The United Republic of Tanzania Millennium Challenge Account - Tanzania
Consulting Services For Energy Projects
Pre Bid Conference Meeting 28th January 2008
2
Disclaimern Information provided in this presentation is an abridged version
of the information in the RFP. Consequently, the RFP and TOR supersede this presentation
3
Presentationn Backgroundn The Role of Consulting Engineern Phases of Contract Activitiesn Project Informationn Procurement and Contracting
Background
5
Objective of MCC Programn The grant received by the Government of the United Republic of
Tanzania from the U.S. Government, Millennium Challenge Corporation (MCC) will be used for investments in transport, energy and water sectors to:
t Stimulate economic growtht Increase household incomet Reduce poverty
6
Due Diligence and Project Selection
Meet MCCEligibility Criteria Countries Develop
and Submit Proposals
MCC Due Diligence,Approval by Investment
Committee, Compact Signed
Implementation,Monitoring &
Evaluation
Must satisfy 17 criteria on an on-going basis:
ß Good governance (6)ß Sound economic
policies (6)ß Investment in people
(5)
Home-grown proposals focus on:
ß Constraints analysisß Consultative
(participatory) process that engages civil society
ß Technical and economic feasibility
ß Social and environmental sustainability
Due diligence ensures compact is based on:
ß Institutional capacity to implement the projects
ß Requirements for long term sustainability of projects (e.g. tariff restructuring, increase O&M funds) are met
ß An enabling policy environment exists
Project implementation and M&E to ensure:
ß Transparent and competitive procurement
ß Monitor and evaluate project and program level indicators
ß Focus on economic growth and impact on beneficiaries
7
Energy Project Activities
n Distribution Systems Rehabilitation and Extension Activity in Six Regions (the “T&D Project”)
n Malagarasi Hydropower and Kigoma Distribution Activity (the “Hydro Project”)
n Zanzibar Interconnector Activity (the “Cable Project”)
8
Project Implementation Structure
MCC(HQ & Country Team)
MCA-Tanzania(Accountable Entity)
Accountable Entity Agreement
TANESCO(Implementing Entity - Energy)
Implementing Entity Agreement
Strategic Planning & Projects
Procurement Management Unit
6-Region T&DMalagarasi Hydro
&Kigoma Mini-Grid
Zanzibar 2nd Interconnector
Mbeya&
IringaDodoma Morogoro Tanga Mwanza Access
Road Sub-Sea Cable &
Overhead Extensions
Specifications and TORs
Oversight, monitoring and supervision on behalf of TANESCO
Engineering Consultantand EPC Construction
Supervisor
Independent Engineer
Contract
Technical consulting, supervision and capacity building
RFP for T&D Activities
TANESCO User Departments
EPC Contract Supervision on behalf of MCA-T
User Departments
TANESCO & ZECO
PowerProject
ExternalProcurement
Advisor
RFP for Cable and Hydro Activities. Procurement oversight, advice and assistance
ESA Oversight
MCC(HQ & Country Team)
MCA-Tanzania(Accountable Entity)
Accountable Entity Agreement
TANESCO(Implementing Entity - Energy)
Implementing Entity Agreement
Strategic Planning & Projects
Procurement Management Unit
6-Region T&DMalagarasi Hydro
&Kigoma Mini-Grid
Zanzibar 2nd Interconnector
Mbeya&
IringaDodoma Morogoro Tanga Mwanza Access
Road Sub-Sea Cable &
Overhead Extensions
Specifications and TORs
Oversight, monitoring and supervision on behalf of TANESCO
Engineering Consultantand EPC Construction
Supervisor
Independent Engineer
Contract
Technical consulting, supervision and capacity building
RFP for T&D Activities
TANESCO User Departments
EPC Contract Supervision on behalf of MCA-T
User Departments
TANESCO & ZECO
PowerProject
ExternalProcurement
Advisor
RFP for Cable and Hydro Activities. Procurement oversight, advice and assistance
ESA Oversight
The Role of Consulting Engineer
10
Consulting Engineer and Supervisorn MCA-Tanzania (MCA-T), as the “employer” intends to hire a
consulting firm based on the Quality and Cost Based Selection (QCBS) to provide the following services:
t Engineering Consulting Servicest Construction Supervision of EPC Contractst Needs Assessment for Capacity Building, Implementation of
Technical Assistance (TA) Activities, and Assistance to MCA-T and TANESCO in the management of specialist TA firms
11
Engineering Consulting Servicesn Carry out supplementary field work, surveys, data collection,
technical studies and preliminary designs so that tenderers can bid with increased confidence
n Develop technical sections of the EPC tender and contract documents for the three Energy Project Activities
