uknf osc meeting @ ral – 31 st january 2011 uknf - status, high lights, plans j. pozimski
TRANSCRIPT
UKNF OsC meeting @ RAL – 31st January 2011
UKNF - Status, high lights, plans
J. Pozimski
UKNF OsC meeting @ RAL – 6th June 2011
WP1 - Major achievements
IDR written, edited and published ECFA review Costing meetings – UKNF leading activity on NF Redesign of Target area for risk mitigation Investigation of particle dynamics in the baseline muon front end lattice and
investigation of the performance of alternative lattices Studies of power deposition in the target and pion capture area due to secondary
radiation Studies of solid and liquidized power jet targets for mercury risk mitigation Multi-particle simulations of the muon linac using field maps, comparison of
gained results from various software packages with good agreement in transversal and longitudinal particle dynamics and particle loss pattern.
Detailed studies of beam injection and extraction into the FFAG, studies of kicker and septum design as well as kicker electronics.
Further studies of FFAG magnets and particle tracking in fieldmaps. Further progress on common proton driver work (ISIS upgrade)
UKNF OsC meeting @ RAL – 6th June 2011
Heat load in target stationSimulation results
UKNF OsC meeting @ RAL – 6th June 2011
Target station design evolution
UKNF OsC meeting @ RAL – 6th June 2011
Front end design work
Muon Front End baseline description:
Longitudinal driftBuncher
Phase-Energy RotationIonisation Cooling
Risks and mitigations :
Transmission losses and secondary particles -> Chicane
RF break down in magnetic fields ->Bucket coil lattice
UKNF OsC meeting @ RAL – 6th June 2011
Chicane for secondary particle suppression
Heat deposition from secondaries is significant:
Three issues:
Activation of the linac
Heat load on superconductors
Radiation damage
Losses are 2-3 orders of magnitude too high → Mitigation:
Chicane for high momentum particles
Proton absorber for low momentum protons as protons stop quicker than pions/muons inmaterial
Transverse collimation
UKNF OsC meeting @ RAL – 6th June 2011
High power RF in magnetic field
Reduced magnetic field at RF cavities
May enable higheraccelerating voltage
Comparable transmissionFor identical number of cells(but longer footprint)
Increased magnetic field energy (and cost)
Slightly higher equilibrium Emittance
UKNF OsC meeting @ RAL – 6th June 2011
FETS
UKNF OsC meeting @ RAL – 6th June 2011
FETS Status
• Ion source operates at nearly design specs (2 ms, 50 mA) but persisting problems with heater electronics and spare parts• LEBT characterization nearly complete, but origin ofresidual source misalignment still unknown • Beam at injection into RFQ ~ 0.3-0.35 pimmmrad (measured)• Detailed study of influence of RFQ modulation on field flatness
finished and RFQ design adjusted.• RFQ beam dynamics frozen• Only a few principle design decisions for RFQ left (coupling)• Copper delivered waiting for manufacture• Drawings for manufacturing started – finished in August• Preliminary cost estimate for manufacture 160-200 k£ - 6 month• Circulator to be delivered in Summer – high power RF setup to be
finalized until autumn• Laser for diagnostics upgraded after first hints with Frankfurt laser
system.
UKNF OsC meeting @ RAL – 6th June 2011
FETS – RFQ fine tuningmatcher and modulation influence field flatness
UKNF OsC meeting @ RAL – 6th June 2011
Next Steps
• RFQ machining should start in September • High power RF setup to be finished in summer when circulator
arrives• Experimental programme involving cold model foreseen for summer - cooling test - high precision beat pull set-up at RHUL• Detailed plan for RFQ assembly and testing under development• MEBT mechanical design started• MEBT beam dump design started• FETS proposal in preparation
UKNF OsC meeting @ RAL – 31st January 2011
Summary
The IDR and numerous Publications, invited talks, PhD's, etc. 1 IDS plenary meeting 1 ECFA review (IDS, EUROnu) EUROnu plenary meeting and costing workshop EUROnu safety workshop this week Work package meetings and workshops Significant contribution to EMMA commissioning UKNF overall on schedule and budget