Ivan Graff 2020 Project Management Symposium WORK BREAKDOWN STRUCTURES FOR FEDERAL CONSTRUCTION PROJECTS

Upload: others

Post on 02-Aug-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: WORK BREAKDOWN STRUCTURES FOR FEDERAL …€¦ · Integration of the work breakdown structure and the organizational structure in a manner that permits cost and schedule performance

Ivan Graff2020 Project Management Symposium

WORK BREAKDOWN STRUCTURES FOR FEDERAL CONSTRUCTION PROJECTS

Page 2: WORK BREAKDOWN STRUCTURES FOR FEDERAL …€¦ · Integration of the work breakdown structure and the organizational structure in a manner that permits cost and schedule performance

WORK BREAKDOWN STRUCTURES

F O R F E D E R A L C O N S T R U C T I O N P R O J E C T S

YO U H AV E L E S S F L E X I B I L I T Y T H A N YO U T H O U G H T

Page 3: WORK BREAKDOWN STRUCTURES FOR FEDERAL …€¦ · Integration of the work breakdown structure and the organizational structure in a manner that permits cost and schedule performance

ABOUT YOUR PRESENTER• Responsible for capital asset acquisition

project policy at the U.S. Department of Energy.

• Agency budgets $3 to $5 billion on capital asset acquisition projects annually.

• Previously employers: National Science Foundation, Smithsonian Institution, USDA, and the University of Maryland College Park.

– M.S., Civil Engineering (Construction Management), UMCP.

– B.S., Bioresource Engineering (Structures), Rutgers University.

Ivan GraffP.E., PMP, CCP, CFM, LEED-AP

[email protected]

The views expressed by the speaker do not necessarily

reflect those of his employer.

May 7, 2020 University of Maryland Project Management Symposium 3

Page 4: WORK BREAKDOWN STRUCTURES FOR FEDERAL …€¦ · Integration of the work breakdown structure and the organizational structure in a manner that permits cost and schedule performance

WBS THEORYSection 2.3 Principles

• Depicts all scope and project deliverables.

• First level accounts for the whole project.

• 100 Percent Rule.

• WBS elements do not:

– Contain costs.

– Imply importance.

– Overlap.

– Assign resources.

– Account for time or sequence.

May 7, 2020 University of Maryland Project Management Symposium 4

Project Management Institute. Practice Standard for Work Breakdown Structures, 3rd Edition. (2019)

Page 5: WORK BREAKDOWN STRUCTURES FOR FEDERAL …€¦ · Integration of the work breakdown structure and the organizational structure in a manner that permits cost and schedule performance

KINDS OF DECOMPOSITIONTable 2-1: “A WBS of only one type of decomposition is rare.”

• Action

• Backlog

• Contract

• Deliverable

• Phase

• Product

• Program

May 7, 2020 University of Maryland Project Management Symposium 5

Project Management Institute. Practice Standard for Work Breakdown Structures, 3rd Edition. (2019)

“Establishing a product-oriented WBS is a best practice” - GAO 20-195G

Page 6: WORK BREAKDOWN STRUCTURES FOR FEDERAL …€¦ · Integration of the work breakdown structure and the organizational structure in a manner that permits cost and schedule performance

EXAMPLE WBS

May 7, 2020 University of Maryland Project Management Symposium 6

Practice Standard for Work Breakdown Structures, 3rd Ed. PMI. 2019

Page 7: WORK BREAKDOWN STRUCTURES FOR FEDERAL …€¦ · Integration of the work breakdown structure and the organizational structure in a manner that permits cost and schedule performance

WBS AS CONTRACT PROXY

May 7, 2020 University of Maryland Project Management Symposium 7

Project

Contractor 1

Sub 1

Sub 2

Sub 3

Contractor 2

Sub 4

Sub 5

Sub 6

Contractor 3

Sub 7

Sub 8

Sub 9

Page 8: WORK BREAKDOWN STRUCTURES FOR FEDERAL …€¦ · Integration of the work breakdown structure and the organizational structure in a manner that permits cost and schedule performance

WBS AS SCHEDULE PROXY

May 7, 2020 University of Maryland Project Management Symposium 8

Project

Phase 1

Milestone 1

Milestone 2

Milestone 3

Phase II

Milestone 4

Milestone 5

Milestone 6

Phase III

Milestone 7

Milestone 8

Milestone 9

Page 9: WORK BREAKDOWN STRUCTURES FOR FEDERAL …€¦ · Integration of the work breakdown structure and the organizational structure in a manner that permits cost and schedule performance

EIA-748D AND GAO 20-195GPMI Says WBS elements do not . . .