n Complete the design, and develop technical sections of the tender and contract documents for the access road to the Hydro Project. Assist MCA-T and TANESCO during contracting of the access road civil contractor
n Work with and assist MCA-T and TANESCO as necessary during the contract period for the successful implementation of the three Energy Projects Activities
12
Construction Supervisionn Review design, monitor construction progress, and check quality
of the various EPC contract activities under the three Energy Project Activities. Activities include but not limited to:t In-factory inspections if/when neededt Site construction activitiest Supervision of commissioning and testst Health, safety and environmentt Review and monitor schedulet Budgetary controlt Progress reportst Disputest Defects notification period
13
Technical Assistance and Implementation
n Needs assessment for institutional development and capacity building at TANESCO and ZECO (a sample of possible specialised technical assistance topics are listed in the TOR of the RFP, Section 2.2.16)
n Design and implement three (3) Technical Assistance (TA) activities per year on topics identified through needs assessment (generally outlined in Section 2.2.16(1))
n Assist MCA-T and TANESCO in hiring and managing specialist TA firms for special TA activities as identified during needs assessment. Assist TANESCO and ZECO in the implementation of additional TA activities (as outlined in Section 2.2.16 (2)) performed by specialist firms
Phases of Contract Activities
15
Phase I
Phase II
6-9 months609(g) funding
5 YearsCompact funding
Exercise option
Phase I
Phase II
6-9 months609(g) funding
5 YearsCompact funding
Exercise option
Contract Timing and Sequencing
16
n Generally includes preparatory work needed to improve the overall schedule prior to issue of tenders for the various EPC contracts (see Section 1.3.1 of the TOR)
n Pre-construction studies, surveys (in order to confirm various engineering factors of the project) and preliminary designs
n Obtain data and information needed for the tenderer to quote with higher degree of confidence
n The work products developed during this phase should lead to the preparation of EPC tender packages in Phase II
Phase I Activities
17
Phase II Activitiesn Expected to cover all the works needed after Phase I to ensure
successful completion of the three Energy Project Activities andTechnical Assistance activities
n General tasks to be completed under this phase are listed in Section 1.3.2 of the TOR
n Specific tasks to be completed under this phase are listed in Sections 3, 4 and 5 of the TOR
Project Information
19
Project Locations and Access
Zanzibar transmission
T&D System Upgrade
Malagarasi hydro and mini-grid
T&D Project Activity
21
T&D Project Descriptionn The T&D Project is spread across six (6) regions:
n Two major activities under this project include:t Up to 257 network extension project activitiest Up to 22 distribution system upgrade and rehabilitation
project activities
t Mwanzat Tangat Morogoro
tMbeyat Iringat Dodoma
22
Network Extension Activityn A total of up to 257 small network extension activities have been
planned
RegionLV Line Service Line
km of 33 kV km of 11 kV
km of LV Line
No of Services No of 50 kVA Trnf S/S
No of 100 kVA Trnf S/S
No of 200 kVA Trnf S/S
No of 315 kVA Trnf S/S
No of 500 kVA Trnf
S/STanga 16.1 30.7 155.8 4,737 31 16 7 1Dodoma 426.0 102.1 156.3 8,249 18 57 33 7Morogoro 374.3 13.1 358.1 11,699 6 62 37 4Iringa 469.0 14.0 108.0 3,820 30 35 8 2Mwanza 737.0 18.0 262.0 12,521 4 34 52 12 3Mbeya 14.1 11.7 29.5 2,450 7 11 2
Totals 2,036.5 189.6 1,069.6 43,476 89 211 148 26 5
Scope of WorkHV Line Distribution Transformer Substations
23
Upgrade and Rehabilitation Activityn Up to 23 distribution system upgrade and rehabilitation activities
have been planned
Region 220 kV Bays
220/33 Trans
132 kV Bays
132/33 Trans
33 kV Line Bays
33 kV Single
Busbars
33/11 Trans
50 kVA Aux Trans
33 kV Line (km)
33 kV Volt Reg
11 kV Line Bays
Control & Prot, AC/DC and SCADA
Civil Works
Tanga - - 2 2 17 3 1 3 - - 4 11 4 Dodoma - - - - 6 - 2 2 15 - 11 6 5 Morogoro 1 1 - 6 - 3 - 20 1 4 9 4 Iringa - - - - 9 1 1 - 9 - 2 2 2 Mwanza - - - - 5 - 4 2 73 - 11 6 4 Mbeya - - - - 7 1 1 2 20 - 13 5 2
Totals 1 1 2 2 50 5 12 9 137 1 45 39 20
24
Phase I –T&D Projectß The main Phase I tasks under the T&D Project include, but
not limited to:t Complete necessary technical studies, field work, data
collection, routing surveys and mapping, and develop performance/technical specifications necessary for standard EPC contracts
t Carry out Environmental Impact Assessment (EIA) or Environmental Assessment (EA) and develop Environmental Management Plans (EMPs) as necessary.
