vision word macro for deltek vision 5.1€¦ · web viewarlington public schools career center ....
TRANSCRIPT
![Page 1: Vision Word Macro for Deltek Vision 5.1€¦ · Web viewArlington Public Schools Career Center . PRIMARY CLIENT REFERENCE. C.R. Lyons. Director, ... Vision Word Macro for Deltek](https://reader031.vdocument.in/reader031/viewer/2022030900/5b3b61e97f8b9a895a8c60de/html5/thumbnails/1.jpg)
Arlington Public Schools Career Center Condition AssessmentArlington, Virginia
Facility Engineering Associates (FEA) was contracted to provide consulting services to accomplish over 700,000 square feet of condition assessments between three Arlington Public schools in Virginia. The aggressive schedule to meet budgetary and bond scheduling commitments included field assessment work of major components and the development of 10 year capital renewal plans for the Career Center as well as a large high school and middle school. The results were used to develop and justify budgets and to recommend interim projects in light of major deferred school renovations that allow the schools to continue to operate until the extended planned renovations were funded.
PRIMARY CLIENT REFERENCEC.R. LyonsDirector, Maintenance ServicesArlington Public Schools2770 South Taylor StreetArlington, VA 22206(703) [email protected] START DATE: February 11, 2008COMPLETION DATE: April 30, 2008
PROJECT SIZE: 325,000 SQFTVALUE OF CONTRACT: $49,000
CLIENT BENEFITS· Professional assessment of the
current condition of the facility· Forecast of on-going recurring
equipment replacement schedules· Consistent assessment approach for
widely varied school types· Immediate response and cost
projection turn around within two weeks
Scope Items: Facility Condition Assessment
o Mechanical, Electrical, & Plumbing Systems (MEP)o Fire & Life Safetyo Façade & Roofo Interior Finishes & ADA Compliance
Hazardous Materials Screening Collected data and costs populated directly into
spreadsheets Recurring maintenance and life-cycle replacement
identification