traffic and circulation technical report...traffic and circulation technical report dingee backbone...
TRANSCRIPT
EAST BAY MUNICIPAL
UTILITY DISTRICT
Dingee Backbone Pipeline
Replacement Project
Traffic and Circulation
Technical Report
March 2011
Prepared for:
East Bay Municipal Utility District 375 Eleventh Street
P. O. Box 24055 Oakland, CA 94623-1055
Prepared by:
Fehr & Peers One Walnut Creek Center
100 Pringle Avenue, Suite 600 Walnut Creek, CA 94596
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
i
TABLE OF CONTENTS
CHAPTER 1. INTRODUCTION ................................................................................................................ 1
Approach to Analysis .............................................................................................................................. 1
Analysis Locations .................................................................................................................................. 1
Roadway Segments .................................................................................................................... 1
Study Intersections ..................................................................................................................... 3
Analysis Methods.................................................................................................................................... 3
Signalized Intersections .............................................................................................................. 3
Unsignalized Intersections .......................................................................................................... 4
Roadway Segments .................................................................................................................... 5
Significance Criteria ................................................................................................................................ 5
California Environmental Quality Act .......................................................................................... 5
City of Oakland ........................................................................................................................... 6
CHAPTER 2. EXISTING CONDITIONS ................................................................................................... 7
Regional Roadways ................................................................................................................................ 7
Local Roadways ..................................................................................................................................... 7
Traffic Volumes ....................................................................................................................................... 8
Transit Service ...................................................................................................................................... 12
Pedestrian/Bicycle Circulation .............................................................................................................. 13
CHAPTER 3. PROJECT DESCRIPTION ............................................................................................... 14
Trip Generation ..................................................................................................................................... 14
Trip Distribution..................................................................................................................................... 15
Phase 1 – Dingee Pumping Plant to Golden Gate Avenue ...................................................... 15
Phase 2 – Golden Gate Avenue to Broadway Terrace ............................................................ 16
Phase 3 – Proctor Avenue to Moraga Avenue ......................................................................... 17
Phase 4 – Contra Costa Road .................................................................................................. 17
Phase 5 – Roble Road .............................................................................................................. 18
CHAPTER 4. IMPACTS AND MITIGATION MEASURES..................................................................... 24
Roadway and Intersection Analysis...................................................................................................... 25
Phase 1 – Dingee Pumping Plant to Golden Gate Avenue ...................................................... 25
Phase 2 – Golden Gate Avenue to Broadway Terrace ............................................................ 26
Phase 3 – Proctor Avenue to Moraga Avenue ......................................................................... 28
Phase 4 – Contra Costa Road .................................................................................................. 29
Phase 5 – Roble Road .............................................................................................................. 30
Multiple Phase Approach .......................................................................................................... 31
Cumulative Construction Traffic ................................................................................................ 33
Roadway Closures During Construction .............................................................................................. 33
Golden Gate Avenue ................................................................................................................ 34
Broadway Terrace ..................................................................................................................... 34
Proctor Avenue ......................................................................................................................... 34
Julia Street ................................................................................................................................ 34
Harbord Drive ............................................................................................................................ 35
Contra Costa Road ................................................................................................................... 35
Roble Road ............................................................................................................................... 35
Emergency Access ............................................................................................................................... 35
Pavement Assessment ......................................................................................................................... 35
Parking Assessment ............................................................................................................................. 36
Impacts and Mitigation Measures ......................................................................................................... 36
CHAPTER 5. REFERENCES ................................................................................................................. 38
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
ii
APPENDICES
Appendix A: Traffic Count Data
Appendix B: EXisting Plus Project Volumes
Appendix C: Level Of Service Worksheets
LIST OF FIGURES
Figure 1 Project Site Vicinity and Analysis Locations ............................................................................... 2
Figure 2 Existing Peak Hour Traffic Volumes and Intersection Lane Configurations ............................. 10
Figure 3 Phase 1 Recommended Truck Routing Plan ........................................................................... 19
Figure 4 Phase 2 Recommended Truck Routing Plan ........................................................................... 20
Figure 5 Phase 3 Recommended Truck Routing Plan ........................................................................... 21
Figure 6 Phase 4 Recommended Truck Routing Plan ........................................................................... 22
Figure 7 Phase 5 Recommended Truck Routing Plan ........................................................................... 23
LIST OF TABLES
Table 1 Signalized Intersection LOS Criteria ........................................................................................... 4
Table 2 Unsignalized Intersection LOS Criteria ....................................................................................... 5
Table 3 Existing Daily Traffic Volumes ..................................................................................................... 9
Table 4 Existing Intersection Operations ............................................................................................... 12
Table 5 Construction Schedule and Trip Generation Estimates ........................................................... 15
Table 6 Existing Daily Traffic Volumes Plus Construction Traffic .......................................................... 25
Table 7 Truck Route 1: Existing Plus Project Intersection Operations .................................................. 26
Table 8 Truck Route 2: Existing Plus Project Intersection Operations .................................................. 27
Table 9 Truck Route 3: Existing Plus Project Intersection Operations .................................................. 28
Table 10 Truck Route 4: Existing Plus Project Intersection Operations .................................................. 29
Table 11 Truck Route 5: Existing Plus project Intersection Operations ................................................... 30
Table 12 Scenario A: Phases 2 & 3 ......................................................................................................... 31
Table 13 Scenario B: Phases 3 & 4 – Large Diameter pipeline on Proctor Avenue ................................ 32
Table 14 Scenario C: phases 3 & 4 - Small Diameter Pipeline on Proctor Avenue ................................ 33
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
1
CHAPTER 1. INTRODUCTION
This Technical Report will serve as the basis for Section 3.6 of the Dingee Backbone Pipeline
Replacement Project Mitigated Negative Declaration under preparation by the East Bay Municipal Utility
District (EBMUD).
The Dingee Backbone Pipeline Replacement Project (Project) could span up to 2 years and would replace 19,000 linear feet of pipe. This does not include down-time, mobilization, or demobilization. Most of the Project involves excavating a trench, installing new pipe, plugging the old pipe, backfilling the trench with aggregate base, and finally repaving the disturbed area to match the adjacent street surface. A small segment of the Project may involve a ‘slip-line’ method (as opposed to replacement), whereby a smaller diameter new pipe is fed through the larger diameter old pipe. Slip-lining would require installation of a trench box every 560 feet instead of having to excavate the entire length. Final paving of disturbed areas would occur approximately every 1000 linear feet or every one to two weeks.
APPROACH TO ANALYSIS
Fehr & Peers evaluated potential traffic and circulation impacts based on the following:
• Field reconnaissance of the Project site and surrounding roadway network, including intersection
control, lane configurations, roadway widths, on-street parking, sight distance, pedestrian and
bicycle facilities, and transit routes.
• Traffic volume counts for local roadways and intersections on a typical weekday (Tuesday –
Thursday).
• Estimated Project-generated daily and peak-hour trips for each construction phase.
ANALYSIS LOCATIONS
Four roadway segments and 14 intersections in the vicinity of the Project site were selected for analysis,
as these locations provide access to the site and could be potentially impacted during the construction
phase of the proposed Project. The locations are listed below and shown on Figure 1.
Roadway Segments
A. Golden Gate Avenue, North of Acacia Avenue
B. Broadway Terrace, West of Proctor Avenue
C. Proctor Avenue, South of Broadway Terrace
D. Harbord Drive, North of Moraga Avenue
A
B
C
D
2
1 34
5 67
8 9 10
11
12 13
14
Broadway Broadway
Harbord Dr
Harbord Dr
Mountain Blvd
Mountain Blvd
Broadway TerBroadway Ter
Chabot Rd
Chabot Rd
Tunnel RdTunnel Rd
Park WayPark Way
Clarewood Dr
Clarewood Dr
Hiller D
r
Hiller D
r
Golden G
ate AveG
olden Gate Ave
Acacia AveAcacia Ave
Florence Ave
Florence Ave
Margarido D
rM
argarido Dr
Ocean View Dr
Ocean View Dr
Robl
e Rd
Robl
e Rd
Buena Vista Ave
Buena Vista Ave
Proctor Ave
Proctor Ave
Pala AvePala Ave
Estates Dr
Estates Dr
Bonita Ave
Bonita Ave
Rom
any R
d
Rom
any R
d
Masonic Ave
Masonic Ave
Leo Way
Leo WayH
ighland Ave
Highland Ave
Plaza DrPlaza Dr
Cross RdCross Rd
Duncan Way
Duncan Way
Scenic AveScenic Ave
Fairlane Dr
Fairlane Dr
Hillcrest RdHillcrest Rd
Woo
d D
rW
ood
Dr
Taur
us A
veTa
urus
Ave
Oakland AveOakland Ave
Swainland Rd
Swainland Rd
El Camino Real
El Camino Real
Miles Ave
Miles Ave
Ruthland RdRuthland Rd
Cochrane Ave
Cochrane Ave
Pinewood Rd
Pinewood Rd
The Uplands The Uplands
Rose Ave
Mandalay Rd
Mandalay Rd
Manila Ave
Manila Ave
Johnston Dr
Johnston Dr
Fernwood Dr
Fernwood Dr
Thorn
hill Dr
Thorn
hill Dr
Piedmont AvePiedmont Ave
Vice
nte R
d
Vice
nte R
d
Alta RdAlta Rd
Mesa Ave
Mesa Ave
Hillside Ave
Hillside Ave
Manor D
r
Monroe Ave
Monroe Ave
Blair Ave
Blair Ave
Hazel RdHazel Rd
Monte Ave
Monte Ave
Virgo RdVirgo Rd
Hilltop Cres
Hilltop Cres
Lawton Ave
Lawton Ave
Oakvale AveOakvale Ave
Bell AveBell Ave
Sheridan Rd
Sheridan Rd
Brookside Ave
Brookside Ave
Glenwood Glade
Glenwood Glade
Heron Dr
Heron Dr
Sonia StSonia St
Glenbrook Dr
Glenbrook Dr
Mor
peth
St
Mor
peth
StCarlton StCarlton St
Agnes StAgnes St
Pacific Ave
Pacific Ave
Roan
oke
RdRo
anok
e Rd
Lane Ct
Lane Ct
Glen
arm
s Dr
Glen
arm
s Dr
Aquarius Way
Aquarius Way
Binn
acle
Hl
Binn
acle
Hl
Blair PlBlair Pl
Estrella
Ave
Tem
plar
Pl
Tem
plar
Pl
Pali CtPali Ct
McAndrew Dr
McAndrew Dr
Alpine Ter
Alpine Ter
Saint Paul C
t
Saint Paul C
t
Abbott Way
Abbott Way
Bridge RdBridge Rd
Gwin RdGwin Rd
West Ln
West Ln
Captains CvCaptains Cv
Hagar AveHagar Ave
Win
dwar
d H
l
Win
dwar
d H
l
Starview Dr
Starview Dr
Wilding Ln
Wilding Ln
Truitt
Ln
Truitt
Ln
Grand View Dr
Grand View Dr
Monzal A
ve
Monzal A
ve
Mar
ie W
ayM
arie
Way
Echo LnEcho Ln
Yankee HlYankee HlSherw
ood Dr
Sherwood D
r
Harbord Ct
Harbord Ct
Doris Pl
Doris Pl
Ramona Ave
Blair Ave
Estates Dr
Estates Dr
Blair AveBlair Ave
Sheridan Rd
Sheridan Rd
Broadway
Harbord Dr
Mountain Blvd
Broadway Ter
Chabot Rd
Tunnel Rd
Park Way
Clarewood Dr
Hiller D
r
Golden G
ate Ave
Acacia Ave
Florence Ave
Margarido D
r
Ocean View Dr
Robl
e Rd
Buena Vista Ave
Proctor Ave
Pala Ave
Estates Dr
Bonita Ave
Rom
any R
d
Masonic Ave
Leo WayH
ighland Ave
Plaza Dr
Cross Rd
Duncan Way
Scenic Ave
Fairlane Dr
Hillcrest Rd
Woo
d D
r
Taur
us A
ve
Oakland Ave
Swainland Rd
El Camino Real
Miles Ave
Ruthland Rd
Cochrane Ave
Pinewood Rd
The Uplands
Rose Ave
Mandalay Rd
Manila Ave
Johnston Dr
Fernwood Dr
Thorn
hill Dr
Piedmont Ave
Vice
nte R
d
Alta RdM
esa Ave
Hillside Ave
Manor D
r
Monroe Ave
Blair Ave
Hazel Rd
Monte Ave
Virgo Rd
Hilltop Cres
Lawton Ave
Oakvale Ave
Bell Ave
Sheridan Rd
Brookside Ave
Glenwood Glade
Heron Dr
Sonia St
Glenbrook Dr
Mor
peth
StCarlton St
Agnes St
Pacific Ave
Roan
oke
Rd
Lane Ct
Glen
arm
s Dr
Aquarius Way
Binn
acle
Hl
Blair Pl
Estrella
Ave
Tem
plar
Pl
Pali Ct
McAndrew Dr
Alpine Ter
Saint Paul C
t
Abbott Way
Bridge Rd
Gwin Rd
West Ln
Captains Cv
Hagar Ave
Win
dwar
d H
l
Starview Dr
Wilding Ln
Truitt
Ln
Grand View Dr
Monzal A
ve
Mar
ie W
ay
Echo Ln
Yankee HlSherw
ood Dr
Harbord Ct
Doris Pl
Ramona Ave
Blair Ave
Estates Dr
Blair Ave
Sheridan Rd
Moraga AveMoraga Ave
Harbord Dr
Harbord Dr
Harbord Dr
Contra Costa Rd
Contra Costa Rd
Tunnel RdTunnel Rd
Caldecott Ln
Contra Costa Rd
Tunnel RdCaldecott L
n
Broadway TerBroadway TerBroadway Ter
Golden Gate Ave
Golden Gate Ave
n
n
n
n
n
n
n
n
24CALIFORNIA
24CALIFORNIA
13CALIFORNIA
13CALIFORNIA
Estrella
Estrella
ona Ave
ona Ave
Blair AiBlair A
Not to Scale
LEGEND
Study Intersection
Study Roadway Segment
RoRoRossseeeeeAe Ae AAAAAAe Ae Ae AveveAAAAAvvvvve
Rososososososossssssssssossse Ae Ae Ae Ae Ae Ae Ae Ae Ae Ae Ae Ae Ae Ae Ae Ae Ae Aevevevevevevevvevevevevvvvvv
Manor D
rMMM
anor Dr
Study Intetuudy IntStu
Study RoaSt
n
1
X
Dingee Backbone Pipeline Replacement
FIGURE 1March 2011WC10-2755_1_StudyArea
PROJECT AREAS AND STUDY INTERSECTION LOCATIONS
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
3
Study Intersections
1. Patton Street/Miles Avenue
2. Broadway/Keith Avenue
3. Broadway/Brookside Avenue
4. Broadway/Golden Gate Way
5. Tunnel Road/SR 13/Hiller Drive
6. Caldecott Lane/Kay Overcrossing
7. Broadway/Kay Overcrossing
8. Broadway Terrace/Golden Gate Avenue
9. Broadway Terrace/Proctor Avenue
10. Broadway Terrace/SR 13 Southbound
11. Broadway Terrace/Glenwood Glade/Pinewood Road
12. Harbord Drive/Moraga Avenue
13. Moraga Avenue/Estates Drive
14. Thornhill Drive/SR13/Moraga Avenue
ANALYSIS METHODS
The operations of roadway facilities are described with the term “level of service” (LOS). LOS is a
qualitative description of traffic flow based on factors such as speed, travel time, delay, and freedom to
maneuver. Six levels of service are defined ranging from LOS A (i.e., best operating conditions) to LOS F
(worst operating conditions). LOS E corresponds to operations “at capacity.” When volumes exceed
capacity, stop-and-go conditions result and operations are designated as LOS F. The City of Oakland
strives to maintain LOS D, although LOS E is permitted at intersections within the downtown area.
Different criteria and methods were used to assess operating conditions for the various types of facilities
analyzed in this study, including signalized and unsignalized intersections, and roadway segments. The
LOS criteria and methods for each of these facilities are described in the following sections.
Signalized Intersections
Traffic conditions at signalized intersections were evaluated using the method from Chapter 16 of the
Transportation Research Board’s 2000 Highway Capacity Manual (HCM). This operations analysis
method uses various intersection characteristics (such as traffic volumes, lane geometry, and signal
phasing) to estimate the average control delay experienced by motorists traveling through an intersection.
Control delay incorporates delay associated with deceleration, acceleration, stopping, and moving up in
the queue. Table 1 summarizes the relationship between average delay per vehicle and LOS for
signalized intersections. Synchro software version 6 was used to calculate signalized intersection LOS.
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
4
TABLE 1 SIGNALIZED INTERSECTION LOS CRITERIA
Level of Service
Description Average Control
Delay Per Vehicle (Seconds)
A Operations with very low delay occurring with favorable progression and/or short cycle lengths.
< 10.0
B Operations with low delay occurring with good progression and/or short cycle lengths.
