vtb capital investment forum russia calling: …...2016 production 46% baikal 9% 21% 24% mineral...
TRANSCRIPT
VTB Capital Investment Forum
Russia Calling: London Session
June 2017
AIM: HGM
Disclaimer
Certain statements within this presentation constitute forward looking statements. Such forward looking statements involve
risks and other factors which may cause the actual results, achievements or performance of the Group to be materially
different from any future results, achievements or performance expressed or implied by such forward looking statements.
Such risks and other factors include, but are not limited to, general economic and business conditions, changes in
government regulations, currency fluctuations (including the US$/RUR rate), the gold price, the Group’s ability to recover its
reserves or develop new reserves, competition, changes in development plans and other risks.
There can be no assurance that the results and events contemplated by the forward looking statements contained in this
presentation will, in fact, occur. These forward-looking statements are correct or represent honestly held views only as at
the date of delivery of this presentation.
The Company will not undertake any obligation to release publicly any revisions to these forward looking statements to
reflect events, circumstances and unanticipated events occurring after the date of this presentation except as required by
law or by regulatory authority.
***
Total cash costs include mine site operating costs such as mining, processing, administration, royalties and production
taxes, but are exclusive of depreciation, depletion and amortisation, capital and exploration costs. Total cash costs are then
divided by ounces sold to arrive at the total cash costs of sales. This data provides additional information and is a non-
GAAP measure.
In line with guidance issued by the World Gold Council, the formula used to define all-in sustaining cash costs measure
commences with total cash costs per ounce sold and then adds sustaining capital expenditures, corporate general and
administrative costs, mine site exploration and evaluation costs and environmental rehabilitation costs. This data seeks to
represent the total costs of producing gold from current operations, and therefore it does not include capital expenditures
attributable to projects or mine expansions, exploration and evaluation costs attributable to growth projects, income tax
payments, interest costs or dividend payments.
2
3
Highland Gold Today
Kekura
Klen
Belaya Gora
Mnogovershinnoye
(MNV)
Baley Hub
Novoshirokinskoye
(Novo)
Blagodatnoye
Lyubov
Khabarovsk
Cluster
Chukotka
Cluster
Baikal
Cluster
Operating Mine
PFS Stage
Scoping Study
46%
54%
2016 Production
46%
9%
21%
24%
Mineral Resources
261
koz
15.1
Moz
---
3.4 g/t
Unkurtash Kyrgyzstan
US$
454
US$
652
Total Cash
Costs
All-In Sustaining
Costs
- JORC-compliant measured, indicated & inferred resources of gold and gold equivalent as of 31
December 2016, adjusted for updated MNV resources (released in May 2017)
- TCC and AISC for FY 2016
US$
162.5M
2016
EBITDA Russia
Khabarovsk Baikal
Khabarovsk
Baikal
Kyrgyzstan
Chukotka
Corporate Overview
4
Listed on London AIM
Publicly-listed company since 2002
Shareholders include a broad range of major high-
quality UK, European and N. American institutional
investors
Committed to Best Practice in
Corporate Governance
Led by an experienced Board of Directors and
management team
Seven directors – executive chairman, one
executive director, and five non-executive directors
Committed to Returning Capital to
Shareholders
FY 2016 total dividends - £0.104
FY 2015 total dividends - £0.045
AIM HGM
Shares 325,222,098
Market Cap* US$ 630M
Enterprise Value* US$ 836M
Net Debt** US$ 206M
Net Debt/EBITDA (LTM)** 1.3x