t Prepare resettlement framework as necessaryt Prepare the draft technical documents for the tender
packages
25
Phase II –T&D Projectß The main Phase II tasks under the T&D Project include, but not limited
to: t Complete technical documentation for EPC bidding packaget Provide technical inputs and assist the Procurement Agent (PA)t Assist PA in preparing short list of pre-qualified tendererst Assist PA in developing contractors’ selection criteriat Assist during technical evaluation process of contractors’ bidst Perform construction supervision and quality control activitiest Carry out factory inspection where necessaryt Ensure contractors finalize health and safety, HIV/AIDS prevention
awareness plans t Prepare monthly progress reportst Supervision of testing and commissioningt Develop and implement TA activities based on needs assessment
targeted to the T&D sector
26
Access to T&D Project Locations n Distribution System
Rehabilitation and Extension Activity. Distance from Dar es Salaam:
City KMt Tanga 384t Morogoro 200t Dodoma 458 t Iringa 552 t Mbeya 882 t Mwanza 1,191
Note: All regions can be reached by all-weather tarmac roads. Mwanza can also be reached by air. Chartered flights are available to all sites.
Morogoro
27
Upgrade and Rehabilitation Examples
Cable Project Activity
29
Cable Project Descriptionn The Cable Project has five main components:
t Upgrade at Ubungo substation to accommodate higher capacity or additional 132kV or 220kV feeder
t Ubungo to Ras Kiromoni (132kV double circuit or 220kV single circuit, along existing route using compact design)
t Ras Kiromoni to Ras Fumba submarine cablet Ras Fumba to Mtoni via existing route and deviations to
avoid settlements and religious structurest Mtoni substation upgrade and expansion
30
Proposed Project Scope
31
Phase I –Cable Project ß In Phase I the CE shall:
t Carry out a sea-bed survey to determine suitability of installing a second submarine cable alongside the existing 45 MW cable
t Develop and carry out surveys for the overhead transmission lines and substations
t Prepare performance specifications for the supply and installation of the submarine cable to enable submission of pre-qualification documents by manufacturers and contractors
t Develop and undertake environmental audit of existing cable followed by ESIA and EMP
t Develop and undertake RAPs as necessaryt Draft the technical sections of the tender document for use in
Phase II
32
Phase II –Cable Projectß In Phase II the CE shall:
t Complete technical documentation for EPC bidding packaget Provide technical inputs and assist the Procurement Agent (PA)t Prepare short list of pre-qualified tendererst Assist the PA in developing contractors’ selection criteriat Assist during technical evaluation process of contractors’ bidst Be responsible for construction supervision and quality controlt Carry out factory inspectiont Ensure contractors finalize health and Safety, HIV/AIDS
prevention awareness plans t Prepare monthly progress reportst Be responsible for supervision of testing and commissioningt Develop and implement TA activities for TANESCO and ZECO
33
Access to Cable Projectn Distance to Unguja Island
approximately 40km from Dar
n Unguja can be accessed by express boat or by air
34
Existing 132kV line to Zanzibar
35
Exiting Cable at Ras Kiromoni
36
Cable Landing Site (Ras Fumba)
37
Overhead Line in Urban Area
38
Mtoni Substation (Zanzibar)
Hydro Project Activity
40
Hydro Project Descriptionn The Hydro Project has three major components:
t Access roadt Dam and 8MW ROR power plantt 33kV T&D network in Kigoma, Kasulu and Uvinza
41
Malagarasi River - Igamba Falls
890m
863m
840m
Canal
Canal
805m
Penstock
Penstock
STAGE I STAGE II STAGE III
9200m 1900m 3100m
42
Proposed Network Expansion
KigomaNetwor k
Exist ing
& TPP
33/ 11kVSubst ation
MalagarasiHPP
To Uvi nza
Recloser
To Kasul aSingl e Circui t Line SelectableFrom Doubl e Circui t
