world bank document · expected to encompass “high-value” contracts as defined in para. 5 of...

34
Kingdom of Morocco World Bank Program-for-Results Operation in support of the National Initiative for Human Development Phase 2 Fiduciary System Assessment June 29, 2012 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 13-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

Kingdom of Morocco

World Bank

Program-for-Results Operation

in support of the National Initiative for Human Development

Phase 2

Fiduciary System Assessment

June 29, 2012

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

wb350881
Typewritten Text
71171
Page 2: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

ii

TABLE OF CONTENTS

A. EXECUTIVE SUMMARY ....................................................................................................... 1

B. BACKGROUND AND INSTITUTIONAL ARRANGEMENTS ............................................... 2

B.1 SCOPE OF THE ASSESSMENT ............................................................................................................. 2 B.2 INSTITUTIONAL FRAMEWORK .......................................................................................................... 2 B.3 PROGRAM ACTIVITIES ...................................................................................................................... 3 B.4 FIDUCIARY ARRANGEMENTS ............................................................................................................ 4

B.4.1 Procurement arrangements ...................................................................................................... 4

B.4.2 FM arrangements ..................................................................................................................... 6

B.5 PROGRAM BUDGETING ..................................................................................................................... 6

C. PROGRAM FIDUCIARY PERFORMANCE .......................................................................... 7

C.1 TIMELINESS: PROCUREMENT PLANNING AND DISBURSEMENT ........................................................ 7 C.2 COST EFFECTIVENESS: BIDDERS’ QUALIFICATIONS, BIDS EVALUATION, AND CONTRACT AWARD . 7 C.3 COMPETITIVENESS AND COMPLIANCE IN PROCUREMENT PROCESS ................................................. 8 C.4 COMPLIANCE: PROCUREMENT REVIEW AND OVERSIGHT ................................................................ 8 C.5 COMPLAINTS HANDLING MECHANISM ............................................................................................. 9 C.6 STAFFING ....................................................................................................................................... 11 C.7 CONTRACT MANAGEMENT ............................................................................................................. 11 C.8 EFFECTIVENESS OF COORDINATION BETWEEN AGENCIES .............................................................. 12 C.9 PLANNING AND BUDGETING ........................................................................................................... 12 C.10 ACCOUNTING AND FINANCIAL REPORTING .................................................................................... 14 C.11 TREASURY MANAGEMENT AND FUNDS FLOW. ............................................................................... 16 C.12 INTERNAL CONTROLS AND AUDIT .................................................................................................. 16 C.13 PROGRAM AUDIT ........................................................................................................................... 18 C.14 FIDUCIARY PERFORMANCE MONITORING ....................................................................................... 20

D. FIDUCIARY RISK ................................................................................................................. 21

D.1 OVERALL RISK ............................................................................................................................... 21 D.2 RISK MITIGATION MEASURES ......................................................................................................... 22

E. GOVERNANCE, ANTI-CORRUPTION AND ACCOUNTABILITY .................................... 24

E.1 FM AND PROCUREMENT ................................................................................................................ 24 E.2 ARBITRATION AND MEASURES TO FIGHT FRAUD AND CORRUPTION ............................................. 25 E.3 IMPROVEMENT OF PROGRAM SYSTEMS TO FIGHT FRAUD AND CORRUPTION ................................. 26 E.4 TRANSPARENCY ............................................................................................................................. 26 E.5 ACCOUNTABILITY .......................................................................................................................... 27

F. INPUTS TO IMPLEMENTATION SUPPORT PLAN ........................................................... 27

G. APPENDICES ........................................................................................................................ 28

G.1 APPENDIX 1: IMPROVEMENTS IN THE NEW DRAFT PPD ................................................................. 28 G.2 APPENDIX 2A: KEY PROCUREMENT PERFORMANCE INDICATORS ................................................ 29 G.3 APPENDIX 2 B: KEY FM PERFORMANCE INDICATORS ................................................................... 31

Page 3: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

iii

ACRONYMS AND ABBREVIATIONS

CDC Cour des Comptes

CDG Caisse de Dépôt et de Gestion

CLDH Comité local de Développement Humain

CN Coordination Nationale

CPDH Comité Provincial de Développement Humain

CRDH Comité Régional Développement Humain

DAS Division de l’Action Sociale

DBM Division du Budget et du Matériel

DLI Disbursement-Linked Indicator

FCC Fiduciary Coordination Committee

IGAT Inspection Génerale d’Administration Territoriale

IGF Inspection Génerale des Finances

INDH National Initiative for Human Development

KFSPI Key Fiduciary Statistic Performance Indicator(s)

PAP Program Action Plan

PFM Procurement and Financial Management

RFI Results Framework Indicator(s)

TGR General Treasury of the Kingdom

Page 4: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

1

A. EXECUTIVE SUMMARY

1. In preparation of the Program for Results operation supporting the second phase of the National

Initiative for Human Development (INDH2) in Morocco, a Program Fiduciary System Assessment1 was

conducted which covered the INDH institutional framework, the fiduciary management capacity and

implementation performances including a sample of executing agencies. This Fiduciary System

Assessment was undertaken based on current knowledge of Moroccan Public Procurement and Financial

Management systems, previous diagnostics2, and the fiduciary performance of INDH 1 completed by a

field assessment over a sample of procuring entities. Morocco has launched an ambitious PFM reform

program that is leading to improved alignment of the Moroccan public procurement and financial

management system with international practices. Overall, public procurement and financial management

systems are considered as having experienced a very positive development over the past decade.

