which were constructed in stage-1 shall be kept as they are. The grading elevations for the area that will be developed in Phase-1 are to be decided in consideration of the road and drainage development plan. As noted in section 1.1, minimum grading elevation shall be higher than 10.0 m above MSL to minimize the flood risk.

(2) General criteria for the drainage plan

According to the original JICA M/P and F/S, water levels of Tich River are estimated at +8.0 m, +8.5 m, +9.5 m and 10.0 m for the return period of 5 years, 10 years, 50 years and 100 years respectively. Serious inundation by the overflow from the Tich River is rare since the average ground level of HHTP is higher than 10.0m.

In this study, the entire HHTP area is divided into 5 basins, the Tan Xa Lake basin, Central Canal basin, South Canal basin, and R1 and R2 basins as shown in Figure 2.3-1. Storm water which is collected by drainage facilities in each basin in the HHTP area is discharged into Tich River in the east side of HHTP.

The Study for Update of Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

2-4

Tan Xa Lake Basin

Central Canal Basin

South Canal Basin

R1 Basin

R2 Basin

Tan Xa Lake Basin

Central Canal Basin

South Canal Basin

R1 Basin

R2 Basin

Source: JICA Study Team

Figure 2.3-1 Drainage Basin

The natural lake and wetlands that in the present high-tech park play the role of storage facilities during heavy rain. However, the lake and wetlands will disappear and discharge volume will be increased after the land preparation is completed. Therefore, it is necessary to construct suitable drainage facilities in accordance with the updated land use, land preparation and road development plan. Moreover, it is necessary for Tan Xa Lake and Canal to have sufficient cross-sectional area to carry the flow to the Tich River.

The Study for Update of Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

2-5

2.3.3 Sector Development Plan

(1) Land Preparation

The land preparation plan is formulated on the basis of the road and the drainage development plans. The land grading volume is estimated on the assumption that the land grading elevations are the same as the planned road elevations. Volume of filling and cutting are calculated by the difference between existing ground levels and planned road elevations. Calculation results show that total filling volume is around 24 million m3 and cutting is around 11 million m3 of which around 9.3 million m3 of filling which represents 40 percent of total filling volume will be required in Phase-1 and 14.8 million m3 of filling which represents 60 percent of total filling volume will be required in Phase-2.

The drainage plan basically follows the existing drainage system. However, it is necessary to modify it to be in conformity with the proposed development plan. Especially, it is necessary to take into account the proposed road alignment which was modified from the original JICA M/P and FS. Existing drainage facilities including those under construction on the road project have less capacity than required. An updated drainage plan in accordance with the proposed road development plan is required in the study. The drainage plan shall be formulated to keep as much of the existing drainage facilities intact as possible.

Table 2.3-2 Drainage Planning Criteria for the Study

Target year Phase-1: 2012, Phase-2: 2020 Target area HHTP Area (1,382 ha) Design storm runoff A return period of 5 years of 70.4 mm/hr Runoff calculation Rational formula Runoff coefficient 0.8 for the developed area Drainage conduit U-shape Channel Hydraulic design Manning’s Formula Standard velocity Max; 3.0 m/s, Min; 0.8m/s Source: JICA Study Team

2.3.4 Development Issues

There is no retention pond planned in the catchment area of the drainage plan in order to keep the area where companies can be located as large as possible. However, the Amusement zone has some ponds which are naturally generated in the lower area. It is suggested that those ponds shall be kept as is when the area will be developed to minimize the flood risk downstream.

And also, to decrease peak flow during the heavy rain, a retention pond will be needed downstream. Further investigation in the future is needed for planning of the location and the volume of the retention pond. Especially, review of the discharge volume at the point of discharge to Tich River shall be necessary.

The Study for Update of Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

2-6

2.4 Proposed Project List

Based on the area for each development phase of the land use and road development plan, land preparation will be developed in Phase-1 and Phase-2.

The drainage project shall the follow the road project which is also divided into two phases since the U-channel will be installed under the sidewalks of the road as shown in Figure 2.4-1. The drainage system of each phase is as shown in Figure 2.4-2.

Main features of the land preparation and drainage are listed in Table 2.4-1.

Source: JICA Study Team

Figure 2.4-1 Typical Cross Section of Drainage Facility

The Study for Update of Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

2-7

Phase 1Phase 2Phase 1Phase 2

Source: JICA Study Team

Figure 2.4-2 Drainage System

The Study for Update of Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

2-8

Table 2.4-1 Project List for Land Preparation and Drainage

No. Project General Description PhaseFilling V= 4.4 mil m3

Cutting & Filling V= 4.9 mil m3

Filling V= 8.9 mil m3

Cutting & Filling V= 5.9 mil m3

3 Installation of U-channel

To install the U-shapedrainage channel, Manholealong the road for the purposeto discharge storm water in

U-Channel 400-2400mm width x46.6 km 1

4 Installation of U-channel

To install the U-shapedrainage channel, Manholealong the road for the purposeto discharge storm water in

U-Channel 800-2400mm width x13.7 km 2

Specification

1 Land preparationTo prepare land by filling andcutting based on the land useplan of Phase-1

2 Land preparationTo prepare land by filling andcutting based on the land useplan of Phase-2

1

2

Source: JICA Study Team

2.5 Technical Study for Phase-1 Development

2.5.1 Land Preparation Plan

The area to be developed is based on the phasing of the land use development plan. As described in Table 2.4-1, total filling volume is estimated at 9.3 million m3, of which, 4.9 million m3 of filling material shall be obtained from somewhere outside of HHTP.

2.5.2 Drainage Plan

(1) Drainage Zones

In principle, the whole HHTP area is divided into five zones by topographical aspects as shown in Figure 2.3-1. Storm water which is collected in each zone shall be discharged into Tan Xa Lake, the Central Canal, South Canal, and Tich River respectively.

According to the brief site investigation of the study area, it is difficult to find the boundary of the water surface especially for the undeveloped area. However, at least, it is necessary for the discharge points at Tan Xa Lake, Central Canal, South Canal and Tich River to be maintained in order for the storm water to be discharged out of the HHTP project boundary after the land preparation is completed.

(2) Planning and Design Criteria

The following criteria are applicable for the planning and design of the drainage facilities. Hydraulic calculation results are shown in Table 2.5-1.

1) Rainfall Intensity

I=0.36 x 5426 x (1 + 0.25 x logP x t0.13) x 1/(t+19)0.82

Where, I : Hourly rainfall intensity (mm/hour)

P : Return period (year)

t : Rainfall duration (min)

The Study for Update of Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

2-9

0

20

40

60

80

100

120

140

160

180

0 50 100 150 200 250 300 350 400Duration (min)

Rai

nfal

l Int

ensi

ty (m

m/h

our)

P=5 years

P=10 years

Note: The rainfall curves were calculatedby the fomula established by the Ministryof Construciton (MOC)in Viet Nam

Source: Master Plan on the Hoa Lac High-tech Park Project

Figure 2.5-1 Rainfall Intensity

2) Runoff calculation

The Rational formula is applied for the runoff calculation of the peak flow.

Q=(1/360) x C x I x A

Where, Q : Peak runoff (m3/sec)

C : Runoff coefficient

I : Design rainfall (mm/hour)

A : Area of drainage basin (ha)

(3) Hydraulic design

Manning’s formula was applied for the hydraulic design for the drainage facilities. The drainage system for each basin is shown in Figures 2.5-2, 2.5-3, 2.5-4. Calculation sheets are shown in Table 2.5-1.

Q=A x V

V=(1/n) x R2/3 x I1/2

Where, A : Cross sectional area (m2)

V : Velocity (m/sec) (Max: 3.0 m/s, Min: 0.8 m/s)

n : Roughness coefficient

I : Hydraulic gradient

R : Hydraulic radius (m)