> 10.0 to 20.0
C Operations with average delays resulting from fair progression and/or longer cycle lengths. Individual cycle failures begin to appear.
> 20.0 to 35.0
D Operations with longer delays due to a combination of unfavorable progression, long cycle lengths, and/or high volume-to-capacity (V/C) ratios. Many vehicles stop and individual cycle failures are noticeable.
> 35.0 to 55.0
E Operations with long delays indicating poor progression, long cycle lengths, and high V/C ratios. Individual cycle failures are frequent occurrences.
> 55.0 to 80.0
F Operations with delays unacceptable to most drivers occurring due to over saturation, poor progression, or very long cycle lengths.
> 80.0
Source: Highway Capacity Manual (Transportation Research Board, 2000).
Unsignalized Intersections
Traffic conditions at unsignalized intersections were evaluated using the method from Chapter 17 of the
2000 Highway Capacity Manual. With this method, operations are defined by the average control delay
per vehicle (measured in seconds) for each movement that must yield the right-of-way. For all-way stop-
controlled intersections, the average control delay is calculated for the intersection as a whole. This
incorporates delay associated with deceleration, acceleration, stopping and moving up in the queue. At
two-way or side street-controlled intersections, the control delay (and LOS) is calculated for each
controlled movement, the left-turn movement from the major street, and the entire intersection. For
controlled approaches composed of a single lane, the control delay is computed as the average of all
movements in that lane. The delays for the entire intersection and for the movement or approach with the
highest delay are reported. Table 2 summarizes the relationship between delay and LOS for unsignalized
intersections.
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
5
TABLE 2 UNSIGNALIZED INTERSECTION LOS CRITERIA
Level of Service Description Average Control Delay Per Vehicle
(Seconds)
A Little or no delays < 10.0
B Short traffic delays > 10.0 to 15.0
C Average traffic delays > 15.0 to 25.0
D Long traffic delays > 25.0 to 35.0
E Very long traffic delays > 35.0 to 50.0
F Extreme traffic delays with intersection capacity exceeded >50.0
Source: Highway Capacity Manual (Transportation Research Board, 2000).
Roadway Segments
Operations of the roadway segments were evaluated by comparing roadway segment volumes to their
theoretical capacities. The definition of the traffic capacity of a local residential street is subjective and
depends upon many factors such as housing set-backs, street width, presence of on-street parking,
location (downtown, suburban, rural), and the connectivity of adjacent streets. Even two-lane local
residential streets are physically capable of carrying volumes in excess of 7,000 vehicles per day (vpd),
where the constraint on capacity is typically the traffic control at each intersection (i.e., stop signs or
signal). Based on guidance from the Institute of Transportation Engineers (ITE) publication
Transportation and Land Development, 2002 (Table 13-6), the daily capacity of the local residential
roadway segments along the Project site is 3,000 vehicles per day where two-way travel occurs, and
1,500 where the roadway narrows and two-way travel is constrained. Residential collectors along the
Project site with wider shoulders and fewer driveways have a daily capacity of up to 8,000 vehicles per
day.
SIGNIFICANCE CRITERIA
California Environmental Quality Act
Based on the California Environmental Quality Act (CEQA) guidelines, a significant traffic and circulation
impact would occur if the Project would:
(a) conflict with an applicable plan, ordinance or policy establishing measures of effectiveness for the performance of the circulation system, taking into account all modes of transportation including mass transit and non-motorized travel and relevant components of the circulation system, including but not limited to intersections, streets, highways and freeways, pedestrian and bicycle paths, and mass transit;
(b) conflict with an applicable congestion management program, including, but not limited to level of service standards and travel demand measures, or other standards established by the county congestion management agency for designated roads or highways;
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
6
(c) result in a change in air traffic patterns, including either an increase in traffic levels or a change in location that results in substantial safety risks;
(d) substantially increase hazards due to a design feature (e.g., sharp curves or dangerous intersections) or incompatible uses (e.g., farm equipment);
(e) result in inadequate emergency access;
(f) conflict with adopted policies, plans, or programs regarding public transit, bicycle, or pedestrian facilities, or otherwise decrease the performance or safety of such facilities.
City of Oakland
Based on City of Oakland significance criteria1, a project is considered to cause a significant impact at
signalized and all-way stop controlled intersections if it causes the following:
(a) at a study, signalized intersection which is located outside the Downtown area, the project
would cause the level of service (LOS) to degrade to worse than LOS D (i.e., E); or
(b) at a study, signalized intersection outside the Downtown area where the level of service is
LOS E, the project would cause the total intersection average vehicle delay to increase by
four (4) or more seconds, or degrade to worse than LOS E (i.e., F); or
(c) at a study, signalized intersection for all areas where the level of service is LOS F, the project
would cause (a) the total intersection average vehicle delay to increase by two (2) or more
seconds, or (b) an increase in average delay for any of the critical movements of four (4)
seconds or more; or (c) the volume-to-capacity (“V/C”) ratio exceeds three (3) percent (but
only if the delay values cannot be measured accurately); or
(d) At a study, unsignalized intersection the project would add ten (10) or more vehicles and after
project completion satisfy the Caltrans peak hour volume signal warrant2.
Government Code 53091(d) states: “(d) Building ordinances of a county or city shall not apply to the location or construction of facilities for the production, generation, storage, treatment, or transmission of water, wastewater, or electrical energy by a local agency.” Thus, ordinances do not strictly apply to EBMUD projects; it is the practice of EBMUD to work with host jurisdictions and agencies during project planning to reasonably consider the local environmental protection policies to conform to the extent possible.
1 City of Oakland, CEQA Thresholds/Criteria of Significance Guidelines, (July 15, 2008)
2 The California Manual on Uniform Traffic Control Devices (Caltrans, 2010) includes eight signal warrants based on traffic volumes
at an intersection, collision data, and other factors to determine if an intersection should be signalized. An intersection satisfying one or more of the warrants may be considered for signalization. However, meeting one or more of the signal warrants does not mean that the intersection must be signalized.
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
7
CHAPTER 2. EXISTING CONDITIONS
This section discusses the existing transportation network in the vicinity of the Project site.
REGIONAL ROADWAYS
State Route 24 (SR 24) is an eight-lane, east-west freeway that connects Interstate 580 (I-580) and
Interstate 980 (I-980) in Oakland and Interstate 680 (I-680) in the City of Walnut Creek. SR 24 is a
designated STAA Network route, with a maximum semitrailer length of 48 feet and no maximum for
kingpin to rear axle.
State Route 13 (SR 13) is a four-lane, north-south freeway that connects State Route 24 (SR 24) and
Interstate 580 (I-580) in the City of Oakland. SR 13 is a designated truck route between Interstates 80 (I-
80) and I-580, with a maximum truck length of 40 feet from kingpin to rear axle and 65 feet overall.
LOCAL ROADWAYS
Broadway is primarily an east-west road in the Project vicinity that runs parallel to SR 24. It is a two-lane
road in this area and provides access to and from SR 24 at multiple locations. It also provides access to
Lake Temescal Regional Park. On-street parking is provided near the park. A Class III bike route
(bicyclists share the road with vehicles) is designated on Broadway east of Golden Gate Way, however
Class II bike lanes are proposed on the entire length of Broadway.
Golden Gate Avenue is a north-south road that connects Chabot Road and Broadway in the north to
Broadway Terrace in the south. It is a two-lane winding road with a double yellow centerline stripe.
Portions of the road have significant grades combined with horizontal curves. In general, Golden Gate
Avenue is 28 feet wide north of Acacia Avenue and 38 feet wide south of Acacia Avenue. Adjacent land
uses are residential and on-street parking is provided on both sides for most of the length of Golden Gate
Avenue. Parking is prohibited between Eustice Avenue and Golden Gate Way. Sidewalks are provided
on both sides of the road. Golden Gate Avenue is also designated as a Class III bike route between
Chabot Road and Golden Gate Way. This segment connects the upper Broadway bike route to the
Rockridge and Temescal neighborhoods in Oakland.
Broadway Terrace is an east-west two-lane road that connects Broadway and SR 13, and continues east,
terminating at Skyline Boulevard. Adjacent land uses are residential within the Project vicinity with on-
street parking provided on both sides of the road except adjacent to SR 13 ramps. Sidewalks are
provided on both sides of the road between Golden Gate Avenue and just east of Sheridan Road. East of
Sheridan Road, sidewalks are provided on the north side only until the SR 13 undercrossing where they
continue on both sides. Broadway Terrace is designated as a Class III bike route.
Proctor Avenue is a north-south residential street that connects Broadway Terrace and Masonic Avenue.
It is a 30-foot wide two-lane road with parking permitted on both sides. Single family homes front the
street and sidewalks are provided on both sides. Speed humps have been installed in multiple locations
along Proctor Avenue.
Harbord Drive is a north-south residential street that ends at Broadway Terrace in the north and continues
south of Moraga Avenue. It is a 30-foot wide two-lane road with parking permitted on both sides, divided
by a dashed yellow line. Single family homes front the street. Sidewalks are not provided on this street.
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
8
Moraga Avenue is an east-west road that connects Pleasant Valley Avenue and SR 13. It is a two-lane
road west of SR 13 and a four-lane road under SR 13. East of SR 13, Moraga Avenue turns south and
meets Mountain Boulevard at La Salle Avenue. Adjacent land uses are residential west of SR 13, with a
retail center east of SR 13. On-street parking is provided on both sides of Moraga Avenue between
Thornhill Avenue and Park Boulevard. A Class III bike route is designated on Moraga Avenue east of SR
13, continuing south along Mountain Boulevard.
Contra Costa Road is a north-south residential street that begins at Buena Vista Avenue and terminates
as a cul-de-sac. It is an approximately 22-foot wide street with parking permitted on the west side.
Sidewalks are also provided on the west side of the street.
Roble Road is a north-south residential street that connects Tunnel Road and Chabot Road. The paved
width of the road is 25 feet or less, with parking permitted on both sides. Sidewalks are provided on both
sides of the street until approximately 800 feet south of Tunnel Road. At this point, the sidewalk stops
and the road divides into separate northbound and southbound lanes with large grade differences
between the two directions and pavement widths of less than 12 feet in each direction. This separation
continues until approximately 450 feet north of Chabot Road and then continues as a 15 to 20 foot wide
two-way street. Where Roble Road is less than 20 feet wide, two-way traffic is constrained.
Tunnel Road is an east-west arterial, portions of which are designated as SR 13, that begins in Berkeley
and provides access to SR 13, and SR 24. It is a two-lane road east of Domingo Avenue. West of
Domingo Avenue, it becomes four lanes and turns into Ashby Avenue. Eastbound and westbound lanes
are physically separated by a retaining wall from Bridge Road to 600 feet east of Vicente Road, restricting
left turns in and out of side streets. Sidewalks are provided on both sides of the road until just west of the
Tunnel Road/Hiller Drive intersection. There are some residential uses fronting the road west of the
Tunnel Road/Hiller Drive intersection, but a hillside fronts the road east of the intersection.
Caldecott Lane is an east-west two-lane road that connects Tunnel Road with SR 24. Residential
condominiums are adjacent to the road at its eastern end. Sidewalks are only provided fronting the
condominiums. Caldecott lane is designated as a Class III bike route (bicyclists share the road with
vehicles) between the Kay Overcrossing and Tunnel Road.
TRAFFIC VOLUMES
Automatic machine traffic counts were conducted over a 96-hour period on clear days with area schools
in normal session on residential streets near the Project locations. Counts collected during the school
year are representative of typical traffic conditions for the majority of the year. Counts collected during
summer months may be lower due to increased vacations and fewer school related trips. The average
daily traffic volumes on these roadways are summarized below in Table 3. Golden Gate Avenue, Proctor
Avenue, and Harbord Drive experience traffic volumes well below the theoretical daily capacity of 3,000
vehicles per day. Broadway Terrace is a larger collector not defined as a local residential street and
experiences daily traffic volumes greater than 6,000.
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
9
TABLE 3 EXISTING DAILY TRAFFIC VOLUMES
Roadway Location Average Daily Traffic
1
AM Peak Hour2 PM Peak Hour
3
A. Golden Gate Avenue South of Golden Gate Way 1,480 242 141
B. Broadway Terrace West of Proctor Avenue 6,260 698 676
C. Proctor Avenue North of Julia Street 480 29 34
D. Harbord Drive North of Moraga Avenue 2,650 344 238
Notes
1. Average daily two-way traffic measured over 4 days.
2. Maximum hourly volume between the hours of 7:00 and 9:00 AM.
3. Maximum hourly volume between the hours of 4:00 and 6:00 PM.
Source: Fehr & Peers, 2010, based on counts taken by Auto-Census.
Peak period traffic counts were conducted between 7:00 and 9:00 AM and 4:00 and 6:00 PM on a clear
day with area schools in normal session at the study intersections. Peak period counts collected during
the school year represent typical traffic conditions during the majority of the year. Peak period counts
collected when schools are not in session may be lower due to less school related traffic peaks at drop-off
and pick-up times. For each intersection, the single hour with the highest traffic volumes during the two
count periods was identified. The peak-hour volumes are presented on Figure 2. The peak-hour data is
used as the basis for intersection operations analysis. Existing intersection lane configurations and traffic
control are also shown on Figure 2. Traffic count worksheets are provided in the Appendix.
Existing peak-hour intersection operations are summarized in Table 4, corresponding to the same
intersection designations labeled in Figure 1. Many of the study intersections currently operate poorly,
characterized by long delays.
The signalized Tunnel Road/SR 13/Hiller Drive and Thornhill Drive/SR 13/Moraga Avenue intersections
operate at unacceptable Levels of Service during the AM and PM peak hours. The all-way stop controlled
Broadway Terrace/Glenwood Glade/Pinewood Road intersection operates at unacceptable Level of
Service during the AM and PM peak hours.
The unsignalized Broadway Terrace/SR 13 southbound ramps, Moraga Avenue/Estates Drive, and
Moraga Avenue/Harbord Drive intersections operate at an overall acceptable service level during both the
AM and PM peak hours. However, side-street stop controlled vehicles experience deficient conditions
with high delays during the AM and PM peak hours. The Broadway/Eastbound SR 24 on-ramp
intersection operates at an overall acceptable service level, but stop controlled vehicles experience
unacceptable delay during the PM peak hour.
Additionally, although HCM analysis indicates that the Caldecott Lane/Kay Overcrossing and
Broadway/Kay Overcrossing operate at acceptable Levels of Service, significant queuing was observed in
the field due to queue spillback from eastbound SR 24 through both of these intersections during the AM
and PM peak hours, resulting in actual operations worse than presented in Table 4.