2016 Earnings/Share US$ 0.145
* On 15 June 2017 ** On 1 January 2017
26.6%
10.0%
46.4%
17.0%
Prosperity Capital
Management
Board &
Management
Institutions
& Retail
Primerod Int’l &
Affiliated Parties
Shareholder Structure
56.4%
Free
Float
5
Our Strategy: Unlocking Value
Maximise
the upside potential
of operating assets
Develop
assets at the PFS
stage into production
Focus development on
regions of presence
Maintain commitment to operating
safety and protecting the environment
- JORC-compliant measured, indicated & inferred resources of gold and
gold equivalent as of 31 December 2016, adjusted for updated MNV
resources (released in May 2017)
De-risk and convert
additional resources
into reserves
MNV
0.6 Moz
7.3 g/t
Novo
1.4 Moz
7.6 g/t
Belaya Gora
0.7 Moz
2.3 g/t
Kekura
2.6 Moz
7.5 g/t
Klen
0.6 Moz
5.0 g/t
Taseevskoye
5.1 Moz
5.1 g/t
Unkurtash
3.7 Moz
1.7 g/t
6
Low Cost, High Margin Producer
986 984 980
917 912 856
813 800 776 766
730 694
652
572
33 40
45 45
35 36
48
35
48 43 45
54 53
62
All-In Sustaining Costs and EBITDA Margin
All figures based on FY 2016 financial data published by company AISC (US$/oz) EBITDA Margin (%)
Commitment to Dividends
7
0.0%
2.0%
4.0%
6.0%
8.0%
10.0%
12.0%
0
2
4
6
8
10
12
2011 2012 2013 2014 2015 2016
GB
X
Dividend per share (pence) Yield (%) Total Payout (US$)
$25.7M $40.3M $26.7M $23.2M $21.9M $41.8M
* Yield based on average share price for the year.
Solid Share Performance, Increased Liquidity
Share Price (pence)
Liquidity
Average Daily Trading Volume
Shares
Value (US$)
HGM
Gold Price
FTSE All Share
MINING
6
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
0
20
40
60
80
100
120
140
160
180
200
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
0
50
100
150
200
250
GB
X
millio
n s
ha
res
$1.5M
$4.6M
Mnogovershinnoye (MNV) – An adjusted
internal Life-of-Mine model for MNV, based
on ongoing near-mine exploration and
reserve recalculations, now provides for
production through at least 2022 (versus
2018 previously).
Novo – Project for expansion to 1.3 mtpa ore
mining and processing capacity underway
and on track for completion in late 2018.
Blagodatnoye - Extensive exploration drilling
carried out to confirm resources.
Baley Hub – De-watering programme initiated
for existing Taseevskoye open-pit with a view
to de-risking the project and allowing for
further reserve confirmation. Exploration work
also carried out on Sredny Golgotay along
with a pilot mining project at the Kaftan site
on the Sredny Golgotay licence.
9
2016 Highlights
Interim dividend of £0.050 per share paid for H1 2016 (2015: £0.020)
Final dividend of £0.054 per share recommended (2015: £0.025)
Total distribution for 2016 of £0.104 per share.
2016 2015
Production of gold and
gold equivalent
261,159
oz
262,485
oz
Total Cash Costs
(per oz)
US$
454
US$
480
All-In Sustaining Costs
(per oz)
US$
652
US$
640
Average realised price
(per oz Au equivalent)
US$
1,136
US$
1,062
EBITDA US$
163 M
US$
133 M
Net debt to EBITDA
ratio 1.26 1.74
Cash inflow from
Operations
US$
136 M
US$
106 M
MNV and Novo improved on Q1 2016
gold and gold equivalent production
by 27.5% and 15.7%, respectively.
At Belaya Gora, continued focus on
processing low-grade ore stockpiles
pending the completion of an ongoing
project review.
Updated MNV JORC reserve
statement completed and published,
with Ore Reserves doubled.
Two licences received for greenfield
sites adjacent to MNV.
Exploration programme at MNV
continues with a view towards further
extension of life of mine.
Work continues on Kekura DFS along
with a drilling programme for reserve
confirmation.
Government approval granted for the
development of a deposit of “federal
significance” (Kekura)
Scoping study for Unkurtash published
and consultants retained to identify
potential partners.