The Study for Update of Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

2-10

1 2

34

5

6 7

89

1011

12

14

13

72

73

74 75 76 77

15

18

16 17

19

20

23 22 24

262527

28 21

59

65 66

67

60 61

68 69

62 63 64

707180

79

8129 30 31

41

35 36 37

3439 40

38

32

33 42

43

46

50 5249 51 44

55

47 48

53

54 58

45 5756

Tan Xa Lake

7882

41

83

Tan Xa Lake Basin

1 2

34

5

6 7

89

1011

12

14

13

72

73

74 75 76 77

15

18

16 17

19

20

23 22 24

262527

28 21

59

65 66

67

60 61

68 69

62 63 64

707180

79

8129 30 31

41

35 36 37

3439 40

38

32

33 42

43

46

50 5249 51 44

55

47 48

53

54 58

45 5756

Tan Xa Lake

7882

41

83

Tan Xa Lake Basin

Source: JICA Study Team

Figure 2.5-2 Drainage System of Tan Xa Lake Basin

8 9

31

21

2 4

1110

40

22 23 24

12

25

5

41

613

1415

1617

18

20

26

27

3031

32

33

39 38 37 36

29

19

35 34

121

42

49

57

58

61

60

63

62

59

43

50

70 71

51

111

65

644452

110

53 54

66 68

45 46

72

55 56

69

47 48

73

74 76

75 77

78 80

79 81

82 85

83 86

84

89

90

92

93

88 87

91

94

98

95

96

101

97 102

119 120

106

104 105

109

108107

113

103

116

115

117

118

Tick River

28

112

Central Canal Basin

Central CanalCentral Canal

Cen

tral

Can

al

8 9

31

21

2 4

1110

40

22 23 24

12

25

5

41

613

1415

1617

18

20

26

27

3031

32

33

39 38 37 36

29

19

35 34

121

42

49

57

58

61

60

63

62

59

43

50

70 71

51

111

65

644452

110

53 54

66 68

45 46

72

55 56

69

47 48

73

74 76

75 77

78 80

79 81

82 85

83 86

84

89

90

92

93

88 87

91

94

98

95

96

101

97 102

119 120

106

104 105

109

108107

113

103

116

115

117

118

Tick River

28

112

Central Canal Basin

8 9

31

21

2 4

1110

40

22 23 24

12

25

5

41

613

1415

1617

18

20

26

27

3031

32

33

39 38 37 36

29

19

35 34

121

42

49

57

58

61

60

63

62

59

43

50

70 71

51

111

65

644452

110

53 54

66 68

45 46

72

55 56

69

47 48

73

74 76

75 77

78 80

79 81

82 85

83 86

84

89

90

92

93

88 87

91

94

98

95

96

101

97 102

119 120

106

104 105

109

108107

113

103

116

115

117

118

Tick River

28

112

Central Canal Basin

Central CanalCentral Canal

Cen

tral

Can

al

Source: JICA Study Team

Figure 2.5-3 Drainage System of Central Canal Basin

The Study for Update of Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

2-11

34

235

5

89

7

37

3

1615

12

1314

11

10

22 23

2120

19

18

17

27

28 33

32

26

25

31

30

3829

40

39

42

41

44

43

46

45

48

47

Tick River

South Canal Basin

South Canal34

235

5

89

7

37

3

1615

12

1314

11

10

22 23

2120

19

18

17

27

28 33

32

26

25

31

30

3829

40

39

42

41

44

43

46

45

48

47

Tick River

South Canal Basin

34

235

5

89

7

37

3

1615

12

1314

11

10

22 23

2120

19

18

17

27

28 33

32

26

25

31

30

3829

40

39

42

41

44

43

46

45

48

47

Tick River

South Canal Basin

South Canal

Source: JICA Study Team

Figure 2.5-4 Drainage System of South Canal Basin

The Study for Update of Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

2-12

Table 2.5-1 Hydraulic Calculation Sheet (1)

7 minRainfallIntensity

( ha ) ( m ) Qo (Qo-Qw)/Qw

0.50 0.80 0.50 0.70 (min) ( m3/s ) ( m

3/s ) ‰ ( m

3/s ) ( % )

Roughness

Coefficient

LengthAccumulated areaPoint

No.-out Drain

Gradient

PointNo.-in

Calculation Sheet (TanXaLake Basin 1)

8.8

8.4

10.1

8.4

7.3

0.8

1.7

19

22.630.013 1.614 1.4530.320

1.185 U1000 2.03.7 514.00 514.00 12.30.00 0.00 3.70 0.8068 69 0.00 3.70

9.12

9.12

0.61

8.83

32.10

22.77

8.02

14.04

21.15

17.47

34.38

6.66

12.37

7.49

2.52

1.49

13.67

5.95

3.59

5.29

11.15

20.34

5.53

5.53

2.52

25.13

25.13

3.36

16.30

18.90

9.96

28.69

14.10

0.70

20.82

20.82

0.63

8.12

4.89

35.90

7.72

8.17

17.90

3.87

1.873

1.873

1.343

2.649

4.283

1.873

1.343

1.133

3.961

0.981

0.456

6.764

2.055

4.574

2.297

0.981

0.981

1.133

0.887

6.764

6.764

15.000

5.246

5.246

2.297

1.453

1.453

0.981

1.325

1.873

0.456

3.234

1.027

0.776

6.965

6.965

2.649

2.649

0.280

0.794

6.764

3.244

3.341

3.341

2.450

0.267

0.584

1.720

1.720

1.843

2.433

2.115

1.720

1.843

1.967

2.415

1.704

1.406

2.761

2.283

2.788

2.552

1.704

1.704

1.967

2.012

2.761

2.761

2.894

2.591

2.591

2.552

1.614

1.614

1.704

1.216

1.720

1.406

1.141

1.064

2.389

1.972

2.389

2.433

2.433

1.245

1.800

2.761

2.979

2.578

2.578

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

2.0

2.0

3.0

4.0

2.0

2.0

3.0

4.0

3.0

3.0

3.0

3.0

4.0

4.0

5.0

3.0

3.0

4.0

5.0

3.0

3.0

2.0

3.0

3.0

5.0

2.0

2.0

3.0

1.0

2.0

3.0

1.0

2.0

1.0

2.0

2.0

U900

3.0

6.0

4.0

4.0

4.0

4.0

3.0

4.0

U1500

U1100

U1100

U1100

U1350

U800

U1100

U1650

U1000

U900

U800

U800

U800

U600

U1650

U1650

U1350

U1000

U1500

U1000

U800

U700

U800

U2400

U1500

U1100

U600

U1000

U1000

U700

U1800

U1800

U1200

U1100

U1100

U500

1.717

1.717

1.335

2.434

3.242

1.526

1.244

0.994

3.270

0.835

0.339

6.342

1.828

4.255

2.241

0.967

0.863

1.070

0.857

6.424

6.085

12.465

4.971

4.971

2.241

1.161

1.161

0.949

6.279

3.000

2.513

5.765

5.765

2.834

3.216

2.632

0.326

0.900

0.770

1.139

1.575

0.414

0.318

0.318

0.348

0.329

0.326

0.327

0.343

0.345

0.339

0.327

0.356

0.345

0.356

0.324

0.343

0.325

0.344

0.323

0.339

0.310

0.321

0.316

12.6

11.6

0.317

0.341

0.337

0.313

0.336

0.334

13.8

12.6

10.4

9.6

11.4

9.0

11.2

11.7

11.5

11.4

8.2

9.3

9.3

10.0

9.6

11.7

11.5

11.4

11.8

11.7

8.2

11.8

10.0

12.0

12.3

12.0

12.8

13.3

9.3

16.3

13.6

12.2

15.3

14.6

524.00

499.00

12.7

9.8

10.2

13.4

13.2

10.4

10.6

9.5

624.00

420.00

191.00

1095.00

449.00

333.00

1186.00

1086.00

906.00

496.00

489.00

931.00

420.00

100.00

191.00

1095.00

449.00

333.00

1.2

410.00

496.00

489.00

25.00

410.00

496.00

267.00

267.00

2.4

3.6

4.8

0.80

0.80

19.80.80

0.80

0.80

0.00

5.40

0.90

2.90

0.00

2.40

1.00

4.10

7.40

0.00

4.80

0.00

5.60

6.70

6.30

2.80

2.50

0.80

2.50

0.00

0.00

0.00

0.00

9.00

6.30

0.00

0.80

2.80

3.60

0.00

1.20

8.60

2.90

2.40

0.00

19.00

1.10

7.30

0.80

1.70

2.60

8.80

8.40

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

5.40

4.10

7.40

0.00

4.80

0.90

2.90

0.00

2.40

1.00

0.00

5.60

6.70

6.30

2.80

2.50

0.80

2.50

0.00

0.00

0.00

0.00

9.00

6.30

0.00

0.80

2.80

3.60

0.00

1.20

8.60

2.90

2.40

0.00

19.00

1.10

7.30

0.80

1.70

2.60

8.80

8.40

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

66

60

62

22

67

66

25

27

25

22

37

21

25

36

35

36

36

31

32

31

37

41

31

30

29

16

18

19

77

15

16

14

73

75

10

11

9

2

3

9

3

6

6

3

60

59

61

24

66

65

27

28

22

23

38

25

26

35

34

39

40

32

33

37

36

31

30

29

81

18

19

20

76

16

17

13

72

74

11

12

2

1

7

8

6

4

5

9

0.80 4.1 514.00 514.00

0.80 5.4 582.00 582.00

5.4 25.00 607.00

0.80 4.8 582.00 582.00

10.2 130.00 737.00

0.80 7.4 615.00 615.00

0.80 2.4 202.00 202.00

9.8 25.00 640.00

0.80 2.9 308.00 308.00

0.80 3.8 202.00 510.00

0.80 5.6 615.00 615.00

19.2 30.00 670.00

0.80 1 256.00 256.00

0.80 2.5 235.00 235.00

0.80 2.8 235.00 235.00

0.80 6.3 179.00 179.00

0.80 13 542.00 721.00

18.3 10.00 731.00

19.3 25.00 756.00

0.80 2.5 315.00 315.00

0.80 3.3 256.00 571.00

0.80 6.3 178.00 178.00

0.80 15.3 545.00 723.00

15.3 10.00 733.00

37.9 30.00 786.00

0.80 2.8 308.00 308.00

0.80 3.6 191.00

3.6 25.00

Qw

Dischargeper ha

TotalDischarge

Catchment area( ha )

C C C

Accumulated Length

U1650

U1100

U1200

DischargeVolume

Velocity

( m/s )

SafetyMargin

( m )

Drainage Plan

Time of Inflow

C

-

ManningTotal

Discharge VolumeConcentration time

267.00

267.00

0.303

906.00

496.00

0.345

0.292 U1350

U1000

U900

U1100

0.80

0.80

0.80

0.80

0.80

0.80

0.80

100.00

1086.00

0.80

8.6

2.9

19

The Study for Update of Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

2-13

Table 2.5-1 Hydraulic Calculation Sheet (2)

7 minRainfallIntensity

( ha ) ( m ) Qo (Qo-Qw)/Qw

0.50 0.80 0.50 0.70 (min) ( m3/s ) ( m

3/s ) ‰ ( m

3/s ) ( % )

