User Manual
for
Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections
for
Division, Sub-Division and Store Panel
Developed for:
Uttar Pradesh Power Corporation Limited
Submitted By: Designed & Developed By:
Uttar Pradesh Power Corporation Limited
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 2 of 31
Table of Content
1. Introduction ............................................................................................................................................ 3
1.1. Overview of the Software ...................................................................................................................... 3
1.2. Scope of the User Manual ...................................................................................................................... 3
1.3. Intended Audience of Application ..................................................................................................... 3
1.4. Application Convention .......................................................................................................................... 3
2. System Requirement ............................................................................................................................ 4
3. Process Flow of Software .................................................................................................................... 5
Division Panel
4. Process to Approve Application/View Status of Application ................................................ 6
4.1. Access Portal ............................................................................................................................................... 6
4.2. Approve New Connection Request .................................................................................................... 7
4.3. View Status of Application at various stages .............................................................................. 15
Sub-Divisional Officer Panel
5. Process to Approve Application/View Status of Application .............................................. 16
5.1. Access Portal ............................................................................................................................................ 16
5.2. Process New Connection Request ................................................................................................... 17
5.3. Process to Add Junior Engineer ....................................................................................................... 23
5.4. Process to Assign Connection Request to JE ............................................................................... 25
5.5. View Status of Application at various stages .............................................................................. 26
Store Panel
6. Process to Approve Application/View Status of Application .............................................. 28
6.1. Access Portal ............................................................................................................................................ 28
6.2. Process Pending Applications........................................................................................................... 29
7. For Any Technical Service Support ............................................................................................... 31
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 3 of 31
1. Introduction
1.1. Overview of the Software
This Web Module for Uttar Pradesh Power Corporation Limited is developed
for applicants who want to apply for Private Tube Well/Pump Set Connection
in Uttar Pradesh. Along with, Department and its various officers at Division
and various levels will be the intended audience of this software who will
perform their role in processing the application.
1.2. Scope of the User Manual
This User Manual will provide step by step guidance on how the Authorities
at Departmental Level will Approve or Reject the applications for the
connection of Private Tube Well/Pump Set and release the connection.
1.3. Intended Audience of Application
Following will be the intended audience of this application:
• Concerned authorities at Departmental Level who will process the
application.
1.4. Application Convention
The Application has following conventions: a. Fields which have * sign indicate mandatory fields.
b. Error Messages will be displayed in Pop-up box.
c. Success Messages will be displayed in pop-up box.
d. All the menu links will be displayed in the side menu.
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 4 of 31
2. System Requirement
Please ensure that your computer meets or exceeds the following system
requirements before using this application.
• Processor: o 450 MHz or faster processor o 32-bit (x86) or 64-bit (x64) processor
• RAM: o 2 GB
• Operating Systems: o Window 7 or higher version
• Sufficient Hard Disk Space • Firefox 30 or above /Chrome 32 or above or latest browser
• Internet Connectivity (256 Kbps or above)
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 5 of 31
3. Process Flow of Software
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 6 of 31
Division Panel
4. Process to Approve Application/View Status of Application
4.1. Access Portal
To access the Single Window Clearance System for Release of Private Tube Well/Pump
Set Electricity Connections, type the address http://apps.uppcl.org/ptw/account/deptlogin
in the search tab of your browser or click on the link given on website. Page will open as
shown below:
• Division will have to fill details like Login ID, Password and Captcha in the respective
fields.
• After filling all the details correctly, Division will have to click on Login button.
• Click on Forgot Password link in case Division has forgotten the password and do the
necessary proceedings to recover the password.
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 7 of 31
4.2. Approve New Connection Request
After successful Login user will be redirected to Dashboard. Page will be displayed as
shown below:
• Count of New Applications Received will be shown on the marked tab.
• Division will have to click on New Connection Request tab to process the applications
received. After clicking on tab, page will open as shown below:
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 8 of 31
• Division can search any particular application by selecting Year or/and filling
Application No. in the respective field(s). After filling the details correctly, Division will
have to click on Search button after which that particular application(s) will appear on
the screen.
