time & motion study
DESCRIPTION
TRANSCRIPT
4/11/2013
© Copyright 2013 Anupam Kumar 1
Time & Motion Study
Presented By:
Anupam Kumar
Reader
SMS Varanasi.
Email: [email protected]
1© Copyright 2013 Anupam Kumar
Time & Motion Study
• Frederick W. Taylor and his followers developed and
refined the Time Study
• A method created to determine the ‘correct time’ it
takes to complete a certain task
• Frank B. Gilbreth and his wife Lillian developed and refined the Motion Study
• A method to establish ‘the one best way to perform a task’
• Historically the two studies are discussed individually, today they generally are discussed as one
2© Copyright 2013 Anupam Kumar
Time Study
• It is a work measurement technique
– for recording the times and rates of working
– for the elements of a specified jobs,
– carried out under specific conditions
– for analyzing the data
– so as to obtain the time necessary
– for carrying out the job
– at an defined level of performance.
3© Copyright 2013 Anupam Kumar
Motion Study
• It is the science of eliminating wastefulness resulting from using– unnecessary,
– ill-directed and
– inefficient motion.
• The aim of the study is to find and perpetuate the scheme of least waste methods of labour.– Workers do not enjoy making unnecessary or wasted
motions, as they result in needless fatigue.
– Motion study thus helps in reducing fatigue & waste motions.
4© Copyright 2013 Anupam Kumar
Use of Time & Motion Study
• Historically:
– T&M Studies were used in the manufacturing industry to
evolve pay scales with the thought that money was the
only motivation for work.
• Today:
– T&M Studies can be effective for performance evaluations
– T&M Studies can be used for planning purposes in order to predict the level of output that may be achieved
– T&M Studies can be used to uncover problems and create solutions
– T&M Studies can be used for time cost analysis
5© Copyright 2013 Anupam Kumar
Objectives of Time & Motion Study
• Estimation of realistic manpower
requirement.
• Comparison of alternative methods of
working.
• Establishment of incentive schemes
• Improved control over operations.
• Proper work distribution.
• Future manpower and cost forecasting.
6© Copyright 2013 Anupam Kumar
4/11/2013
© Copyright 2013 Anupam Kumar 2
Steps Involved in T&M Study
• Selection
• Obtain all necessary information
• Divide the job into job-elements
• Time each element
• Number of cycles to be timed
• Rate the operator
• The rating of the operator to be objective
• Make provisions for allowances.
7© Copyright 2013 Anupam Kumar
Job Element
• Should be as short as possible and should be conveniently timed.
• Should be unified and should have logical sequence of basic motions.
• Constant and variable elements should be separated for generation of data for subsequent studies.
• Regular and Irregular elements should be separated so as to provide for time allowances.
• Elements involving heavy and fatigue work should be separated to allow for proper allowances.
8© Copyright 2013 Anupam Kumar
Determination of Times
• Standard Time
– It is the time required
– by an operator of average skill
– who expends an average amount of effort and
– is working under average conditions.
• Use of Standard Time
– To establish minimum performance requirements
– Control of labour cost
– Planning wage incentive schemes
– Product line balancing.
9© Copyright 2013 Anupam Kumar
Determination of Times
• Performance Rating
– It is the pace of the actual work being done as a
percentage of the standard pace of doing the same work.
• Level of Performance
– It is the rate of output achieved by a qualified worker as an
average for the day.
• Normal Time
– It is the productive time needed to perform a task, utilizing
appropriate work methods, work area layout and
performing at a pace the firm defines as normal.
10© Copyright 2013 Anupam Kumar
Determination of Times
• Actual Time
– It is the time actually taken in completing the desired task.
– If the operator works at 100% efficiency then the actual time would be equal to the normal time.
• Use of Actual Time
– In method study
– In plant layout planning
– In setting realistic starting and finishing times for operator.
11© Copyright 2013 Anupam Kumar
Determination of Times
• Allowance
– Standard times for elements or jobs are necessary to
provide for allowances for compensating fatigue, personal
needs, contingencies, etc.
– These are generally given as a percentage of the standards
time or normal time.