48 CFR §34.201(b)Earned Value Management Systems, EIA-748D, January 2019

Cost Estimating and Assessment Guide, GAO 20-195G, March 2020

Contain costs Summarize direct costs from control accounts [2.3(b)]

Provides a basic framework for . . . estimating costs. [Page 56]

Imply importance Multi-level hierarchical breakdown [3.2] Breaks down product-oriented elements into a hierarchical parent-child structure. [Page 56]

Assign resources Integration of the work breakdown structure and the organizational structure in a manner that permits cost and schedule performance measurement [2.1(e)]

Provides a basic framework for . . . identifying resources. [Page 56]

Account for time or sequence

Integration of the work breakdown structure and the organizational structure in a manner that permits cost and schedule performance measurement. [2.1(e)]

Provides a basic framework for . . . developing schedules. [Page 56]

May 7, 2020 University of Maryland Project Management Symposium 9

Page 10: WORK BREAKDOWN STRUCTURES FOR FEDERAL …€¦ · Integration of the work breakdown structure and the organizational structure in a manner that permits cost and schedule performance

May 7, 2020 University of Maryland Project Management Symposium 10

Standardized work breakdown structure benefits:• Consistent cost estimates• Data sharing• Efficient program execution

Cost Estimating and Assessment Guide, GAO 20-195G, Page 64

Does the Government have a way to

standardize construction work breakdown

structures?

Project

Asset

System

System

Asset

System

System

Asset

System

System

Page 11: WORK BREAKDOWN STRUCTURES FOR FEDERAL …€¦ · Integration of the work breakdown structure and the organizational structure in a manner that permits cost and schedule performance

ROAD TO STANDARDIZATION

May 7, 2020 University of Maryland Project Management Symposium 11

Federal Property Management

Reform Act of 201640 USC §524(a)(11)(B)(vi) & (xi)

Report the total cost of capital expenditures for each asset into . . .

Federal AssetsSale and Transfer

Act of 201640 USC §1303 Note

41 CFR §102-84a

. . . a single database of all Federal real property.

Note a: New location of regulation as of 2019 not cited.

Statute and Regulations

Page 12: WORK BREAKDOWN STRUCTURES FOR FEDERAL …€¦ · Integration of the work breakdown structure and the organizational structure in a manner that permits cost and schedule performance

ROAD TO STANDARDIZATION•What do agencies report? (41 CFR §102-84.40)

•Historical Capital Expenditures (Data Element 16)

• Estimated Future Capital Expenditures (Data Element 17)

May 7, 2020 University of Maryland Project Management Symposium 12

Federal Real Property Council Guidance (2019)

Page 13: WORK BREAKDOWN STRUCTURES FOR FEDERAL …€¦ · Integration of the work breakdown structure and the organizational structure in a manner that permits cost and schedule performance

ROAD TO STANDARDIZATIONBUILDING USE CODES

10 Office

14 Post Office

17 Outpatient Healthcare

21 Hospital

22 Prisons

23 School

24 Comfort Stations

25 Data Center

28 Museum

29 Other Institutional Uses

30 Family Housing

31 Dormitories/Barracks

41 Warehouses

50 Industrial

60 Service

72 Communication Systems

73 Navigation and Traffic Aids

74 Laboratories

80 All Other

84 Border/ Inspection Station

85 Facility Security

86 Land Port of Entry

87 Aviation Security Related

88 Public Facing Facility

89 Child Care Center

STRUCTURE USE CODES

12 Airfield Pavements

13 Harbors and Ports

15 Power Development and Distribution

16 Reclamation and Irrigation

18 Flood Control and Navigation

28 Museum

40 Storage

50 Industrial

60 Service

65 Space Exploration

66 Parking Structures

70 Research and Development

71 Utility Systems

72 Communication Systems

73 Navigation and Traffic Aids

75 Recreational

76 Roads and Bridges

77 Railroads

78 Monuments and Memorials

79 Miscellaneous Military Facilities

80 All Other

82 Weapons Ranges

83 Renewable Energy

May 7, 2020 University of Maryland Project Management Symposium 13

Federal Real Property Council Guidance (2019)

