tunnel in soft soil

Upload: irene-margaretha-lumban-raja

Post on 01-Jun-2018

218 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/9/2019 Tunnel in Soft Soil

    1/50

    Geotechnical Surveys for Designing andConstruction

    of Underground Works in Big Cities

    Seminar on Tunnel Construction in Soft SoilCondition

    Hanoi, VietnamFebruary 29, 2008

    byHarvey W. Parker

    Past PresidentInternational Tunnelling and Underground Space Association

    (ITA)

  • 8/9/2019 Tunnel in Soft Soil

    2/50

  • 8/9/2019 Tunnel in Soft Soil

    3/50

    Geotechnology & Planning

    Everyone in planning and design oftunnels must give geology seriousconsideration

    Therefore, Use Geology & Geotechnology

    as early as possibleConceptual stage

  • 8/9/2019 Tunnel in Soft Soil

    4/50

    Challenges of the Underground

  • 8/9/2019 Tunnel in Soft Soil

    5/50

    Strange & Unique Functions of the

    Ground in Tunnels The ground and groundwater is the load

    The ground is the medium that transfersthis load to the tunnel lining

    The ground is the structural material that

    actually carries most of the load Tunnel linings only have to carry part of totalload

    We call it Arching

  • 8/9/2019 Tunnel in Soft Soil

    6/50

    Selected Challenges of theUnderground: Variability

    Geology can be Subtle and IllusiveVariability is Often Abrupt

    PropertiesMagnitude Varies Significantly

    Time, Seasons, Sample Size, Rate of Loading

    Properties of Geologic Materials have anenormous range of values

  • 8/9/2019 Tunnel in Soft Soil

    7/50

    Range of permeability

    Greater than any other engineering parameter Roughly 10 -7 to 10 +3 cm/secFactor of 10,000,000,000

    Units used are factors of 10

    For Comparison: Strength

    Much Smaller RangeSoft Clay to Concrete ~ 1,000Soft Clay to Steel/Rock ~ 100,000

  • 8/9/2019 Tunnel in Soft Soil

    8/50

    Geotechnical ExplorationsComparative Sampling Frequency

    Concrete Structure Every 20 to 50 m 3

    ~ 0.1% See 100% off Truck

    Geotechnical Exploration Borings: 6 to 8 cm Diameter

    core @ 90 m spacing = ~ 0.0005%

  • 8/9/2019 Tunnel in Soft Soil

    9/50

    Geotech sees only 0.0005% of Tunnel Volume

    (Thimble to ~50 Oil Drums)

  • 8/9/2019 Tunnel in Soft Soil

    10/50

    Selected Important GeotechnicalIssues

    Geology Groundwater Groundwater

    Groundwater Contaminated Soil & Groundwater

    Obstructions, Gas, & Other Safety Issues Ground and Groundwater Properties

  • 8/9/2019 Tunnel in Soft Soil

    11/50

    Challenges of theUnderground

    Geologic investigations are more difficult

    Use Well-Qualified Engineering Geologistand Geotechnical Engineer with Tunnel

    Experience

  • 8/9/2019 Tunnel in Soft Soil

    12/50

    Success in Spite of Vast Uncertainty

    Exploration sees only miniscule volume Never see ahead of the face

    Major TBM issue

    Yet Fortunately - Owners, Designers &Contractors do a remarkable job

  • 8/9/2019 Tunnel in Soft Soil

    13/50

    Special Challenges in Big Cities

    Very Few outcrops to actually see & touch soil Difficult to find safe location for borings Because of Utilities or other obstructions

    May not get all borings on alignment or wherewanted Borings may not be equally spaced or off line

    May encounter: Obstructions contaminated soil

  • 8/9/2019 Tunnel in Soft Soil

    14/50

    Geotechnical Database for Cities

    Summarizes all available Geotechnical data All cities should create, maintain, & update such a database

    Note the quality of the data entries; some are better than others Should Include:

    Geotechnical Records Borings, Test Pits, Basement Excavations Existing Foundations including Pile Driving Records

    Water, Oil, and Geothermal Well Logs Groundwater Information

    Information on Contamination Archeological Information Man-made Subsurface Features

    Obstructions such as Utilities, Old Sea Walls, Piers, Piles, WellCasings, Tunnels, etc

  • 8/9/2019 Tunnel in Soft Soil

    15/50

    Groundwater Information for Cities Document all information on groundwater

    Water Levels and Pressure Trends Current (Include Artesian Conditions) Future (Consider Global Warming)