Accumulated Length

Concentration time

SafetyMargin

Drain

Gradient

Roughness

Coefficient

PointNo.-out

Accumulated area

Length

315.00

163.00

2.6

1.2

1.4

0.6

0.80

25.00

0.80

0.80

0.80

0.80

0.80

0.80

0.80

0.409

0.335

U900

U600

U700

U600

U450

U800

634.00

0.342

610.00

178.00

0.316

0.338

( m )

Drainage Plan

Time of Inflow

C

-

ManningTotal

PointNo.-in

U700

U600

U1500

DischargeVolume

Velocity

( m/s )

Discharge VolumeQw

Dischargeper ha

TotalDischarge

Catchment area( ha )

C C C

0.80 3.2 390.00

63

70

79

78

82

83

44

43

42

45

47

46

48

49

51

53

57

56

64

71

80

79

79

79

55

44

43

44

44

47

47

50

52

54

58

57

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.90

1.10

2.00

5.10

2.70

4.00

0.00

1.40

2.40

0.60

0.00

1.20

1.40

1.00

0.60

2.30

2.60

3.20

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.90

1.10

2.00

5.10

2.70

4.00

0.00

1.40

2.40

0.60

0.00

1.20

1.40

1.00

0.60

2.30

2.60

3.20

0.80

0.90.80

0.80

0.80

0.80

0.80

0.80 1

0.6

2.3

5.8

234.00

234.00

316.00

610.00

610.00

178.00

20.00

299.00

299.00

163.00

235.00

235.00

349.00

349.00

234.00

234.00

926.00

610.00

614.00

315.00

163.00

324.00

299.00

163.00

235.00

235.00

349.00

349.00

390.00

11.3

10.4

16.3

12.9

13.8

8.8

13.0

12.8

10.1

9.7

10.8

10.5

9.1

9.8

10.4

10.4

3.4

11.3

0.328

0.336

0.292

0.316

0.309

0.350

0.328

0.347

0.341

0.336

0.336

0.341

0.201

0.772

2.370

0.295

0.369

0.402

0.486

0.812

0.205

0.888

4.033

1.610

0.834

1.050

U1100

U900

U1000

U1500

U900

U800

U500

U1100

U900

1.0

2.0

2.0

2.0

2.0

2.0

1.0

3.0

3.0

2.0

2.0

2.0

3.0

3.0

3.0

3.0

2.0

2.0

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.900

1.148

2.115

1.720

1.505

1.614

1.496

1.843

1.273

1.406

1.017

1.505

1.406

1.704

1.161

1.704

1.720

1.505

1.400

2.295

1.202

0.397

0.372

4.283

1.873

1.097

1.453

3.029

1.343

0.981

0.229

1.097

0.456

0.561

0.456

0.212

0.981

1.873

1.097

34.38

0.77

6.22

16.37

31.47

3.79

31.97

11.75

20.89

11.59

23.56

13.42

15.47

33.68

5.07

27.12

-20.96

4.47

2.4

Calculation Sheet (TanXaLake Basin 2)

1.1

13.8

5.1

2.7

4

7

3.8

The Study for Update of Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

2-14

Table 2.5-1 Hydraulic Calculation Sheet (3)

7 minRainfallIntensity

( ha ) ( m ) Qo (Qo-Qw)/Qw

0.50 0.80 0.50 0.70 (min) ( m3/s ) ( m

3/s ) ‰ ( m

3/s ) ( % )

SafetyMargin

Drain

Gradient

Roughness

Coefficient

Calculation Sheet (Central Canal 1)

PointNo.-in

PointNo.-out

Accumulated area

LengthAccumulated Length

Concentration time

21.94

23.6

17.8

12.9

4.9

1

0.9

1.7

2.1

1.9

0.013 1.064 0.7760.335

0.636 U900 1.01.9 223.00 223.00 10.50.00 0.00 1.90 0.8064 65 0.00 1.90

0.948 0.173 1.100.171 U450 2.0 0.013151.00 151.00 9.70.342

23.73

62 63 0.00 0.50 0.00 0.00 0.50 0.80 0.5

0.013 0.876 0.1260.340

0.102 U400 2.00.3 151.00 151.00 9.90.00 0.00 0.30 0.8060 61 0.00 0.30

28.79

23.99

25.25

5.31

8.65

20.81

8.35

2.83

29.01

8.27

1.01

2.91

0.77

25.36

33.96

14.55

0.63

19.44

17.40

5.72

8.61

13.02

24.82

17.98

9.25

15.32

16.11

17.04

23.54

2.83

2.83

1.24

8.18

4.36

0.67

36.74

6.41

0.93

2.23

9.15

4.66

34.12

20.83

15.34

7.57

7.79

1.343

0.561

1.779

0.687

1.097

2.294

1.779

1.343

0.229

5.523

3.234

1.453

0.372

6.965

0.372

0.801

9.225

1.343

2.362

1.453

3.341

1.551

0.801

0.561

4.283

0.981

1.343

1.453

1.097

0.456

0.456

4.283

4.574

3.735

2.649

0.981

0.687

5.523

1.734

0.372

0.324

0.794

15.000

8.531

6.058

4.574

0.341

0.309

0.592

0.718

1.843

1.273

1.977

1.559

1.505

2.107

1.977

1.843

1.017

2.254

1.972

1.614

1.148

2.389

1.148

1.391

2.562

1.843

1.823

1.614

2.578

2.128

1.391

1.273

2.115

1.704

1.843

1.614

1.505

1.406

1.406

1.704

2.788

2.882

2.433

2.254

2.115

1.559

2.379

1.148

1.438

1.800

2.894

2.925

2.991

2.788

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

3.0

2.0

3.0

3.0

2.0

3.0

3.0

3.0

2.0

2.0

2.0

2.0

2.0

2.0

2.0

2.0

2.0

3.0

2.0

2.0

4.0

4.0

2.0

2.0

2.0

3.0

3.0

2.0

2.0

3.0

3.0

5.0

2.0

2.0

4.0

3.0

3.0

4.0

U1000

U700

2.0

3.0

4.0

4.0

5.0

2.0

4.0

4.0

U1000

U900

U900

U700

U1350

U1000

U900

U1100

U1800

U600

U500

U1650

U900

U600

U1200

U800

U2000

U700

U1500

U1200

U1000

U900

U900

U800

U600

U600

U800

U700

U800

U700

U1350

U900

U600

U500

1.043

0.453

1.421

0.653

1.010

1.899

1.642

1.306

0.177

5.101

3.202

1.412

0.369

5.556

0.278

0.699

9.167

1.125

2.012

1.374

3.076

1.373

0.642

0.476

3.921

0.851

1.157

12.415

7.396

4.231

4.228

0.646

5.472

5.631

4.243

1.697

0.344

3.579

2.632

1.241

0.888

0.443

0.443

0.319

0.336

0.323

0.338

0.307

0.326

0.297

0.304

0.347

0.355

0.302

0.336

0.308

0.333

0.308

0.341

0.295

0.319

0.344

0.335

0.321

0.317

0.348

0.327

0.331

0.318

0.331

0.346

0.303

0.317

11.9

10.1

9.5

0.293

0.313

0.316

0.329

0.346

0.341

0.344

15.6

14.5

12.5

10.3

15.8

14.8

14.1

11.6

17.2

9.1

8.3

14.0

9.8

10.4

9.5

14.0

10.7

12.2

12.7

15.9

12.4

11.0

10.5

11.4

14.7

12.7

10.1

9.8

13.2

12.6

10.9

9.2

9.7

9.9

14.9

445.00

16.1

13.2

12.8

11.2

9.2

9.8

9.5

9.0

263.00

691.00

501.00

238.00

968.00

890.00

607.00

315.00

271.00

271.00

999.00

1199.00

968.00

890.00

607.00

190.00

238.00

25.00

238.00

78.00

283.00

292.00

315.00

1.3

200.00

78.00

283.00

292.00

315.00

190.00

217.00

217.00

271.00

7.6

4.1

2.8

1.3

0.80

0.80

0.80

42.30.80

0.80

0.80

0.80

3.10

1.40

4.20

0.50

0.00

0.40

1.50

1.10

1.90

3.10

1.00

1.30

1.00

0.00

0.80

2.10

29.80

3.30

2.30

4.00

10.00

4.10

2.00

1.50

7.00

2.60

3.50

1.30

1.50

0.00

1.30

0.20

2.50

3.20

7.60

2.10

1.90

0.00

4.90

1.00

0.90

1.70

0.10

1.80

4.90

5.40

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

3.10

1.40

4.20

1.90

3.10

1.00

1.30

1.00

0.50

0.00

0.40

1.50

1.10

0.00

0.80

2.10

29.80

3.30

2.30

4.00

10.00

4.10

2.00

1.50

7.00

2.60

3.50

1.30

1.50

0.00

1.30

0.20

2.50

3.20

7.60

2.10

1.90

0.00

4.90

1.00

0.90

1.70

0.10

1.80

4.90

5.40

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

58

51

51

121

52

50

49

57

43

43

50

51

41

59

43

34

35

35

17

18

34

32

32

33

33

30

31

12

13

14

15

12

11

10

9

4

4

5

2

5

2

2

25

5

4

3

111

70

71

42

110

49

57

58

44

50

51

52

40

43

42

38

19

39

18

20

29

28

36

37

17

26

27

13

14

15

16

11

10

9

8

23

24

12

1

6

21

22

5

4

3

2

0.80 1.9 236.00 236.00

0.80 4.2 372.00 372.00

0.80 1.4 372.00 372.00

0.80 3.1 366.00 366.00

0.80 4.1 238.00 604.00

0.80 5.4 238.00 842.00

0.80 6.4 142.00 984.00

0.80 3.1 416.00 416.00

0.80 4.6 238.00 654.00

0.80 10.6 80.00 734.00

17 25.00 1009.00

0.80 0.5 80.00 80.00

0.80 0.8 143.00 143.00

18.3 200.00 1209.00

0.80 1.1 236.00 236.00

0.80 3.3 310.00 310.00

0.80 29.8 1079.00 1079.00

0.80 2.1 310.00 310.00

0.80 10 1079.00 1079.00

0.80 4 242.00 242.00

0.80 6.3 320.00 562.00

0.80 13.3 445.00 1007.00

0.80 1.5 436.00 436.00

0.80 2 436.00 436.00

0.80 4.1 445.00 445.00

0.80 3.5 445.00 445.00

0.80 2.6 445.00

Qw

Dischargeper ha

TotalDischarge

Catchment area( ha )