– If allowance is given as a percentage of normal time
• Standard Time = Normal Time (1+Allowance)
– If allowance is given as a percentage of standard time
• Normal Time = Standard Time (1 – Allowance)
12© Copyright 2013 Anupam Kumar
4/11/2013
© Copyright 2013 Anupam Kumar 3
Allowances or Time Allowances
• Relaxation Allowance
– For fatigue and personal needs
• Contingency Allowance
– For duties of periodic nature
• Tools and Machinery Allowance
– For adjusting machines, sharpening tools, etc.
• Reject Allowance
– Time used up in producing items which turn out to be defective
• Interference Allowance
– Stoppage of 2 or machines
• Excessive Work Allowance
– Due to unforeseen temporary changes
13© Copyright 2013 Anupam Kumar
Illustration 1
• How many working minutes do you expect
would take a worker to produce a part for
which
– the time standard is 10 minutes,
– if the allowance for this work is 25% of the normal
time and
– the worker is rated at 80%?
Click for Solutions
14© Copyright 2013 Anupam Kumar
Solution to Illustration No. 1
Standard time = 10 Min
Allowance = 25% of N.T.
ST = NT (1+All.)
⇒NT = ST / (1 + All.)
⇒NT = 10/(1+25%)
⇒NT = 8 Min
Performance Rating = (Normal
time) / (Observed time)
⇒OT = NT / (Per. Rating)
⇒OT = 8/(80%)
⇒OT = 10 Min.
Standard time = 10 Min
Performance Rating = 80%
Actual time = ST/Per. Ratg
⇒AT = 10/(80%)
⇒AT = 12.5 Min.
Actual time = Observed time
*(1+All.)
⇒OT = AT / (1+ All.)
⇒OT = 12.5 / (1+25%)
⇒OT = 12.5 X 4/5
⇒OT = 10 Min.15© Copyright 2013 Anupam Kumar
Illustration 2
• Calculate the standard production per shift of
8 hours duration, with the following data.
– Observed time per unit = 5 minutes
– Rating factor = 120%
– Total Allowance = 33.33% of normal time.
Click for Solutions
16© Copyright 2013 Anupam Kumar
Solution to Illustration No. 2
OT = 5 Min
Per. Ratg. = 120%
All. = 33.33% of NT
NT = OT * Per. Ratg.
⇒NT = 5 X 120/100
⇒NT = 6 Min.
ST = NT (1+ All.)
⇒ST = 6 (1+33.33%)
⇒ST = 6X4/3
⇒ST = 8 Min.
8 Min. is needed for 1 Unit
⇒ 1 Min. is needed for 1/8 unit
⇒ 8 Hrs. is needed for 8 X 60/8
Units
⇒ 8 Hrs. is needed for 60 units.
• The standard production
per shift is 60 Units.
17© Copyright 2013 Anupam Kumar
Methods of Time Estimation
• Study of Past Production Records
– It is an invaluable source of information regarding
the time taken to perform a particular task.
– It is however assumed that the nature of activities
performed in the process does not change over
the period of time.
• Estimation Method
– It involves the analysis based on the experience &
judgment of the observer.
18© Copyright 2013 Anupam Kumar
4/11/2013
© Copyright 2013 Anupam Kumar 4
Work Measurement Techniques
• Direct Time Study Methods
– Analytical Estimation
– Work Sampling
• It is based on statistical estimation of work during various time samples.
• Indirect Time Study Methods
– Synthetic Timing Data
• It is based on the previous data available with the establishment which helps in synthesizing the overall data
– Predetermined Motion Time Studies (PMTS)
• It is based on the standard data available based on the various micro motion studies.
19© Copyright 2013 Anupam Kumar
Illustration 3
• Calculate the standard time per article produced
from the following data obtained by a work sampling
study.
– Total No. of observations = 2500
– No. of working observations = 2100
– No. of units produced in 100 hours duration = 6000
– Proportion of manual labour = 2/3
– Proportion of machine time = 1/3
– Observed rating factor = 115%
– Total allowance = 12% of normal time.Hint
20© Copyright 2013 Anupam Kumar
Hint for Illustration 3
• Actual Working time in 100 hours = 100*2100/2500 = 84
• Time taken per article = 84*60/6000 = 0.84 Min.