    Groundwater Flow Directions For environmental purposes To evaluate flow of contaminated plumes To evaluate salt water intrusion, if applicable

    Document Permeability of Ground Part of Geotechnical Database Identify strata or features of High or Low Permeability

    Impermeable layers

    Highly permeable zones Obstructions to water flow

  • 8/9/2019 Tunnel in Soft Soil

    16/50

    Asset Management Program Database of Existing Utilities and Other

    Subsurface Features Documents Location and Condition

    Very useful for managing potential replacementand upgrading costs during your project or infuture

    Valuable Input to Overall Planning ofUnderground Space for your City

  • 8/9/2019 Tunnel in Soft Soil

    17/50

    Geotechnical SurveyExplorations

    Methods & Principles

  • 8/9/2019 Tunnel in Soft Soil

    18/50

    NO LONGER SUFFICIENT TODESCRIBE STRATIGRAPHY &

    GROUNDWATER TABLE

    MUST PREDICT BEHAVIOR

    MUST ESTABLISH A BASELINE

    So "changed condition" (if encountered) can be administered fairly

  • 8/9/2019 Tunnel in Soft Soil

    19/50

    Intact vs. Mass PhysicalProperties

    Intact properties are the properties of thesoil on a small (core sample size) scale

    Mass physical properties govern behavior Includes the fundamental intact properties Modified by the effects of the ground at the

    scale of the tunnel

  • 8/9/2019 Tunnel in Soft Soil

    20/50

    Determine Groundwater Location

    & Mass Permeability of Soil

    After Parker, 1996After Parker, 1996

  • 8/9/2019 Tunnel in Soft Soil

    21/50

    Tunnel Behavior is Complex Behavior of the Ground During Tunnelling

    Determined by MANY factors including: Geology Engineering Properties of Materials Means and Methods

    Excavation Method Ground Support & Lining Method Ground Modification Method, if any

    Terzaghis Tunnelmans Ground Classification Firm, Ravelling, Squeezing, Running, Flowing, Swelling

    Generally: Owner Owns the Ground Contractor Owns the effects of Means & Methods But these are always interdependent and never so clear

  • 8/9/2019 Tunnel in Soft Soil

    22/50

    Past PracticesNo accepted standard

    # BoringsSpacingDepth

    Geo.Investigation Cost1/2 to 3+ Percent of Construction Cost

    Some up to 8++ % have been reported.Special Class over these guidelines

    Nuclear Waste

    Hazardous Waste

  • 8/9/2019 Tunnel in Soft Soil

    23/50

    USNC/TT Recommendations onSite Investigation

    1984 Study of exploration practices in USA

    U.S. National Committee on Tunneling Technology(USNC/TT)

    Exploration = 3.0 percent of project cost

    Boring Length = 1.5 linear meters of boreholeper route meter of tunnel alignment

    For typical urban tunnel situation

  • 8/9/2019 Tunnel in Soft Soil

    24/50

    USNC/TT Recommendations onSite Investigation

    Make Geotechnical Report a ContractDocument (Now Required by ITIG)

    No DisclaimersEstablish a BaselineThis evolved into the Geotechnical Baseline Report(GBR) also called Geotechnical Conditions Report

    Compile As-Built Report

  • 8/9/2019 Tunnel in Soft Soil

    25/50

    Recommendations for How Much to DoDetermine Project Magnitude

    Major or Complex Project

    Small or Ordinary Project

  • 8/9/2019 Tunnel in Soft Soil

    26/50

    Guidelines for Determining Project

    MagnitudeMajor or Complex Tunnel Projects

    Greater than 4 m in diameterLength greater than 300 m

    Alternative Alignments ConsideredMultiple PhasesUnusual, complex, or unproven construction procedures

    Difficult or adverse geologyConsiderable risk

    Considerable sharing of risk

  • 8/9/2019 Tunnel in Soft Soil

    27/50

    Guidelines for Level of GeotechnicalEffort

    All Tunnel Projects

    Emphasize GeologyConduct at least two exploration phasesFund the initial phase well

    confidently select the alignmentestimate of the likely construction methods, liningand cost

    Pre-approve contingency fund Answer technical questions resulting frominitial boring program