2
1 34
5 67
8 9 10
11
12 13
14
Broadway Broadway
Harbord Dr
Harbord Dr
Mountain Blvd
Mountain Blvd
Broadway TerBroadway Ter
Chabot Rd
Chabot Rd
nel RdTunnel Rd
Park WayPark Way
Clarewood Dr
Clarewood Dr
Hiller D
r
Hiller D
r
Golden G
ate AveG
olden Gate Ave
Acacia AveAcacia Ave
Florence Ave
Florence Ave
Margarido D
rM
argarido Dr
Ocean View Dr
Ocean View Dr
Robl
e Rd
Robl
e Rd
Buena Vista Ave
Buena Vista Ave
Proctor Ave
Proctor Ave
Pala AvePala Ave
Ramona AveRamona Ave
Estates Dr
Estates Dr
Bonita Ave
Rom
any R
d
Rom
any R
d
Masonic Ave
Masonic Ave
Leo Way
Leo Way
HHighland Ave
Plaza Dr
Cross RdCross Rd
Duncan Way
Duncan Way
Scenic AveScenic Ave
Fairlane Dr
Fairlane Dr
Hillcrest RdHillcrest Rd
Woo
d D
r
Taur
us A
veTa
urus
Ave
Oakland Ave
Ronada AveRonada Ave
Swainland Rd
Swainland Rdeal
El Camino Real
Miles Ave
Miles Ave
York Dr
Ruthland RdRuthland Rd
Cochrane Ave
Cochrane Ave
Pinewood Rd
Pinewood Rd
The Uplands The Uplands
Rose Ave
Mandalay Rd
Mandalay Rd
Manila Ave
Manila Ave
Johnston Dr
Johnston Dr
Fernwood Dr
Fernwood Dr
Thorn
hill Dr
Thorn
hill Dr
Piedmont AvePiedmont Ave
Vice
nte R
d
Alta RdAlta Rd
Mesa Ave
Mesa Ave
Hillside Ave
Manor D
r
Monroe Ave
Monroe Ave
Blair Ave
Blair Ave
Hazel Rd
Monte Ave
Monte Ave
Grand Ave
Ricardo Ave
Virgo RdVirgo Rd
Hilltop Cres
Hilltop Cres
Lawton Ave
Lawton Ave
Oakvale AveBell Ave
Sheridan Rd
Sheridan Rd
Brookside Ave
Brookside Ave
Glenwood Glade
Glenwood Glade
Ave
Dra
cena
Ave
Heron Dr
Heron Dr
Sonia StSonia St
Glenbrook Dr
Glenbrook Dr
Mor
peth
St
Mor
peth
StCarlton StCarlton St
Agnes StAgnes St
Pacific Ave
Roan
oke
RdRo
anok
e Rd
Lane Ct
Lane Ct
Glen
arm
s Dr
Glen
arm
s Dr
Aquarius Way
Aquarius Way
Binn
acle
Hl
Binn
acle
Hl
Blair Pl
Estrella
Ave
Estrella
Ave
Tem
plar
Pl
Tem
plar
Pl
Pali CtPali Ct
McAndreMcAndrew Dr
Alpine Ter
Alpine Ter
Saint Paul C
t
Saint Paul C
t
Abbott Way
Abbott Way
Bridge Rd
Gwin RdGwin Rd
West Ln
West Ln
vCaptains Cv
Hagar Ave
Win
dwar
d H
l
Win
dwar
d H
l
Starview Dr
Starview Dr
Wilding Ln
Wilding Ln
Truitt
Ln
Truitt
Ln
Grand View Dr
Monzal A
ve
Monzal A
ve
Mar
ie W
ayM
arie
Way
Echo LnEcho Ln
Yankee Hl
Sherwood D
rSherw
ood Dr
Harbord Ct
Harbord Ct
Doris Pl
Blair Ave
Estates Dr
Estates Dr
Blair Ave
Sheridan Rd
Sheridan Rd
Broadway
Harbord Dr
Mountain Blvd
Broadway Ter
Chabot Rd
nel Rd
Park Way
Clarewood Dr
Hiller D
r
Golden G
ate Ave
Acacia Ave
Florence Ave
Margarido D
r
Ocean View Dr
Robl
e Rd
Buena Vista Ave
Proctor Ave
Pala Ave
Ramona Ave
Estates Dr
Rom
any R
d
Masonic Ave
Leo Way
H
Cross Rd
Duncan Way
Scenic Ave
Fairlane Dr
Hillcrest Rd
Taur
us A
ve
Ronada Ave
Swainland Rdeal
Miles Ave
Ruthland Rd
Cochrane Ave
Pinewood Rd
The Uplands
Mandalay Rd
Manila Ave
Johnston Dr
Fernwood Dr
Thorn
hill Dr
Piedmont Ave
Alta Rd
Mesa Ave
Monroe Ave
Blair Ave
Monte Ave
Virgo Rd
Hilltop Cres
Lawton Ave
Sheridan Rd
Brookside Ave
Glenwood Glade
Ave
Heron Dr
Sonia St
Glenbrook Dr
Mor
peth
StCarlton St
Agnes St
Roan
oke
RdLane Ct
Glen
arm
s Dr
Aquarius Way
Binn
acle
Hl
Estrella
Ave
Tem
plar
Pl
Pali Ct
McAndre
Alpine Ter
Saint Paul C
t
Abbott Way
Gwin Rd
West Ln
v
Win
dwar
d H
l
Starview Dr
Wilding Ln
Truitt
Ln
Monzal A
ve
Mar
ie W
ay
Echo Ln
Sherwood D
r
Harbord Ct
Estates Dr
Sheridan Rd
MMoraga AveMoraga Ave
Harbord Dr
Harbord Dr
Harbord Dr
Contra Costa Rd
Contra Costa Rd
Tunnel RdTunnel Rd
Caldecott Ln
Contra Costa Rd
Tunnel RdCaldecott L
n
Broadway TerBroadway TerBroadway Ter
GGolden Gate Ave
Golden Gate Aven
n
n
n
n
n
24CALIFORNIA
13CALIFORNIA
414
(868
)18
9 (3
99)
131
(60)
SR
13
Tunn
el R
oad
1,14
4 (8
31)
144
(60)
144
(154
)
186
(48)
93 (4
3)10
2 (1
7)
SR
13
Hille
r Driv
e
109
(43)
126
(76)
107
(17)
123
3 (1
04)
107
(87)
396
(231
)24
7 (1
97)
Miles Avenue
P
atto
n S
treet
549
(491
)34
4 (1
,155
)
Bro
adw
ayS
R-2
4
97 (40)
108 (60)
Broadway
3
730
(1,0
47)
183 (234)
Keith Avenue
802 (1,067)
Bro
adw
ay
2
538
(359
)
Gol
den
Gat
e W
ay
472 (464)
93 (2
9)
75 (4
4)
82 (30)
Broadway
38 (53)15 (19)
4
5
120
(64)
658
(651
)
Kay Overpass
213
(90)
71 (1
5)
80 (83)
6
20 (48)
Cal
deco
tt La
ne
71 (14)
73 (7
3)
0 (27)
Firescape Garden Dwy
1 (34)
47
7 (3
84)
3 (2
6)
2 (5)
Kay Overpass
1 (21)673 (632)
Bro
adw
ay
7
33 (2
9)1
(8)
2 (1
4)
Not to Scale
VOLUMES KEY
MAP KEY
School
Study Intersection
AM (PM) Peak Hour Traffic Volumes
Stop Sign
Signalized Intersection
XX (YY)
1
Dingee Backbone Pipeline Replacement
FIGURE 2AMarch 2011WC10-2755_2A_ExVol
EXISTING CONDITIONS PEAK HOUR INTERSECTION TRAFFIC VOLUMES,LANE CONFIGURATIONS AND TRAFFIC CONTROL
2
1 34
5 67
8 9 10
11
12 13
14
Broadway Broadway
Harbord Dr
Harbord Dr
Mountain Blvd
Mountain Blvd
Broadway TerBroadway Ter
Chabot Rd
Chabot Rd
nel RdTunnel Rd
Park WayPark Way
Clarewood Dr
Clarewood Dr
Hiller D
r
Hiller D
r
Golden G
ate AveG
olden Gate Ave
Acacia AveAcacia Ave
Florence Ave
Florence Ave
Margarido D
rM
argarido Dr
Ocean View Dr
Ocean View Dr
Robl
e Rd
Robl
e Rd
Buena Vista Ave
Buena Vista Ave
Proctor Ave
Proctor Ave
Pala AvePala Ave
Ramona AveRamona Ave
Estates Dr
Estates Dr
Bonita Ave
Rom
any R
d
Rom
any R
d
Masonic Ave
Masonic Ave
Leo Way
Leo Way
HHighland Ave
Plaza Dr
Cross RdCross Rd
Duncan Way
Duncan Way
Scenic AveScenic Ave
Fairlane Dr
Fairlane Dr
Hillcrest RdHillcrest Rd
Woo
d D
r
Taur
us A
veTa
urus
Ave
Oakland Ave
Ronada AveRonada Ave
Swainland Rd
Swainland Rdeal
El Camino Real
Miles Ave
Miles Ave
York Dr
Ruthland RdRuthland Rd
Cochrane Ave
Cochrane Ave
Pinewood Rd
Pinewood Rd
The Uplands The Uplands
Rose Ave
Mandalay Rd
Mandalay Rd
Manila Ave
Manila Ave
Johnston Dr
Johnston Dr
Fernwood Dr
Fernwood Dr
Thorn
hill Dr
Thorn
hill Dr
Piedmont AvePiedmont Ave
Vice
nte R
d
Alta RdAlta Rd
Mesa Ave
Mesa Ave
Hillside Ave
Manor D
r
Monroe Ave
Monroe Ave
Blair Ave
Blair Ave
Hazel Rd
Monte Ave
Monte Ave
Grand Ave
Ricardo Ave
Virgo RdVirgo Rd
Hilltop Cres
Hilltop Cres
Lawton Ave
Lawton Ave
Oakvale AveBell Ave
Sheridan Rd
Sheridan Rd
Brookside Ave
Brookside Ave
Glenwood Glade
Glenwood Glade
Ave
Dra
cena
Ave
Heron Dr
Heron Dr
Sonia StSonia St
Glenbrook Dr
Glenbrook Dr
Mor
peth
St
Mor
peth
StCarlton StCarlton St
Agnes StAgnes St
Pacific Ave
Roan
oke
RdRo
anok
e Rd
Lane Ct
Lane Ct
Glen
arm
s Dr
Glen
arm
s Dr
Aquarius Way
Aquarius Way
Binn
acle
Hl
Binn
acle
Hl
Blair Pl
Estrella
Ave
Estrella
Ave
Tem
plar
Pl
Tem
plar
Pl
Pali CtPali Ct
McAndreMcAndrew Dr
Alpine Ter
Alpine Ter
Saint Paul C
t
Saint Paul C
t
Abbott Way
Abbott Way
Bridge Rd
Gwin RdGwin Rd
West Ln
West Ln
vCaptains Cv
Hagar Ave
Win
dwar
d H
l
Win
dwar
d H
l
Starview Dr
Starview Dr
Wilding Ln
Wilding Ln
Truitt
Ln
Truitt
Ln
Grand View Dr
Monzal A
ve
Monzal A
ve
Mar
ie W
ayM
arie
Way
Echo LnEcho Ln
Yankee Hl
Sherwood D
rSherw
ood Dr
Harbord Ct
Harbord Ct
Doris Pl
Blair Ave
Estates Dr
Estates Dr
Blair Ave
Sheridan Rd
Sheridan Rd
Broadway
Harbord Dr
Mountain Blvd
Broadway Ter
Chabot Rd
nel Rd
Park Way
Clarewood Dr
Hiller D
r
Golden G
ate Ave
Acacia Ave
Florence Ave
Margarido D
r
Ocean View Dr
Robl
e Rd
Buena Vista Ave
Proctor Ave
Pala Ave
Ramona Ave
Estates Dr
Rom
any R
d
Masonic Ave
Leo Way
H
Cross Rd
Duncan Way
Scenic Ave
Fairlane Dr
Hillcrest Rd
Taur
us A
ve
Ronada Ave
Swainland Rdeal
Miles Ave
Ruthland Rd
Cochrane Ave
Pinewood Rd
The Uplands
Mandalay Rd
Manila Ave
Johnston Dr
Fernwood Dr
Thorn
hill Dr
Piedmont Ave
Alta Rd
Mesa Ave
Monroe Ave
Blair Ave
Monte Ave
Virgo Rd
Hilltop Cres
Lawton Ave
Sheridan Rd
Brookside Ave
Glenwood Glade
Ave
Heron Dr
Sonia St
Glenbrook Dr
Mor
peth
StCarlton St
Agnes St
Roan
oke
RdLane Ct
Glen
arm
s Dr
Aquarius Way
Binn
acle
Hl
Estrella
Ave
Tem
plar
Pl
Pali Ct
McAndre
Alpine Ter
Saint Paul C
t
Abbott Way
Gwin Rd
West Ln
v
Win
dwar
d H
l
Starview Dr
Wilding Ln
Truitt
Ln
Monzal A
ve
Mar
ie W
ay
Echo Ln
Sherwood D
r
Harbord Ct
Estates Dr
Sheridan Rd
MMoraga AveMoraga Ave
Harbord Dr
Harbord Dr
Harbord Dr
Contra Costa Rd
Contra Costa Rd
Tunnel RdTunnel Rd
Caldecott Ln
Contra Costa Rd
Tunnel RdCaldecott L
n
Broadway TerBroadway TerBroadway Ter
GGolden Gate Ave
Golden Gate Aven
n
n
n
n
n
24CALIFORNIA
13CALIFORNIA
Broadway Terrace
Pinewoo
d Rd
SR 24
Glenwood Glade
190 (107)42 (81)
89 (180)6 (9)
18 (5)326 (166)165 (78)0 (0)
6 (29)
33 (21)
54 (278)
197 (155)
65 (3
9)66
(46)
2 (2)
17 (1
0)
104
(62)
342
(219
)
Bro
adw
ay T
erra
ce
136 (140)
0 (0)
103 (184)
SR-13 Off Ramp
10
237
(249
)22
5 (2
33) 11
Proct
or A
venu
e
30 (0
)
45 (0
)
12 (28)
401 (442)
17 (23)
Broadway Terrace
475 (339)
9
23 (5
)
8 (4)
Her
mos
a A
venu
e
166 (361)
17 (13)
28 (1
1)64
(33)
Broadway TerraceG
olde
n G
ate
Aven
ue8107 (54)312 (190)
4 (4
)24
(6)
56 (6
0)
38 (31)
169 (74)
12
38 (5
0)3
(14)
39 (30)789 (430)
8 (4
)13
(7)
44 (2
9)
40 (42)281 (704)
4 (11)
49 (5
9)
Har
bord
Driv
e
Moraga Avenue
11 (6
)0
(3)
68 (4
1)E
stat
es
E
stat
es D
rive
7 (8)1,012 (367)37 (40)
Moraga Avenue
13
1 (3
)1
(1)
16 (1
1)
1 (2)506 (796)
5 (21)
231
(129
)
1 (0)175 (192)444 (164)
519
(381
)M
orag
a A
venu
e
645 (350)
103 (79)
Thornhill Drive
14
110
(128
)31
7 (5
22)
244
(459
)
Not to Scale
VOLUMES KEY
MAP KEY
School
Study Intersection
AM (PM) Peak Hour Traffic Volumes
Stop Sign
Signalized Intersection
XX (YY)
1
Dingee Backbone Pipeline Replacement
FIGURE 2BMarch 2011WC10-2755_2B_ExVol
EXISTING CONDITIONS PEAK HOUR INTERSECTION TRAFFIC VOLUMES,LANE CONFIGURATIONS AND TRAFFIC CONTROL
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
12
TABLE 4 EXISTING INTERSECTION OPERATIONS
Intersection Control Peak Hour
Delay LOS Meets Peak Hour Signal Warrant
1. Patton Street/Miles Avenue All-way Stop AM
PM
4.4
3.2
A
A No
2. Broadway/Keith Avenue Signal AM
PM
16.8
13.7
B
B -
3. Broadway/SR 24 Eastbound
On-ramp
Side-Street Stop
1
AM
PM
2.2 (WB 12.2)
3.4 (WB 68.6)
A (B)
A (F) No
4. Broadway/Golden Gate Way Side-Street
Stop1
AM
PM
4.0 (NB 17.8)
1.8 (NB 13.8)
A (C)
A (B) No
5. Tunnel Road/SR 13/Hiller Drive Signal AM
PM
98.1
>100
F
F -
6. Caldecott Lane/
Kay Overcrossing
Side-Street Stop
1
AM
PM
2.4 (WB 20.8)
1.9 (WB 13.6)
A (C)2
A (B) 2
No
7. Broadway/Kay Overcrossing Signal AM
PM
35.4
36.1
D2
D2
-
8. Broadway Terrace/
Golden Gate Avenue All-way Stop
AM
PM
14.3
11.0
B
B No
9. Broadway Terrace/
Proctor Avenue
Side-Street Stop
1
AM
PM
1.5 (NB 16.2)
1.0 (NB 14.3)
A (C)
A (B) No
10. Broadway Terrace/SR 13 southbound ramps
Side-Street Stop
1
AM
PM
6.6 (WB 44.5)
8.2 (SB 36.5)
A (E)
A (E) No
11. Broadway Terrace/Glenwood Glade/Pinewood Road
All-way Stop AM
PM
>100
>100
F
F Yes
12. Harbord Drive/Moraga Avenue Side-Street
Stop1
AM
PM
7.8 (SB 92.0)
10.0 (SB 99.5)
A (F)
A (F) No
13. Moraga Avenue/Estates Drive Side-Street
Stop1
AM
PM
2.6 (SB > 100)
1.8 (SB 49.2)
A (F)
A (E) No
14. Thornhill Drive/SR 13/
Moraga Avenue Signal
AM
PM
>100
62.1
F
E -
Notes
1. For side-street-stop intersections, average delay is listed first followed by the delay for the worst approach.
2. Field observations indicate LOS F conditions due to queue spillback from the eastbound SR 24 on-ramp.
Source: Fehr & Peers, 2010
TRANSIT SERVICE
Multiple AC Transit routes operate within the Project site. Line 61 operates on Golden Gate Avenue
south of Acacia Avenue and continues east on Broadway Terrace on weekdays between 6:00 AM and
8:00 PM with one hour headways. Transbay Line V operates on Broadway Terrace; Line CB operates on
Broadway Terrace, Harbord Drive, and Moraga Avenue; and Line E operates on Tunnel Road and
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
13
Caldecott Lane. These three transbay routes operate on weekdays during morning and evening peak
periods, approximately 6:00 AM and 9:00 AM, and 4:00 PM and 8:00 PM.
PEDESTRIAN/BICYCLE CIRCULATION
Pedestrian facilities include sidewalks, crosswalks, and pedestrian signals. Sidewalks are provided on
Broadway, Golden Gate Avenue, Contra Costa Road, Proctor Avenue, portions of Broadway Terrace,
portions of Moraga Avenue, portions of Roble Road, and portions of Tunnel Road within the study area.
Sidewalks are not provided on Harbord Drive.
Bicycle facilities include:
• Bike paths (Class I) – Paved trails that are separated from roadways.
• Bike lanes (Class II) – Lanes on roadways designated for use by bicycles through striping, pavement legends, and signs.
• Bike routes (Class III) – Designated roadways for bicycle use by signs only; may or may not include additional pavement width for cyclists.