• User will have to click on Process button of particular application to process it. After
clicking on button page will be displayed as shown below:
• Division will have to fill Survey Letter No. and Survey Letter Date in the respective
fields and upload Survey Letter in JPG/JPEG/PDF format whose file size should not
exceed 1 MB.
• After filling the details and uploading the document, Division will have to select SDO to
whom he/she wants to appoint for further processing of application.
• After selecting the respective SDO, user will have to click on Submit button, after which
application will be forwarded to the Concerned SDO for further proceedings.
• Once the application is approved from SDO level, Division will receive a notification
regarding same on their dashboard and application will appear in Pending Approved
Estimate Document section. Division can access the application through below
process:
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 9 of 31
• Count of Applications Pending for Estimate Approval will be shown on the marked tab.
• Division will have to click on Pending Approved Estimate Document tab to process
the applications received. After clicking on tab, page will open as shown below:
• User will have to click on Process button. Page will open as shown below:
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 10 of 31
• User will have to fill TC Letter Number, TC Letter Date, Approved Estimate Amount
and can select/de-select List of Material provided by SDO and can view the quantity
filled by SDO. User can also fill the Quantity from his/her (Division) level after which he
can give final approval.
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 11 of 31
• Along with, user will also have to Upload Scanned copies of Approved Estimate and TC
Letter in JPG/JPEG/PDF format whose file size should not exceed 1 MB each.
• After completing the formalities of this form, user will have to click on Save button.
• As soon as the Division will click on Save button, changes of form will freeze and no
changes will be allowed in this form.
• After saving the form, it will be forwarded to concerned applicant for further processing
and payment of approved estimate.
• If applicant pays the fee through online mode then Division will not have to do any
approval but incase applicant submits the details of fee payment related to Demand
Draft/RTGS/NEFT (Offline Mode) then Division will have to approve the payment
related details. Division will have to follow the below process to approve the payment
details:
• Count of Applications Pending for Payment verification will be shown on the marked
tab.
• User will have to click on Pending for Verify Payment tab to process the applications
pending for payment verification. After clicking on tab, page will open as shown below:
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 12 of 31
• User will have to click on Verify button of particular application to verify the payment
details.
• After clicking on Verify button page will open as shown below:
• Division can view the details of payment uploaded by the applicant on this page.
• After viewing the details, user will have to click on Confirm button to verify the
payment details.
• As soon as the Division will verify the payment details it will be forwarded to applicant
for further proceedings.
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 13 of 31
• Once the application formalities are completed by Applicant, it will appear to Division’s
dashboard in Pending Line Order section for uploading. Division can upload the Line
Order through following process:
• Count of Applications Pending for Line Order will be shown on the marked tab.
• Division will have to click on Pending Line Order tab to process the applications
pending for Line Order. After clicking on tab, page will open as shown below:
• Division will have to click on Click Here button of particular application to process the
application. As soon as the user will click on the aforesaid button page will open as
shown below:
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 14 of 31
• User will have to upload Line Order on this page by clicking on Upload Line Order
button. File of Line Order should be in JPG/JPEG/PDF format whose size should not
exceed 1 MB.
• After successfully uploading the file, User will have to click on Save button, after which
Line Order will be submitted and application will be forwarded to Concerned Store for
further proceedings.
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 15 of 31
4.3. View Status of Application at various stages
Division can view the status of application at various stages through his/her dashboard. After
Logging In through the process as mentioned above, Dashboard will appear as shown below:
• Count of applications pending at any stage will be displayed on its respective tab.
• Division can click on respective tab to view the status of applications
pending/transferred in that particular section like Feasible Connection, Rejected
Connections, Estimated Cost Paid, Applications Pending at Store, Applications Pending
for Metering and Connections and Number of Metering and Connections Released.
• Along with, Division can also view the Released Connection Report, Pendency Report,
Revenue Report and SDO Updation (SDO Details).