2. The main deficiencies raised by previous diagnostics, and INDH 1 implementation experience that

could affect the Program are the following: (i) the lack of an independent procurement appeals system and

clear process for handling complaints; (ii) quality and timeliness of annual audited financial statements;

(iii) weak effectiveness of internal audit function and follow-up of audit recommendations, (iv) a heavy

reliance on Management Information Systems (MIS) for DLIs verification protocol, (v) low capacity of

small or remote entities procurement staff which often leads to low quality of technical specifications,

ToR, and bidding documents; (vi) lack of thoroughness of bid evaluation linked to choice of criteria or

scoring system; and (vii) occurrences of questionable quality of works, goods or services delivered to

small or remote entities. The procedures and control framework are adequate, but the risks persist

because of the large number of small contracts and sponsors, often with low capacity, dispersed over

more than 20 000 activities or locations.

3. Under INDH 1, the large number of sub-program /projects sponsors inexperienced in fiduciary

matters was a risk factor. This risk will increase in INDH 2 with the significant extension of its scope to

increase the number of beneficiaries/sponsors new to the Program. Consequently the mitigation

measures described below are proposed.

4. Most of the country-level weaknesses will be addressed under ongoing reforms and new legislation

including the Organic Law to be enacted and the public procurement reform in progress (including draft

laws or decrees currently under preparation). The new public procurement decree currently under

preparation will apply to local Governments; introduce an improved complaint handling mechanism and

e-procurement procedures. In the meantime, specific measures to deal with these issues in relation to

INDH are going to be built into the Program as agreed with the Government of Morocco (GoM), such as

an improved Grievance Redress Mechanism (GRM) to be implemented at all levels of the Program

(including the decentralized level) and which will include features contributing to handle procurement-

specific complaints.

5. The main proposed mitigating measures to address identified risks are to: (i) design and implement

a capacity building program (Program action Plan (PAP)#10), (ii) improve Program oversight and internal

audit function,(iii) develop and disseminate new simplified fiduciary Guide and guidance tools for

bidding documents preparation and contract templates, and measure percentage of project sponsors

mastering the procedures (see fiduciary Result Fiduciary Indicator(RFI) # 13 and 16),( iv) revise Program

Audit TORs; (v) reflect Audit recommendations in yearly provincial Action Plans, and ensure that

priority audit recommendations are implemented (see the two fiduciary DLIs 7 and 8). (vi) ensuring that

1 This assessment was done according to the draft PforR Financing Guidance Notes (dated January 3, 2012)

2 2010 UCS Pilot review report, 2009 PEFA and 2007 CFAA

Page 5: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

2

the MIS is robust and effective so that quick disbursement is not jeopardized and it will enable better

procurement reporting (RFI #12); (vii) monitoring KPSI during implementation support and Audits, (viii)

improving assurance framework, (ix) expanding audit reviews with TORs covering procurement; (x)

providing new guidance tools for bidding documents preparation and contract templates and verify that

commissioned infrastructure projects comply with technical specifications (RFI #13 and #6); (xi)

implementing a fiduciary training program; (xii) establishing a Fiduciary Coordination Committee to

oversee fiduciary performance (see PAP#12); (xiii) strengthening grievance mechanisms procedures

which include the handling of procurement-related complaints (PAP #8); and (xiv) providing formalized

technical support through a customized clause in project sponsor agreements (see RFI#13).

B. BACKGROUND AND INSTITUTIONAL ARRANGEMENTS

B.1 Scope of the Assessment

6. In preparation for the Program for Results operation in support of the second phase of the National

Initiative for Human Development (INDH 2), a Program Fiduciary Assessment was conducted. The

assessment covers the INDH institutional framework, the fiduciary management capacity and

implementation performances including site visits to a sample of 20 executing agencies and procuring

entities. The findings outlined in this report are based on the results of the site visits, the current

knowledge of Moroccan Public Procurement and Financial Management systems (as documented in the

2010 Use of Country System Piloting Program report, 2009 PEFA and 2007 CFAA), and on the fiduciary

performance of phase one of the INDH, referred to as INDH 1.

7. This report begins with a presentation of the institutional arrangements under INDH 2, followed by

the performance of the Program’s fiduciary setup according to specific topics. Based on those findings, a

section on fiduciary risks presents the overall and specific risks, and although the entire report touches

upon the areas of Governance, Anti-Corruption and Social Accountability throughout, a special section is

dedicated to these issues. The final sections cover the inputs to the implementation support plan and the

supporting annexes.

B.2 Institutional framework

8. The INDH institutional structure connects the central government to the lowest levels of

administration which involves hundreds of entities across all levels (i.e., central, regional, provincial, and

municipal / neighborhood or community).

9. The Steering Committee responsible for the Program is chaired by the Prime Minister and its

membership is composed of the INDH National Coordinator and the Ministers of Interior, Finance, and

Social Development. This committee oversees progress in overall INDH 2 implementation and reports to

the Strategic Committee.

The Ministry of Interior, through its INDH Coordination Unit, is ultimately accountable for meeting the

objectives of INDH. This INDH Coordination Unit provides technical support to the various levels of

committees (regional, provincial and local) as well as other stakeholders that participate in the program.

Importantly, it oversees the execution of procurement and financial management and centrally gathers all

technical and financial data related to the program as a whole, which it uses to prepare consolidated

reports for monitoring program implementation. Additional institutional and technical support is

provided by various line ministries and government agencies.

10. From a financial perspective, the Head of the Government has overall responsibility for the INDH

special revenue account (SRA, Compte d’affectation special). As such, he allocates funds to the eligible

executing agencies (Ministry of Interior, “Walis” of regions and governors of provinces/prefectures)

Page 6: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

3

based on an annual disbursement schedule by program. These funds are then executed according to

applicable public expenditure regulations, either through partnership agreements with project sponsors or

through direct payments to providers of goods and services.

B.3 Program activities

11. The INDH program is implemented through a decentralized and participatory process wherein sub-

projects are undertaken by project sponsors (such as municipalities, NGOs and community associations)

or by the decentralized executing agencies (Walis or governors) themselves. Some activities such as

studies or technical assistance can also be carried out at the central level by the eligible executing

agencies (i.e. Head of Government office, Coordination Nationale). The Program will be implemented

using the same institutional arrangements as INDH 1.