10
2017 YTD Operating Highlights
Q1 2017 Q1 2016
Production of gold and
gold equivalent
65,243
oz
56,889
oz
Average realised price
(per oz Au equivalent)
US$
1,222
US$
1,174
The Company affirms its forecast for total 2017 production of
255,000-265,000 oz of gold and gold equivalent.
Highland Gold marked
its 15th anniversary
on May 23, 2017.
Focus on Exploration
11
2016 Exploration Drilling (74 km) = US$ 8.2 M*
MNV (14.3 km)
USD 1.2 m
Kekura (25.0 km)
USD 3.2 m
Sredny
Golgotay (15.9 km)
USD 1.5 m
Belaya Gora (3.9 km)
USD 0.3 m
Preliminary
PFS DFS PFS
MNV
Au reserves under GKZ increased by ~3.0 tonnes:
‒ Northern OB (+1.3 t**)
‒ Southern OB (+1.0 t**)
‒ Central OB (+0.4 t)
‒ Low grade stockpiles (+0.2 t)
Life of mine extended to 2022
New JORC reserve estimation published in May
Blagodatnoye (15 km)
USD 2.0 m
* Expenses include the cost of related research work ** Company reserve estimate
Northern Southern Tea
MNV Drilling by Ore Body
11.3 km
2.0 km 1.1 km
Location Khabarovsk Cluster
Opened 1991 (HGM 1999)
LoM 2022
Mine Type Open pit & underground
Processing Gravity + cyanide leaching
Processing Capacity 1.4 mtpa
Au Production (2016) 96,188 oz
Avg Head Grade (2016) 2.36 g/t
Total Cash Costs US$ 607/oz
12
Mnogovershinnoye (MNV)
Oldest operating mine in our portfolio
Recently extended life of mine by four years
following a broad review and regulatory approval of
reserves under Russian (GKZ) classification
New JORC audit completed with ~104% increase in
total reserves (from 246 koz to 500 koz)
Key Challenge: To identify additional resources to
feed the MNV mill beyond 2022
MNV Snapshot Khabarovsk Cluster
122.3
91.8 94.6 90.4
96.2 91.5
Production (koz) Recovery (%) Grade (g/t) TCC (US$)
2014 2015 2016
3.04
2.29 2.36
722 691
607
Unlocking Value:
Extending life of mine
Updated JORC-compliant Mineral Resource and Ore Reserve estimates have been completed with total Ore Reserves increased to 500 koz Au compared to previously estimate of 246 koz
Russian-standard (GKZ) reserves re-estimation carried out on 12 ore bodies across the licence area in 2016-2017
Extensive near-mine exploration focused on upgrading existing resources and targeting additional resources
– Over 14,000 m of exploration drilling
– Annual budget of US$ 3-5 M
Exploration focused on four key targets:
– Lower horizons of existing underground mine
– Areas around existing open pit operations
– Near-mine greenfields on adjacent licences
– Historic rock dumps
US$ 1 M budgeted for 2017 exploration work on new adjacent greenfield licences.
– Kulibinskaya (38 sq km)
– Zamanchivaya (4.2 sq km) 13
Mnogovershinnoye (MNV)
Northern
Southern
Flank
MNV
MNV NW Flank
MNV W Flank
Kulibinskaya
Zamanchivaya
38.8
61.7 61.3
75.4
45.9
71.4
Production (koz) Recovery (%) Grade (g/t) TCC (US$)
2014 2015 201614
Belaya Gora
14 14
Location Khabarovsk Cluster
Opened 2014
LoM 2023
Mine Type Open pit
Processing Gravity
Processing Capacity 1.8 mtpa
Au Production (2016) 45,909 oz
Avg Head Grade (2016) 1.21 g/t
Total Cash Costs US$ 678
Youngest operating mine, developed from
greenfield
GKZ reserves re-estimated in 2016 at lower
cut-off grade (0.3 g/t) leading to drop in LoM
average head grade and resulting in
impairment charge of US$ 22.8 M
Key Challenges
– Irregular grade distribution
– Upgrading mill to improve recovery
Belaya Gora Snapshot Khabarovsk Cluster
1.58 1.64 1.21
926
465
678
Unlocking Value:
Upgrading mill to improve recovery
+ adding new resources
Successful programme to stabilise mill input rate
in 2016 resulted in lower tailings grade
Currently working with SRK on designs for adding
cyanide leach (CIL) capacity to improve recovery
3,900 metres of drilling in 2016 for reserve
confirmation and improved mine planning
A new JORC-compliant reserve statement is
expected in Q3 together with PFS
Targeted for adding resources to Belaya Gora
Preliminarily-measured С2 category reserves for
open pit mining of about 10 million tonnes of ore
Initial metallurgical testwork supports gold
recovery of over 90% via cyanidation.
