Page 1: Using RAMM to Improve Contract Management Charmaine Okros

Using RAMM to Improve Contract ManagementCharmaine Okros

Page 2: Using RAMM to Improve Contract Management Charmaine Okros

2

• Attention to Detail in Contract setup

• Systems to Support Contracts

• Reporting and Data Analysis

How do we use RAMM Contractor to Improve our Contract Management?

Page 3: Using RAMM to Improve Contract Management Charmaine Okros

3

• Schedule linked to Client Account Codes (WBS)

• Dayworks have specific claim lines to pull down the correct WBS Code

• Programme categories to flag WBS overrides

Automating the WBS Codes

Page 4: Using RAMM to Improve Contract Management Charmaine Okros

4

Automatic Estimating

Page 5: Using RAMM to Improve Contract Management Charmaine Okros

5

Schedule Aligned with Assets

Page 6: Using RAMM to Improve Contract Management Charmaine Okros

6

• Contractors % Overheads set up against Dayworks items

• Entire Schedule updated with the %

No need for manual calculations

Contractors Overhead %

Page 7: Using RAMM to Improve Contract Management Charmaine Okros

7

• All costs are associated with the correct WBS Code to allow for even distribution across the budget.

P & G Spread Across WBS Codes

Page 8: Using RAMM to Improve Contract Management Charmaine Okros

8

Patrol Templates

Page 9: Using RAMM to Improve Contract Management Charmaine Okros

9

Meeting & Presentations

Page 10: Using RAMM to Improve Contract Management Charmaine Okros

10

Works Management Process

Page 11: Using RAMM to Improve Contract Management Charmaine Okros

11

Cardinal Rules to Raising a Dispatch

• One Dispatch per Asset Type

• One Dispatch per Maintenance Activity – refer Table 4‑1

• The Dispatch dimensions must reflect the scope of Work

• The Dispatch location (Start – End) must reflect where the work area, where defined by the fault code

• Dispatch Asset Type must be valid in terms of Unsealed Activity on Unsealed asset, Sealed Activity on Sealed roads asset, Signs activity on Sign assets etc...

Dispatch Guide with Cardinal Rules

Page 12: Using RAMM to Improve Contract Management Charmaine Okros

12

Asset Update Guide

Page 13: Using RAMM to Improve Contract Management Charmaine Okros

13

Annual Planner

Page 14: Using RAMM to Improve Contract Management Charmaine Okros

14

Missing Data Reports

Page 15: Using RAMM to Improve Contract Management Charmaine Okros

15

Maintenance Cost Data

Page 16: Using RAMM to Improve Contract Management Charmaine Okros

16

GIS Layers

Page 17: Using RAMM to Improve Contract Management Charmaine Okros

17

Patrol & RAMM Contractor

Page 18: Using RAMM to Improve Contract Management Charmaine Okros

18

Routine Achievement Report

Page 19: Using RAMM to Improve Contract Management Charmaine Okros

19

• Improved maintenance and renewal decisions

• Improved asset updating

• Improved maintenance achievement and cost records

If you get contract setup and support this with strong reporting and analytics

Page 20: Using RAMM to Improve Contract Management Charmaine Okros

20

Network Owners Control the Contracts

Page 21: Using RAMM to Improve Contract Management Charmaine Okros

Thank you.

Page 22: Using RAMM to Improve Contract Management Charmaine Okros