    Use Contingency only if needed

  • 8/9/2019 Tunnel in Soft Soil

    28/50

    Guidelines for Level of Geotechnical

    Effort All Tunnel Projects

    Get more information than needed for design

    Get enough data to predict Ground Behavior Alternative construction methods

    TBM or Traditional techniques

    Get enough data to minimize uncertainty

  • 8/9/2019 Tunnel in Soft Soil

    29/50

    Guidelines for Level of Geotechnical

    Effort All Tunnel Projects

    Don't do any exploration unless itspecifically fills a genuine need

    Often, reduction of uncertainty is a genuine need

    Good Exploration reduces BID COST by:10 to 15 Times Exploration cost

  • 8/9/2019 Tunnel in Soft Soil

    30/50

    Guidelines for Level of GeotechnicalEffort

    All Tunnel Projects

    Conduct a Supplementary CostExploration Phase

    After alignment is fixed & after designedTo Confirm the design concept

    Get information contractor needs to estimateProductivity (rate of advance)Estimate the costs and to bid the job

  • 8/9/2019 Tunnel in Soft Soil

    31/50

    Guidelines for Level of GeotechnicalEffort

    Large or Major Projects

    Develop multi-phased program to fill actualneeds

    Phasing increases quality and reduces cost

    Use non-traditional techniques if theyreduce uncertainty

    Geophysics

    In Situ TestsPressuremeterspump tests, etc., as appropriateshafts, adits, pilot tunnels

  • 8/9/2019 Tunnel in Soft Soil

    32/50

    Guidelines for Level of Geotechnical

    EffortLarge or Major Projects

    For initial phases of design, budget,and fund

    Boring length = About equal to route lengthCost = 1.5 to 2.25 percent of construction cost

    Overall budget = 3.0 Percent of

    ConstructionIncluding contingenciesImplementation of contingencies must be quick

    and easy

  • 8/9/2019 Tunnel in Soft Soil

    33/50

    Selected Geotechnical Issues

    Sonic Drilling

    Geophysics/TomographyGPS and GIS

    Video & Digital PhotographySystematic Risk Management ProgramComputer GraphicsMethane, H 2S, & Ground ContaminationMuck Disposal

  • 8/9/2019 Tunnel in Soft Soil

    34/50

    RISK & CHOICES ARE PLENTIFUL

  • 8/9/2019 Tunnel in Soft Soil

    35/50

    Geotechnical RiskManagement

    Conduct Geotechnical SurveysSpecifically to Reduce Uncertainty of High-risk Issues

    Identify Issues using Risk Management

    TechniquesWorkshop sessions by technical staff

  • 8/9/2019 Tunnel in Soft Soil

    36/50

    ITA Guidelines for Risk ManagementTUST, 2004

  • 8/9/2019 Tunnel in Soft Soil

    37/50

    ITIG International Risk Code Requires Risk Registers and

    RMP from project conceptionthrough construction

    Re-Insurance Industry isdemanding compliance withCode

    Revised following ITAintervention. Use 30 January2006 version

  • 8/9/2019 Tunnel in Soft Soil

    38/50

    Risk Worksessions Risk worksessions force the project team toconsider potential problems

    Not complicated Process:1. Identify & characterize potential threats2. Develop risk reduction strategies3. Determine cost/benefits for these strategies4. Decide a prudent course of action.

    Source: Reilly

  • 8/9/2019 Tunnel in Soft Soil

    39/50

    C Ro

    R r

    p

    RMP: Risk IdentificationRMP: Risk Identification

    Probability/Impact classification - exampleProbability/Impact classification - example

    RISKRISKIntolerableSignificantSubstantialTolerable

    Insignificant

    17-2513-169-125-8

    1-4

    UnacceptableUnacceptableEarly attentionRegular attention

    Monitor

    Negligible Unlikely Likely Probable Very likely

    I M P A C T

    PROBABILITY

    Very high

    High

    MediumLow

    Very low

    5

    4

    32

    1

    10

    8

    64

    2

    15

    12

    96

    3

    20

    16

    128

    4

    25

    20

    1510

    5

    R=P IR=P I RESPONSERESPONSE

    In this case the impact prevails tothe likelihood of the event

    In this case the impact prevails to

    the likelihood of the event

    The detailed process of riskidentification is project-specific

    The detailed process of riskidentification is project-specific

    Source: Grasso

  • 8/9/2019 Tunnel in Soft Soil

    40/50

    Methane, Hydrogen Sulfide &Ground Contamination

    More Prevalent in Tunnels & Mines thanPreviously Thought

    Must Investigate for these HazardsImportant Decision Regarding SafetyMeasures and Cost