Portions of Broadway, Broadway Terrace, and Caldecott Lane are designated as Class III bike routes
within the study area.
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
14
CHAPTER 3. PROJECT DESCRIPTION
The section describes the trip generating potential during the proposed construction stage of the proposed Project. Upon completion of the Project, the Project would not generate any trips except for occasional maintenance, similar to existing conditions.
TRIP GENERATION
Project trips would be generated during the construction phase as trucks and workers travel to and from
the site. EBMUD identified a preliminary construction schedule and the number of trucks and workers
anticipated for each phase. The estimates were based on the number of haul trucks, material trucks and
worker vehicles needed during each phase. The following assumptions were used in the development of
the trip generation estimates by phase:
• Excavated soil is to be hauled off site and replaced by aggregate base in the street.
• Haul trucks average 9 cubic yards per load and include trench pavement and soil disposal as well
as fill import deliveries.
• Material trucks trips per day include deliveries for pipeline, appurtenance, paving, equipment
delivery, and materials for plugging existing transmission pipelines.
• Worker vehicles include nine vehicles for crew, one contractor superintendent, one district
inspector, one city inspector, and one visitor.
For the purposes of this report, the Project was broken into five phases, representing five different
segments of the pipeline. The five phases are differentiated by different truck routes being used for each
the five segments. The number of daily and hourly truck and worker vehicles for each phase are
summarized in Table 5. The daily trip generation is expected to be consistent throughout the duration of
each phase. While each of the five phases could occur sequentially, without overlapping construction
traffic, some phases could proceed concurrently, thus reducing the overall construction schedule. The
following three scenarios with overlapping phases are possible:
A. Phases 2 and 3 – Installation of the large diameter pipeline on Golden Gate Avenue and Proctor
Avenue
B. Phases 3 and 4 – Installation of the large diameter pipeline on Proctor Avenue and the
distribution pipeline on Contra Costa Road
C. Phases 3 and 4 – Installation of the small diameter distribution lines on both Proctor Avenue and
Contra Costa Road
Trucks behave differently than passenger vehicles as they take longer to accelerate, decelerate, and
negotiate turns. Therefore, they also affect intersection and roadway operations differently. Truck
behavior was accounted for in the assessment of roadway and intersection operations.
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
15
TABLE 5 CONSTRUCTION SCHEDULE AND TRIP GENERATION ESTIMATES
(INCLUDES TRIPS TO AND FROM THE SITE)
Construction Phase Duration (weeks)
Daily Trips (one-way) Hourly1 Trips (one-way)
Trucks2 Workers
3 Trucks
2 Workers
3
Transmission Pipeline
1. Dingee Pumping Plant to Golden Gate Avenue 4 34 26 4 13
2. Golden Gate Avenue to Broadway Terrace at Proctor Avenue
19 30 26 4 13
3. Proctor Avenue to Moraga Avenue 334
30 26 4 13
Ancillary Projects
4. Contra Costa Road 15 30 24 4 12
5. Roble Road 2 10 24 1 12
Notes
1. Hourly trips refers to the number of trips expected to occur during the AM and PM peak hours.
2. Hourly truck trip estimates assume truck trips occur equally across a 7-hour workday, and rounded up to the nearest trip.
3. Hourly worker trip estimates assume one third of daily workers arrive during the peak hour.
4. Includes 15 weeks for Proctor Avenue to Julia Street distribution line. A maximum of 3 hourly truck trips are expected for distribution line construction.
Source: EBMUD, Fehr & Peers
TRIP DISTRIBUTION
The Project would generate two types of trips; construction worker trips and truck trips. This section
describes the distribution patterns during each phase of construction. Routes to/from each phase of the
Project and the regional roadway network were reviewed in the development of preliminary truck routing
plans. Factors considered in development of the routes include roadway geometry, circulation efficiency,
dispersing impacts to residential streets and sensitive receptors (such as schools and recreation areas),
and truck, vehicle and pedestrian safety. Truck trips through residential streets were limited as much as
possible to streets where pipeline work is occurring since these roadways would be repaved after
construction. Due to truck restrictions on Interstate 580 south of SR 13, it was assumed that all truck trips
would use SR 24 from the east or west to travel to the Project site.
Phase 1 – Dingee Pumping Plant to Golden Gate Avenue
This portion of the Project includes construction of the pipeline from the Dingee Pumping Plan located just north of the Golden Gate Avenue/Chabot Road intersection just north of SR 24 to the Golden Gate Avenue/Golden Gate Way intersection (see Figure 3). Construction is expected to last for approximately four weeks.
Construction Worker Trip Distribution
It is expected that approximately 90 percent of site worker trips would access the site from SR 24, with 10
percent of trips from Broadway south. Of the trips to/from SR 24, about one-half is expected from the
west while the remaining half is expected from the east, including from SR 13. Worker trips from SR 24 to
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
16
the west would access the Project site via the Broadway Interchange, and travel east on Broadway, to
Golden Gate Way to the Project site. Worker trips from SR 24 to the east would access the Project site
via the Tunnel Road interchange, cross SR 24 using the Kay Overcrossing to Broadway, then turn left
onto Golden Gate Way to the Project Site. While construction workers would be encouraged to remain
on the main travel routes, some may deviate and travel on Patton Street to Chabot Road.
Truck Trip Distribution
All trucks would be directed to use SR 24 to enter the site access the site. The recommended truck route
plan is shown on Figure 3. The plan shows two possible origins for inbound truck traffic, either coming
from westbound or eastbound SR 24. Truck trips from eastbound SR 24 would access the Project site via
the Broadway Interchange, and travel east on Broadway, to Golden Gate Way to the Project site. Truck
trips from westbound SR 24 would access the Project site via the Tunnel Road interchange, cross SR 24
using the Kay Overcrossing to Broadway, then turn left onto Golden Gate Way to the Project site.
Outbound trucks would be directed back to Golden Gate Way and left onto Broadway. Trucks would
access eastbound SR 24 from Broadway or westbound SR 24 by turning right onto Patton Street and left
onto Miles Avenue. A flagger is recommended at the Golden Gate Way/Golden Gate Avenue intersection
to assist with truck maneuvering.
Phase 2 – Golden Gate Avenue to Broadway Terrace
This portion of the Project includes construction of the pipeline along Golden Gate Avenue from Golden Gate Way to Broadway Terrace, then along Broadway Terrace to Proctor Avenue (see Figure 4). Construction is expected to last for approximately 19 weeks.
Construction Worker Trip Distribution
It is expected that approximately 50 percent of site worker trips would access the site from SR 24 and 50
percent of trips from SR 13. Of the trips to/from SR 24, about one-half is expected from the west while
the remaining half is expected from the east. Of the trips to/from SR 13, about 90 percent are expected
from the south while the remaining 10 percent is expected from the north. Worker trips from SR 24 would
access the site similar to Phase 1. Worker trips from SR 13 would access the Project site from the
Broadway Terrace interchange.
Truck Trip Distribution
All trucks would be directed to use SR 24 to enter the Project area and SR 13 to exit the Project area.
The recommended truck route plan is shown on Figure 4. Similar to the Phase 1 truck route plan, the
plan shows two possible origins for inbound truck traffic, either coming from westbound or eastbound SR
24. Truck trips from eastbound SR 24 would access the Project site via the Broadway Interchange, and
travel east on Broadway, to Golden Gate Way to the Project site. Truck trips from westbound SR 24
would access the Project site via the Tunnel Road interchange, cross SR 24 using the Kay Overcrossing
to Broadway, then turn left onto Golden Gate Way to the Project site.
Through the Project site, Golden Gate Avenue is winding with steep grades. Because of this, a one-way
truck route was identified to eliminate the need for inbound and outbound trucks to pass side by side.
Outbound trucks would be directed to Broadway Terrace and onto northbound SR 13. From SR 13,
trucks would then access westbound or eastbound SR 24.
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
17
Phase 3 – Proctor Avenue to Moraga Avenue
This portion of the Project includes construction of the pipeline along Proctor Avenue (including a distribution pipeline), Julia Street, and Harbord Avenue to Moraga Avenue (see Figure 5). Construction in this area is expected to last for approximately 33 weeks.
Construction Worker Trip Distribution
It is expected that approximately 40 percent of site worker trips would access the site from southbound
SR 13 and 45 percent northbound SR 13. The remaining 15 percent of worker trips would come from
Broadway Terrace or Moraga Avenue. Worker trips from southbound SR 13 would use the Broadway
Terrace interchange, while worker trips from northbound SR 13 would use the Moraga Avenue
interchange to access the Project site.
Truck Trip Distribution
All trucks would be directed to the Project site from SR 24 via southbound SR 13. The recommended
truck route plan is shown on Figure 5. Truck trips from southbound SR 13 would access the Project site
via the Moraga Avenue Interchange and turn right onto Proctor Avenue.
Through the Project site, Proctor Avenue and Harbord Drive are winding with steep grades. Because of
this, a one-way truck route was identified to eliminate the need for inbound and outbound trucks to pass
side by side. Outbound trucks would be directed to Broadway Terrace and onto northbound SR 13.
From SR 13, trucks would then access westbound or eastbound SR 24.
Phase 4 – Contra Costa Road
This portion of the Project includes construction of a distribution pipeline along Contra Costa Road (see Figure 6) and is expected to last 15 weeks.
Construction Worker Trip Distribution
It is expected that approximately 40 percent of site worker trips would access the site from southbound
SR 13 and 45 percent northbound SR 13. The remaining 15 percent of worker trips would come from
Broadway Terrace. Worker trips from SR 13 would use the Broadway Terrace interchange, and Golden
Gate Avenue to Acacia Avenue to access the Project site. While construction workers would be
encouraged to remain on the main travel routes, some may deviate and travel on Buena Vista Avenue
since vehicles traveling from SR 13 reach Buena Vista Avenue before Golden Gate Avenue.
Truck Trip Distribution
All trucks would be directed to the Project site from SR 24 via southbound SR 13. The recommended
truck route plan is shown on Figure 6. Truck trips from southbound SR 13 would access the Project site
via the Broadway Terrace Interchange and turn right onto Golden Gate Avenue. Trucks would then turn
right onto Acacia Avenue, left onto Buena Vista Avenue, and right onto Contra Costa Road. Acacia
Avenue, Buena Vista Avenue, Contra Costa Road are narrow residential streets, and semi-trucks would
need flaggers at the Acacia Avenue/Buena Vista Avenue and Buena Vista Avenue/Contra Costa Road
intersections as they are on steep grades with limited sight distance. The flaggers would help control
residential traffic while trucks negotiate the turns.
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
18
Outbound trucks would be directed to Broadway Terrace using the same roadways as inbound trucks.
Inbound trucks may need to be held on Golden Gate Avenue or Broadway Terrace while outbound trucks
negotiate Buena Vista Avenue and Acacia Avenue. Flaggers can also provide additional assistance at
these locations. Directing outbound trucks to Broadway on Golden Gate Avenue is less desirable due to
the sharp curves on Golden Gate Avenue north of Acacia Avenue.
Phase 5 – Roble Road
This portion of the Project includes construction of a distribution pipeline along Roble Road using slip-line method, as well as installation of a new regulator at the Roble Road/Roble Court intersection and connection to the Claremont Center from Roble Court (see Figure 7). Construction in this area is expected to last 2 weeks.
Construction Worker Trip Distribution
It is expected that approximately 90 percent of site worker trips would access the site from SR 24, with 10
percent of trips from Tunnel Road north. Of the trips to/from SR 24, about one-half is expected from the
west while the remaining half is expected from the east. Worker trips from SR 24 to the west would
access the Project site via the Broadway Interchange, and travel east on Broadway, to Golden Gate Way,
Golden Gate Avenue, then Chabot Road to Roble Road. Worker trips from SR 24 to the east would
access the Project site via the Tunnel Road interchange, cross SR 24 using the Kay Overcrossing to
Broadway, then turn left onto Golden Gate Way, to Golden Gate Avenue, then Chabot Road to Roble
Road. These routes assume worker trips access the site from the south, since the Tunnel Road/Roble
Road intersection to the north is right-in/right-out only.
Truck Trip Distribution
All trucks would be directed to use SR 24 to access the site. The recommended truck route plan is shown
on Figure 7. The plan shows two possible origins for inbound truck traffic, either coming from westbound
or eastbound SR 24. Truck trips from eastbound SR 24 would access the Project site via the Broadway
Interchange, and travel east on Broadway, to Golden Gate Way. Truck trips from westbound SR 24
would access the Project site via the Tunnel Road interchange, cross SR 24 using the Kay Overcrossing
to Broadway, then turn left onto Golden Gate Way. From Golden Gate Way, trucks would turn right onto
Golden Gate Avenue, right onto Chabot Road, and left onto Roble Road. This section of Roble Road
becomes very narrow, with as little as 12 feet of pavement in some sections. Low hanging tree branches
further constrain the roadway. Larger semi-trucks would need to access the site from Tunnel Road. As
discussed above, this intersection is only right-in/right-out; therefore truck trips would likely need to travel
from Interstate 80 along SR 13 (Ashby Avenue) to Tunnel Road.
Outbound trucks would turn right onto Tunnel Road. From Tunnel Road, trucks would access westbound
SR 24 from Caldecott Lane or eastbound SR 24 from Broadway.