15,000 metres of drilling in 2016 to confirm
reserves
– JORC-compliant reserves statement in Q3
together with PFS
15
Belaya Gora & Blagodatnoye
Belaya Gora
Blagodatnoye
MNV
30 km
Blagodatnoye
97.8
84.9
105.9
86.0
117.6
85.9
Production (koz) Recovery (%) Grade (g/t) TCC (US$)
2014 2015 201616
Novoshirokinskoye (Novo)
16
Location Baikal Cluster
Opened 2009
LoM 2029
Mine Type Underground
Processing Gravity-flotation circuit
Processing Capacity 0.8 mtpa
Au Production (2016) 117,577 oz gold equivalent
Avg Head Grade (2016) 5.62 g/t
Total Cash Costs US$ 254/oz
Polymetallic mine – gold, silver, lead, and zinc
Produces lead and zinc concentrates
– Outside processing costs of 168 US$/oz
Highest contributor to EBITDA
– 45% of production, 55% of EBITDA
Key Challenge: Increase throughput to offset
expected decline in average grade
Novo Snapshot Baikal Cluster
6.20
5.58 5.62
428
302 254
Unlocking Value:
Expanding capacity
Russian-standard (GKZ) reserves re-
estimation resulted in a 77% increase in ore
volumes and 36% decrease in average
grade, with total gold equivalents rising by
13% to 85.7 tonnes (2.6 Moz)
– New JORC reserve statement expected
in Q2
Larger ore volume at lower grades justified
boosting mill capacity from 700 ktpa to 1.3
mtpa
Underground expansion underway in order
to gain access to new horizons
Engineering and design documentation,
preparations for construction work, and
selection of contractors are all underway
Novo is expected to achieve its new target
production capacity in late 2018
17
Novoshirokinskoye (Novo)
Ore body outlines before reserve re-estimation
Ore body outlines after reserve re-estimation
18
Kekura – Premier Development Project…
Location Chukotka Cluster
Start Date 2020
LoM 2029
Mine Type Open pit & underground
Processing Gravity + Cyanide Leaching
Processing Capacity 0.8 mtpa
Au Production (est. annual) 209,000 oz
Reserve Grade 10.73 g/t
Kekura Snapshot
Kekura Mineral Resources*
Classification Tonnage
(Mt)
Au Grade
(g/t)
Metal Au
(Moz)
Indicated 7.412 8.64 2.06
Inferred 3.266 4.80 0.51
Total 10.678 7.47 2.57
Kekura Ore Reserves*
Classification Tonnage
[Mt]
Au Grade
[g/t]
Metal Au
[Moz]
Proven - - -
Probable Open Pit 4.296 10.94 1.51
Underground 0.541 9.04 0.16
Total 4.837 10.73 1.67
* Reserves & resources compliant to JORC Code 2012. Resources cut-off grade of 1.0
g/t Au. Reserves cut-off grade of 2.2 g/t Au at the open pit and 4.2 g/t Au for the
underground mine. A gold price of US$1,150 per ounce has been applied.
Licence Area: 1,497 sq km
Located 100 km from Kupol
High grade, open pit and underground mining and favourable metallurgy to make Kekura a low cost operation
– Projected TCC of 495 US$/oz
Fluor Canada developing a definitive feasibility study (DFS)
Construction preparations at advanced stage.