12. INDH 2 is implemented by hundreds of implementing agencies, many of them inexperienced in

fiduciary activities and located in remote rural or difficult to access municipalities. INDH 2 essentially

follows the same structure and activities as INDH 1 but with an enhanced scope that increases both the

financing amount and the number of beneficiaries. Therefore, the typical types and values contracts under

INDH 2 are expected to be similar to those under INDH 1 and will include two main types of

expenditures: (i) small value contracts for social infrastructure (construction, rehabilitation, extension or

improvement of road and street infrastructure, electricity or water supply, sanitation or solid waste

services, schools, local health centers or community centers, public gardens, sports or other public

facilities, etc.), and (ii) financial support for developing small and local businesses with regard to

improved organization, product quality, or marketing, business training as well as activities allowing for

the participation of INDH target population in infrastructure or service projects (e.g. local household

waste collection, water management, and recycling management) that generate revenues for the local

communities. As under INDH 1, the subprograms of INDH 2 which the Bank will support are not

expected to encompass “high-value” contracts as defined in para. 5 of BP9.00.

13. Based on the information furnished during the preliminary assessment, in INDH 1 works contracts

represented more than 75% of the cost of all contracts awarded, followed by goods contracts with about

15% of the total cost. Consultant contracts represented less than 5%. Though the number of contracts

awarded through open national competitive bidding (ONCB) and shopping procedures are both about

equal, the corresponding amounts are dramatically different: the value of ONCB contracts represents

more than 90% of the total amount.

14. Therefore, the typology /procurement profile of the INDH phase 2 could be roughly extrapolated

on the basis of the data furnished for INDH1, as follows (purely indicative orders of magnitude):

Total amount of subprojects to be financed would be approximately $2 billion and the part used

to finance Works, Goods and Services contracts to be procured in an amount (excluding the

territorial upgrading component and non-contract related AGRs amounts) of $900 million to $1

billion corresponding to nearly 40 000 contracts, including approximately $700 million in the

aggregate for Works contracts, $120-$150 million in the aggregate for Goods contracts, and less

than 50 million USD for Consultants contracts. About 18,000 to 20,000 procedures would be

NCB –National Competitive Bidding (average estimated cost for each contract procured under

NCB in the range of 40,000 to 50,000 USD), and the estimated number of Shopping processes3

(or “Purchase Orders”), is approximately 20,000 with an average amount of approximately 5,000

USD each.

3 (*The threshold, i.e. upper limit for use of the Shopping procedure “for similar items” was set in INDH first phase

at the level of 200 000 MAD (< 25 000 USD). This threshold comes from article 75 of the current PPD.)

Page 7: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

4

B.4 Fiduciary arrangements

15. The “Walis” and governors are responsible for the management of INDH funds including

implementation. They may delegate their authority to the project sponsors they select (i.e., municipalities,

NGOs and associations). If the “Walis” or governors decide that the project sponsors do not possess

adequate capacity to implement the project, it would instead be implemented using the provincial services

(DAS, DBM and Division Technique), although the vast majority of the projects will be implemented at

the decentralized level.

16. Authority delegations for procurement and FM activities granted by the Walis/governors were

decided during INDH 1 without prior formal capacity assessments of the municipalities and NGOs

undertaking implementation. Under INDH 2, systematic and benchmarked assessments of the fiduciary

capacity of project sponsors will be implemented before Walis/governors decide whether their

procurement activities will be delegated to provincial services.

17. The executing agencies manage delegated funds by programming activities, which results in

allocating funds under budget lines defined jointly by the accounting department and the Division of

Social Action (DAS). This programming exercise results from a strategic planning process described in

the operations manuals which involves the population and the decision-making entities (CLDH, CPDH

and CRDH). These funds are executed according to the decree no 2-05- 1017 of July 19, 2005 which

offers more flexibility than traditional public expenditure procedures.

18. The execution of the INDH is based on administrative structures and existing communal and

associations will be involved. Responsibilities within the administrative services and municipalities are

clearly defined but less so in NGOs. Regarding new implementing agencies and procuring entities (those

not involved before in the Program, small or remote, NGOs, and associations), fiduciary capacity is a

serious concern and would require intensive intervention.

19. The involvement and role of each administrative entity or project sponsor in the INDH is defined

in the Operational Manual that will be updated, simplified and reviewed for the sections linked to

fiduciary aspects by the Fiduciary Coordination Committee and issued as a Fiduciary Guide under INDH

2.

20. The fiduciary innovation team which was put in place for INDH 1 is potentially a good mitigation

measure but unfortunately it did not work efficiently during the first phase, partly because it was not

empowered to enforce its proposals and partly because it was not permanent and faded out in the last

years. The new Fiduciary Coordination Committee envisaged to be piloted by CN, would be instituted

under INDH2 and would include representatives from TGR, IGF and IGAT. The CN will chair the

committee and manage the secretariat. The Committee would be permanent and would have clear;

detailed TORs reviewed by the Bank as well as a mission letter. Its role would include the

review/elaboration of (i) Fiduciary Guide, (ii) standard documents and other tools, (iii) fiduciary capacity

building plans, (iv) oversight of fiduciary activities under the Program, and (v) Key Statistic Fiduciary

Indicators (KSFPI) generated by the improved program Information System/MIS.

B.4.1 Procurement arrangements

21. The procurement arrangements under INDH 1 largely followed the GoM’s national procurement

procedures with small modifications made to compensate for important differences between the national

law and Bank procedures (these changes were introduced through list of provisions in the legal

agreement, known as the “NCB List”. Compliance of standard Bidding Documents with these provisions

was mandatory under INDH1). As INDH 2 is anticipated to use the Bank’s PforR instrument,

Page 8: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

5

procurement will not be subject to the Bank’s Procurement Guidelines and instead will be executed in

accordance with the GoM’s procurement procedures and regulatory framework.

22. The award of contracts under INDH 1 as well as for all other departments of the administration

(including local authorities indirectly) is governed by the Moroccan public procurement decree (PPD) No.