Broadway Ter
Broadway Ter
Chabot Rd
Broadway Broadway
Mile
s Ave
Mile
s Ave
Mo
un
tain B
lvd
Mo
un
tain B
lvd
Harbord Dr
Harbord Dr
Keith Ave
Keith Ave
Cla
rem
on
t A
ve
Cla
rem
on
t A
ve
Ocean View Dr
Ocean View Dr
Go
lde
nG
old
en
Ga
te A
ve
Ga
te A
ve
Acacia AveAcacia Ave
Florence Ave
Florence Ave
Margarido DrMargarido Dr
Ro
ble
Rd
Ro
ble
Rd
Buena Vista Ave
Buena Vista Ave
Proctor Ave
Proctor Ave
Hiller Dr
Hiller Dr
Taft Ave
Taft Ave
Fairlane D
r
Fairlane D
r
Hillcrest RdHillcrest Rd
Ro
ma
ny
Rd
Ro
ma
ny
Rd
Lawton Ave
Lawton Ave
Kales Ave
Kales AveClarew
ood Dr
Clarewood D
r
Contra Costa Rd
Contra Costa Rd
Le
o W
ay
Le
o W
ay
Harwood Ave
Cro
ss Rd
Cro
ss Rd
The Uplands The Uplands
Th
om
as
Ave
Th
om
as
Ave
Woolsey St
Florio St
Swain
land R
d
Swain
land R
d
Du
ncan
Way
Du
ncan
Way
Monroe Ave
Monroe Ave
Cochrane Ave
Cochrane Ave
Pinew
ood Rd
Pinew
ood Rd
Man
dalay R
d
Man
dalay R
d
Birch Ct
Birch Ct
Bry
an
t A
ve
Bo
yd A
ve
Bo
yd A
ve
Jam
es A
ve
Jam
es A
ve
Alta RdAlta Rd
Hill C
tH
ill Ct
Ca
rlton
St
Ca
rlton
St
Clifton St
Ruthland RdRuthland Rd
Co
un
try C
lub
Dr
Co
un
try C
lub
Dr
Forest St
Forest St
Hudson St
Hudson St
Cald
well R
d
Cald
well R
d
Sheridan Rd
Sheridan Rd
Brookside Ave
Brookside Ave
Sp
y G
lass
Hl
Sp
y G
lass
Hl
Ma
nch
este
r Dr
Ma
nch
este
r Dr
Clare
wo
od
Ln
Clare
wo
od
Ln
Glenw
oo
d G
lade
Glenw
oo
d G
lade
Be
lgra
ve P
l
Be
lgra
ve P
l
Be
nv
en
ue
Av
e
63rd St
Ro
ss St
Ro
ss St
Sonia St
Sonia St
Gle
nb
roo
k D
rG
len
bro
ok
Dr
Me
nd
oci
no
Ave
Me
nd
oci
no
Ave
Mo
rpet
h S
t
Mo
rpet
h S
t
Agnes StAgnes St
Hermosa Ave
Hermosa Ave
Ro
an
ok
e R
dR
oa
no
ke
Rd
Gle
nar
ms
Dr
Gle
nar
ms
Dr
Aquarius Way
Aquarius Way
Ma
thie
u A
ve
Ma
thie
u A
ve
Bin
na
cle
Hl
Bin
na
cle
Hl
Hill RdHill Rd
Vicente Rd
Vicente Rd
Pa
li Ct
Pa
li Ct
Alp
ine Ter
Alp
ine Ter
Ch
ab
ot C
t
Ch
ab
ot C
t
Ada StAda St
Ch
ab
oly
n Te
r
Ch
ab
oly
n Te
r
Ross Cir
Win
dw
ard
Hl
Win
dw
ard
Hl
Ch
ab
ot C
rstC
ha
bo
t Crst
Starview Dr
Starview Dr
Rockridge Blvd
Rockridge Blvd
Wilding Ln
Wilding Ln
Reata P
l
Reata P
l
Modoc AveModoc Ave
Eust
ice
Ave
Eust
ice
Ave
Fairlane DrFairlane Dr
Sheridan Rd
Sheridan Rd
Broadway Ter
Chabot Rd
Broadway
Mile
s Ave
Mo
un
tain B
lvd
Harbord Dr
Keith Ave
Cla
rem
on
t A
ve
Ocean View Dr
Acacia Ave
Florence Ave
Margarido Dr
Ro
ble
Rd
Buena Vista Ave
Proctor Ave
Hiller Dr
Taft Ave
Fairlane D
r
Hillcrest Rd
Ro
ma
ny
Rd
Lawton Ave
Kales AveClarew
ood Dr
Contra Costa Rd
Le
o W
ay
Harwood Ave
Cro
ss Rd
The Uplands
Th
om
as
Ave
Woolsey St
Florio St
Swain
land R
d
Du
ncan
Way
Monroe Ave
Cochrane Ave
Pinew
ood Rd
Man
dalay R
d
Birch Ct
Bry
an
t A
ve
Bo
yd A
ve
Jam
es A
ve
Alta Rd
Hill C
t
Ca
rlton
St
Clifton St
Ruthland Rd
Co
un
try C
lub
Dr
Forest St
Hudson St
Cald
well R
d
Sheridan Rd
Brookside Ave
Sp
y G
lass
Hl
Ma
nch
este
r Dr
Clare
wo
od
Ln
Glenw
oo
d G
lade
Be
lgra
ve P
l
Be
nv
en
ue
Av
e
63rd St
Ro
ss St
Sonia St
Gle
nb
roo
k D
r
Me
nd
oci
no
Ave
Mo
rpet
h S
t
Agnes St
Hermosa Ave
Ro
an
ok
e R
d
Gle
nar
ms
Dr
Aquarius Way
Ma
thie
u A
ve
Bin
na
cle
Hl
Hill Rd
Vicente Rd
Pa
li Ct
Alp
ine Ter
Ch
ab
ot C
t
Ada St
Ch
ab
oly
n Te
r
Ross Cir
Win
dw
ard
Hl
Ch
ab
ot C
rst
Starview Dr
Rockridge Blvd
Wilding Ln
Reata P
l
Modoc Ave
Eust
ice
Ave
Fairlane Dr
Sheridan Rd
Go
lde
n
Ga
te A
ve
Tunnel Rd
Tunnel Rd
Tunnel Rd
Tunnel RdTunnel Rd
Caldecott L
n
Tunnel Rd
Caldecott L
n
Golden Gate Ave
Golden Gate Ave
n
n
n
n
n
n
n
n
n
n
n3
4
67
2
1
24CALIFORNIA
24CALIFORNIA
13CALIFORNIA
13CALIFORNIA
HHHarwood Ad
Harwood A
Woolsey StWoolsey St
Florilorio Stiiiiii St
Florio St63rd Std63rd St
Ross CiriRoss Cir
t
Clifton S
ifClifton St
Not to Scale
LEGEND
To/From Oakland
To/From Caldecott Tunnel
BA
ve
Bee
nv
en
e
eeeeeeeeeeu
eAAAAA
uB
en
ve
nnnnnnu
e
ue
ue
ue
ue
ue
ue
ue
ueeee
uee
Av
eAA
To/From OTTTo
T /F CTo/From C/F m C
n
Study Intersection1
Flagger Location
Dingeee Backbone Pipeline Replacement
FIGURE 3March 2011WC10-2755_3_Dingee-GoldenGate
PHASE 1 – DINGEE PIPELINE TO GOLDEN GATE AVENUE TRUCK ROUTE
Broadway Ter
Broadway Ter
Chabot Rd
Chabot Rd
Broadway Broadway
Mile
s Ave
Mile
s Ave
Man
ila A
veM
ou
ntain
Blvd
Mo
un
tain B
lvd
Harbord Dr
Harbord Dr
Keith Ave
Keith Ave
Cla
rem
on
t A
ve
Cla
rem
on
t A
ve
Ocean View Dr
Ocean View Dr
Acacia AveAcacia Ave
Florence Ave
Florence Ave
Margarido DrMargarido Dr
Ro
ble
Rd
Ro
ble
Rd
Buena Vista Ave
Buena Vista Ave
Proctor Ave
Proctor Ave
Hiller Dr
Hiller Dr
Taft Ave
Taft Ave
Fairlane D
r
Fairlane D
r
Hillcrest RdHillcrest Rd
Ro
ma
ny
Rd
Ro
ma
ny
Rd
Lawton Ave
Lawton Ave
Kales Ave
Kales AveClarew
ood Dr
Clarewood D
r
Contra Costa Rd
Contra Costa Rd
Le
o W
ay
Le
o W
ay
Harwood Ave
Cro
ss Rd
Cro
ss Rd
The Uplands The Uplands
Th
om
as
Ave
Th
om
as
Ave
Woolsey St
Florio St
Swain
land R
d
Swain
land R
d
Du
ncan
Way
Du
ncan
Way
Monroe Ave
Monroe Ave
Cochrane Ave
Cochrane Ave
Pinew
ood Rd
Pinew
ood Rd
Man
dalay R
d
Man
dalay R
d
Birch Ct
Birch Ct
Bry
an
t A
ve
Bo
yd A
ve
Bo
yd A
ve
Jam
es A
ve
Jam
es A
ve
Alta RdAlta Rd
Hill C
tH
ill Ct
Ca
rlton
St
Ca
rlton
St
Clifton St
Ruthland RdRuthland Rd
Co
un
try C
lub
Dr
Co
un
try C
lub
Dr
Forest St
Forest St
Hudson St
Hudson St
Cald
well R
d
Cald
well R
d
Sheridan Rd
Sheridan Rd
Brookside Ave
Brookside Ave
Sp
y G
lass
Hl
Sp
y G
lass
Hl
Ma
nch
este
r Dr
Ma
nch
este
r Dr
Clare
wo
od
Ln
Clare
wo
od
Ln
Glenw
oo
d G
lade
Glenw
oo
d G
lade
Be
lgra
ve P
l
Be
lgra
ve P
l
Be
nv
en
ue
Av
e
63rd St
Ro
ss St
Ro
ss St
Sonia St
Sonia St
Gle
nb
roo
k D
rG
len
bro
ok
Dr
Me
nd
oci
no
Ave
Me
nd
oci
no
Ave
Mo
rpet
h S
t
Mo
rpet
h S
t
Agnes StAgnes St
Hermosa Ave
Hermosa Ave
Ro
an
ok
e R
dR
oa
no
ke
Rd
Gle
nar
ms
Dr
Gle
nar
ms
Dr
Aquarius Way
Aquarius Way
Ma
thie
u A
ve
Ma
thie
u A
ve
Bin
na
cle
Hl
Bin
na
cle
Hl
Hill RdHill Rd
Vicente Rd
Vicente Rd
Pa
li Ct
Pa
li Ct
Alp
ine Ter
Alp
ine Ter
Ch
ab
ot C
t
Ch
ab
ot C
t
Ada StAda St
Ch
ab
oly
n Te
r
Ch
ab
oly
n Te
r
Ross Cir
Win
dw
ard
Hl
Win
dw
ard
Hl
Ch
ab
ot C
rstC
ha
bo
t Crst
Starview Dr
Starview Dr
Rockridge Blvd
Rockridge Blvd
Wilding Ln
Wilding Ln
Reata P
l
Reata P
l
Modoc AveModoc Ave
Eust
ice
Ave
Eust
ice
Ave
Fairlane DrFairlane Dr
Sheridan Rd
Sheridan Rd
Broadway Ter
Chabot Rd
Broadway
Mile
s Ave
Man
ila A
veM
ou
ntain
Blvd
Harbord Dr
Keith Ave
Cla
rem
on
t A
ve
Ocean View Dr
Acacia Ave
Florence Ave
Margarido Dr
Ro
ble
Rd
Buena Vista Ave
Proctor Ave
Hiller Dr
Taft Ave
Fairlane D
r
Hillcrest Rd
Ro
ma
ny
Rd
Lawton Ave
Kales AveClarew
ood Dr
Contra Costa Rd
Le
o W
ay
Harwood Ave
Cro
ss Rd
The Uplands
Th
om
as
Ave
Woolsey St
Florio St
Swain
land R
d
Du
ncan
Way
Monroe Ave
Cochrane Ave
Pinew
ood Rd
Man
dalay R
d
Birch Ct
Bry
an
t A
ve
Bo
yd A
ve
Jam
es A
ve
Alta Rd
Hill C
t
Ca
rlton
St
Clifton St
Ruthland Rd
Co
un
try C
lub
Dr
Forest St
Hudson St
Cald
well R
d
Sheridan Rd
Brookside Ave
Sp
y G
lass
Hl
Ma
nch
este
r Dr
Clare
wo
od
Ln
Glenw
oo
d G
lade
Be
lgra
ve P
l
Be
nv
en
ue
Av
e
63rd St
Ro
ss St
Sonia St
Gle
nb
roo
k D
r
Me
nd
oci
no
Ave
Mo
rpet
h S
t
Agnes St
Hermosa Ave
Ro
an
ok
e R
d
Gle
nar
ms
Dr
Aquarius Way
Ma
thie
u A
ve
Bin
na
cle
Hl
Hill Rd
Vicente Rd
Pa
li Ct
Alp
ine Ter
Ch
ab
ot C
t
Ada St
Ch
ab
oly
n Te
r
Ross Cir
Win
dw
ard
Hl
Ch
ab
ot C
rst
Starview Dr
Rockridge Blvd
Wilding Ln
Reata P
l
Modoc Ave
Eust
ice
Ave
Fairlane Dr
Sheridan Rd
Go
lde
nG
old
en
Ga
te A
ve
Ga
te A
ve
Go
lde
n
Ga
te A
ve
Tunnel Rd
Tunnel Rd
Tunnel Rd
Tunnel RdTunnel Rd
Caldecott L
n
Tunnel Rd
Caldecott L
n
Golden Gate Ave
Golden Gate Ave
n
n
n
n
n
n
n
n
n
n
n
2
3
4
89 10
11
67
24CALIFORNIA
24CALIFORNIA
13CALIFORNIA
13CALIFORNIA
Woolsey StWoolsey St
tStStSt
Ross CiriRoss Cir
Man
iiM
anila
t
Clifton S
ifClifton St
Not to Scale
LEGEND
To/From Oakland
en
ve
Be
nv
en
uA
ve
Bee
nv
en
e
eeeeeeeeeeeu
eeeAAAAA
uB
en
ve
nnnnnu
e
ue
ue
ue
ue
ue
ue
ue
ueeee
uee
Av
eA
To/From OTTTo
nStudy Intersection1
To/From Caldecott Tunnel
Dingeee Backbone Pipeline Replacement
FIGURE 4March 2011WC10-2755_4_GoldenGate-BroadwayTer
PHASE 2 – GOLDEN GATE AVENUE TO BROADWAY TERRACE TRUCK ROUTE
Harbord Dr
Harbord Dr
Moraga Ave
Moraga Ave
Mo
un
tain B
lvd
Mo
un
tain B
lvdB
roa
dw
ay
Bro
ad
way
Broadway Ter
Broadway Ter
Clarewood D
r
Clarewood D
r
Manila Ave
Manila Ave
Ocean View Dr
Ocean View Dr
Keith Ave
Keith Ave
Acacia AveAcacia Ave
Florence Ave
Florence Ave
How
e St
Margarido DrMargarido Dr
Am
y Dr
Am
y Dr
Proctor Ave
Proctor Ave
Estates Dr
Estates Dr
Miles Ave
Miles Ave
Ro
ma
ny
Rd
Ro
ma
ny
Rd
Masonic AveMasonic Ave
Taft Ave
Taft Ave
Buena Vista Ave
Buena Vista Ave
Contra Costa Rd
Contra Costa Rd
Le
o W
ay
Le
o W
ay
Lawton Ave
Lawton Ave
Kales Ave
Kales Ave
Cro
ss Rd
Cro
ss Rd
Du
ncan
Way
Du
ncan
Way
Th
om
as
Ave
Th
om
as
Ave
Fairlane D
r
Fairlane D
r
Swain
land R
d
Swain
land R
d
Monroe Ave
Monroe Ave
Ruthland RdRuthland Rd
Ronada AveRonada Ave
Cochrane Ave
Cochrane Ave
Pinew
ood Rd
Pinew
ood Rd
Ca
pri
corn
Av
e
Ca
pri
corn
Av
e
Man
dalay R
d
Man
dalay R
d
Ta
uru
s A
ve
Ta
uru
s A
ve
Maxwelton Rd
Maxwelton Rd
Johnston Dr
Johnston Dr
Fernwood Dr
Fernwood Dr
Pleasant Valley Ave
Piedmont Ave
Piedmont Ave
Alta RdAlta Rd
Pa
la A
ve
Pa
la A
ve
Ca
rlton
St
Ca
rlton
StB
rya
nt
Ave
Bry
an
t A
ve
Co
un
try C
lub
Dr
Co
un
try C
lub
Dr
Vir
go
Rd
Vir
go
Rd
Cald
well R
d
Cald
well R
d
Hillto
p C
res
Hillto
p C
res
Ramona AveRamona Ave
View
St
Sheridan Rd
Sheridan Rd
Bullard Dr
Bullard Dr
Ma
nch
este
r Dr
Ma
nch
este
r Dr
Clare
wo
od
Ln
Clare
wo
od
Ln
Glenw
oo
d G
lade
Glenw
oo
d G
lade
Birch Ct
Birch Ct
Be
lgra
ve P
l
Be
lgra
ve P
l
Heron Dr
Heron Dr
Sonia St
Sonia St
Gle
nb
roo
k D
rG
len
bro
ok
Dr
Me
nd
oci
no
Ave
Me
nd
oci
no
Ave
Mo
rpet
h S
t
Mo
rpet
h S
t
Agnes StAgnes St
Clifton St
Clifton St
Mo
nte
Av
e
Mo
nte
Av
e
Hermosa Ave
Hermosa Ave
Gle
nar
ms
Dr
Gle
nar
ms
Dr
Aquarius Way
Aquarius Way
Ma
thie
u A
ve
Ma
thie
u A
ve
Hill RdHill Rd
Scenic Ave
Scenic Ave
Me
sa A
ve
Me
sa A
ve
Tem
pla
r P
lTe
mp
lar
Pl
Pa
li Ct
Pa
li Ct
Bo
nita
Av
e
Bo
nita
Av
e
Alp
ine Ter
Alp
ine Ter
Saint P
aul Ct
Saint P
aul Ct
Abbott Way
Abbott Way
Th
orn
hil
l Dr
Th
orn
hil
l Dr
Rockridge Blvd
Rockridge Blvd
Wilding Ln
Wilding Ln
Truit
t Ln
Truit
t Ln
Modoc AveModoc Ave
Novara RdNovara Rd
Stark Knoll Pl
Stark Knoll Pl
Gw
in C
t
Ramona Ave
Sheridan Rd
Sheridan Rd
Proctor Ave
Proctor Ave
Estate
s Dr
Estate
s Dr
Harbord Dr
Moraga Ave
Mo
un
tain B
lvdB
roa
dw
ay
Broadway Ter
Clarewood D
r
Manila Ave
Ocean View Dr
Keith Ave