Mayskoye
Kupol Klen
Dvoinoye Kekura
Chukotka
Polymetal Kinross
Valunisty
Pevek
Anadyr
Chukotka Cluster
25,000 m exploration drilling program
completed in 2016
Drilling focused on the eastern flank of the
deposit with the aim of improving resource
quality and adding reserves for underground
mining
As part of DFS preparation, 2017 programme
of 11,000 metres of RC-drilling and 4,750 m of
core drilling for reserve confirmation
An additional 1,600 m of core and 2,750 m of
RC drilling scheduled in order to confirm sterile
ground at the planned locations of rock dumps
and infrastructure facilities
11 prospects have been identified within the
Kekura licence area as warranting further
prospecting work
19
…with Great Upside Potential
1 – Zabytiy
2 – Granat
3 – Ryzhiy
4 – Iris
5 – Bond
6 – Zakol
7 – Gonch
8 – Zapadny 2
9 – Zapadny 1
10 – Iris (detailed)
11 – Alpinist
Kekura Deposit
Western site
Central site
Eastern site
Kekura
63 km² licence, located in an existing mining
area with access to roads, power, and water
supply, and plans for infrastructure upgrades
Audited JORC resources of 3.7 Moz of gold at a
grade of 1.7 g/t
Scoping study published in March 2017 showing
favorable economics
Highland Gold is considering partnership
opportunities to develop this promising resource
20
Unkurtash
Unkurtash
Sarytube
Karatube
Baikonur 0 1000 m
Unkurtash
Kazakhstan
Kyrgyzstan
Kumtor
Bishkek
Bozymchak
Ishtamberdy
Centerra Kazakhmys
Full Gold Mining
China
Unkurtash Licence Area Location Kyrgyzstan
LoM 18 years
Mine Type Open pit
Processing Gravity + Cyanide Leaching
Processing Capacity 4 mtpa
Au Production (est. annual) 133,000 oz
Resource Grade 1.7 g/t
Avg. Operating Costs (est.) US$ 616/oz
Capex Required US$ 322 M
NPV (10%) US$ 200 M
Unkurtash Snapshot
Figures based on March 2017 scoping study
Kyrgyzstan
Largest of Baley Hub projects (Baikal Cluster)
with resources of 5.1 Moz at 5.1 g/t
Refractory ore
Previously mined both open pit and
underground in mid-20th century
Currently de-risking the project by pumping
water out of the Taseevskoye pit and
monitoring inflow from the Baley pit
– Three pumps are up and running, current
daily volume is 21.6k m3
– 3.3M m3 pumped out in H2 2016 and
January 2017
– 5.7 metre decrease in water level
– No water inflow from Baley pit detected at
the present water levels
– De-watering programme to continue
throughout 2017
After de-watering the pit, a drilling programme
will be implemented to confirm reserves
21
Taseevskoye
Baley Open Pit Taseevskoye Open Pit
567
568
569
570
571
572
573
574
AS
L,
m
Water Level Change in Pits
Тасеевский Балейский Baley Taseevskoye
Jul Aug Sep Oct Nov Dec Jan
171 142 160
29 119
140
200
2010 2016 2020
2017 Production Guidance: 255-265 koz
2020 Production Target: 500 koz
– Includes only operating mines and Kekura
– Additional upside potential with Klen, Baley Hub (Taseevskoye,
Sredny Golgotay), and Unkurtash
Delivering Growth
22
Baikal Novo
Chukotka Kekura
Khabarovsk MNV
Belaya Gora
Blagodatnoye
~500
200
261 4.4%
CAGR
~
~
~
Comfortable Balance Sheet
Gross debt decreased by US$ 42M in
2016
Effective interest rate of 4.54% p.a. on
01 Jan 2017
– Down from 5.43% on 01 Jan 2016
Average tenor – 23 months.