2-06-388 of 05 February 2007. State-owned enterprises (SOE) are not automatically subject to the PPD

and may establish and apply their own procurement rules once the rules are adopted by their respective

Boards and approved by the Ministry of Finance. The GoM is currently preparing a new PPD that makes

several improvements to and expands the scope of the 2007 PPD. Once the new PPD is enacted, it will

be applicable to the INDH 2 as well. This enactment is currently expected to happen before end of year

2012. In addition to the short discussions of improvements in the new PPD contained throughout this

document, a summary of the major changes introduced in the PPD is included in Annex 1.

23. As mentioned in para. 13, the two main procurement methods expected to be used under INDH 2

for Goods and Works contracts are Open National Competitive Bidding (ONCB), and Shopping (for

purchase orders).

24. Controls and oversight of Evaluation Committees. The PPD lays out various methods for the

control and oversight of evaluation committees, as they are involved in one of the most critical aspects in

the procurement process. The first control is outlined in Article 34 of PPD and provides for an ex-ante

review by a Moroccan “Controleur des Engagements” (controller) who represents the MoF/TGR and is

responsible to check compliance with the provisions of the PPD, especially in terms of bid opening. After

the evaluation is completed (in which the controller is not involved), the report and the draft contract are

submitted for the controller’s review and approval/formal clearance (“Visa préalable”) which is required

before a contract can be signed. Although contracts awarded by associations / NGOs are not subject to

the controller’s review, the PPD includes other provisions to mitigate risk in such contracts including (i)

requiring the tender committee to include a representative of DAS and another from the relevant INDH

committee (ii) subjecting the last payment (10%) to the physical inspection (final acceptance) by a

commission chaired by a representative of Wali / Governor in accordance with standard financing

agreement to be signed by project owner and (iii) the ex-post audit by the joint IGF/IGAT as described

below.

25. A second control is an annual audit that was established for all INDH activities performed by

implementing agencies in all provinces (77/83 provinces are under financed subprograms) on a

representative sample of 20 to 30 % of the contracts in each province. This audit covers a review of

procurement procedures and contract management and is conducted jointly by the General Inspectorate of

Finance (IGF) under the Ministry of Finance and the General Inspectorate for Territorial Administration

(IGAT) under the Ministry of Interior. Summaries of the annual audit reports are published on the website

of the INDH.

26. Finally, all entities implementing Program activities are also subject to review on regularity,

economy, and efficiency by the Supreme Audit Institution (Cour des Comptes).

27. Record Keeping and Document Management Systems. In general, procurement documentation

is kept in all public entities including rural municipalities. At the provincial level, procurement documents

are managed by three different services: (i) "service des marchés", (ii) the accounting service under

“Division du Budget et du Matériel", and (iii) the accounting service under the "Division de

l'Equipement". Associations and NGOs do not always have space of their own, which makes it difficult

for them to maintain the documentation. (Such an issue would be one of the factors for the proposed

Wali/governor’s new systematic assessment for delegation as a mitigation measure under INDH 2

described in in para. 16). Centrally, CN has recently added a contracts/procurement module named

"Marchés" in the existing information system that is reportedly being further improved to streamline the

Page 9: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

6

data entry and report generation processes. The expected improvements including more user friendly and

exhaustive data acquisition as well as customized output generation (of KSFPI, program wide aggregates)

are scheduled to be in place by the beginning of INDH 2 and are anticipated to provide a substantial

improvement to collecting information and to enable the production of customized aggregated statistic

fiduciary data, indicators and reports

B.4.2 FM arrangements

28. A Special Purpose Account (Compte d’Affectation Special- CAS) was introduced by the Decree of

19 July 2005 for the purpose of INDH1 with budget sub-headings for each component. The NGOs and

cooperatives also pay their contribution from funds transferred to them by the CAS. The CAS is a special

account, separated from the general budget for the line ministries, but fully transparent within the budget

law and ruled by the same financial regulations as for the general budget. The expenditures of INDH 2

CAS, as for INDH 1, are authorized by the Head of the Government (authorizing officer, ordonnateur

principal), the Deputy authorizing officers (sous- ordonnateurs) being the Governors of the provinces.

Provincial authorizing officers have provided during INDH 1 the bulk of the implementation of the

program because of the low capacity of the communes. To this regard, the use of CAS by the local

municipalities has been below initial expectations

B.5 Program Budgeting

29. PFM reform. A new organic budget law has been drafted and should be submitted to parliament

before the end of 2012 according to authorities. Its implementation will be phased over five years, starting

with pilot testing in the most advanced ministries in 2013. This reform will introduce a programmatic

budget structure with corresponding performance objectives, indicators and reports. This would improve

the transparency of budget allocations to the government’s policies and programs and increase

accountability on their outcomes, both internal (within the administration) and external (towards the

parliament and the public). The administration’s performance will be reviewed by the Government, the

Parliament and subjected to performance audits.

30. The budget comprehensiveness should be improved by including in the finance law all public

sector entities relying on transfers from the budget and by subjecting them to the same performance

management approach. Furthermore, the special treasury accounts will be consolidated in the budget to

improve transparency. The revision of the accounting rules and the adoption of modified accrual

accounting will further improve financial information. The authorities are currently finalizing the

evaluation of the State’s assets, which is necessary for the adoption of accrual accounting.

31. Budget classification, predictability and composition. As described in the Technical

Assessment, expenditure monitoring is supplemented by an economic and functional classification

system. This classification system is detailed, stable and viable, and consistent with GFMS 2001.

Investment programming system in Morocco includes a sophisticated multi-year budgeting including a

multi-year commitment authorization (autorisations d’engagement) consistent with an annual payment

system (crédits d’engagement). Regarding the predictability of donors’ aid, Government is targeting a

total contribution of external (bilateral) donors of 7% (Bank contribution is counted towards the General

Budget share).4 At the moment only the EU has pledged a contribution of 20 million euro with the

possibility of increasing it in the context of a new PIN. Additional contributions from other donors are

likely. Overall, funding appears adequate to achieve the Program objectives and is likely to be sustained.