Acacia Ave
Florence Ave
How
e St
Margarido Dr
Am
y Dr
Proctor Ave
Estates Dr
Miles Ave
Ro
ma
ny
Rd
Masonic Ave
Taft Ave
Buena Vista Ave
Contra Costa Rd
Le
o W
ay
Lawton Ave
Kales Ave
Cro
ss Rd
Du
ncan
Way
Th
om
as
Ave
Fairlane D
r
Swain
land R
d
Monroe Ave
Ruthland Rd
Ronada Ave
Cochrane Ave
Pinew
ood Rd
Ca
pri
corn
Av
e
Man
dalay R
d
Ta
uru
s A
ve
Maxwelton Rd
Johnston Dr
Fernwood Dr
Pleasant Valley Ave
Piedmont Ave
Alta Rd
Pa
la A
ve
Ca
rlton
StB
rya
nt
Ave
Co
un
try C
lub
Dr
Vir
go
Rd
Cald
well R
d
Hillto
p C
res
Ramona Ave
View
St
Sheridan Rd
Bullard Dr
Ma
nch
este
r Dr
Clare
wo
od
Ln
Glenw
oo
d G
lade
Birch Ct
Be
lgra
ve P
l
Heron Dr
Sonia St
Gle
nb
roo
k D
r
Me
nd
oci
no
Ave
Mo
rpet
h S
t
Agnes St
Clifton St
Mo
nte
Av
e
Hermosa Ave
Gle
nar
ms
Dr
Aquarius Way
Ma
thie
u A
ve
Hill Rd
Scenic Ave
Me
sa A
ve
Tem
pla
r P
l
Pa
li Ct
Bo
nita
Av
e
Alp
ine Ter
Saint P
aul Ct
Abbott Way
Th
orn
hil
l Dr
Rockridge Blvd
Wilding Ln
Truit
t Ln
Modoc Ave
Novara Rd
Stark Knoll Pl
Gw
in C
t
Ramona Ave
Sheridan Rd
Proctor Ave
Estate
s Dr
Moraga AveMoraga Ave
Ha
rbo
rd D
r
Ha
rbo
rd D
r
Ha
rbo
rd D
r
Golden Gate Ave
Golden Gate Ave
n
n
n
n
n
n
n
nn
n
12
9 10
11
13
14
24CALIFORNIA 13
CALIFORNIA
13CALIFORNIA
Gw
in C
t
Gw
iG
win
Ct
Not to Scale
veveeve
RaRam
LEGENDTruck Route
Project
School
VVVi
HHHow
e St
How
e St
vAA
leyA
ey Av
Avve
Valleey
Valley
Valley Ave
leasana
PPPPPPPPPPlPlPlePlPP
asaa
PPPPPPPlPlPlPlPlePlePlePlePlePlePlePPlPleP
asan
VViiew
St
iew
View
St
LEGENDELETruck RouTru
Projectect
hoolhoScS
nt Vnt Vt VVnt Vnt Vn
Study Intersection1
Dingeee Backbone Pipeline Replacement
FIGURE 5March 2011WC10-2755_5_Broadway-Moraga
PHASE 3 – BROADWAY TERRACE TO MORAGA AVENUE TRUCK ROUTE
Broadway Ter
Broadway Ter
Chabot Rd
Chabot Rd
Broadway Broadway
Mile
s Ave
Mile
s Ave
Man
ila A
veM
ou
ntain
Blvd
Mo
un
tain B
lvd
Harbord Dr
Harbord Dr
Keith Ave
Keith Ave
Cla
rem
on
t A
ve
Cla
rem
on
t A
ve
Ocean View Dr
Ocean View Dr
Go
lde
n G
ate
Av
eG
old
en
Ga
te A
ve
Acacia AveAcacia Ave
Florence Ave
Florence Ave
Margarido DrMargarido Dr
Ro
ble
Rd
Ro
ble
Rd
Buena Vista Ave
Buena Vista Ave
Proctor Ave
Proctor Ave
Hiller Dr
Hiller Dr
Taft Ave
Taft Ave
Fairlane D
r
Fairlane D
r
Hillcrest RdHillcrest Rd
Ro
ma
ny
Rd
Ro
ma
ny
Rd
Lawton Ave
Lawton Ave
Kales Ave
Kales AveClarew
ood Dr
Clarewood D
r
Contra Costa Rd
Contra Costa Rd
Le
o W
ay
Le
o W
ay
Harwood Ave
Harwood Ave
The Uplands The Uplands
Th
om
as
Ave
Th
om
as
Ave
Woolsey St
Florio St
Swain
land R
d
Swain
land R
d
Du
ncan
Way
Du
ncan
Way
Monroe Ave
Monroe Ave
Cochrane Ave
Cochrane Ave
Pinew
ood Rd
Pinew
ood Rd
Man
dalay R
d
Man
dalay R
d
Birch Ct
Birch Ct
Bry
an
t A
ve
Bo
yd A
ve
Bo
yd A
ve
Jam
es A
ve
Jam
es A
ve
Alta RdAlta Rd
Hill C
tH
ill Ct
Ca
rlton
St
Ca
rlton
St
Clifton St
Ruthland RdRuthland Rd
Co
un
try C
lub
Dr
Co
un
try C
lub
Dr
Forest St
Forest St
Hudson St
Hudson St
Cald
well R
d
Cald
well R
d
Sheridan Rd
Sheridan Rd
Brookside Ave
Brookside Ave
Sp
y G
lass
Hl
Sp
y G
lass
Hl
Ma
nch
este
r Dr
Ma
nch
este
r Dr
Clare
wo
od
Ln
Clare
wo
od
Ln
Glenw
oo
d G
lade
Glenw
oo
d G
lade
Be
lgra
ve P
l
Be
lgra
ve P
l
Be
nv
en
ue
Av
e
63rd St
Ro
ss St
Ro
ss St
Sonia St
Sonia St
Gle
nb
roo
k D
rG
len
bro
ok
Dr
Me
nd
oci
no
Ave
Me
nd
oci
no
Ave
Mo
rpet
h S
t
Mo
rpet
h S
t
Agnes StAgnes St
Hermosa Ave
Hermosa Ave
Ro
an
ok
e R
dR
oa
no
ke
Rd
Gle
nar
ms
Dr
Gle
nar
ms
Dr
Aquarius Way
Aquarius Way
Ma
thie
u A
ve
Ma
thie
u A
ve
Bin
na
cle
Hl
Bin
na
cle
Hl
Hill RdHill Rd
Vicente Rd
Vicente Rd
Pa
li Ct
Pa
li Ct
Alp
ine Ter
Alp
ine Ter
Ch
ab
ot C
t
Ch
ab
ot C
t
Ada StAda St
Ch
ab
oly
n Te
r
Ch
ab
oly
n Te
r
Ross Cir
Win
dw
ard
Hl
Win
dw
ard
Hl
Ch
ab
ot C
rstC
ha
bo
t Crst
Starview Dr
Starview Dr
Rockridge Blvd
Rockridge Blvd
Wilding Ln
Wilding Ln
Reata P
l
Reata P
l
Modoc AveModoc Ave
Eust
ice
Ave
Eust
ice
Ave
Fairlane DrFairlane Dr
Sheridan Rd
Sheridan Rd
Broadway Ter
Chabot Rd
Broadway
Mile
s Ave
Man
ila A
veM
ou
ntain
Blvd
Harbord Dr
Keith Ave
Cla
rem
on
t A
ve
Ocean View Dr
Go
lde
n G
ate
Av
e
Acacia Ave
Florence Ave
Margarido Dr
Ro
ble
Rd
Buena Vista Ave
Proctor Ave
Hiller Dr
Taft Ave
Fairlane D
r
Hillcrest Rd
Ro
ma
ny
Rd
Lawton Ave
Kales AveClarew
ood Dr
Contra Costa Rd
Le
o W
ay
Harwood Ave
The Uplands
Th
om
as
Ave
Woolsey St
Florio St
Swain
land R
d
Du
ncan
Way
Monroe Ave
Cochrane Ave
Pinew
ood Rd
Man
dalay R
d
Birch Ct
Bry
an
t A
ve
Bo
yd A
ve
Jam
es A
ve
Alta Rd
Hill C
t
Ca
rlton
St
Clifton St
Ruthland Rd
Co
un
try C
lub
Dr
Forest St
Hudson St
Cald
well R
d
Sheridan Rd
Brookside Ave
Sp
y G
lass
Hl
Ma
nch
este
r Dr
Clare
wo
od
Ln
Glenw
oo
d G
lade
Be
lgra
ve P
l
Be
nv
en
ue
Av
e
63rd St
Ro
ss St
Sonia St
Gle
nb
roo
k D
r
Me
nd
oci
no
Ave
Mo
rpet
h S
t
Agnes St
Hermosa Ave
Ro
an
ok
e R
d
Gle
nar
ms
Dr
Aquarius Way
Ma
thie
u A
ve
Bin
na
cle
Hl
Hill Rd
Vicente Rd
Pa
li Ct
Alp
ine Ter
Ch
ab
ot C
t
Ada St
Ch
ab
oly
n Te
r
Ross Cir
Win
dw
ard
Hl
Ch
ab
ot C
rst
Starview Dr
Rockridge Blvd
Wilding Ln
Reata P
l
Modoc Ave
Eust
ice
Ave
Fairlane Dr
Sheridan Rd
Tunnel Rd
Tunnel Rd
Tunnel Rd
Tunnel RdTunnel Rd
Caldecott L
n
Tunnel Rd
Caldecott L
n
Broadway TerBroadway Ter
Cro
ss Rd
Cro
ss Rd Broadway Ter
Cro
ss Rd
Aca
cia
Aca
cia
Av
eA
ve
Aca
cia
Av
e Golden Gate Ave
Golden Gate Ave
n
n
n
n
n
n
n
n
n
n
n
89 10
11
24CALIFORNIA
24CALIFORNIA
13CALIFORNIA
13CALIFORNIA
y Sty St
io SStio St3rd St3rd St
Ross CRoss C
Study Intersection1
Man
iiM
anila
t
Clifton S
ifClifton St
Not to Scale
LEGENDTruck Route
en
ve
Be
nv
en
u
WoolseyWoolsey
Av
eB
een
ve
nu
e A
uB
en
ve
nu
e A
ve
LEGENDGTruck RouTruTTr
n
Dingeee Backbone Pipeline Replacement
FIGURE 6March 2011WC10-2755_6_ContraCosta
PHASE 4 – CONTRA COSTA ROAD TRUCK ROUTE
n
n
n
n
n
n
n
n
n
n
n
Go
lde
nG
old
en
Ga
te A
ve
Ga
te A
ve
Go
lde
n
Ga
te A
ve
Broadway Ter
Broadway Ter
Chabot Rd
Broadway Broadway
Co
lleg
e A
ve
Mile
s Ave
Mile
s Ave
Man
ila A
veM
ou
ntain
Blvd
Mo
un
tain B
lvd
Harbord Dr
Harbord Dr
Keith Ave
Keith Ave
Cla
rem
on
t A
ve
Cla
rem
on
t A
ve
Ocean View Dr
Ocean View Dr
Acacia AveAcacia Ave
Florence Ave
Florence Ave
Margarido DrMargarido Dr
Ro
ble
Rd
Ro
ble
Rd
Buena Vista Ave
Buena Vista Ave
Proctor Ave
Proctor Ave
Hiller Dr
Hiller Dr
Taft Ave
Taft Ave
Fairlane D
r
Fairlane D
r
Hillcrest RdHillcrest Rd
Ro
ma
ny
Rd
Ro
ma
ny
Rd
Lawton Ave
Lawton Ave
Kales Ave
Kales AveClarew
ood Dr
Clarewood D
r
Contra Costa Rd
Contra Costa Rd
Le
o W
ay
Le
o W
ay
Harwood Ave
Cro
ss Rd
Cro
ss Rd
The Uplands The Uplands
Th
om
as
Ave
Th
om
as
Ave
Woolsey St
Florio St
Swain
land R
d
Swain
land R
d
Du
ncan
Way
Du
ncan
Way
Monroe Ave
Monroe Ave
Cochrane Ave
Cochrane Ave
Pinew
ood Rd
Pinew
ood Rd
Man
dalay R
d
Man
dalay R
d
Birch Ct
Birch Ct
Bry
an
t A
ve
Bo
yd A
ve
Bo
yd A
ve
Jam
es A
ve
Jam
es A
ve
Alta RdAlta Rd
Hill C
tH
ill Ct
Ca
rlton
St
Ca
rlton
St
Clifton St
Ruthland RdRuthland Rd
Co
un
try C
lub
Dr
Co
un
try C
lub
Dr
Alcatraz Ave
Forest St
Forest St
Hudson St
Hudson St
Cald
well R
d
Cald
well R
d
Eton
Ave
Sheridan Rd
Sheridan Rd
Brookside Ave
Brookside Ave
Sp
y G
lass
Hl
Sp
y G
lass
Hl
Ma
nch
este
r Dr
Ma
nch
este
r Dr
Clare
wo
od
Ln
Clare
wo
od
Ln
Glenw
oo
d G
lade
Glenw
oo
d G
lade
Be
lgra
ve P
l
Be
lgra
ve P
l
Be
nv
en
ue
Av
e
63rd St
Ro
ss St
Ro
ss St
Sonia St
Sonia St
Gle
nb
roo
k D
rG
len
bro
ok
Dr
Me
nd
oci
no
Ave
Me
nd
oci
no
Ave
Mo
rpet
h S
t
Mo
rpet
h S
t
Agnes StAgnes St
Hermosa Ave
Hermosa Ave
Ro
an
ok
e R
dR
oa
no
ke
Rd
Gle
nar
ms
Dr
Gle
nar
ms
Dr
Aquarius Way
Aquarius Way
Ma
thie
u A
ve
Ma
thie
u A
ve
Bin
na
cle
Hl
Bin
na
cle
Hl
Hill RdHill Rd
Vicente Rd
Vicente Rd
Pa
li Ct
Pa
li Ct
Alp
ine Ter
Alp
ine Ter
Ch
ab
ot C
t
Ch
ab
ot C
t
Ada StAda St
Ch
ab
oly
n Te
r
Ch
ab
oly
n Te
r
Ross Cir
Win
dw
ard
Hl
Win
dw
ard
Hl
Ch
ab
ot C
rstC
ha
bo
t Crst
Starview Dr
Starview Dr
Rockridge Blvd
Rockridge Blvd
Wilding Ln
Wilding Ln
Reata P
l
Reata P
l
Modoc AveModoc Ave
Eust
ice
Ave
Eust
ice
Ave
Fairlane DrFairlane Dr
Sheridan Rd
Sheridan Rd
Broadway Ter
Chabot Rd
Broadway
Co
lleg
e A
ve
Mile
s Ave
Man
ila A
veM
ou
ntain
Blvd
Harbord Dr
Keith Ave
Cla
rem
on
t A
ve
Ocean View Dr
Acacia Ave
Florence Ave
Margarido Dr
Ro
ble
Rd
Buena Vista Ave
Proctor Ave
Hiller Dr
Taft Ave
Fairlane D
r
Hillcrest Rd
Ro
ma
ny
Rd
Lawton Ave
Kales AveClarew
ood Dr
Contra Costa Rd
Le
o W
ay
Harwood Ave
Cro
ss Rd
The Uplands
Th
om
as
Ave
Woolsey St
Florio St
Swain
land R
d
Du
ncan
Way
Monroe Ave
Cochrane Ave
Pinew
ood Rd
Man
dalay R
d
Birch Ct
Bry
an
t A
ve
Bo
yd A
ve
Jam
es A
ve
Alta Rd
Hill C
t
Ca
rlton
St
Clifton St
Ruthland Rd
Co
un
try C
lub
Dr
Alcatraz Ave
Forest St
Hudson St
Cald
well R
d
Eton
Ave
Sheridan Rd
Brookside Ave
Sp
y G
lass
Hl
Ma
nch
este
r Dr
Clare
wo
od
Ln
Glenw
oo
d G
lade
Be
lgra
ve P
l
Be
nv
en
ue
Av
e
63rd St
Ro
ss St
Sonia St
Gle
nb
roo
k D
r
Me
nd
oci
no
Ave
Mo
rpet
h S
t
Agnes St
Hermosa Ave
Ro
an
ok
e R
d
Gle
nar
ms
Dr
Aquarius Way
Ma
thie
u A
ve
Bin
na
cle
Hl
Hill Rd
Vicente Rd
Pa
li Ct
Alp
ine Ter
Ch
ab
ot C
t
Ada St
Ch
ab
oly
n Te
r
Ross Cir
Win
dw
ard
Hl
Ch
ab
ot C
rst
Starview Dr
Rockridge Blvd
Wilding Ln
Reata P
l
Modoc Ave
Eust
ice
Ave
Fairlane Dr
Sheridan Rd
Tunnel Rd
Tunnel Rd
Tunnel RdTunnel Rd
Tunnel Rd
Caldecott L
n
Tunnel Rd
Caldecott L
n
Golden Gate Ave
Golden Gate Ave
2
1 3
4
56
7
24CALIFORNIA
24CALIFORNIA
13CALIFORNIA
13CALIFORNIA
Man
iiM
anila
t
Clifton S
ifClifton St
Not to Scale
HHHarwood Ad
Harwood A
Woolsey StWoolsey St
Florilorio Stiiiiii St
Florio St63rd Std63rd St
Ross CiriRoss Cir
LEGEND
To/From Oakland
To/From Caldecott Tunnel
Project
B
eg
eee AAAAAAA
veeee
Co
Co
Co
lleg
eee AAAAAAAAAA
veeeeee
AAAAlcatraralcatrrtraz AAve
Alcatraz Ave
Ave
Ave
Eton
Eton
Av
eB
een
ve
ne
eeeeeeeeee
ue
AAAAAu
Be
nv
ennnnnn
ue
u
eu
eu
eu
eu
eu
eu
eu
eeeeu
eeA
ve
AA
To/From OTTo FrE
Com Cm CmT /FTo/Fro/FFFrono
nA
nA
on
An
A
Projectt
CC
n
Study Intersection1
Flagger Location
e
Dingeee Backbone Pipeline Replacement
FIGURE 7March 2011WC10-2755_7_Roble
PHASE 5 – ROBLE ROAD TRUCK ROUTE
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
24
CHAPTER 4. IMPACTS AND MITIGATION MEASURES
This chapter discusses the potential transportation and circulation impacts during the construction phase.
The duration of Project impacts are limited to the construction period, as trip generation characteristics
after construction would be limited to occasional maintenance activities similar to existing conditions.