• Observed Manual time = (2/3) * 0.84 = 0.56 Min.
• Observed Machine time = (1/3) * 0.84 = 0.28 Min.
• Normal Labour time = Observed Manual time * Rating Factor
= 0.56 * 1.15
• Standard Labour Time = (0.56*1.15) * (1+ 12/100)
= 0.56*1.15*1.12
• Standard time per unit = Standard Labour Time + Observed Machine Time
21© Copyright 2013 Anupam Kumar
Illustration 4
• After application of work simplification techniques and a
direct time study of elements the following time elements in
minutes were obtained as in table below.
Job
Element
Cycle
1 2 3 4 5
1 0.16 0.12 0.13 0.15 0.24
2 0.60 0.60 0.60 0.60 0.60
3 0.33 0.50 0.35 0.37 0.35
4 0.50 0.50 0.50 0.50 0.50
5 0.24 0.24 0.25 0.27 0.25
22© Copyright 2013 Anupam Kumar
Illustration 4 (Contd.)
• The following information was also determined about the job.
– Job Element 2 & 4 are machine controlled and cannot be speeded up
by the operator
– There were 2 irregular occurrences while timing.
– The operator was rated at 110% when working.
– Personal allowance – 30 min/day; Unavoidable delays – 20 min/day &
Fatigue 10% of the operator’s actual physical time.
– Shift is 8 hour long.
• Calculate standard time per unit & shift output standard.
Hint
23© Copyright 2013 Anupam Kumar
Hint for Illustration 4
• Identify the Irregular occurrences.
• Calculate the average time for each job element.
• Calculate Normal Time and then Standard Time by using the
data given for allowances.
Job
Element
Cycle Ave.
Time1 2 3 4 5
1 0.16 0.12 0.13 0.15 0.24 0.14
2 0.60 0.60 0.60 0.60 0.60 0.60
3 0.33 0.50 0.35 0.37 0.35 0.35
4 0.50 0.50 0.50 0.50 0.50 0.50
5 0.24 0.24 0.25 0.27 0.25 0.25
24© Copyright 2013 Anupam Kumar
Solution
4/11/2013
© Copyright 2013 Anupam Kumar 5
Solution for Illustration No. 4
OTJE1 = 0.14
⇒NTJE1 = OTJE1 X Per. Rat.
⇒NTJE1 = 1.4 X 110/100
⇒NTJE1 = 1.54
Similarly,
NTJE3 = 0.385
NTJE5 = 0.275
NTmanual = 0.814
Tmanual = 0.814 * 1.10 = 0.8954
NTtotal = Tmanual + Tmachine
NTtotal =0.8954+0.50+0.60 =
1.9954
ST = NTtotal / (1 – AllowanceST)
Allowance = (30 + 20) / (8 * 60)
Allowance = 0.104167
ST = 1.9954 / (1- 0.1042)
ST = 1.9954 / 0.8958 = 2.227
min
Standard Time = 2.23 minute
Shift Output = 8 * 60 / 2.23
Shift Output = 215.25 Units.
© Copyright 2013 Anupam Kumar 25
Illustration No. 5
• An operator manufactures 50 jobs in 6 hours
and 30 minutes. If this time includes the time
for setting the machine. Calculate the
operator’s efficiency. Standard time allowed
for the job is as follows.
© Copyright 2013 Anupam Kumar 26
Sr. No. Job Element Details
1. Setting Time 35 minutes
2. Production time per piece 8 minutes
Solution
Solution for Illustration No. 5
• 50 Jobs in 6 hours and 30 minutes
⇒50 Job in (6*60 +30) minutes = 390 minutes
• Standard Time = Setting time+Production time
⇒S.T. = 35 + 8*50 = 35 + 400 = 435 minutes
• Per. Rating = Standard Time / Actual time
⇒Per. Rat. = (435 / 390)*100 = 111.5%
© Copyright 2013 Anupam Kumar 27
Illustration 5
• Time data taken for a bulk filling activity in Bangalore were recorded on a
continuous basis as shown below.