C C C

U2400

U1800

U1500

DischargeVolume

Velocity

( m/s )

( m )

Drainage Plan

Time of Inflow

C

-

ManningTotal

Discharge Volume

217.00

217.00

315.00

190.00

0.342

0.340

0.341

0.313

U1650

U1500

U1350

U1200

U1100

U1000

U900

0.80

0.80

0.80

0.80

0.80

0.80

0.80

0.80

271.00

0.80

17.6

13.5

13.3

10.8

0.80

31.00

The Study for Update of Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

2-15

Table 2.5-1 Hydraulic Calculation Sheet (4)

7 minRainfallIntensity

( ha ) ( m ) Qo (Qo-Qw)/Qw

0.50 0.80 0.50 0.70 (min) ( m3/s ) ( m

3/s ) ‰ ( m

3/s ) ( % )

SafetyMargin

Drain

Gradient

Roughness

Coefficient

25.00

0.80

4.4

4.7

10.1

9.1

251.00

0.80

0.80

0.80

0.80

0.80

0.80

0.80

0.344

0.347

0.341

U1000

U1000

U1350

U1000

U800

U800

404.00

0.326

0.343330.00

ManningTotal

Discharge Volume

223.00

Accumulated area

LengthAccumulated Length

Concentration time

Drainage Plan

Time of Inflow -

PointNo.-in

PointNo.-out

U1500

U900

U1200

DischargeVolume

Velocity

( m/s )

Qw

Dischargeper ha

TotalDischarge

Catchment area( ha )

C C C( m )

C

0.80 5.7 789.00

0.80 4.2 196.00 196.00

0.80 2 136.00 136.00

0.80 2.6 278.00 278.00

0.80 2.7 278.00 278.00

0.80 3.3 340.00 340.00

0.80 1.7 340.00 340.00

0.80 0.3 89.00 89.00

0.80 4.3 161.00 551.00

0.80 3.4 390.00 390.00

0.80 3.9 201.00 539.00

2.7 25.00 338.00

0.80 2.7 313.00 313.00

0.80 2.9 201.00 402.00

0.80 1.9 201.00 201.00

0.80 5.2 130.00 459.00

0.80 1.8 304.00 304.00

3 25.00 329.00

0.80 3 304.00 304.00

0.80 0.7 130.00 130.00

0.80 4.1 243.00 243.00

46

45

54

72

53

45

47

48

55

73

56

105

104

120

119

108

112

116

117

74

76

78

80

82

85

84

89

88

87

92

91

96

98

95

94

101

113

68

46

46

54

54

66

69

47

47

55

55

106

105

105

120

109

107

115

118

75

77

79

81

83

86

85

90

89

88

93

92

97

96

96

95

102

103

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

1.40

4.30

0.00

2.10

4.80

1.20

1.70

5.70

0.00

4.40

4.70

2.50

5.20

0.00

2.40

6.20

5.70

4.20

2.00

2.60

2.70

3.30

1.70

0.30

0.90

3.40

1.20

0.00

2.70

1.00

1.90

0.40

1.80

0.00

3.00

0.70

4.10

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

1.40

4.30

0.00

2.10

4.80

1.20

1.70

5.70

0.00

4.40

4.70

2.50

5.20

0.00

2.40

6.20

5.70

4.20

2.00

2.60

2.70

3.30

1.70

0.30

1.00

0.90

3.40

1.20

0.00

3.00

0.70

0.80

4.10

1.90

0.40

1.80

0.00

2.70

12.60.80

0.80

0.80

0.80 5.2

2.4

2.4

6.2

212.00

404.00

25.00

251.00

404.00

223.00

212.00

330.00

300.00

278.00

25.00

278.00

300.00

641.00

404.00

429.00

251.00

567.00

330.00

355.00

251.00

330.00

603.00

278.00

303.00

278.00

300.00

789.00

11.9

10.2

10.1

9.3

9.9

11.1

11.6

9.6

10.0

9.1

9.8

12.0

9.0

9.9

9.7

9.4

9.5

9.1

12.8

9.7

10.1

10.8

11.5

8.7

12.2

10.5

12.1

10.3

10.1

11.1

9.1

11.4

10.3

9.8

9.6

9.7

10.1

0.323

0.337

0.345

0.340

0.330

0.316

0.323

0.348

0.342

0.344

0.347

0.342

0.338

0.332

0.326

0.351

0.321

0.335

0.322

0.338

0.330

0.347

0.327

0.336

0.343

3.257

1.810

0.820

0.820

2.135

0.342

0.338

4.074

1.451

1.602

1.953

3.130

1.528

2.357

0.725

1.632

1.803

1.443

0.694

0.889

0.913

1.096

0.555

0.105

1.380

1.138

1.255

0.913

0.913

0.956

0.660

1.702

0.606

1.028

1.028

0.239

1.387

U700

U1000

U700

U1650

U1100

U1350

U1100

U1000

U1200

U900

U800

U900

U900

U700

U400

U1000

U900

U900

U800

U800

U800

U700

U1000

U700

U900

U800

U600

U1200

2.0

4.0

2.0

4.0

4.0

1.0

2.0

3.0

3.0

3.0

3.0

3.0

4.0

3.0

3.0

3.0

4.0

1.0

1.0

3.0

2.0

2.0

2.0

2.0

2.0

3.0

3.0

3.0

3.0

3.0

3.0

3.0

3.0

3.0

4.0

1.0

1.0

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

2.115

2.128

1.823

1.800

2.283

0.900

2.254

2.415

2.283

2.415

1.977

1.977

2.107

1.704

1.704

2.107

2.283

1.289

1.064

1.704

1.505

1.505

1.273

0.876

1.614

1.843

1.843

1.704

1.704

1.704

1.559

1.977

1.559

1.843

1.967

0.812

1.289

0.396

5.374

4.283

1.551

2.362

0.794

2.055

0.397

5.523

2.294

3.961

1.779

1.779

3.961

2.055

0.981

0.981

2.294

2.055

1.670

0.776

0.981

1.097

1.097

0.561

0.126

1.453

1.343

1.343

0.981

0.981

0.981

0.687

1.779

0.687

1.343

1.133

0.263

1.670

5.15

6.94

0.23

9.44

25.90

0.29

2.77

17.47

26.57

16.48

11.07

21.60

13.51

19.65

19.65

7.43

13.93

15.78

11.71

10.45

20.12

0.05

1.11

19.88

5.27

18.03

7.07

7.46

7.46

2.62

4.20

4.54

13.48

30.70

10.24

9.98

20.46

5.7

Calculation Sheet (Central Canal 2)

4.3

6.9

2.1

4.8

1.2

16.5

The Study for Update of Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

2-16

Table 2.5-1 Hydraulic Calculation Sheet (5)

7 minRainfallIntensity

( ha ) ( m ) Qo (Qo-Qw)/Qw

0.50 0.80 0.50 0.70 (min) ( m3/s ) ( m

3/s ) ‰ ( m

3/s ) ( % )

Concentration time

SafetyMargin

Drain

Gradient

Roughness

Coefficient

Accumulated area

LengthAccumulated Length

243.00

0.80

34.9

10.7

8

8

17.8

689.00

0.80

0.80

0.80

0.80

0.80

0.80

U1200

0.80

0.337

0.302

0.338

0.80

41.5

7.4

452.00

U2200

U1350

U1200

448.00

U2400

U1200

416.00

0.352

0.346

1166.00

( m )

28.2 1134.00

768.00

Drainage Plan

Time of Inflow Calculation Sheet (South Canal)

PointNo.-in

PointNo.-out C

-

ManningTotal

Discharge VolumeQw

Dischargeper ha

TotalDischarge

Catchment area( ha )

U2000

U1800

U1350

DischargeVolume

Velocity

( m/s )