Therefore, the mitigation measures presented in this chapter are designed to reduce the impact of the
short-term effects of construction traffic. The CEQA checklist for transportation impacts is presented
below:
Environmental Factors and Focused Questions for
Determination of Environmental Impact
Potentially
Significant
Impact
Less Than
Significant with
Mitigation
Less Than
Significant
Impact
No
Impact
TRANSPORTATION/TRAFFC — Would the Project:
a) Conflict with an applicable plan, ordinance or policy establishing measures of effectiveness for the performance of the circulation system, taking into account all modes of transportation including mass transit and non-motorized travel and relevant components of the circulation system, including but not limited to intersections, streets, highways and freeways, pedestrian and bicycle paths, and mass transit?
[ ] [ X ] [ ] [ ]
b) Conflict with an applicable congestion management program, including, but not limited to level of service standards and travel demand measures, or other standards established by the county congestion management agency for designated roads or highways?
[ ] [ X ] [ ] [ ]
c) Result in a change in air traffic patterns, including either an increase in traffic levels or a change in location that results in substantial safety risks?
[ ] [ ] [ ] [ X ]
d) Substantially increase hazards due to a design feature (e.g., sharp curves or dangerous intersections) or incompatible uses (e.g., farm equipment)?
[ ] [ X ] [ ] [ ]
e) Result in inadequate emergency access? [ ] [ X ] [ ] [ ]
f) Conflict with adopted policies, plans, or programs regarding public transit, bicycle, or pedestrian facilities, or otherwise decrease the performance or safety of such facilities?
[ ] [ ] [ ] [ X ]
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
25
ROADWAY AND INTERSECTION ANALYSIS
Daily traffic volumes during construction periods were added to the existing daily traffic volumes based on
the trip generation and trip distribution percentages presented in Chapter 3. The results are presented in
Table 6. All streets would continue to operate below their theoretical daily capacity. Project traffic
represents less than a 2 percent increase in daily traffic on Broadway Terrace, which is considered within
typical daily fluctuations.
TABLE 6 EXISTING DAILY TRAFFIC VOLUMES PLUS CONSTRUCTION TRAFFIC
Roadway Location Existing
Daily Traffic
Maximum Project
Daily Added Traffic
Total Maximum
Daily Traffic
Theoretical Daily
Capacity1
A. Golden Gate Avenue South of Golden Gate Way 1,480 112 1,586 3,000
B. Broadway Terrace West of Proctor Avenue 6,260 100 6,358 N/A
C. Proctor Avenue North of Julia Street 480 51 530 1,500
D. Harbord Drive North of Moraga Avenue 2,650 51 2,701 3,000
Notes
1. Daily capacities taken from Table 13-6 of the Institute of Transportation Engineers (ITE) Transportation and Land Development, 2002.
Source: Fehr & Peers, 2010; Transportation and Land Development, ITE, 2002.
Using the hourly trip generation estimates from Table 5 and trip distribution described above, Existing
Plus Project peak hour traffic volumes were determined for each construction phase. It was assumed
that all worker vehicle trips would travel to the Project site during the AM peak hour and leave during the
PM peak hour. It was assumed that half of the hourly truck trips would be arriving at the site and half
would be leaving the Project site during each peak hour. During phases 1, 2, and 5, where there are two
truck routes presented, the maximum number of trucks was assumed for each route as a conservative
estimate. Existing Plus Project peak hour volumes for each phase are presented in Appendix B. As
discussed in Chapter 3, multiple project phases could be constructed at the same time. The three
possible scenarios were evaluated by combining the truck routes and trip generation from individual
construction phases.
Phase 1 – Dingee Pumping Plant to Golden Gate Avenue
Phase 1 peak hour intersection operations with construction traffic volumes assigned to the roadway
network are summarized in Table 7. Results are only shown for intersections with added Project traffic
during Phase 1.
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
26
As shown in Table 7, Project construction traffic is not expected to significantly degrade intersection
operations from an acceptable level to an unacceptable level. Additionally, the unsignalized intersections
do not meet Caltrans peak hour signal warrants. Thus, the added Project traffic is considered to have a
less than significant impact to intersection operations considering the CEQA guidelines and the City of
Oakland significance criteria.
Construction traffic would also temporarily reduce the traffic speed on Golden Gate Avenue as trucks
would travel more slowly through the area. This is considered a short-term significant impact.
Phase 2 – Golden Gate Avenue to Broadway Terrace
Phase 2 peak hour intersection operations with construction traffic volumes assigned to the roadway
network are summarized in Table 8. Results are only shown for intersections with Project traffic during
Phase 2.
TABLE 7 TRUCK ROUTE 1: DINGEE PP TO GOLDEN GATE AVENUE EXISTING PLUS PROJECT INTERSECTION OPERATIONS
Intersection Control Peak Hour
Existing Truck Route 1
Delay LOS Delay LOS
1. Patton Street/Miles Avenue All-way
Stop
AM
PM
4.4
3.2
A
A
4.4
3.3
A
A
2. Broadway/Keith Avenue Signal AM
PM
16.8
13.7
B
B
16.9
13.8
B
B
3. Broadway/Brookside Avenue/SR 24 Side-Street Stop
1
AM
PM
2.2 (WB 12.2)
3.4 (WB 68.6)
A (B)
A (F)
2.3 (WB 12.3)
5.0 (WB 83.5)
A (B)
A (F)
4. Broadway/Golden Gate Way Side-Street Stop
1
AM
PM
4.0 (NB 17.8)
1.8 (NB 13.8)
A (C)
A (B)
4.5 (NB 19.3)
2.4 (NB 14.9)
A (C)
A (B)
6. Caldecott Lane/Kay Overcrossing Side-Street Stop
1
AM
PM
2.4 (WB 20.8)
1.9 (WB 13.6)
A (C)2
A (B) 2
2.6 (WB 22.0)
2.0 (WB 13.9)
A (C)2
A (B) 2
7. Broadway/Kay Overcrossing Signal AM
PM
35.4
36.1
D2
D2
36.7
36.3
D2
D2
Notes
1. For side-street-stop intersections, average delay is listed first followed by the delay for the worst approach.
2. Field observations indicate LOS F conditions due to queue spillback from the eastbound SR 24 on-ramp.
Source: Fehr & Peers, 2010
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
27
As shown in Table 8, the Project construction traffic is not expected to significantly degrade intersection
operations from an acceptable level to an unacceptable level at signalized intersections.
The unsignalized intersection of Broadway Terrace/Glenwood Glade/Pinewood Road meets Caltrans
peak hour signal warrant and the project is expected to add more than 10 vehicles during the AM peak
hour. Thus, the added Project traffic is considered to have a short-term significant impact to
intersection operations considering the City of Oakland significance criteria. All other unsignalized study
intersections do not meet Caltrans peak hour signal warrant.
Construction traffic would also temporarily reduce the traffic speed on Golden Gate Avenue and
Broadway Terrace as trucks would travel more slowly through the area. Additionally, transit riders could
TABLE 8 TRUCK ROUTE 2: GOLDEN GATE AVENUE TO BROADWAY TERRACE
EXISTING PLUS PROJECT INTERSECTION OPERATIONS
Intersection Control Peak Hour
Existing Truck Route 1
Delay LOS Delay LOS
1. Patton Street/Miles Avenue All-way
Stop
AM
PM
4.4
3.2
A
A
--
3.0
--
A
2. Broadway/Keith Avenue Signal AM
PM
16.8
13.7
B
B
16.9
13.8
B
B
3. Broadway/SR 24 eastbound on-ramp
Side-Street Stop
1
AM
PM
2.2 (WB 12.2)
3.4 (WB 68.6)
A (B)
A (F)
2.2 (WB 12.2)
3.7 (WB 71.4)
A (B)
A (F)
4. Broadway/Golden Gate Way Side-Street Stop
1
AM
PM
4.0 (NB 17.8)
1.8 (NB 13.8)
A (C)
A (B)
4.2 (NB 18.5)
2.1 (NB 13.8)
A (C)
A (B)
6. Caldecott Lane/Kay Overcrossing Side-Street Stop
1
AM
PM
2.4 (WB 20.8)
1.9 (WB 13.6)
A (C)2
A (B) 2
2.6 (WB 21.7)
2.0 (WB 13.9)
A (C)2
A (B) 2
7. Broadway/Kay Overcrossing Signal AM
PM
35.4
36.1
D2
D2
36.4
36.3
D2
D2
8. Broadway Terrace/Golden Gate Avenue
All-way Stop
AM
PM
14.3
11.0
B
B
14.7
11.2
B
B
9. Broadway Terrace/Proctor Avenue
Side-Street Stop
1
AM
PM
1.5 (NB 16.2)
1.0 (NB 14.3)
A (C)
A (B)
1.5 (WB 16.4)
1.0 (NB 14.5)
A (C)
A (B)
10. Broadway Terrace/SR 13 southbound ramps
Side-Street Stop
1
AM
PM
6.6 (WB 44.5)
8.2 (SB 36.5)
A (E)
A (E)
6.7 (WB 45.7)
8.3 (SB 38.0)
A (E)
A (E)
11. Broadway Terrace/Glenwood Glade/Pinewood Road
All-way Stop
AM
PM
>100
>100
F
F
> 100.0
>100.0
F
F
Notes
1. For side-street-stop intersections, average delay is listed first followed by the delay for the worst approach.
2. Fieldwork observations show an LOS of F due to queuing from surrounding intersections.
Source: Fehr & Peers, 2010
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
28
potentially be delayed when buses along the proposed haul routes travel behind construction vehicles.
This is considered a short-term significant impact.
Phase 3 – Proctor Avenue to Moraga Avenue
Phase 3 peak hour intersection operations with construction traffic volumes assigned to the roadway
network are summarized in Table 9. Results are only shown for intersections with Project traffic during
Phase 3.
As shown in Table 9, the Project would add construction traffic to the Thornhill Drive/Highway 13/Moraga
Avenue intersection that operates at unacceptable LOS F during the AM peak hour. The Project would
not increase intersection delay by more than two seconds. Thus, the added Project traffic is considered
to have a less than significant impact to intersection operations considering the City of Oakland
significance criteria.
The unsignalized intersection of Broadway Terrace/Glenwood Glade/Pinewood Road meets Caltrans
peak hour signal warrant and the project is expected to add more than 10 vehicles during the PM peak
hour. Thus, the added Project traffic is considered to have a short-term significant impact to
intersection operations considering the City of Oakland significance criteria. All other unsignalized study
intersections do not meet Caltrans peak hour signal warrant.
TABLE 9 TRUCK ROUTE 3: PROCTOR AVENUE TO MORAGA AVENUE
EXISTING PLUS PROJECT INTERSECTION OPERATIONS
Intersection Control Peak Hour
Existing Truck Route 1
Delay LOS Delay LOS
9. Broadway Terrace/Proctor Avenue
Side-Street Stop
1
AM
PM
1.5 (NB 16.2)
1.0 (NB 14.3)
A (C)
A (B)
1.7 (NB 16.4)
1.2 (NB 14.1)
A (C)
A (B)
10. Broadway Terrace/SR 13 southbound ramps
Side-Street Stop
1
AM
PM
6.6 (WB 44.5)
8.2 (SB 36.5)
A (E)
A (E)
6.7 (WB 45.5)
8.4 (SB 38.2)
A (E)
A (E)
11. Broadway Terrace/Glenwood Glade/Pinewood Road
All-way Stop
AM
PM
>100
>100
F
F
> 100
>100
F
F
12. Harbord Drive/Moraga Avenue Side-Street Stop
1
AM
PM
7.8 (SB 92.0)
10.0 (SB 99.5)
A (F)
A (F)
8.0 (SB 95.2)
12.1 (SB >100.0)
A (F)
A (F)
13. Moraga Avenue/Estates Drive Side-Street Stop
1
AM
PM
2.6 (SB >100.0)
1.8 (SB 49.2)
A (F)
A (E)
2.7 (SB >100.0)
1.8 (SB 50.6)
A (F)
A (F)
14. Thornhill Drive/SR 13/Moraga Avenue
Signal AM
PM
>100.0
62.1
F
E
> 100.0
--
F
--
Notes
1. For side-street-stop intersections, average delay is listed first followed by the delay for the worst approach.
Source: Fehr & Peers, 2010
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
29
Construction traffic would also temporarily reduce the traffic speed on Broadway Terrace, Proctor
Avenue, Harbord Drive, and Moraga Avenue as trucks would travel more slowly through the area.
Additionally, transit riders could potentially be delayed when buses along the proposed haul routes travel
behind construction vehicles. This is considered a short-term significant impact.
Phase 4 – Contra Costa Road
Phase 4 peak hour intersection operations with construction traffic volumes assigned to the roadway
network are summarized in Table 10. Results are only shown for intersections with Project traffic during
Phase 4.
As shown in Table 10, the Project construction traffic is not expected to significantly degrade intersection
operations from an acceptable level to an unacceptable level at signalized intersections.
The unsignalized intersection of Broadway Terrace/Glenwood Glade/Pinewood Road meets Caltrans
peak hour signal warrant and the project is expected to add more than 10 vehicles during the PM peak
hour. Thus, the added Project traffic is considered to have a short-term significant impact to
intersection operations considering the City of Oakland significance criteria. All other unsignalized study
intersections do not meet Caltrans peak hour signal warrant.
Construction traffic would also temporarily reduce the traffic speed on Golden Gate Avenue and
Broadway Terrace as trucks would travel more slowly through the area. Additionally, transit riders could
potentially be delayed when buses along the proposed haul routes travel behind construction vehicles.
This is considered a short-term significant impact.
TABLE 10 TRUCK ROUTE 4: CONTRA COSTA ROAD
EXISTING PLUS PROJECT INTERSECTION OPERATIONS
Intersection Control Peak Hour
Existing Truck Route 1
Delay LOS Delay LOS
8. Broadway Terrace/Golden Gate Avenue
All-way Stop
AM
PM
14.3
11.0
B
B
15.3 (WB 19.1)
11.3 (EB 12.5)
C (C)
B (B)
9. Broadway Terrace/Proctor Avenue
Side-Street Stop
1
AM
PM
1.5 (NB 16.5)
1.0 (NB 14.3)
A (C)
A (B)
1.5 (NB 16.5)
1.0 (NB 14.6)
A (C)
A (B)
10. Broadway Terrace/SR 13 southbound ramps
Side-Street Stop
1
AM
PM
6.6 (WB 44.5)
8.2 (SB 36.5)
A (E)
A (E)
6.8 (WB 46.4)
8.4 (SB 38.7)
A (E)
A (E)
11. Broadway Terrace/Glenwood Glade/Pinewood Road
All-way Stop
AM
PM
>100
>100
F
F
>100
>100
F
F
Notes
1. For side-street-stop intersections, average delay is listed first followed by the delay for the worst approach.
Source: Fehr & Peers, 2010
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
30
Phase 5 – Roble Road
Phase 5 peak hour intersection operations with construction traffic volumes assigned to the roadway
network are summarized in Table 11. Results are only shown for intersections with Project traffic during
Phase 5.
As shown in Table 11, the Project would add construction traffic to the Tunnel Road/SR 13/Hiller Drive
intersection that operates at unacceptable LOS F during the AM and PM peak hour. The Project would
not increase intersection delay by more than two seconds. Thus, the added Project traffic is considered
to have a less than significant impact to intersection operations considering the City of Oakland
significance criteria.
Unsignalized study intersections do not meet Caltrans peak hour signal warrants during this Construction
phase. Thus, the added Project traffic is considered to have a less than significant impact to
intersection operations considering the CEQA guidelines and the City of Oakland significance criteria.
Construction traffic would also temporarily reduce the traffic speed on Tunnel Road and Caldecott Lane
as trucks would travel more slowly through the area. Additionally, transit riders could potentially be
delayed when buses along the proposed haul routes travel behind construction vehicles. This is
considered a short-term significant impact.
TABLE 11 TRUCK ROUTE 5: ROBLE ROAD
EXISTING PLUS PROJECT INTERSECTION OPERATIONS
Intersection Control Peak Hour
Existing Truck Route 1
Delay LOS Delay LOS
2. Broadway/Keith Avenue Signal AM
PM
16.8
13.7
B
B
16.9
13.8
B
B
3. Broadway/Brookside Avenue/SR-24
Side-Street Stop
1
AM
PM
2.2 (WB 12.2)
3.4 (WB 68.6)
A (B)
A (F)
2.2 (WB 12.2)
3.4 (WB 68.6)
A (B)
A (F)
4. Broadway/Golden Gate Way Side-Street Stop
1
AM
PM
4.0 (NB 17.8)
1.8 (NB 13.8)
A (C)
A (B)
4.3 (NB 18.8)
1.9 (NB 14.0)
A (C)
A (B)
5. Tunnel Road/State Route 13/Hiller Drive
Signal AM
PM
98.1
>100
F
F
99.0
>100
F
F
6. Caldecott Lane/Kay Overcrossing
Side-Street Stop
1
AM
PM
2.4 (WB 20.8)
1.9 (WB 13.6)
A (C)2
A (B) 2
2.6 (WB 22.4)
2.0 (WB 14.2)
A (C)2
A (B) 2
7. Broadway/Kay Overcrossing Signal AM
PM
35.4
36.1
D2
D2
37.3
36.8
D2
D2
Notes
1. For side-street-stop intersections, average delay is listed first followed by the delay for the worst approach.
2. Fieldwork observations show an LOS of F due to queuing from surrounding intersections.
Source: Fehr & Peers, 2010
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
31
Multiple Phase Approach
To reduce the overall project construction schedule, some construction phases presented above could be constructed simultaneously. Three scenarios are possible that would construct Phases 2 and 3, or Phases 3 and 4 concurrently. Truck routes for these phases overlap on Broadway Terrace; therefore, study intersections on Broadway Terrace were evaluated to consider the additional traffic from multiple construction phases.