  • 8/9/2019 Tunnel in Soft Soil

    41/50

    Muck Disposal- Major Issue(Often Neglected)

    Muck is generated 24 hours/day Potential Public Disturbance

    Muck disposal sites are often far away

    Cost and Disturbance Issue Muck is sometimes contaminated

    Can go only to certain very expensive disposalsites

    EPB and Slurry Muck needs special treatment

  • 8/9/2019 Tunnel in Soft Soil

    42/50

    Geotechnical Aspects ofContracting Practices

    No Disclaimers for ground conditions

    Include a Fair Changed Condition Clause

    Share Risk and Share Fairly

    Adapt ITIG Requirements to your Country

    Prepare Geotechnical Baseline Report (GBR)GBR also called Ground Reference ConditionsCross-checked with plans & specificationsMake GBR part of contract documents

    Provide for Disputes Review Board (DRB)

  • 8/9/2019 Tunnel in Soft Soil

    43/50

    References AFTES, 1994, The Choice of geotechnical Parameters and

    Tests Useful to the Design, Dimensioning and Construction ofUnderground Structures, Association Francaise de Travauxen Souterrain, Paris, France

    Guglielmetti, Vittorio; Grasso, Piergiorgio; Mahtab, Ashraf; &Xu, Shulin; Editors, 2008, Mechanized Tunnelling in Urban

    Areas , Taylor & Francis Group, London, 507 pp.

    Parker, Harvey W. 1996, Geotechnical Investigations,Chapter 4 of Tunnel Engineering Handbook , 2nd Edition,edited by Kuesel & King, Chapman & Hall, New York

    USNC/TT (1984), Geotechnical Site Investigations forUnderground Projects , U.S. National Committee on TunnelingTechnology, National Research Council, Washington, D.C.

    Geotechnical Surveys:

  • 8/9/2019 Tunnel in Soft Soil

    44/50

    Geotechnical Surveys:

    ConclusionsGeology Dominates Every Major Decision

    Allow Geo-Issues their Proper Role in PlanningChallenges and Potential Benefits of theUnderground are EnormousExploration programs see only a very small % ofvolume to be tunnelled. (0.0005%)

    The Ground is the Load and it also Provides

    Support for Most of the Load

  • 8/9/2019 Tunnel in Soft Soil

    45/50

    Geotechnical Surveys:Conclusions

    Incorporate Formal Systematic Risk Studies

    As soon as project identifiedUse risk management to direct geotechnical studies

    Follow Guidelines: Adapt to ITIG Code

    Start Geotechnical Work in Conceptual Stage &

    Continue Geotechnical Observations During Construction Prepare As-Built Report

    While in Service

  • 8/9/2019 Tunnel in Soft Soil

    46/50

    Geotechnical Surveys:Conclusions

    Many Challenges Exist in Big Cities

    Difficult to find safe boring locations Few outcrops Many Obstructions; Archeological Issues Contaminated Soil & Groundwater

    Recommended Practices

    Geotechnical Database Groundwater Trends

    Asset Management Program

    Formal Planning of Underground Space

    h l

  • 8/9/2019 Tunnel in Soft Soil

    47/50

    Geotechnical Surveys:Conclusions

    Determine Mass Physical Properties at Full Scale

    Not just intact properties Behavior is Complex & Hard to Identify Cause:

    Owner owns ground

    Contractor owns means & methods Prepare a Geotechnical Baseline Report (GBR)

    (also known as Geotechnical Reference

    Conditions Report) Distinguish between Fact and Interpretation

  • 8/9/2019 Tunnel in Soft Soil

    48/50

    Geotechnical Surveys:Conclusions

    Budget 3% for Geotechnical Investigation

    Don't do any exploration unless it specifically fills

    a genuine needHowever, often, reduction of uncertainty is a genuine need

    Good Exploration reduces BID COST by:10 to 15 Times the Cost of Exploration

  • 8/9/2019 Tunnel in Soft Soil

    49/50

    Overall Conclusion

    Geology & Geotechnology areEssential to Planning, Design &Construction

  • 8/9/2019 Tunnel in Soft Soil

    50/50

    Thank YouHarvey W. Parker

    Past PresidentInternational Tunnelling and Underground Space Associaton

    Source: Apollo 17