• The firm’s labour contract requires a 15% allowance based on total time
for all workers on the bulk filling line
• Compute the standard time for this activity.
Cycle Time (in Sec.) Rating
Factor
1 2 3 4 5
Grasp Bag 4 37 74 105 338 120
Locate for fill 16 51 84 117 352 120
Machine Fill 26 61 94 127 362
Set on Conveyor 34 68 102 334 369 110
28© Copyright 2013 Anupam Kumar
Hint
Hint for Illustration No. 6
© Copyright 2013 Anupam Kumar 29
Cycle Time (in Sec.) Rating
Factor
1 2 3 4 5
Grasp Bag 4 37 74 105 338 120
Locate for fill 16 51 84 117 352 120
Machine Fill 26 61 94 127 362
Set on Conveyor 34 68 102 334 369 110
Grasp Bag 4 3 6 3 4 120
Locate for fill 12 14 10 12 14 120
Machine Fill 10 10 10 10 10
Set on Conveyor 8 7 8 207 7 110
Solution
Solution for Illustration No. 6
• Allowance = 15% on total time = 15% of Standard Time
• Normal Time = (OT1 XPer.Rat.1 + OT2 XPer.Rat.2 +OT3 + OT4 XPer.Rat.4)
• Normal Time = 4*1.2 + 12.4*1.2+10+7.5*1.1 = 4.8 + 14.88 + 10 + 8.25
• Normal Time = 37.93 sec.
• Standard Time = NT / (1 – All.) = 37.93 / (1 – 0.15) = 37.93/0.85
• Standard Time = 44.62 sec.
© Copyright 2013 Anupam Kumar 30
Cycle Time (in Sec.) Average
1 2 3 4 5
Grasp Bag 4 3 6 3 4 4
Locate for fill 12 14 10 12 14 12.4
Machine Fill 10 10 10 10 10 10
Set on Conveyor 8 7 8 207 7 7.5
4/11/2013
© Copyright 2013 Anupam Kumar 6
Further Numericals
• Assuming that the total observed time for an operation of
assembling an electric switch is 1 minute. If the rating is 125%,
find normal time. If an allowance of 20% is allowed for the
operation for employee fatigue, determine the standard time.
• Find out the standard time using the following data:
© Copyright 2013 Anupam Kumar 31
Sr. No. Job Element Details
1. Average time for machine element 7 min.
2. Average time for manual element 5 min.
3. Performance Rating 120%
4. Allowance (as a percentage of S.T.) 15%
For further details,…
Contact:
Anupam Kumar
Reader,
SMS Varanasi.
Email: [email protected]
32© Copyright 2013 Anupam Kumar
Bibliography
• Buffa, E.S. and Sarin, R.K., “Modern Production/Operations Management,” Eighth Edition. Singapore: John Wiley & Sons (Asia). 1994.
• Martinich, J.S., “Production and Operations Management: An Applied Approach”, Singapore: John Wiley & Sons (Asia), 2003.
• Badi, R.V. and Badi, N.V., “Production and Operations Management”, Second Edition, New Delhi: VrindaPublication, 2008.
• Chary, S.N., “Productions and Operations Management,” Third Edition, New Delhi: Tata McGraw Hill, 2004
• Kumar Anil, S. and Suresh, N.. “Production and Operations Management,” New Delhi: New Age International Publishers Second Edition, 2008.
• Goel, B.S., “Production Operations Management”, Twenty Second Edition, Meerut, U.P.: Pragati Prakashan, 2010.
• Kachru, U. “Production and Operations Management: Text and Cases,” New Delhi: Excel Books, 2007.
• Rama Murthy, P., “Production and Operations Management,” New Delhi: New Age International, 2012.
• Chunawalla, S.A., and Patel, D.R., “Production and Operations Management,” Mumbai: Himalaya Publishing House, 2006.
• Jauhari, V. and Dutta, K., “Services: Marketing Operations and Management,” New Delhi: Oxford University Press, 2010.
• Verma, H.V., “Services Marketing: Text and Cases,” New Delhi: Dorling Kindersley, Pearson Education, 2009.
33© Copyright 2013 Anupam Kumar