Scenario A: Phases 2 and 3 – Installation of pipeline on Golden Gate Avenue and Proctor Avenue
Peak hour intersection operations with construction traffic volumes for Phases 2 and 3 assigned to the
roadway network are summarized in Table 12. Results are only shown for intersections on Broadway
Terrace where the truck routes and worker trips for Phases 2 and 3 overlap.
The unsignalized intersection of Broadway Terrace/Glenwood Glade/Pinewood Road meets Caltrans peak hour signal warrant and the project is expected to add more than 10 vehicles during the PM peak hour. Thus, the added Project traffic is considered to have a short-term significant impact to intersection operations considering the City of Oakland significance criteria. All other unsignalized study intersections do not meet Caltrans peak hour signal warrant.
Scenario B: Phases 3 and 4 – Installation of large diameter pipeline on Proctor Avenue and distribution pipeline on Contra Costa Road
Peak hour intersection operations with construction traffic volumes for Phases 3 and 4 assigned to the roadway network are summarized in Table 13. Results are only shown for intersections on Broadway Terrace where the truck routes and worker trips for Phases 3 and 4 overlap.
TABLE 12
SCENARIO A: PHASES 2 & 3 EXISTING PLUS PROJECT INTERSECTION OPERATIONS
Intersection Control Peak Hour
Existing Scenario A
Delay LOS Delay LOS
8. Broadway Terrace/Golden Gate Avenue
All-way Stop
AM
PM
14.3
11.0
B
B
14.7
11.2
B
B
9. Broadway Terrace/Proctor Avenue
Side-Street Stop
1
AM
PM
1.5 (NB 16.2)
1.0 (NB 14.3)
A (C)
A (B)
17.2 (WB 20.00)
1.2 (NB 14.3)
C (C)
A (B)
10. Broadway Terrace/SR 13 southbound ramps
Side-Street Stop
1
AM
PM
6.6 (WB 44.5)
8.2 (SB 36.5)
A (E)
A (E)
6.7 (WB 44.9)
8.5 (WB 39.8)
A (D)
A (D)
11. Broadway Terrace/Glenwood Glade/Pinewood Road
All-way Stop
AM
PM
>100
>100
F
F
>100
>100
F
F
Notes
1. For side-street-stop intersections, average delay is listed first followed by the delay for the worst approach.
Source: Fehr & Peers, 2010
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
32
The unsignalized intersection of Broadway Terrace/Glenwood Glade/Pinewood Road meets Caltrans peak hour signal warrant and the project is expected to add more than 10 vehicles during the PM peak hour. Thus, the added Project traffic is considered to have a short-term significant impact to intersection operations considering the City of Oakland significance criteria. All other unsignalized study intersections do not meet Caltrans peak hour signal warrant.
Scenario C: Phases 3 and 4 – Installation of small diameter distribution lines on both Proctor Avenue and Contra Costa Road
Peak hour intersection operations with construction traffic volumes for Phases 3 and 4 assigned to the roadway network are summarized in Table 14. Construction of the distribution line under Phase 4 would require a maximum of three trucks during the peak hour as opposed to the four required for construction of the large diameter pipeline. Results are only shown for intersections on Broadway Terrace where the truck routes and worker trips for Phases 3 and 4 overlap.
TABLE 13
SCENARIO B: PHASES 3 & 4 – LARGE DIAMETER PIPELINE ON PROCTOR AVENUE EXISTING PLUS PROJECT INTERSECTION OPERATIONS
Intersection Control Peak Hour
Existing Scenario B
Delay LOS Delay LOS
8. Broadway Terrace/Golden Gate Avenue
All-way Stop
AM
PM
14.3
11.0
B
B
15.3
11.3
C
B
9. Broadway Terrace/Proctor Avenue
Side-Street Stop
1
AM
PM
1.5 (NB 16.2)
1.0 (NB 14.3)
A (C)
A (B)
17.8 (WB 21.0)
1.2 (NB 14.4)
C (C)
A (B)
10. Broadway Terrace/SR 13 southbound ramps
Side-Street Stop
1
AM
PM
6.6 (WB 44.5)
8.2 (SB 36.5)
A (E)
A (E)
6.8 (WB 45.6)
8.6 (WB 40.6)
A (E)
A (E)
11. Broadway Terrace/Glenwood Glade/Pinewood Road
All-way Stop
AM
PM
>100
>100
F
F
>100
>100
F
F
Notes
1. For side-street-stop intersections, average delay is listed first followed by the delay for the worst approach.
Source: Fehr & Peers, 2010
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
33
The unsignalized intersection of Broadway Terrace/Glenwood Glade/Pinewood Road meets Caltrans peak hour signal warrant and the project is expected to add more than 10 vehicles during the PM peak hour. Thus, the added Project traffic is considered to have a short-term significant impact to intersection operations considering the City of Oakland significance criteria. All other unsignalized study intersections do not meet Caltrans peak hour signal warrant.
Cumulative Construction Traffic
Project Construction is expected to overlap with construction of the Caldecott Tunnel Fourth Bore project (expected to be completed late 2013/early 2014). Truck traffic from tunnel construction may use the Caldecott Lane/Kay Overcrossing and Broadway/Kay Overcrossing intersections (study intersections 6 and 7). According to the Final Environmental Assessment/Environmental Impact Report for the Caldecott Tunnel (California Department of Transportation, August 2007), a maximum of 40-50 trucks are expected from construction activities over a four hour period. The Dingee Pipeline Project would add a relatively small number of trucks to the intersections when compared to the Caldecott Tunnel project (maximum of 16 over a four hour period) and the Caldecott Lane/Kay Overcrossing intersection would still not meet the peak hour signal warrant; therefore, the potential overlap of construction activities would not result in additional Project impacts at the study intersections.
ROADWAY CLOSURES DURING CONSTRUCTION
The majority of Project construction takes place within existing roadways, which would require partial or
full closure during construction. The degree of closure would depend on roadway width and alignment,
as well as the design of the pipeline. Below are recommendations for roadway closures based on
roadway geometry, existing traffic volumes, and alternative routes.
TABLE 14
SCENARIO C: PHASES 3 & 4 - SMALL DIAMETER PIPELINE ON PROCTOR AVENUE EXISTING PLUS PROJECT INTERSECTION OPERATIONS
Intersection Control Peak Hour
Existing Scenario C
Delay LOS Delay LOS
8. Broadway Terrace/Golden Gate Avenue
All-way Stop
AM
PM
14.3
11.0
B
B
15.1
11.2
C
B
9. Broadway Terrace/Proctor Avenue
Side-Street Stop
1
AM
PM
1.5 (NB 16.2)
1.0 (NB 14.3)
A (C)
A (B)
17.7 (WB 20.7)
1.2 (NB 14.4)
C (C)
A (B)
10. Broadway Terrace/SR 13 southbound ramps
Side-Street Stop
1
AM
PM
6.6 (WB 44.5)
8.2 (SB 36.5)
A (E)
A (E)
6.8 (WB 45.6)
8.6 (WB 40.1)
A (E)
A (E)
11. Broadway Terrace/Glenwood Glade/Pinewood Road
All-way Stop
AM
PM
>100
>100
F
F
>100
>100
F
F
Notes
1. For side-street-stop intersections, average delay is listed first followed by the delay for the worst approach.
Source: Fehr & Peers, 2010
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
34
Golden Gate Avenue
It is recommended that two-way traffic be maintained whenever possible on Golden Gate Avenue. The parking lane on either side of the street could be used for construction work and/or rerouting of traffic. Parking should not be permitted adjacent to the work area during construction.
Daily traffic volumes on Golden Gate Avenue are below 1,500 vehicles, so one-lane traffic control may be used when necessary, such as during construction on the sharp curve just south of Eustice Avenue. Additionally, if full closure is necessary, Buena Vista Avenue and Ocean View Drive are potential detour routes. It is recommended that full closures be limited to off-peak hours (between 9:00 AM and 4:00 PM). Full closures during peak hours may be considered if they could reduce the length of time road closures are needed overall, local access is maintained, and a reasonable detour route is provided.
Local access to residential driveways should be maintained at all times and two-way traffic should be restored at the end of each work day. Bus routes on Golden Gate Avenue should also be considered when planning road closures.
Broadway Terrace
It is recommended that two-way traffic be maintained at all times on Broadway Terrace. The parking lane on either side of the street could be used for construction work and/or rerouting of traffic. Parking should not be permitted adjacent to the work area during construction. Local access to residential driveways should be maintained at all times.
Full closure of Broadway Terrace is not recommended, as alternative routes are limited and require use of smaller residential streets and several bus routes use this road.
Proctor Avenue
Daily traffic volumes on Proctor Avenue are below 500 vehicles, so one-lane traffic control may be used when necessary, such as during construction on the sharp curve near Agnes Street. The parking lane on either side of the street could be used for construction work and/or rerouting of traffic. Parking should not be permitted adjacent to the work area during construction.
Additionally, if full closure is necessary, Sheridan Road, Florence Road, and Cochrane Avenue are potential detour routes, running parallel to Proctor Avenue. It is recommended that full closures be limited to off-peak hours (between 9:00 AM and 4:00 PM). Full closures during peak hours may be considered if they could reduce the length of time road closures are needed overall, local access is maintained, and a reasonable detour route is provided.
Local access to residential driveways should be maintained at all times and two-way traffic should be restored at the end of each work day.
Julia Street
Partial or full closure of Julia Street is possible during construction. Florence Avenue provides an alternative route and there are only two residential driveways located on Julia Street. Local access to residential driveways should be maintained at all times and two-way traffic should be restored at the end of each work day.
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
35
Harbord Drive
It is recommended that two-way traffic be maintained whenever possible on Harbord Drive. The parking lane on either side of the street can be used for construction work and/or rerouting of traffic. Parking should not be permitted adjacent to the work area during construction.
Since daily traffic volumes on Harbord Drive are higher than on the other residential streets within the Project area, it is recommended that one-lane traffic control be limited to off-peak hours (between 9:00 AM and 4:00 PM. If full closure is necessary, traffic could be diverted to Proctor Avenue and Masonic Avenue. Full closures should be limited to off-peak hours (between 9:00 AM and 4:00 PM). Full closures during peak hours may be considered if they could reduce the length of time road closures are needed overall, local access is maintained, and a reasonable detour route is provided.
Local access to residential driveways should be maintained at all times and two-way traffic should be restored at the end of each work day. Bus routes on Harbord Drive should also be considered when planning road closures.
Contra Costa Road
Since Contra Costa Road is a cul-de-sac, one lane of traffic must be maintained at all times. Vehicle trips are limited to local residents, so traffic volumes are low, and one-way traffic control is acceptable. Parking should not be permitted adjacent to the work area during construction.
Local access to residential driveways should be maintained at all times and two-way traffic should be restored at the end of each work day.
Roble Road
It is recommended that one lane of traffic be maintained at all times on Roble Road. The Uplands could be used as a possible detour route if full closure is needed. It is recommended that full closures be limited to off-peak hours (between 9:00 AM and 4:00 PM). Parking on Roble Route should not be permitted adjacent to the work area during construction.
Local access to residential driveways and Roble Court should be maintained at all times and two-way traffic should be restored at the end of each work day.
EMERGENCY ACCESS
Project construction activity could impede emergency access in and through the Project site. Partial and
full roadway closures would reduce travel speeds for vehicles responding to emergencies. Large
firetrucks would have difficulty turning around on the residential streets in the Project vicinity if these are
closed to through traffic. This is considered a short-term significant impact.
PAVEMENT ASSESSMENT
Large trucks would be used to haul material to and from the Project sites. Although arterials such as
Broadway, Broadway Terrace, Moraga Avenue and Tunnel Road are designed to withstand substantial
truck volumes, minor residential roads such as Golden Gate Avenue, Proctor Avenue, Contra Costa
Road, and Roble Road are not. These roadways would likely experience increased wear-and-tear as a
result of Project construction.
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
36
PARKING ASSESSMENT
During construction activities, on-street parking within the vicinity of the construction area would likely
need to be restricted. This would change from day to day depending on the location of the construction.
Parking restrictions should provide sufficient space to accommodate construction activities, including
staging, worker vehicles, and proper taper distance for lane shifts (if through traffic is being diverted into
the parking lanes). Worker vehicle parking would be constrained to the work zone area. Residents
should be notified of parking restrictions at least 48 hours in advance through temporary street signs.
IMPACTS AND MITIGATION MEASURES
Project construction would generate short-term vehicle trips by trucks and construction workers and would
represent an increased traffic load on the roadways surrounding the Project site. The near-term impact to
intersections is Significant but mitigable. The long-term cumulative impact of the Project is less-than-
significant.
Impact T-1: The addition of traffic during Project construction would exacerbate an existing
deficiency at the unsignalized Broadway Terrace/Glenwood Glade/Pinewood Road
intersection. The Project would add more than 10 trips during construction Phase 2 in the AM
peak hour, and Phases 3 and 4 in the PM peak hour, and during both peak hours during each of
the three multiple phase scenarios; and the intersection meets the Caltrans peak hour signal
warrant; therefore this is considered a significant impact according City of Oakland significance
criteria.
Mitigation Measure T-1: Limit construction trucks to three or less through this intersection during
construction Phase 2 in the AM peak hour, and Phases 3 and 4 in the PM peak hour and during both
peak hours during each of the three multiple phase scenarios. EBMUD construction inspectors shall
enforce these vehicle limits. With implementation of this measure, the impact would be reduced to less-
than-significant.
Subsequent to completion of the Project, no additional traffic would be generated by the site and the long term impact of the Project would be less-than-significant.
_________________________
Project construction would occur within existing roadways, requiring partial and full closures, and
increasing delay for traffic. Further, residential streets within the Project study are not designed to
accommodate large trucks. The near-term impact is significant. The long-term cumulative impact of the
Project is less-than-significant.
Impact T-2: Construction activities would reduce roadway speeds, increase roadway hazards,
and create potential conflicts between transit buses, pedestrians, and bicyclists. Emergency
access would also be constrained at Project construction locations. Based on the significance
criteria, these impacts are considered significant.
Mitigation Measure T-2: EBMUD contract specifications shall require preparation and implementation of
a Traffic Management Plan, which shall include the following elements:
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
37
• The work hours for each phase of Project construction, the process for notifying residents of
construction activity, and the means for people to report construction-related problems.
• Traffic control plans showing typical work areas for each phase of construction along with details
for partial and full road closures, detours, and construction area signage. The plans should
indicate a minimum roadway width to maintain for emergency vehicle access through the site.
The plans will include temporary “Share The Road” signage adjacent to work zones when
construction is taking place on Broadway Terrace to alert vehicles to the presence of bicycles
using this Class III bicycle route.
• Procedures for notifying emergency services of full roadway closures and detours.
• Haul routes for each construction phase, based on the routes shown on Figures 3 through 7 that
shall be provided to all trucks serving the site during the construction period. The haul route will
indicate that portions of Broadway Terrace, Broadway, and Caldecott Lane are designated as
Class III bike routes within the study area, and to exercise caution when using these roads.
• Flaggers at the construction site to direct construction vehicles and control traffic as needed.
• Flaggers at the Golden Gate Avenue/Golden Gate Way intersection during construction on
Golden Gate Avenue north of Golden Gate Way.
• Flaggers at the Acacia Avenue/Buena Vista Avenue and Buena Vista Avenue/Contra Costa Road
intersections during construction on Contra Costa Road.
• Documentation of road pavement conditions for all routes that would be used by construction
vehicles both before and after Project construction. Roads found to have been damaged by
construction vehicles shall be repaired to the level at which they existed prior to Project
construction.
The Traffic Management Plan shall be enforced by EBMUD construction inspectors. With implementation
of this mitigation measure, the impact T-2 would be reduced to less-than-significant.
_________________________
Traffic and Circulation Technical Report
Dingee Backbone Pipeline Replacement Project
March 2011
38
CHAPTER 5. REFERENCES
Alameda-Contra Costa Transit District Bus System Map, available online at
http://www.actransit.org/
Caltrans, Truck Networks on California State Highways, available online at
http://www.dot.ca.gov/hq/traffops/trucks/truckmap/truckmap-d04.pdf
Caltrans, Truck Route List, available online at
http://www.dot.ca.gov/hq/traffops/trucks/truckmap/truck-route-list.xls
City of Oakland, CEQA Thresholds/Criteria of Significance Guidelines, (July 15, 2008)
http://www.oaklandnet.com/government/ceda/revised/AttachH.pdf
Institute of Transportation Engineers (ITE), Transportation and Land Development, 2002. Table 13-6.
Transportation Research Board’s 2000 Highway Capacity Manual.