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 16 of 31
Sub-Divisional Officer Panel
5. Process to Approve Application/View Status of Application
5.1. Access Portal
To access the Single Window Clearance System for Release of Private Tube Well/Pump
Set Electricity Connections, type the address http://apps.uppcl.org/ptw/account/deptlogin
in the search tab of your browser or click on the link given on website. Page will open as
shown below:
• Sub-Divisional Officer (SDO) will have to fill Login ID, Password and Captcha in the
respective fields.
• After filling all the details correctly, SDO will have to click on Login button.
• Click on Forgot Password link in case SDO has forgotten the password and do the
necessary proceedings to recover the password.
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 17 of 31
5.2. Process New Connection Request
After successful Login, SDO will be redirected to Dashboard. Page will be displayed as
shown below:
• Count of New Applications Received will be shown on the marked tab.
• SDO will have to click on New Connection Request tab to process the applications
received. After clicking on tab page will open as shown below:
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 18 of 31
• SDO can search any particular application by selecting Year or/and filling Application
No. in the respective field(s). After filling the details correctly, SDO will have to click on
Search button after which that particular application(s) will appear on the screen.
• SDO will have to click on Process button of particular application to process it. After
clicking on button, page will display as shown below:
• SDO will have to choose one date out three (as selected by Applicant) for inspection of
feasibility of site.
• After selecting a particular date, SDO will have to click on Approve button. After
clicking on Approve button, inspection date, selected by SDO will be sent to the
concerned applicant through SMS for intimation.
• Once the inspection date has been approved by SDO, next page will open as shown
below:
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 19 of 31
• After inspection, SDO will have to select the status of New Connection Feasibility State
by selecting radio button of OK or NOT OK.
• If SDO selects OK, page will open as shown below:
• SDO will have to ensure that whether TFR is uploaded or not by selecting checkbox.
After selecting the checkbox, SDO will have to select Distribution Mains Category,
upload New Connection Feasibility State Report in PDF/JPG/JPEG format whose file size
should not exceed 1 MB and click on Save TFR button.
• After clicking on Save TFR button, next page will open as shown below:
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 20 of 31
• On this page, SDO will have to fill/select Feeder Details like Feeder Code, Connection
Area, SDO Office, Customer Type, Supply Type Code, Town, Enclosure-Indemnity Bond,
Enclosure-Owner Consent Letter, Route Sequence, Estimate Letter Reference No.,
Estimate Letter Date, Area, Type of Connection, Particular Details(Indent/Job Card),
Line Related Details and Amount to be paid by applicant.
• After filling/selecting the required details, SDO will have to upload a copy Estimate
Copy and Line Chart in JPG/JPEG/PDF format whose file size should not exceed 1 MB
each.
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 21 of 31
• After uploading the documents, click on Save button. Application will be forwarded to
Concerned Division for further proceedings.
• Once the application has been proceeded by the Division, it will be displayed on SDO’s
Dashboard to Release Connection.
• SDO will Login with the same process as mentioned before. After Logging In, dashboard
will appear as shown below:
• Count of applications Pending for Metering and Connection will be shown on the
marked tab.
• SDO will have to click on Pending Metering and Connection tab to process the
applications received. After clicking on tab, page will open as shown below:
• SDO will have to click on Release Connection button of particular application to
process it. Page will open as shown below:
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 22 of 31
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 23 of 31
• SDO will have to fill details like Category of Supply, Consumer Type, Meter Lab
No/Badge No., Manufacture, Meter Manufacturing Seal No., Meter Configuration Type,
Initial Reading in KW, Initial Reading in KWH, Initial Reading in KVA, Initial Reading in
KVAH, MF, Service Connection No., Book Number, Village Code, Habitation Code, Date of
Connection Release, Meter Sealing Certificate No., Meter Serial No., Meter Status, Meter
Phase, Rating of Meter, Stock of Location, Full Scale Value of Register, Meter Type, Digits
Left, Post TFR Data-Pole Number, Number of Meter Seal, Number of Box Seal, Number of
CT/BT Chamber Seal.
• After filling the details, SDO will have to upload scanned copies of Meter Sealing
Certificate and Meter Certificate in JPG/JPEG/PDF format whose file size should not
exceed 1 MB.