It is expected to reach US$2.1 billion, up from US$1.2 billion during INDH I. About 55 percent of the

4 The team will review if donors, involved in INDH, provide complete budget estimates for disbursement of project aid at stages

consistent with the Government’s budget calendar and with a breakdown consistent with the Government’s budget classification.

Page 10: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

7

total funding is expected to come from central government (down from 60 percent), 38 percent from local

governments (up from 20 percent) and 7 percent in grants from international donors (down from 18

percent). Contributions from central and local governments have been secured. Due to high level and

widespread ownership of INDH 2, funding is expected to continue over the years. The proposed Bank

loan of US$ 300million over four years (2012-2015) will contribute to the Central government's funding

share. However, despite the increase in resources from INDH I to INDH 2, INDH 2 funding will remain

at roughly 3% percent of GOM’s total social investments. The economic and financial reports annexed to

the draft budget bills introduced to Parliament, along with the Budget Directorate’s activity reports,

provide details of overall targets and achievements of special government programs, and targets and

allocations for the current year. For INDH, the reports indicate the quantified goals for the year including

employment, literacy etc.

C. PROGRAM FIDUCIARY PERFORMANCE

C.1 Timeliness: Procurement Planning and disbursement

32. The PPD requires all national implementing agencies to publish provisional procurement plans that

include all contracts planned to be launched under the budget. The plans are made available no later than

the end of the first quarter of each fiscal year in at least two national newspapers (one in Arabic and one

in foreign language) and on the procurement electronic portal.

33. In INDH 1, which is a CDD type program this publishing requirement was followed at central

level but not at the decentralized levels. However, even when published the details of the contract

information included were not always sufficient for potential bidders. For example, descriptions of

contracts in these provisional plans were sometimes vague and included neither the size nor estimated

cost of the contract. In addition, the lack of sufficient information in the plans made it impossible to

assess the timeline taken for procurement procedures under INDH 1.

34. Under INDH 2, elaboration of more detailed procurement plans would become mandatory for all

including local governments thanks to the new PPD currently under preparation. In addition,

improvements to the information system would allow to track key fiduciary statistic performance

indicators (KFSPIs) of the procurement process that will allow a more in-depth analysis of the timeliness

of procurement activities. (A full list of the KFSPIs related to procurement can be found in Annex 3 of

this document.)

C.2 Cost effectiveness: Bidders’ qualifications, bids evaluation, and contract award

35. The PPD states that bidding documents (DAO) must state the qualification criteria of bidders

("eligibilité") and bid evaluation criteria ("classement des offres"). However, it is not explicitly stated

that the bid evaluation criteria, other than price, must be expressed in monetary terms. Such practices can

decrease the level of transparency in procurement processes as they allow the potential for procurement

processes to unjustifiably favor a specific candidate and therefore affect negatively thoroughness of bid

evaluation.

36. The potential negative impact on the INDH 1 of these practices was limited given the

standardization of bidding documents, although in some cases the rating/scoring system was also used for

qualification. To further mitigate this risk, the GoM has prepared guides and made them available in the

public procurement portal that explain the preparation of bidding documents, however inexperienced staff

may need more details than is provided in the guides. For example, in the sites visited, the team noted that

standard bidding documents are used in a very mechanical manner due to lack of fiduciary skills or

Page 11: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

8

training (implementation strictly following ”word for word” the Standard Forms rather than procurement

principles) even if it lead to some inconsistencies.

37. In INDH 2, this risk will be mitigated in part by increasing the knowledge of responsible

stakeholders through a large capacity building initiative including (i) dissemination of simplified and

updated manuals for procurement, (ii) availability of other documentation tools (electronic web based

etc.); and (iii) implementation of provincial fiduciary capacity building plans.

38. In addition, technical support of external services (provided by provincial, line ministries, or SOEs

such as ONE or ONEP etc.) to project sponsors to assist with bidding documents and specs preparation,

TOR design, project preparation and works supervision during implementation will be systematically

formalized and customized through a specific clause in the partnership contracts/agreements (see RFI #

13).

C.3 Competitiveness and compliance in Procurement process

39. The PPD requires that public procurement announcements of specific bidding opportunities be

advertised in at least two newspapers (one in Arabic and other in foreign language) and on the public

procurement portal. In all sites visited, this requirement was enforced except in some rare cases in rural

communes where the publication is limited to newspapers due to the difficulty or impossibility of

accessing to the Internet. As stated earlier, the new PPD will also increase exposure to bidding

opportunities by requiring all levels of government (including the local level) to publish procurement

plans.

40. One potential way of limiting competition is to split larger contracts into smaller ones to allow the

use of less competitive procurement methods. In Morocco, the practice of splitting of contracts is

difficult because the PPD limits the use of shopping method (one of the least competitive methods) to

200,000 DH (<25,000 USD) per empowered person, by fiscal year and by type of expenditure (see further

the corresponding reference of PPD article). As part of the INDH, this rule has been softenedlaxed to

allow for increased flexibility and the threshold is applied to type of expenditure only instead of including

the empowered person and fiscal year. Currently, the lack of details in the annual procurement plans does

not allow an analysis to identify possible procurement processes to merge together to increase efficiency

and competition.

41. Bidding documents are free of charge and can be downloaded from the online procurement portal.

Bids opening sessions are public. Although the PPD allows administrative and financial envelopes to be

opened at different times, in most cases these openings are held on the same day and during the same

meeting due to the simplicity of related operations. This was not an issue in INDH 1 as the simultaneous

opening of envelopes was required in the aforementioned “NCB List.” The list of attendees during bid

opening is not systematically established.

42. In INDH 2, this risk would be mitigated by having the Program’s bidding documents requiring

simultaneous bid opening.