Page 14: WORK BREAKDOWN STRUCTURES FOR FEDERAL …€¦ · Integration of the work breakdown structure and the organizational structure in a manner that permits cost and schedule performance

ROAD TO STANDARDIZATION

May 7, 2020 University of Maryland Project Management Symposium 14

Federal Participation in the Development and

Use of Voluntary Consensus Standards

15 USC §272 NoteOMB Circ. A-119, Section 5 (2016)

Agencies must use voluntary consensus standards

Industry Standards

Options for Construction (non-inclusive)

ASTM E1557-09 (2015)Systems oriented

SpecsIntact (2020) based onCSI MASTERFORMAT (2018)Item oriented

North American Industry Classification System (2017)Vendor oriented

Page 15: WORK BREAKDOWN STRUCTURES FOR FEDERAL …€¦ · Integration of the work breakdown structure and the organizational structure in a manner that permits cost and schedule performance

May 7, 2020 University of Maryland Project Management Symposium 15

Level 0

Level 1

Level 2

Level 3

Level 4

Level 5

PROJECT 2

ASSET 1 ASSET 2 ASSET 3

GROUP ELEMENT 1

GROUP ELEMENT 2

GROUP ELEMENT 3

INDIVIDUAL ELEMENT 1

INDIVIDUAL ELEMENT 2

INDIVIDUAL ELEMENT 3

Work Package 1

Work Package 2

Work Package 3

WBS levels above the projectcorrespond to sites or programs.

Multiple levels of group elements permitted.

Multiple levels of individual elements permitted.

Include level of effort items such as management on this or lower levels.

BasisFederal Real Property Profile Use Codes. 40 USC § 524(a), 40 USC §1303 Note, and 41 CFR § 102-84

UNIFORMAT II (ASTM E1557) or CSI MASTERFORMAT Spec. 01 50 ff. or NAICS

UNIFORMAT II (ASTM E1557) or CSI MASTERFORMAT Spec. 01 50 ff. or NAICS

CSI MASTERFORMAT or NAICS

Work Breakdown Structure Standardization

for Capital Asset Acquisition Projects

PROGRAM

PROJECT 1 PROJECT 3

Page 16: WORK BREAKDOWN STRUCTURES FOR FEDERAL …€¦ · Integration of the work breakdown structure and the organizational structure in a manner that permits cost and schedule performance

WBS CHALLENGES• Allocating costs collected through a “WBS with

issues” to assets.

• Documenting level of effort activities such as project management.

• Distinguishing between enduring (products) and ephemeral (deliverables) outputs.

• Expanding the Federal Real Property Profile’s library of use codes.

• Accommodating unique assemblies not listed in industry standards.

May 7, 2020 University of Maryland Project Management Symposium 16

Page 17: WORK BREAKDOWN STRUCTURES FOR FEDERAL …€¦ · Integration of the work breakdown structure and the organizational structure in a manner that permits cost and schedule performance

MORE CHALLENGES• Sharing cost estimating relationships between

agencies.

• Detangling projects and assets (e.g., OMB M-20-03, Real Property Capital Planning).

• Explaining the Federal Real Property Profile’s rolling five year horizon for collected capital costs.

• Communicating plans in a database oriented toward actuals.

• Parity between real and personal property (Federal Personal Property Management Act of 2018).

May 7, 2020 University of Maryland Project Management Symposium 17

Page 18: WORK BREAKDOWN STRUCTURES FOR FEDERAL …€¦ · Integration of the work breakdown structure and the organizational structure in a manner that permits cost and schedule performance

QUESTIONS?P L E A S E T Y P E YO U R Q U E S T I O N S I N TO T H E C H AT B OX .

May 7, 2020 University of Maryland Project Management Symposium 18