C C C

0.80

0.00

0.00

0.00

0.00

0.00

0.00

11.7 504.00

0.80 16.9 857.00 857.00

0.80 4.4 504.00 504.00

0.80 28.6 857.00 857.00

0.80 6 789.00 789.00

0.80 5.4 396.00 396.00

0.80 5.5 170.00 170.00

0.80 3.7 352.00 352.00

0.80 5.3 367.00 367.00

0.80 1.5 117.00 117.00

34

2

35

3

8

9

37

10

17

13

14

15

16

20

21

22

23

25

28

30

33

38

40

41

44

45

48

5

34

2

35

2

35

7

11

18

12

13

13

15

19

20

20

22

26

27

31

32

29

39

42

43

46

47

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

9.20

3.20

0.00

3.30

6.70

5.80

11.40

6.50

3.80

16.20

10.70

0.00

8.00

16.30

7.40

0.00

17.80

11.70

16.90

4.40

28.60

6.00

5.40

5.50

3.70

5.30

1.50

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

9.20

3.20

0.00

3.30

6.70

5.80

11.40

6.50

3.80

16.20

10.70

0.00

8.00

16.30

7.40

0.00

17.80

11.70

16.90

4.40

28.60

6.00

5.40

5.50

3.70

5.30

1.50

0.80

0.80

0.80

0.80

0.80

17.8

366.00

320.00

25.00

242.00

423.00

423.00

416.00

243.00

452.00

25.00

452.00

689.00

577.00

25.00

577.00

242.00

243.00

243.00

423.00

423.00

477.00

452.00

602.00

1291.00

577.00

577.00

504.00

15.1

12.7

10.5

9.2

9.8

10.3

9.9

8.6

9.2

14.8

10.1

10.6

10.4

15.3

11.3

10.3

10.2

11.8

10.9

12.6

10.5

14.6

11.7

9.0

11.8

11.4

9.0

0.300

0.317

0.346

0.341

0.336

0.340

0.335

0.324

0.336

0.299

0.328

0.331

0.318

0.303

0.325

0.348

0.324

0.327

0.348

2.685

12.396

2.428

6.005

6.005

8.461

6.025

3.619

2.685

1.316

10.542

3.094

1.143

2.284

3.917

5.477

1.458

9.091

1.821

1.754

1.914

1.199

1.735

0.522

U900

U1000

U1100

U1350

U1000

U900

U1500

U1500

U1350

U1500

U900

U2000

U1100

U1350

U1350

U1100

U1350

U800

2.0

2.0

2.0

3.0

5.0

3.0

3.0

5.0

3.0

3.0

3.0

2.0

3.0

2.0

3.0

4.0

4.0

3.0

4.0

4.0

2.0

2.0

1.0

1.0

1.0

1.0

1.0

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

0.013

2.562

2.389

1.972

1.843

2.552

2.107

2.415

2.552

2.233

2.233

2.731

2.415

1.843

2.894

2.233

2.991

2.991

2.415

2.991

2.128

2.562

1.720

1.394

1.394

1.216

1.394

0.984

1.952

3.876

2.287

9.225

6.965

3.234

1.343

2.297

2.294

3.961

2.297

1.343

11.894

3.961

2.893

2.893

15.000

2.893

6.058

6.058

3.961

6.058

1.551

9.225

1.873

2.287

2.287

1.325

2.287

0.567

9.03

15.60

4.52

17.58

0.58

17.55

2.20

0.44

2.11

12.83

9.45

7.76

7.76

21.01

19.16

0.88

0.88

1.12

10.59

6.38

1.47

2.89

30.35

19.45

10.46

31.83

8.51

19

9.1

3.3

6.7

5.8

11.4

6.5

3.8

The Study for Update of Hoa Lac High-Tech Park Master Plan Final Report, Supporting Report, Volume I

2-17

2.5.3 Project Cost

The direct project construction cost is estimated based on the following conditions and assumptions; however, these are subject to change in a later stage based on the further study/design result and market price.

The construction cost of the works is estimated based on the following conditions.

(1) The quantities of the works are roughly estimated based on the preliminary design.

(2) The unit prices of the work are estimated based on the prices in the similar project and converted into 2007 current price.

(3) Exchange rate: 1 USD = 120 JPY = 16,000 VND.

(4) Value Added Tax (VAT) and Import Tax are excluded.

The Study for Update of H

oa Lac High-Tech Park M

aster Plan Final Report, Supporting Report, Volum

e I

2-18

Quantity Cost(USD) Quantity Cost(USD) Quantity Cost(USD)Land Fill m3 10 4,385,253 43,852,533 8,950,409 89,504,085 13,335,662 133,356,618 Transportation Dist. 30kmLand Cut & Fill m3 5 4,899,135 24,495,677 5,952,749 29,763,747 10,851,885 54,259,424 Excavation, embankment, transportation

Total 68,348,210 119,267,832 187,616,042- 68,348,210 119,267,832 187,616,042

Quantity Cost(USD) Quantity Cost

(USD) Quantity Cost(USD)

U-shape Drain 400x400x400 m 110 240 26,400 0 0 240 26,400 including earth work U-shape Drain 450x450x500 m 120 390 46,800 0 0 390 46,800U-shape Drain 500x500x500 m 130 730 94,900 0 0 730 94,900U-shape Drain 600x600x600 m 145 2,180 316,536 0 0 2,180 316,536U-shape Drain 700x700x700 m 170 3,830 651,100 0 0 3,830 651,100U-shape Drain 800x800x800 m 185 4,900 906,500 310 57,350 5,210 963,850U-shape Drain 900x900x900 m 200 7,320 1,464,000 810 162,000 8,130 1,626,000U-shape Drain 1000x1000x1000 m 300 6,620 1,986,000 0 0 6,620 1,986,000U-shape Drain 1100x1100x1100 m 330 7,340 2,422,200 0 0 7,340 2,422,200U-shape Drain 1200x1200x1200 m 350 2,070 724,500 8,660 3,031,000 10,730 3,755,500U-shape Drain 1350x1350x1350 m 390 4,470 1,743,300 500 195,000 4,970 1,938,300U-shape Drain 1500x1500x1500 m 425 2,060 875,500 1,430 607,750 3,490 1,483,250U-shape Drain 1650x1650x1650 m 460 740 340,400 0 0 740 340,400U-shape Drain 1800x1800x1800 m 500 1,780 890,000 0 0 1,780 890,000U-shape Drain 2000x2000x2000 m 700 370 259,000 1,940 1,358,000 2,310 1,617,000U-shape Drain 2200x2200x2200 m 760 690 524,400 0 0 690 524,400U-shape Drain 2400x2400x2400 m 820 920 754,400 0 0 920 754,400

Total 14,025,936 5,411,100 19,437,0362 Outlet Structure incl. Slope Protection unit 20,000 14 280,000 2 40,000 16 320,000

3 Demolition ofExisting Pipelines

HCP 600mm - 1500mm m 12 12,000 144,000 0 0 12,000 144,000

14,305,936 5,451,100 19,757,036

Remarks

1

Installation(includingmanhole andinstallation cost)

GRAND TOTAL

Table 2.5-2 Project Cost for Land Preparation and Drainage

Drainage

No. Project Specification unit Unit Cost(USD)

Phase-1 Phase-2 TOTAL

Phase-2 TOTAL Remarks

Land Preparation

unit Unit Cost(USD)

Phase-1

1 Land Preparation

GRAND TOTAL

No. Project Specification

The Study for Update the Hoa Lac High-Tech Park Master Plan Final Repot, Supporting Report, Volume I

3-1

3. ROAD AND TRANSPORTATION SYSTEM

3.1 Outline of Original Sector Plan

In the original road sector plan, seven types of internal road were planned to cope with different requirement by various kind of land use in the HHTP such as Research and Development Zone, Residential Zone, Urban/Business Zone, etc. Road length of the internal road, which were included in the HHTP project, and the external roads, which were not included in the HHTP project, would amount to 19.8 kilometers and 13.7 kilometers, respectively, as shown in Table 3.1-1.

Table 3.1-1 Road Length by Type in the Original Master Plan

Type by ROW 50m 26m 22m 20m 14m 12m 7.5m Total I. Internal Road 1. R&D Zone 4,450 1,400 5,850 2. Center Area 0 3. High-Tech Industrial Zone 200 3,225 3,425 4. Urban/Business Zone 0 5. High Grade Residential

Zone 950 450 1,350 2,750

6. New Towns Zone 1,820 2,990 3,000 7,810 7. Sub-total 0 4,650 2,770 3,225 4,840 1,350 3,000 19,835II. External Road 6,360 6,460 850 13,670III. Others Expansion of Hanoi-Hoa Lac Highway (L=28.2km, W=12m), etc.IV. Total 6,360 11,110 2,770 3,225 5,690 1,350 3,000 33,505

In the original sector plan, the traffic demand in the HHTP was estimated at 27,000 PCU per day in 2020, and a main road with four lanes was considered as necessary to cope with the traffic demand. However, considering enough room in the planning of the HHTP, the main road was designed to have six lanes in 2020.

As for passenger transport, the development plan of a railway for electric train service between Hanoi and the HHTP was still in the master plan stage and immature, two stations were planned in the Urban/Business Zone and in the vicinity of the High-Tech Industrial Zone assuming the train passenger demand of 3,000 persons per day.

3.2 Present Condition

3.2.1 Current Development Progress

Current road development in the HHTP has been in line with land acquisition. Development status of road is shown in Figure 3.2-1. Development of roads has been delayed due to the slow progress in land acquisition. However, among the total roads of 8.7 kilometers that are to be developed under Stage 1 of Phase- 1, 6.2 kilometers have been complete or near complete. The remaining 2.5 kilometers of roads are in process of construction.

The Study for Update the Hoa Lac High-Tech Park Master Plan Final Repot, Supporting Report, Volume I

3-2

c ・

Phase-1 (810ha)Acquired Land (270ha)

Land Grading (31.5ha)

Present DevelopmentStatus of Road

A

Existing Facilities (11.5ha)

Main Road (w=50m)Sub Road (w=26m, 22m)

Source: JICA Study Team

Figure 3.2-1 Current Road Development (Stage-1 of Phase- 1)

The Study for Update the Hoa Lac High-Tech Park Master Plan Final Repot, Supporting Report, Volume I

3-3

3.2.2 Related Project

There are two ongoing key road projects that are related to the HHTP: Lang-Hoa Lac Highway and Hanoi Ring Road 3 South.

(1) Lang-Hoa Lac Highway

The project to expand the existing two-lane Lang-Hoa Lac Highway (12 meters in width), which links Hanoi and Hoa Lac, to six lanes is one of the most important road projects for development of not only the HHTP but also new satellite urban areas of Hoa Lac, Xuan Mai, and Mieu Mon. The highway is 30.169 kilometers in length from Trung Kinh bridge in Hanoi to Hoa Lac center. In the expansion and completion project for the Lang-Hoa Lac Highway, the highway will be expanded from current 12 meters to 140 meters in width, consisting of a three-lane expressway road and a two-lane frontage road in each direction.