303
254
212 247
231 206
0
100
200
300
01.01.2015 01.01.2016 01.01.2017
Gross Debt Net Debt (M US$)
23
Net Debt / EBITDA ratio = 1.3 as of 01 January 2017
16
227
Cash & cash equivalents Undrawn credit facilities
Liquidity Position – 31.03.2017
US$
243M
PFS
MNV
Novo
Belaya Gora
Blagodatnoye
Kekura
24
Milestones for 2017
Updated JORC Reserves
Unkurtash
Scoping Study
Belaya Gora + Blagodatnoye
Klen
Kekura
DFS
25
The Highland Gold Investment Case
Upside Potential in Existing
Operating Assets
Growth Potential in High
Grade Deposits
Development Strategy
Focused on Regional Hubs
Disciplined Capital
Allocation Unlocking the
Value of
Highland Gold’s
Resource Base Commitment to Dividend
15-Year Track Record
as a Public Company
www.highlandgold.com [email protected] +7 495 424-9521
0 Appendices
27
Appendix 1:
2016 Financial Highlights
2016 2015 2014
Gold and GE Production, koz 261.2 262.5 258.9
Revenue, USD m 305.9 276.2 304.2
Operating Profit w/o Impairment, USD m 92.2 58.4 67.3
Impairment Losses, USD m -22.8 -36.0 -11.4
EBITDA, USD m 162.5 133.3 123.6
STRONG BALANCE SHEET
Total Assets, USD m 1120.6 1167.2 1243.8
Total Equity, USD m 755.6 739.6 770.1
Gross Debt, USD m 211.6 253.5 303.4
KEY RATIOS
TCC, USD / oz 454 480 645
AISC, USD / oz 652 640 809
Net Debt / EBITDA 1.3 1.7 2.0
EBITDA margin 53% 48% 41%
DIVIDENDS
Dividends paid during the year, USD m 31.7 20.1 26.8
Dividends declared during the year
interim, GBP per share 0.050 0.020 0.025
final, GBP per share 0.054 0.025 0.020
total, GBP per share 0.104 0.045 0.045
Total Dividends declared during the year, USD m 41.8 21.8 23.2
28
Appendix 2:
2016 Consolidated Income
2016
US$000
2015
US$000
Revenue 305,901 276,175
Cost of sales (183,995) (199,365)
Gross profit 121,906 76,810
Administrative expenses (14,293) (13,127)
Other operating income 1,255 2,882
Other operating expenses (16,675) (8,170)
Impairment losses (22,832) (35,982)
Operating profit 69,361 22,413
Foreign exchange gain /(loss) 1,909 (4,321)
Finance income 145 1,331
Finance costs (5,187) (5,529)
Profit before income tax 66,228 13,894
Total income tax expense (18,319) (23,913)
Total comprehensive income for the period 47,909 (10,019)
Profit/(loss) per share (US$ per share) 0.145 (0.032)
Appendix 3:
2016 EBITDA
29
+ USD 22.9 m – increase in Au price (+8%) and
GE price (+9%)
+ USD 5.2 m – change in the volume of sales by
3%, including:
‒ Novo + 19 722 oz of GE
‒ MNV + 3 877 oz of Au
‒ BG - 4 560 oz of Au
- USD 5.8 m – increase in cost of sales due to BG
- USD 1.5 m – increase in G&A
133 162
9 23 5 7 1
0
50
100
150
200
250
2015 ExchangeRate
MetalPrices
Volumeof Sales
Cost of sales G&A 2016
EBITDA Bridge, US$ m
55
96
26 - 15
45%
76%
45%
MNV NOVO BG G&A
EBITDA, USD m EBITDA margin, %
EBITDA Breakdown by Mine
Appendix 4:
2016 Cash Flow
30
Key Cash Outflows
34% - Debt Service
33% - CAPEX and exploration
20% - Dividends
24 9
141 12 31
9 18
42
12 32
3
Cash & CE01.01.2016
OperatingAssets
Contribution
MaintenanceCAPEX
DevelopmentCAPEX
ExplorationCAPEX
G & A BankLoans
BankInterest
Dividend Other(ForEx)
Cash31.12.2016
HGML Cash Flow, US$ M
27%
6%
34%
20%
13%
Cash Outflow Breakdown
Other
Dividends
Banks
CAPEX
Exploration
Appendix 5:
2016 TCC & AISC
31
Higher costs at BG prevented us from taking full advantage of the weak
rouble and limited the decrease in HGML TCC to 6%.