C.4 Compliance: Procurement review and oversight

43. As explained in para. 24, public contracts executed by the administrative departments or municipal

services are subject to systematic ex-ante control by the regional services of the TGR. An exception is

made for contracts awarded by municipalities in the INDH which limits the scope of the review to only a

verification of the availability of funds.

44. Although the governance body set-up proved generally effective under INDH1, there was scope to

improve accountability, reduce persisting fraud and corruption risk, and avoid elite capture.

Page 12: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

9

45. An earlier section of this assessment covered the controls and oversight mechanisms in place for

contracts awarded by the associations/NGOs and the joint audits of the IGF / IGAT. The Governors and

Walis as INDH managers are the recipients of audit interim reports and they have a time given to respond

before finalization of the report. CN annually forwards the joint audit recommendations to the entities

responsible for implementing the Program (“Lettre d’orientation”). Nevertheless, it is noteworthy that

auditors highlighted a list of recommendations that remained recurrent from year to year. This indicates a

lack of close monitoring and follow-up of auditors' recommendations under INDH 1.

46. It is also worth noting that the findings of ex-post reviews by the World Bank and the independent

review conducted for INDH overlap substantially with and corroborate IGF / IGAT’s joint audit findings.

The main findings for INDH 1 were in general caused by weakness of staff capacities in small or remote

procuring entities as evidenced by (i) unclear or imprecise technical specifications and ToRs, (ii) poor

quality of bid evaluation reports due to poor quality of bidding documents; (iii) non-compliance with

contract terms, (iv) additional work not formalized contractually; (v) short-lists including unqualified

bidders.

47. As indicated earlier, in INDH 2, a formal clause in the partnership agreement providing for

technical support in various areas (technical and bidding document creation, works supervision, etc.) will

be included which will help to mitigate these risks.

48. The other main issue identified in previous Bank’s diagnostics that could affect the Program is the

lack of an independent procurement appeal system and a clear process for handling complaints, which is

discussed in the following section. The GoM is taking action on this weakness in the ongoing public

procurement reform process through new laws or decrees currently under preparation as well as through

the procurement complaints handling component of an improved Program Grievance Redress Mechanism

(GRM) for INDH2.

C.5 Complaints handling mechanism

49. The existing PPD provides a basic complaint mechanism relating to public procurement

procedures. According to the PPD currently in force, (Décret n° 2-06-388 du 16 Moharrem 1428 (5

février 2007, article 95), a bidder who wants to raise a complaint must do so first with the contracting

authority (i.e., the official procuring entity). If the response received is not satisfactory, the bidder may

only address it to the Minister and, if not satisfied with his answer, to the Secretaire General du

Gouvernement. The latter can (but not “shall”) transmit the request to the Commission des Marches

which would render a simple advice without any means for enforcement. In comparison to international

best practices, this complaint mechanism for procurement procedures lacks three vital elements: (1) No

independent bodies to which an appeal can be made, (2) No provision guaranteeing processing time or

granting the power to suspend the process pending the closing of the complaints, and (3) No publishing of

information arising from complaints, even in redacted form.

50. In the sites visited, very rare cases of complaints to the contracting authority had been reported

(but not beyond this first level), and in each case, the complainant received a response letter from the

contracting authority. (Under INDH1, no complaints were recorded at the central level.) There is no

system in place to track complaints managed by entities that implement contracts or at the National

Coordination level, and the systematic recording of procurement complaints and tracking their resolution

is not a common practice.

51. The proposed new public procurement decree which is expected to be enacted before end of year

2012 contains significant improvements to the complaints handling system by introducing: (i) direct

referrals to the Contract Review Committee and a direct response to the complainant, and (ii) power to

freeze procurement process and award proceedings pending closing of the complaint. These

Page 13: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

10

improvements are nevertheless dependent on the reform transforming the Central Procurement Board

(CPB) (Commission Centrale des Marchés) from an ad-hoc committee composed solely of representatives

of different administrations into a permanent, more independent and powerful “Commission de la

Commande Publique” which will give it the level of independence required. The GoM is preparing the

draft decree to reform the CPB which aims at (i) reinforcing the representation of the public procurement

key stakeholders (local governments, ministries, SOEs and private sector), (ii) enhancing the authority of

the CPB with regards to administrative complaints handling procedures, (iii) setting time limits for

complaints treatment, (iv) providing the possibility for complainants to address their complaints directly

to the CPB and (v) defining the minimum professional and ethical qualification criteria for members of

the CPB. Once the new PPD and CPB decrees are passed, Morocco will have laid the groundwork for a

modern complaints handling mechanism based on good international practices.

52. In the interim, procurement complaints under INDH 2 will be addressed through an agreed-upon

broader cross-sectoral Program Grievance Redress Mechanism, of which procurement complaints are a

part.

53. Grievance redress related to the Program takes place through a variety of institutions, and it is

convenient to refer to is as a Grievance Redress System (GRS). At the National Level the National

Integrity and Anti-Corruption Agency (NIAA), the Ombudsman Office, and the National Council of

Human Rights can all receive any allegation, grievances notice and complaint related to the Program from

any actor or simple citizen. Additionally, both IGAT and IGF have internal grievance redress procedures.

54. Specifically for INDH, the IGAT has developed a system whereby it can receive complaints from

INDH implementing agencies, associations, private sector actors, or simple citizens. Complaints relating

to the INDH are dealt with by IGAT’s Audit Pole. If the complaint has a more general nature, the

complaint is dealt with by the Pole Inspection’. INDH related complaints are dealt with as follows: a) if

the complaint lacks sufficient backing information but seems to require further investigation, an

inspection commission is tasked with following up and collecting additional information; b) If the

information backing the complaint is sufficient, but the substance does not require to be addressed as a

matter of priority, its treatment is planned in the context of the audit missions with a view to increasing

efficiency; c) if the complaint has an urgent character, IGAT Audit Pole launches an inspection mission in

concertation with the Inspection Pole.

