unit commitment
TRANSCRIPT
Unit commitment
Ahmed Mohamed abdel-hakeem Elkholy
Economic operation of power system
March 19, 2016
1. Introduction
1.1 Definition
determining the mix of generators and their estimated output
level to meet the expected demand of electricity over a given
time horizon (a day or a week), while satisfying constraints such
as ramp rate limits, up-time and down-time constraints, reserve
and energy requirements. While the load profile is given and also
the unit available to work is given.
Example 1.1
To fully illustrate the uc study the following sample example is
shown. There are three unit with following data.
Unit 1:
PMin = 250 MW, PMax = 600 MW
C1 = 510.0 + 7.9 P1 + 0.00172 P12 $/h
Unit 2:
PMin = 200 MW, PMax = 400 MW
C2 = 310.0 + 7.85 P2 + 0.00194 P22 $/h
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 1 of 14
Unit 3:
PMin = 150 MW, PMax = 500 MW
C3 = 78.0 + 9.56 P3 + 0.00694 P32 $/h
What combination of units 1, 2 and 3 will produce 550 MW at minimum cost?
How much should each unit in that combination generate?
Solution:
Taking consideration of above given using excel sheet to solve all possible scenarios of operations for illustration we will solve one case manual
Case 6
Scenario is
Unit 1 is off
Unit 1 is on
Unit 1 is on
λ=pd+∑
i=1
n β i2∗γi
∑i=1
n 12∗γi
=550+ 7.85
2∗.00194+ 9.562∗.00694
12∗.00194
+ 12∗.00694
=9.891369369
And the power will be
p= λ−β2∗γ
Power generated from unit 2 =
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 2 of 14
¿ 9.891369369−7.852∗.00194
=526.1261261MW
To meet constrains the power of unit 2 will be 400 mw
P2=400 mw
The power generated from unit3
¿ 9.891369369−9.562∗.00694=23.87387387MW
Also to meet constrains of unit 3 will be 150 mw
P2=150 mw
Also we also cheek constrain of power demand that’s
Pload =p1+p2=400+150=550 mw
The total cost by substituted in cost equation (given)
Total cost will be = 5428.55
This is for one case.
All case in table below
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 3 of 14
in above example for one loading case imagine that we can
consider above example for one hour in a day so we have to
calculate for 24 hour imagine for a week or month
so we find it possible to solve uc problem in that way not just for
long calculation but also considering constrains above example
not taking all constrain as we will illustrate in this report .
But we can learn from example 1.1 that
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 4 of 14
pmin pmax
U1 U2 U2 250 600 U1 U2 U2α for units 510 310 78 200 400 510 310 78β for units 7.9 7.85 9.56 150 500 7.9 7.85 9.56γ for units 0.0017 0.0019 0.0069 0.002 0.002 0.007case 1 0 0 0 #DIV/0! 0 0 0 #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0! #DIV/0!
case 2 0 0 1 17.194 150 500 0 0 0 0 0 0 0 0
case 3 0 1 0 9.984 200 400 0 0 0 0 0 0 0 0
case 4 1 0 0 9.792 250 600 1 550 0 0 5375.3 0 0 5375.3
case 5 0 1 1 9.89136937 350 900 1 0 400 150 0 3760.4 1668.15 5428.55
case 6 1 1 0 8.87936612 450 1000 1 284.7 265.3 0 2898.538 2529.155 0 5427.693
case 7 1 0 1 9.74592148 400 1100 1 400 0 150 3945.2 0 1668.15 5613.35
case 8 1 1 1 8.95839745600 1500
0 0 0 00 0 0 0
cost
cost
Units data
λ opration p1 p2 p3
1. When the few units committed then the units can’t meet the demand.
2. When the units is not enough to be committed then some units operate above optimum.
3. When the units is many to be committed then some units below optimum.
4. When the units is too many to be committed then minimum generation exceeds demand.
5. No-load cost affects choice of optimal combination.
1.2 Type of units or stations.
If we take considerable load profile like
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 5 of 14
100
50
210 6 1Tim
Loa
And solve for every hour then
LOAD UNIT 1 UNIT 2 UNIT 3
1100 On On On
1000 On On Off
900 On On Off
800 On On Off
700 On On Off
600 On Off Off
500 On Off Off
From solution we find that
1. There is unit will operate all time so we called it base unit.2. There is unit will operate part time so we called it
intermediate unit3. There is unit will operate few time so we called it peak unit
As coming figure describe
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 6 of 14
2. Constrains
2.1Definition
Constrain is limitations in power system avoiding it cause serious problem. This limitation can be technical for unit or technical limitation for power system or can be environmental limitations.