MNV and NOVO TCC decreased by 12% and 16%, respectively, as
compared with 2015, reflecting the weak rouble and increases in sales of
gold and GE (MNV +4%, NOVO + 19%)
A 46% increase in BG TCC was due to low grades and recovery rates.
HGML AISC increased by 2% to USD 652/oz
‒ The positive effect of lower TCC was offset by an increase in
maintenance CAPEX (+6%) due to BG and growth of G&A (+7%)
480 454
691 607 465
678
302 254
148 168
2015 2016 2015 2016 2015 2016 2015 2016
HGML TCC,
US$/oz.
TCC by Mine, US$/oz.
-6 %
MNV TCC BG TCC Adjusted NOVO TCC
as if producing DORE
Kazzink Processing Costs, USD/oz sold
-12 %
-6 % +46 %
432 450
640 652
2015 2016
+2%
HGML AISC ,
USD/oz.
Appendix 6:
2016 Capital Expenditure
32
57 34
51
2014 2015 2016
Total Capital Expenditure, US$ M (excl. VAT)
+50%
k US$ excl. VAT 2014 2015 2016
KHABAROVSK CLUSTER 26,983 13,596 15,945
MNV 6,305 3,895 10,059
Belaya Gora 20,678 9,701 5,886
BAIKAL CLUSTER 8,492 7,067 16,551
Novo 7,837 5,598 11,077
Taseevskoye + Kaftan 295 1,312 5,373
Lubov 360 157 101
CHUKOTKA CLUSTER 21,449 13,475 18,233
Kekura 12,239 12,137 17,952
Klen + VK area 9,211 1,338 282
OTHER 493 60 436
Highland Exploration 493 60 436
Total Capital Expenditure 57,417 34,198 51,165
* including capitalized expenses of development projects & excluding ore bodies, stripping activity assets and capitalized inventory
Appendix 7:
2016 Operating Data
33
Mining
Processing
In 2016, the volume of mined ore
decreased by 15% mainly due to a
decrease at BG (-0.7Mt)
The stripping ratio increased by 31%
due to 2x growth at BG
Volume of ore mined:
‒ 1 425 kt at MNV (-5% y-o-y)
‒ 1 561 kt at Belay Gora (-30% y-o-y)
‒ 761 kt at Novo (+9% y-o-y)
The share of ore mined underground
increased to 40% from 33% in 2015
Volume of ore processed:
‒ 1 381 kt at MNV (-2% y-o-y)
‒ 1 643 kt at Belaya Gora (+6% y-o-y)
‒ 758 kt at Novo (+10% y-o-y)
Recovery rates remained stable due to
improvement at MNV
Average grade decreased by 5% due to
a 26% decrease at BG.
12,432
20,112 19,251
6.6 5.8 7.6
2014 Actual
2015Actual
2016Actual
Rock Mined , kt Stripping Ratio, t/t
Rock Mined and Stripping Ratio
-4%
1,193 1,467 1,501
1,627
2,961 2,245
2,820
4,428 3,746
2014 Actual
2015Actual
2016Actual
Underground Open Pit
Ore Mined, kt
-15%
3,177
3,655 3,782
2014 Actual
2015Actual
2016Actual
Ore processed, kt
+3%
3.05 2.64 2.51
83% 85% 85%
2014 Actual
2015Actual
2016Actual
Average Grade, g/t Recovery Rate, %
Average Grade and Recovery Rate