55. At Program level, the internal regulation of INDH governance bodies as described in the

Program’s Operational Manuals includes mechanisms for receiving and addressing grievances with a

view to enabling the mediation mandate of these bodies.5 Local level mechanisms tend to vary, reflecting

the decentralized nature of INDH. However, common elements include: -The Social Action Division at

Provincial level includes a Grievance office charged with receiving and addressing complaints, including

F&C allegations:

- At provincial level a complaint unit is set up reporting directly to the governor;

- At commune level INDH set up ‘complaints box’ allowing for anonymity of the plaintiff;

- The presence of CSO representative within the Governance bodies, together with technical

services and elected members, allows for addressing F&C allegations brought to the knowledge of

CSO representatives;

56. Only a few provinces today have performing internal GRMs. Therefore the Program introduces

elements in order to improve the effectiveness and reliability of INDH grievance redress mechanisms to

5 For example, the INDH1 Rural subprogram OM states that ‘local authorities are tasked with ‘receiving complaints,

address them and attempt to resolve them

Page 14: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

11

be implemented during INDH 2 (see Program Action Plan # 6). The goal is to enable a more systematic

application of processes and procedures within Governance bodies starting from the provincial level

DASs and reinforcing the capacities of the actors in charge of receiving and following up on complaints.

Technical assistance will be provided during Implementation Support (see Annex 9) to the provincial and

local levels to design a practicable system that will then be written up in the Operational Manual and

generalized. GRM data will be integrated within the overall MIS so that findings can be used for

supervision by the CN and for oversight and control by governance and audit functions. The Program

Annual Report will be the vehicle to report on grievances submitted under the Program.

C.6 Staffing

57. In general, at the provincial level, there is sufficient staff with relatively good experience. The

procurement workload at the provincial level justifies the number and the qualifications of their staff

(engineers, technicians with various specialized skills and highly graduated staff). Urban communities

faced with insufficient human resources generally often obtain needed support from nearby provinces and

prefectures due to their close proximity. The staffing in rural communities is more challenging, as the

number and skills of those involved in procurement or preparation of technical sections of bidding

documents, and supervision of works are in most cases not sufficient. Procurement staff members’

recruitment, salaries, and careers are identical to those of any other staff of government and municipal.

Associations and NGOs rarely have dedicated staff and instead rely primarily on volunteers.

58. During INDH 1, local Governments procurement staff in general benefited from training sessions

on procurement, but these sessions seem to have been focused on all key aspects of the INDH 1 , and less

focused on fiduciary aspects. However, the General Treasury of the Kingdom (TGR, part of MoF) has

conducted several more focused fiduciary training campaigns using its own provincial network

throughout the country. The Interior Ministry is conducting a major effort to train local government staff

and local communities and INDH 1 has contributed greatly to this effort. Despite these initiatives, the

provision of training for local authorities remains insufficient in comparison to the needs, with the

exception of large cities that have ample training budgets. Therefore, those responsible for procurement

within rural communities have rarely benefited from training in this area and most are forced to learn on

the job without a mentoring system.

59. Under INDH 1, the Bank worked on improving the FM and Procurement capacity of the

implementing agencies staff and systems. There are signs of improvement however there is still room for

further improvement under INDH2. Regarding new implementing agencies (those not involved before in

the Program), capacity is a serious concern for many of them (e.g., NGOs and associations, rural staff)

and would require intensive intervention. With this structural weakness, the lack of a clear matrix

structure of the institutional arrangement constitutes another risk. For INDH 2, capacity building

programs will be elaborated and implemented “per province”, including fiduciary modules covering

procurement. In addition, a formal agreement providing technical support to those who need it will be in

place.

C.7 Contract management

60. At provincial, prefectural and urban municipal levels, contract management is done without much

difficulty thanks to the availability of various skill sets and resources, including access to the private

sector resources (consultants). This can be generalized to rural communities easily accessible from the

provinces. For remote rural municipalities and associations in these zones, an acute capacity problem for

monitoring contracts execution arises. Due to the remoteness, accessibility issues, and to the low volume

of activity that does not justify provision of permanent staff, monitoring contracts at different stages of

implementation is very difficult. The support services available in the provinces are generally limited to

the start-up of contract execution and to receiving/commissioning works.

Page 15: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

12

61. In general, however, the INDH 1 experience showed that implementing agencies are largely

respectful of formal contract clauses: delays are justified by documented works suspensions; cost

extensions are also usually justified, etc. However, these examples cannot be extrapolated to infer that the

quality of works is acceptable and ensured given the lack of regular follow-up.

62. For INDH 2, the formalized and systematic technical support clause to be included in the project

sponsors’ agreements, will, in conjunction with the capacity building provincial programs, contractually

provide for acceptable quality of works design studies and for technically skilled supervision and

commissioning of works (RFI #13).

C.8 Effectiveness of coordination between agencies

63. At the national level, CN coordinates the budget allocation, supervision and monitoring of

activities execution. However, there is no hierarchical relationship between CN and the provinces that are

under the authority of their Governor.

64. There is a relative lack of effectiveness in the “convergence” approach to coordination with the

sectoral ministries such as Education, Health, and Public Works etc. In this regard the role of

Coordination Nationale is weak in procurement, even in terms of monitoring and evaluation, a domain

where its role is in fact limited to collecting information, and no analysis was performed during INDH 1.

The planned improvement of the Program MIS (see R.I # 12 in PAD, annex 2) and of its functionalities

more particularly the fiduciary modules (with production of specific KFSPIs as outlined in Annex 2) at

the beginning of INDH 2 should contribute to the mitigation of this weakness.

C.9 Planning and budgeting

65. The Morocco PFM system lies on well-organized planning and budgeting functions. The budget is

built on a credible macrofiscal framework in line with government policies. The budget preparation

procedure provides for due regard to line ministries’ requests as assessed by the 2007 CFAA and 2009

PEFA (indicator PI 11, rated A). Moreover, the authorities have begun implementing a program-oriented

budget framework to more than 30 eligible ministries in 2011 after a period of testing during the previous

years. A set of various performance indicators with related objectives has been developed accordingly.