With investment capital of VND 5,379 billion (336 million US dollars), the project is expected to be finished by the end of 2009. The Vietnam Construction and Import-Export Corporation (VINACONEX) is the investor and contractor of this project. The Lang-Hoa Lac Highway will be turned into the most modern highway in Vietnam.

(2) Hanoi Ring Road 3 South (section between Lang-Hoa Lac Highway and National Highway 5)

In the master plan proposed in HAIDEP1, the Hanoi Metropolitan Area should have eight radial roads.2 Moreover, the HAIDEP master plan includes four ring roads, none of which have been completed yet. Some of these roads can be considered as the key to the successful development of the HHTP in terms of road transportation, and therefore listed as external infrastructure for the HTTP.

By completing missing southern part of Hanoi Rind Road 3 (RR3), Lang-Hoa Lac Highway will be linked with National Highways (NH) 6, 1 (1A and 1B), and 5. Though this project is located in Hanoi, it serves as a bypass for passenger and freight traffic to and from Lang-Hoa Lac Highway. Thus, it is urgently necessary to improve this imporant access from the HHTP to the main ports in northern Vietnam such as Hai Phong and Cai Lan as well as to the main artery, NH1.

RR3 is planned as a primary six-lane road with a typical cross section of 36 meters in width. The project of RR3 South is divided into two sections: southeast section (between NH1 and NH6) and southwest section (between NH1 and Lang-Hoa Lac Highway). The southeast section3, which is about 13.5 kilometers in length, connects

1 Japan International Cooperation Agency (JICA) and Hanoi People’s Committee, The Comprehensive Urban Development Programme in Hanoi Capital City of the Socialist Republic of Vietnam (HAIDEP), Final Report, March 2007. 2 The eight radial roads are: NH1 North and South, NH5 (to Hai Phong), NH3 (to Thai Nguyen), NH2 (to Vinh Phuc), NH32 (to Phu Tho), Lang-Hoa Lac Highway, and NH6 (to Hoa Binh). 3 The project of the southeast section of RR3 is referred to as TR-08 and part of TR-01 in HAIDEP

The Study for Update the Hoa Lac High-Tech Park Master Plan Final Repot, Supporting Report, Volume I

3-4

three main radial roads, that is, NH1A, NH1B, and NH5 through three bridges and approach roads. At present only the Thanh Tri Bridge, which crosses the Hong River, is complete and in use. Total project cost for this section is some 490 million US dollars, about 70 percent of which will be provided by the Yen loan. This section is to be completed in 2011.

Meanwhile, the southwest section4, which is about 6.1 kilometers in length, connects three main radial roads, that is, NH1A, NH6, and Lang-Hoa Lac Highway. Total project cost for this section is some 356 million US dollars. At present Phase-1 of the project is complete.

3.3 Update of Sector Plan

3.3.1 Sector Development Missions, Strategies and Goals

It is necessary to develop the various infrastructures to realize the urban plans, accumulate population, and attract high-tech industries to the HHTP. Roads are particularly the most basic development infrastructures. Roads have two types of important functions, namely, transportation functions and spatial functions. First, roads should serve as the main means of transportation, supporting various kinds of activities in the HHTP. As such, the following strategies need to be considered.

• Roads should be planned as an optimum both for private road users including bicycles, motorcycles, and cars and for public transport users including bus and future UMRT passengers. It is important to design roads and lanes leaving enough space and flexibility for adjustment and redevelopment that might be necessary in the later stage.

• It is also important to make safe, comfortable road and transportation plans for all users including residents, visitors, workers, students, and heavy vehicles. In line with their major means of transport and their major destinations in the HHTP, proper separation of those different types of traffic flow should be considered.

• Apart from the original master plan, roads in the HHTP should be treated as either internal or zonal infrastructure rather than external infrastructure. Moreover, some roads that are located outside the HHTP gates are directly related to the HHTP, and thus they should be planned as “internal infrastructure” for comprehensive development.

• It is not until proper linkage to external transportation infrastructure is provided that the HHTP will become fully attractive for prospective investors. Therefore, connectivity with external transportation infrastructure, especially, adjacent Lang-Hoa Lac Highway, should be reinforced not only for road planning but also for transportation planning.

4 The project of the southwest section of RR3 is referred to as TR-07 in HAIDEP.

The Study for Update the Hoa Lac High-Tech Park Master Plan Final Repot, Supporting Report, Volume I

3-5

Second, roads should provide space for other infrastructures including water, sewerage, drainage, electricity, and communications, supporting various kinds of activities in the HHTP. As such, the following strategies need to be considered.

• Roads should provide enough underground space for utilities leaving flexibility for future development and maintenance. Width of cross sections should be based on the maximum size of utilities, and thus the number of different cross section types should be simplified.

• Some important zonal roads should be planned and developed as part of the master plan in order to make reasonable, comprehensive utility infrastructure network plans. On the other hand, smaller zonal roads may be constructed in each zone by actual developers to serve local areas, but those are not included in the master plan.

To summarize, missions, strategies, and goals for road and transportation sector are set forth as below.

Table 3.3-1 Missions, Strategies and Goals for Road and Transportation Sector

Missions To provide transportation functions to support various kinds of activities in the HHTP

To provide spatial functions for other infrastructures including water, sewerage, drainage, electricity, and communications

Strategies To design roads and lanes leaving enough space and flexibility for later adjustment and redevelopment To separate traffic flow of different types of users for safer, more comfortable transportation To include some roads located outside the HHTP gates for comprehensive road development To reinforce connectivity with external transportation infrastructure, especially, Lang-Hoa Lac Highway

To provide enough space under the roads for utilities leaving flexibility for future development and maintenance To develop some important zonal roads along with the internal roads for reasonable, comprehensive utility infrastructure networks

Goals To complete the development of road and transportation as the most basic infrastructure of the HHTP by 2012 (for Phase-1) and by 2020 (for Phase-2)

Furthermore, it is important that roads should comply with the present conditions of the HHTP, from an economic and environmental point of view. As such, the following strategies need to be considered.

• For update of the master plan network, it is necessary to make the best use of the roads that have already been constructed or are currently under construction under Stage-1 of Phase-1.

• For road planning, it is necessary to leave some critical points unchanged including infrastructure and buildings that have already been constructed, canals, rivers, and lakes. Landscape design should also be taken into consideration.

The Study for Update the Hoa Lac High-Tech Park Master Plan Final Repot, Supporting Report, Volume I

3-6

3.3.2 Planning Framework

For planning purpose, transportation can be classified into external and internal transportation infrastructures. For the HHTP, it is important to be linked with the external transportation infrastructure, while internal transportation planning should be properly designed taking into the future travel demand into consideration.

(1) Linkage with External Transportation Infrastructure 1) Lang-Hoa Lac Highway

In the expansion and completion project for the Lang-Hoa Lac Highway, the highway will be expanded from current 12 meters to 140 meters in width, consisting of a three-lane expressway road and a two-lane frontage road in each direction. Furthermore, 20-meter technical corridors have been reserved between the roads for future development of a UMRT (urban mass rapid transit) system. A typical cross section of the expanded Lang-Hoa Lac Highway is exhibited in Figure 3.3-1. Trees will be planted along both sides of the highway. There are a total of 10 interchanges5 planned on the way, and a toll plaza is to be constructed around the 21-kilometer post from Hanoi. Although the nearest interchange to the HHTP was planned just in front of the main gate (i.e. KM28+971), the current interchange plan has been canceled so far.

Source: VINACONEX

Figure 3.3-1 Typical Cross Section of Lang-Hoa Lac Highway

Since the expansion project of Lang-Hoa Lac Highway will be the most crucial for external transportation to/from the HHTP, it should be completed without any delay. Moreover, for closer linkage with the HHTP, an interchange, which directly connects the eastern sub-gate and Lang-Hoa Lac Highway, should be added (i.e., KM27+000). Furthermore, access from the main gate to Lang-Hoa Lac Highway should also be considered.

2) Urban Mass Rapid Transit Line 3 (Hoa Lac-Ba Dinh route)

In HAIDEP, an urban mass rapid transit (UMRT) is defined as a public transportation system with a large passenger capacity at more than 5,000 passengers per direction per day. It is operated at high speed and segregated from other traffic. It may include various types of rail-based system such as commuter rail, light rail transit (LRT), and subway as well as bus rapid transit (BRT) which

5 Some “interchanges” are simple grade separation connecting crossing roads with the frontage roads of Lang-Hoa Lac Highway.

The Study for Update the Hoa Lac High-Tech Park Master Plan Final Repot, Supporting Report, Volume I

3-7

can be selected depending on the demand. For example, a UMRT line can be initiated with a BRT and eventually converting it to urban rail as demand increases. The BRT must be planned in a way that its structure and land can be smoothly converted to urban rail. Alternatively, a UMRT line could be comprised of a rail-based system (where the demand is high) and a BRT (where the demand is moderate) with an intermodal facility at the connecting point.

The UMRT lines originally proposed by the Ministry of Transport (MOT) were consolidated into four UMRT lines on the basis of the future urban structure and demand in HAIDEP. UMRT Line 3 consists of two major components, Nhon-Hoang Mai route and Hoa Lac-Ba Dinh route. The former route connects the western suburb of Nhon and southeastern suburb of Hoang Mai via Hai Ba Trung, while the latter route connects Hoa Lac and Ba Dinh (transfer station with UMRT Line 2) on the southern banks of the West Lake. The latter Hoa Lac-Ba Dinh route, shown in Figure 3.3-2, runs parallel to Lang-Hoa Lac Highway and has a major interchange with the Nhon-Hoang Mai route near Daewoo Hotel on Kim Ma.