• Once all the details are filled & documents are uploaded, SDO will have to click on
Submit button.
• After clicking on Submit button application will be shifted to Released Metering and
Connection section and will be forwarded to Applicant for further proceedings.
5.3. Process to Add Junior Engineer
To add Junior Engineer (JE), SDO will have to Login through the Process as mentioned before.
After successful Login, dashboard will open as shown below:
• SDO will have to click on Add Junior Engineer tab to add JE. After clicking on the tab,
SDO will be redirected to the next page as shown below:
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 24 of 31
• SDO will have to fill details like Name of JE, Name of Sub-station and Mobile Number
of JE.
• After filling all the details, SDO will have to click on Save button. As soon as the SDO will
click on Save button JE will be added.
• Once the JE is Added, page will appear as shown below:
• SDO can Edit/Remove the details of JE by clicking on respective Icon/Button.
• If SDO edits the details then he/she has to click on Update button which will appear
after clicking on Edit icon.
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 25 of 31
5.4. Process to Assign Connection Request to JE
SDO will have to assign the Connection Request to JE after adding him/her. To assign connection
request to JE, SDO will have to Login through same process as mentioned above. Dashboard will
appear as shown below:
• SDO will have to click on Assign Connection Request to JE tab. Page will open as
shown below:
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 26 of 31
• For assigning connection request to JE, SDO will have to select type of JE in particular
application. After selecting JE, a pop-up will appear as shown below:
• SDO will have to click on Yes, Assign button, in case he/she is sure to assign JE, else
click on Cancel button.
• As soon as the SDO will click on Yes, Assign button, JE will be assigned for the particular
application.
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 27 of 31
5.5. View Status of Application at various stages
SDO can view the status of application at various stages by Logging In through same process as
mentioned above. After Logging In, Dashboard will appear as shown below:
• Count of applications pending/consist at any stage will be displayed on the respective
tab.
• SDO can click on respective tab to view the status of applications pending/transferred
in that particular section like Feasible Connection, Rejected Connection List, Estimated
Cost Paid, Pending at Store, Pending for Metering and Connection and Released
Metering and Connection.
• Along with, SDO can also view the Total Connections Released and Revenue Report by
clicking on respective tab.
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 28 of 31
Store Panel
6. Process to Approve Application/View Status of Application
6.1. Access Portal
To access the Single Window Clearance System for Release of Private Tube Well/Pump
Set Electricity Connections, type the address http://apps.uppcl.org/ptw/account/deptlogin
in the search tab of your browser or click on the link given on website. Page will open as
shown below:
• Store Officer will have to fill Login ID, Password and Captcha in the respective fields.
• After filling all the details, Officer will have to click on Login button.
• Click on Forgot Password link in case Officer has forgotten the password and do the
necessary proceedings to recover the password.
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 29 of 31
6.2. Process Pending Applications
After successful Login, concerned authority of Store will be redirected to Dashboard.
Page will be displayed as shown below:
• Count of Total Pending Receiving applications will be shown on the marked tab.
• Authority will have to click on Total Pending Receiving tab to process the application.
Page will open as shown below:
• All the pending applications will be shown on this page. Authority will have to click on
Click Here button of respective application to process it.
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 30 of 31
• After clicking on button, application will be displayed as shown below:
• In the application, authority can view the status of Line Order Issued and Estimated
details.
• After viewing the details, authority will have to fill details of Quantity of Material Issued
against the Quantity of Material Approved.
• After filling the details, Authority will have to upload scanned copy of Receiving Letter
in JPG/JPEG/PDF format whose file size should not exceed 1 MB.
User Manual for Single Window Clearance System for Release of Private Tube Well/Pump Set Electricity Connections for Uttar Pradesh Power Corporation Limited Version 1.0
Page 31 of 31
• Once the file has been uploaded, user will have to click on Save button for successful
submission of the details.
• After successful submission of the details application will be forwarded to the
Concerned Sub-Divisional Officer (SDO) for further proceedings.
7. For Any Technical Service Support