We can classified into
Unit constrains System constrains Environmental constraints Network Constraints
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 7 of 14
Unit 3 or peak unit
Unit 2 or intermediate unit
Unit 1 or base unit
24180 6 12Time
Load
2.2Unit constrains
2.2.1 Maximum generating capacityThat constrain stat that the power generated from the unit mustn’t exceed specific value because of thermal stability of the unit exceeding this constrain cause damage to the unit. Represented in mathematical formula as below.
x (i , t )< pmax
Wherex (i , t ) is output power oftheunit i∈thetime t
2.2.2 Minimum stable generationAs above constrain the power outage from the unit mustn’t fall down specific value because of technical limitation like flam stability in the gas and steam units. Represented in mathematical formula as below.
x (i , t )> pmin
2.2.3 Minimum up timeThis constrain stat that once the unit is running mustn’t shut down immediately due technical limitation and mechanical characteristic of the unit. This constrain represented mathematically as:
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 8 of 14
Where
2.2.4 Minimum down timeThis constrain stat that once the unit is running mustn’t shut down immediately due technical limitation and mechanical characteristic of the unit. This constrain represented mathematically as:
2.2.5 Ramp rates 2.2.5.1 Definition
To avoid damaging the turbine, the electrical output of a unit cannot change by
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 9 of 14
Status of unit i at period t
Unit i is on during period t
Unit i is off during period t
more than a certain amount over a period of time.
2.2.5.2 Ramp Up rate2.2.5.2.1 Start-up ramp rate
According to this constrain the unit can’t start immediately but taking time this time called start up time.
2.2.5.2.2 Running up ramp rateAccording to this one in case of running condition. the unit can’t immediate changing the power up without taking time called ramp rate running up time. The change here means increasing outage power.
2.2.5.3 Ramp down rate2.2.5.3.1 Shut down ramp rate
Look like previse constrain the unit take time to shut down.
2.2.5.3.2 Running down ramp rateAccording to this one in case of running condition. the unit can’t immediate changing the power down without taking time called ramp rate running down time. The change here means decreasing outage power.
2.2.5.4 Mathematical representationramp up rate
ramp down rate
2.3 System constrainsThis constrain that effect more than one unit divide into:
2.3.1 Load / generation balanceStat as the power generated from all unit must be equal the load and the losses. Mathematically represented as
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 10 of 14
∑i=1
n
u (i , t )∗x ( i ,t )=l (t )
where l (t ) isthe load power at time t2.3.2 Reserve constrain2.3.2.1 Reason to keep reserve power
Sudden unexpected increase in the load demand Force outage of some generating units Force outage of supplementary equipment’s due to stability
problem Underestimating the load due to error in load for casting Local shortage in the generated power
2.3.2.2 Type of reserve2.3.2.2.1 Cold reserve
Cold reserve is unit kept reserved for service but they are not available in the immediate loading.
2.3.2.2.2 Hot (spinning) reserveHot reserve refers to the extra amount of capacity that unit can provide immediately when require.
2.3.2.2.3 Operating reserve Operating reserve is referring to the capacity that already in service in excess of peak demand.
2.3.2.3 Other source of reserveThere is other source of reserve like
Pumped hydro plants Demand reduction (e.g. voluntary load shedding)
2.3.2.4 Condition of reserve Reserve must be higher than largest unit Should be spread around the network Must be able to deploy reserve even if the network
is congested The unit must operate at 80-85% of its rated
2.4 Network constrainTransmission network may have an effect on the commitment of units because of
Some units must run to provide voltage support
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 11 of 14
The output of some units may be limited because their output would exceed the transmission capacity of the network
2.5Environmental constrainuc study is effected by environmental constrains because of
constraints on pollutants such SO2, NOx various forms:o Limit on each plant at each houro Limit on plant over a yearo Limit on a group of plants over a year
Constraints on hydro generationo Protection of wildlifeo Navigation, recreation
2.6Cost constrains Cost constrain taking two type of cost in consideration
2.6.1 Start-up costStart-up cost depends on varicose factor like
warming up because the unit can’t bring on line immediately Start-up cost depends on time unit has been off
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 12 of 14
2.6.2 Running cost
A balance between start-up costs and running costs is important because of
How long should a unit run to “recover” its start-up cost?
Start-up one more large unit or a diesel generator to cover the peak?
Shutdown one more unit at night or run several units’ part-loaded?
Example: Diesel generator: low start-up cost, high running
cost Coal plant: high start-up cost, low running cost
3 SummaryThe summary of all above that• Some constraints link periods together• Minimizing the total cost (start-up + running) must be done over the whole
period of study• Generation scheduling or unit commitment is a more general problem than
economic dispatch• Economic dispatch is a sub-problem of generation scheduling
4 Type of units according flexibility4.1Flexible unit
Power output can be adjusting within limitsExample of this unit
– Coal-fired– Oil-fired
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 13 of 14
– Open cycle gas turbines– Combined cycle gas turbines– Hydro plants with storage
4.2Inflexible unit Power output cannot be adjusted for technical or commercial reasonsExample of this unit
– Nuclear– Run-of-the-river hydro– Renewables (wind, solar,…….)– Combined heat and power (CHP, cogeneration)
4.2.1.14.2.1.24.2.2
4.34.4
4.4.1.14.4.1.2
4.4.1.2.1 4.4.1.2.2
4.4.1.3
Unit commitment | Ahmed Mohamed abdel-hakeem Elkholy Page 14 of 14