33kV Double Ci rcui t
43
Ki g o m a A i rp o r t
Sim b o
M ah em b e
Ka l en g e
M a lag ar as i H PP
Uv in z a
M at en d o
Kw aj a Ru sesa
Ka z an g es i
M u z y e
Bu g ag e
N y u m b i g w a
N y am t areKa su la
Ka m ar a
Ki d ah w e
Ki t o n g o n i
Ki g o n d oRu f i t i
N y an sh a
La lam b e
T i t y eN y en g e
Sa l t M in esN y an z a
Ch ak u l u
T an d a la M alag ar asi
Il a lan g u ru
Bu y en z eSeb ag u s i
Ka g o n g o
Ka h am aBu so n d o
Ka lam a
T PP
Proposed T & D Network
• 3 new Substations
• 392km of new 33kV Line
• 171km of new LV Line
• 46 Transformers
• 6,230 Connections
44
Phase I –Hydro Projectn The CE shall carry out:
t Survey, plan, design, prepare technical specification for the access road and bridge construction
t T&D system analysis (load-flow study)t T&D line route surveyt Topographical survey for damt Geotechnical site investigation t Hydrological studiest ESIA and prepare RAPt Draft preliminary engineer design of power plantt Draft technical documentation for EPC, including
performance specifications of both hydro and T&D sub-components
45
Phase II –Hydro Projectß In Phase II the CE shall :
t Complete technical documentation for EPC bidding packaget Provide technical inputs and assist the Procurement Agent (PA)t Prepare short list of pre-qualified tendererst Assist the PA in developing contractors’ selection criteriat Assist during technical evaluation process of contractors’ bidst Undertake site supervision and quality controlt Carry out factory inspectiont Ensure contractors finalize health and safety, HIV/AIDS
prevention awareness plans t Prepare monthly progress reportst Be responsible for supervision of testing and commissioningt Carry out all technical work for institutional arrangements and
operator concession of the Kigoma mini-grid
46
n Distance to Kigoma is 1,620kmt Can be accessed by rail/air/roadt Distance from Kigoma to Malagarasi is about 100 km
n Access from Kigoma to Malagarasi site is through a rough road that requires a four 4WD vehicle
Access to Hydro Project
47
Dam Site at Malagarasi River
48
Igamba Falls
Procurement and Contracting
50
Estimated Project TimelineYEAR
Preparatory Works: All three projectsTechnical studies and surveyESIA and RAPPreliminary designTOR for EPC bid package
Construction works:Tedering: access road (Hydro project)
Access road construction
Final EPC bid packages
Tendering and contract signing
In-factory Inspection Tests
Capacity building workshopsTOR for Third Party Technical AssistanceTesting and comissioning of all three projectsFinal certificate after defect notification period
PHASE I PHASE II
2008 2009 2010 2011 2012 2013
51
n The proposal shall be delivered at the address stated in the data sheet of the RFP not later than 2:00 pm local time on March 6, 2008.
n Proposal must be submitted as follows:t One original and five (5) copies of the technical proposalt One original and five (5) copies of the financial proposalt CD ROM of the technical proposal
Note: more details available in the data sheet of the RFP
Proposal Submittal
52
n The proposal will be evaluated based on QCBS as stated in the data sheet of the RFP. The following criteria will apply:
1. Organizational capability, experience and past performance
2. Submitted proposal technical approach, work plan and schedule, management plan and facilities/equipment
3. Key staff capabilities, experience and past performance
Note: Sub-criteria and scores for each of the above are listed in the data sheet of the RFP.
Evaluation and Selection
53
n Clarifications may be requested up to 14 working days before the RFP submission date, i.e. by 18th February at the following address:
The Chief Executive OfficerMillennium Challenge Account - TanzaniaDevelopment HouseKivukoni Front/Ohio Street,P.O. Box 8327Dar es SalaamTanzaniaAttention: Marieth s. Ngaida, Director of Procurement, MCA-TFax: +255 22 2124644 e-mail: [email protected]