The Study for Update the Hoa Lac High-Tech Park Master Plan Final Repot, Supporting Report, Volume I

3-8

Source: HAIDEP

Figure 3.3-2 Proposed UMRT Network

Hoa Lac-Ba Dinh route of UMRT Line 3 is considered as an effective means of passenger transport connecting the HHTP and Hanoi. It is expected to promote urban development on the Lang-Hoa Lac Highway. The 20-meter technical corridors that have been reserved on Lang-Hoa Lac Highway may facilitate construction of this UMRT line. For this route, phased implementation plan with a combination of different modes of transport may be effective to satisfy current and future passenger demand. For example, this route could be initially served by a road-based BRT system and a connecting feeder bus network, especially on the Lang-Hoa Lac Highway section, and then the BRT could be gradually upgraded to a high-capacity rail-based system. For the best connectivity with the HHTP, a branch line of this UMRT route and as well as several stations should be planned in the HHTP.

(2) Travel Demand Projection within HHTP

Travel demand has been projected for the gateway trunk roads which will connect two interchanges and three HHTP gates. Projection of the traffic volume is based on the

Hoa Lac-Ba Dinh Route

Nhon-Hoang Mai Route

The Study for Update the Hoa Lac High-Tech Park Master Plan Final Repot, Supporting Report, Volume I

3-9

planned population of the HHTP. In addition, future characteristics of travel in the Hanoi Metropolitan Area projected in HAIDEP including trip rates, mode shares, and occupancy rates are taken into consideration, as shown in Table 3.3-2. Excluding public transport, future daily traffic volume on the gateway trunk roads is estimated at around 27,000 PCU per day for 2012 and around 67,000 PCU per day for 2020. Road planning should be based on these figures.

As for public transport, which consists of UMRT and conventional bus, total passengers are estimated at around 12,000 persons for 2012 and 59,000 persons for 2020, though the actual mode shares are highly dependent on the locations of the workers and students who live outside the HHTP.

Table 3.3-2 Travel Demand Projection

Trip DemandTrip

2012 2020 Rate/1,2 2012 2020Residents within HHTP 19,500 82,750 2.0 39,000 165,500

Daytime Population 85,400 218,000 - - -People from outside HHTP 65,900 135,250 2.0 131,800 270,500

Modal Split

2005 2012 2020 2012 2020Bicycle 25.3 16.0 3.8 21,053 10,279

Motorcycle 63.3 61.1 52.9 80,527 143,095Car 3.6 9.7 15.8 12,816 42,739

Truck 1.1 2.3 3.5 3,061 9,468Public Transport 6.7 10.9 24.0 14,342 64,920

Total 100.0 100.0 100.0 131,800 270,500

Traffic Demand ProjectionPCU

2005 2012 2020 2012 2020 Factor 2012 2020Passenger Car 2.02 2.02 2.02 6,345 21,158 1.0 6,345 21,158

Motorcycle 1.36 1.36 1.36 59,211 105,217 0.3 17,763 31,565Bicycle 1.13 1.13 1.13 18,631 9,096 0.2 3,726 1,819Truck 1.70 1.70 1.70 1,801 5,569 2.5 4,502 13,923

Subtotal 85,988 141,040 32,336 68,465Public Transport 17.92 23.56 30.00 609 2,164 2.5 1,522 5,410

Total 86,597 143,204 33,858 73,875

Note: /1 Excluding walk trips. /2 Source: JICA (2007) "Hanoi Integrated Development and Environmental Programme (HAIDEP)"

Daily Trips (VT) Daily Trips (PCU)

Population Daily Trips

Mode Share (%)/2 Daily Trips (PT)

Mode Occupancy Rate/2

Source: JICA Study Team

3.3.3 Sector Development Plan

(1) Internal Road Infrastructure

The following criteria have been used to define the internal road infrastructure of the HHTP:

The Study for Update the Hoa Lac High-Tech Park Master Plan Final Repot, Supporting Report, Volume I

3-10

• Main roads in the HHTP that traverse and connect different zones of land use (except for residential zones);

• Roads in the HHTP that are expected to serve major traffic to and from outside the HHTP; or

• Roads that are outside the HHTP boundary but are dedicated mainly to the traffic to and from the HHTP.

Internal road infrastructure is presented in Figure 3.3-3 along with the zonal roads. Total length of the planned internal roads sums up to approximately 21.7 kilometers. Two roundabouts are also planned in the HHTP as part of internal road infrastructure. Moreover, it should be noted that an interchange/grade separation which directly connects the frontage roads of Lang-Hoa Lac Highway and the gates to the HHTP could also be included as internal road infrastructure because most trips between Hanoi and the HHTP are planned to be made through the interchange/grade separation dedicated for the HHTP.6 There are two possible locations: one (KM28+971) in front of the HHTP main gate, and the other (KM27+000) connecting with the eastern sub-gate of the HHTP. The former is a simple grade separation providing a ramp from the HHTP to the direction of Hanoi. The latter is an interchange of which structure needs to be studied. Typical interchange types include the following:

- Cloverleaf interchange,

- Stack interchange,

- Roundabout interchange,

- Trumpet interchange,

- Diamond interchange, and

- Partial cloverleaf interchange.

Further study is necessary to determine the structure and design. It should also be noted that the structure and design should have only a marginal influence on UMRT Line 3, which may be designed and constructed later as a road or rail-based transport using the reserved zone within the right-of-way of the Lang-Hoa Lac Highway.

6 The interchange(s) can also be shared with the Phu Cat Industrial Park.

The Study for Update the Hoa Lac High-Tech Park Master Plan Final Repot, Supporting Report, Volume I

3-11

Source: JICA Study Team

Figure 3.3-3 HHTP Internal and Zonal Road Development Plan

The Study for Update the Hoa Lac High-Tech Park Master Plan Final Repot, Supporting Report, Volume I

3-12

Number of lanes for the trunk roads which connect major gates of the HHTP is considered based on the traffic demand projection in Table 3.3-2. Assuming that the standard road traffic capacity of an urban area is approximately 12,000 PCU per day per lane, necessary number of lanes should be four lanes for 2012 (Phase-1) and six lanes for 2020 (Phase-2) including both directions. Although only four lanes will be necessary in Phase-1, it is preferable to provide enough room for the forecasted traffic from the initial stage especially as the main gateway to the HHTP. Thus, six-lane roads (Type I) are planned for these trunk roads (total length of 6.7 kilometers) from the initial stage (Phase-1). Furthermore, for easier movement of heavy vehicles such as trailer trucks, enough road width may be desirable for all internal roads. Hence, four-lane roads (Type II) are planned for the rest of the internal roads (total length of 15.1 kilometers).

Typical cross sections of a 50 meter-wide, six-lane road (Type I) and a 33 meter-wide, four-lane road (Type II) are exhibited in Figure 3.3-4. The width of Type I roads is the same as that of the widest road in the original master plan. Meanwhile, sectional composition of Type II roads is essentially the same as that of the second widest (i.e., 26 meter-wide) roads in the original master plan except that a 3.5 meter-wide buffer zone is added on each side of the road in order to secure underground space for utility pipes. Both types of roads are divided by a median strip which may be used for future rail-based UMRT lines (elevated structure). Sidewalks are also provided on both sides to ensure safety of pedestrians. In the case of a six-lane road, the rightmost lane may be physically separated to be dedicated for bicycle and/or motorcycle traffic, depending on the actual traffic situation.

The Study for Update the Hoa Lac High-Tech Park Master Plan Final Repot, Supporting Report, Volume I

3-13

[Type I]

3%2%2%

110001250

Banking soil for Separator

Type I-1

82504500

3% 2% 2%

11000 12508250 4500

R.O.W = 50000

[Type II]

3%1.5%2%

Banking soil for Separator

Type II-1

350045007500

3% 1.5% 2%

3500 4500 7500 1000 1000

R.O.W=33000

Source: JICA Study Team

Figure 3.3-4 Typical Cross Section of an Internal Road

(2) Zonal Road Infrastructure

All the roads in the HHTP except for the above-mentioned internal roads can be defined as zonal roads. Trunk zonal roads should be provided at the minimum from a road network point of view (both for transportation and for utilities) as shown in Figure 3.3-3. Those trunk zonal roads are defined as Type III roads which are 29 meters wide.

Total length of the planned zonal roads is approximately 10.1 kilometers. The rest of zonal roads are to be planned and constructed by a developer or tenant in charge of each zone or lot depending on the actual demarcation of land. Overall, approximate road density, which is defined as total road length per unit area, should be close to the standard road density for each land use zone presented in Table 3.3-3.

The Study for Update the Hoa Lac High-Tech Park Master Plan Final Repot, Supporting Report, Volume I

3-14

Table 3.3-3 Standard Road Density by Land Use Type

Land Use Standard Road Density (km/km2)

Software Park 2.0

Research and Development 2.0

High-tech Industrial Area 1.0

Education and Training 2.0

Center of High-tech City 5.0

Mixed Use Area 4.5

Residential Area 4.0

Source: JICA Study Team

Typical cross section of a zonal road (Type III) is exhibited in Figure 3.3-5. Sectional composition of Type III roads is essentially the same as that of the third widest (i.e., 22 meter-wide) roads in the original master plan except that a 3.5 meter-wide buffer zone is added on each side of the road in order to secure underground space for utility pipes. Although this is the widest type of zonal road with four lanes, median strips will not be constructed for flexibility purposes. The road may be divided later by placing movable barriers depending on the traffic situation from roadside tenants or local roads. Sidewalks are provided on both sides to ensure safety of pedestrians.

[Type III]

3%1.5%2%

35003500

Type III

3% 1.5% 2%

3500 3500 7500 7500

R.O.W=29000

Source: JICA Study Team

Figure 3.3-5 Typical Cross Section of a Zonal Road

The Study for Update the Hoa Lac High-Tech Park Master Plan Final Repot, Supporting Report, Volume I

3-15

(3) Transportation

In the HHTP master plan, it is important to make safe, comfortable road and transportation plans for all users including residents, visitors, workers, students, and heavy vehicles. In line with their major means of transport and their major destinations in the HHTP, proper separation of those different types of traffic should be considered. As such, it is preferable to limit the use of the main gate only to passenger cars that are used by visitors to and residents in the HHTP. In addition, trucks and trailers should use only the eastern sub-gate which is the closest to the High-tech Industrial Zone.

As for public transport, conventional bus services (except for company buses) should end at one of the three bus terminals that are planned beside the gates, and the passengers should take shuttle buses that are provided by the HHTP. For this, at least three shuttle bus routes are proposed. Each route should connect two of the three bus terminals and the routes should eventually cover most of the areas in the HHTP. Those shuttle buses should also serve as feeder bus services for future UMRT lines connecting with Hanoi.

3.3.4 Development Issues

(1) External Road and Transportation Infrastructure

Development of the HHTP cannot be fully completed without planning adequate external infrastructure which connects with outside the HHTP. As such, external road and transportation infrastructure can be defined as infrastructure which contributes to the development of the HHTP as well as the regional economy or public goods in the Hanoi Metropolitan Area. It may include several projects of arterial roads, transit systems, and transportation facilities that have been planned in Ha Tay, Hanoi, or some other province. Although such projects are not located within the HHTP, they are crucial for development of the HHTP. Thus, the following three road and transportation projects that were explained earlier are included in the external infrastructure:

- Lang-Hoa Lac Highway,

- Hanoi Ring Road 3 South (section between Lang-Hoa Lac Highway and National Highway 5), and

- Urban Mass Rapid Transit Line 3 (Hoa Lac-Ba Dinh route).

In addition, two more projects are considered as part of the external road infrastructure that has a great influence on the development of the HHTP, namely:

- Hanoi Ring Road 4 West (section between National Highway 2 and National Highway 1A), and

- Logistic Center for the Western Hanoi Metropolitan Area.

Locations of the above projects are shown in Figure 3.3-6. Updates of the last two projects are described below.

The Study for Update the Hoa Lac High-Tech Park Master Plan Final Repot, Supporting Report, Volume I

3-16

Source: JICA Study Team

Figure 3.3-6 HHTP External Road and Transportation Development Projects

1) Hanoi Ring Road 4 West (section between National Highway 2 and National Highway 1A)

In the HAIDEP network, Hanoi Ring Road 4 (RR4) performs as the outer ring road in the urban road network, which aims to enhance the connectivity among suburban centers surrounding Hanoi CBD and to create a bypass around Hanoi, thereby minimizing the need for inter-provincial through traffic from entering the city center. Moreover, RR4 functions as a physical barrier to control urban sprawl, as it creates a boundary for the Hanoi urban growth region as proposed in the HAIDEP urban development plan for Hanoi. While RR3 runs in the urban area of Hanoi, RR4, which is located on the periphery of the Hanoi Metropolitan Area, is expected to serve as a more effective interface between urban and regional transportation in the long term. Without RR4, the future urban development orientations in HAIDEP would not be realized.

For this purpose, high level of service (i.e., high speed and access control) is required of RR4. Thus, it is proposed that RR4 should be developed as an expressway, initially with four lanes. RR4 proposed in HAIDEP is almost an entirely newly built road, except for sections overlapping NH2. In the HAIDEP urban transportation master plan, RR4, which is about 100 kilometers in length, is located around 15-20 kilometers from the city center and 5-8 kilometers from RR3.

RR4 West is the western segment of the fourth ring road of Hanoi proposed in the HAIDEP master plan, and is scheduled for operation by 2013. Pre-feasibility study of RR4 West was also conducted in HAIDEP. RR4 West starts from NH2 in

The Study for Update the Hoa Lac High-Tech Park Master Plan Final Repot, Supporting Report, Volume I

3-17

Noi Bai in the north and ends on NH1A in Thanh Tri in the south for a total length of 45.35 kilometers, traversing the boundaries of Hanoi, Vinh Phuc, and Ha Tay provinces. This segment, which is directly connected to Lang-Hoa Lac Highway, is also closely related as a more efficient regional transportation route from the HHTP northward to Noi Bai and south/westward to the national trunk highway (NH1) as well as the main ports in northern Vietnam. The role of this segment is expected to become even more important if a logistic center for the Western Hanoi Metropolitan Area, which is another external infrastructure for the HHTP, is developed on RR4 West.

HAIDEP suggests that a four-lane divided cross-section would be sufficient. The median will be enlarged to reserve space for additional two lanes for future expansion. In addition, frontage roads will be provided along the sides of RR4 West to offer access to developments along its corridor. As such, the typical cross section of RR4 West is 80 meters in width. RR4 West will feature six interchanges on NH2, NH23, NH32, Lang-Hoa Lac Highway, NH6, and NH1.

RR4 West is estimated to cost 639 million US dollars, which includes construction, engineering, contingency, and land. Land cost is 128 million US dollars or 20 percent of project cost. A breakdown of the total project cost per section is shown below:

- Package 1 (NH1 – NH6), 12.8 kilometers: 134 US million dollars,

- Package 2 (NH6 – Red River), 15.0 kilometers: 160 US million dollars,

- Package 3 (Red River Bridge including approaches), 7.1 kilometers: 235 US million dollars, and

- Package 4 (Red River – NH2), 10.5 kilometers: 109 US million dollars.

2) Logistic Center for the Western Hanoi Metropolitan Area

For freight transportation, in the HAIDEP master plan, a total of four logistic centers have been planned for north, south, east, and west of the Hanoi Metropolitan Area. All the four logistic centers, with services such as storage, consolidation, depot, customs clearance, and bonded transportation, have been planned along RR4, which is an important arterial road for the future of Hanoi in terms of both managing urban growth and establishing an effective interface between urban and regional transportation. Among others, the logistic center for the western Hanoi Metropolitan Area will be very important for the HHTP as freight to and from Hoa Lac should be transported through this logistic center.

In HAIDEP, location of the logistic center for the western Hanoi Metropolitan Area is planned beside RR4 near the interchange with NH6 as shown in Figure 8.3-4. Although this location may be good for connectivity with railway, the location is still tentative and it may be moved westward toward Lang-Hoa Lac Highway. In any case, this logistic center is expected to serve as a base for transportation of goods and commodities between the HTTP and the main ports in

The Study for Update the Hoa Lac High-Tech Park Master Plan Final Repot, Supporting Report, Volume I

3-18

northern Vietnam such as Hai Phong and Cai Lan and for other long-distance or international freight transportation. A detailed study will be necessary to select the site, determine the scope and size (including customs houses, banks, shipping company offices, inspection companies, and bonded warehouses), design the facility, and investigate its project feasibility of the logistic center.

The above-mentioned five external road and transportation infrastructure projects for the HHTP are summarized in Table 3.3-4.

Table 3.3-4 Summary of the HHTP External Road and Transportation Infrastructure

Infrastructure Location Completion Year

Cost (million US$)

Feasibility Study

Lang-Hoa Lac Highway Ha Tay, Hanoi 2009 336 F/S done

Hanoi Ring Road 3 South (section between Lang-Hoa Lac

Highway and NH5) Hanoi 2011/1 846 F/S done

Hanoi Ring Road 4 West (section between NH2 and

NH1A)

Ha Tay, Hanoi,

Vinh Phuc 2013 639 PreF/S done

Urban Mass Rapid Transit Line 3 (Hoa Lac-Ba Dinh route)

Ha Tay, Hanoi Unfixed Unfixed No

Logistic Center for the Western Hanoi Metropolitan Area Ha Tay Unfixed Unfixed No

Note: /1 Southeast section (between NH1 and NH6) only. Source: JICA Study Team

(2) Other Infrastructure

The Northern Phu Cat Industrial Park (NPIP) with total development area of 1,507 hectares (1st phase: 307 ha, 2nd phase: 1,207 ha) is located on the south of the HHTP across Lang-Hoa Lac Highway. It is expected that supporting industries for the HHTP High-Tech industries should be located in this Industrial Park, and both HHTP and NPIP could share common external infrastructure such as Lang-Hoa Lac Highway. An interchange connecting the HHTP and the frontage roads of Lang-Hoa Lac Highway can also connect the NPIP. Hence, the development of the HHTP is closely related to the development of the NPIP.

The layout of the NPIP is shown in Figure 3.3-7. At present, about 250 hectares of the land for 1st phase has been developed and two factories (brick manufacturer and glass fiber reinforced pipe manufacturer) are operating and about 10 enterprises are under process of investment application according to VINACONEX. As for the eastern boundary road, it is currently under construction and will be developed as a provincial road. This 42 meter-wide road will also serve the reserved area for future expansion of the HHTP, which is located on the east of the NPIP. One of the planned interchanges/ grade separations for the HHTP is this location, connecting this road with Lang-Hoa Lac Highway and the HHTP eastern sub-gate as shown in Figure 3.3-3 (Location B).