However, the level of program appropriations (budget heading) has still to be fixed at a higher level of

aggregation following a recommendation of the 2007 CFAA. In addition, the budgeting at the

deconcentrated/decentralized level remains of concern for some appropriations, especially for capital

expenditures, due to delays is issuing the budget sub-allotments (delegations de credit) and despite recent

improvements due to the automation of the budget system (GFMIS). Such delays were observed during

the beginning of the INDH 1 program in 2006 but were quickly improved subsequently.

66. Budget classification. According to the Art. 29 of the Organic Finance Law of November 26, 1998,

budget expenditures are classified under three aggregate-type headings of the general budget (operating

costs, investment, and public debt). Expenditures are then classified by chapters, articles, paragraphs and

lines according to their economic purpose (payroll, supply costs, miscellaneous, and investment). An

administrative classification is also cross-cutting expenditures according to the level of the administrative

authority by which expenditures are implemented (ministry, central or deconcentrated/decentralized unit,

regional and provincial). A third classification, derived from the two other classifications, provides for

functional classification in line with COFOG norm. Overall, the budget classification is very detailed,

stable, viable, and consistent with GFSM 2001. A comprehensive coding system entails this classification

enabling a proper fit with the GFMIS’ requirements for the accounting classification included in the Chart

of accounts. Further upgrade of this classification is planned in order to facilitate direct monitoring of

priority programs implementation, as part of amendments that may be made to the Organic Finance Law.

In any event, the budget coding allows for such monitoring. Budget classification has been rated A by

2009 PEFA (PI-5).

Page 16: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

13

67. Budget transparency. The transparency of information disclosed with the budget proposal was

assessed by the 2009 PEFA and rated B. Among the 9 required criteria, 6 were fulfilled, but 3 were not,

namely: no disclosure of value of financial assets of agencies; no systematic disclosure of in-year

reporting in the same format than the proposal making comparisons uneasy; and presentation of out-turns

budget for the current year but in a different format that the one for the budget proposal. It is to be noted

that the implementation of an accrual accounting system in the near future will automatically resolve the

first weakness. Regarding the two other criteria, they do not impact the Program.

68. Budget Calendar. The budget preparation is framed under a clear and detailed annual budget

calendar for each step of the procedure providing line ministries with a clear schedule for formulating

their budget requests in a predictable way. The calendar provides ministries; departments and agencies

with reasonable delays for meaningfully complete their detailed estimates. However, in practice some

delays are often experienced. (Rated B by 2009 PEFA, PI-11, dimension (i)). Furthermore, the guidance

provided to line ministries for establishing their budget requests is in line with core best practices (rated A

by 2009 PEFA, Pi-11, dimension (ii)). The approval of the budget by the Parliament is timely (Rated A

by 2009 PEFA, PI-11, dimension (iii)). Regarding the budget execution calendar, delays for budget

allotments to deconcentrated and other local units remain of concern despite recent improvements (see

below “Flow of Funds”).

69. Medium-term budgeting. Investment programming system in Morocco includes a sophisticated

multi-year budgeting including a multi-year commitment authorization (autorisations d’engagement)

consistent with an annual payment system (crédits d’engagement). Such procedure should greatly

facilitate any further introduction of multi-year forecasting. However, the link between multi-year

sectoral estimates and their subsequent annual budget ceilings is to be improved. (Rated C+ by 2009

PEFA).

70. Budget execution. The Organic Finance Law of November 26, 1998 includes a certain number of

adjustments possible during the execution. These adjustments frequently account for a quarter of the total

expenditures, including a number of sub-adjustments at the lowest level. However, these are operated in

transparency vis à vis the Parliament, especially the monthly reports and mid-term progress report. These

procedures have been rated B or C by the 2009 PEFA. It is important to note that regarding INDH1, no

funds have been diverted, as confirmed by the audit report.

71. Sectoral Strategies. The statement of budget spending allocated to sector strategies indicates that

these funds are monitored under the existing budget classification system by ministry. The economic and

financial reports annexed to the draft budget acts, along with the Budget Directorate’s activity reports,

provide details for some of these programs on new budget allocations and funds spent since their launch,

in comparison to the overall program funding initially pledged. The most notable of these are programs

supporting INDH with a series of quantified goals. Procurement planning. As has been previous

discussed in this assessment report, there was a lack of procurement planning in some areas under Phase

1. The new Public Procurement Law/Decree (PPD) in the pipeline to be enacted (draft “Dahir” recently

signed by the new Minister of Finance) will address this deficiency by making the elaboration and

dissemination of procurement plans mandatory for all Local Governments (“collectivites territoriales”)

which will fall under the realm of this new PPD. The updated Operational Manuals should also include,

and from early start of INDH2, the preparation of Procurement Plans as a mandatory first step in the

procurement cycle. (A standard model of Procurement Plan should be provided in the Fiduciary guide.

Page 17: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

14

Strengths Areas for improvement

Most funds transfers to regional and local governments

are governed and effected through transparent

arrangements and following defined rules6

The economic and financial reports annexed to the

draft budget acts, along with the Budget Directorate’s

activity reports, provide details for some of the INDH

on new budget allocations (dotations) and funds spent

since their launch, in comparison to the overall

program funding initially pledged.

Delayed projects’ execution due to late release of

spending authorization

Carried forward credit not notified on time ( by

the end of May 2010 for FY10)

Unpredictable availability of funds

C.10 Accounting and financial reporting

72. Delays and quality. Accounting and reporting are primarily handled by the General Treasury of

the Kingdom (TGR) in relationship with the line ministries. ) The TGR “send a monthly report to the

Finance Ministry presenting a statement of budget transactions, special account transactions, and cash

flow transactions for the month,” accompanied by statements for previous periods (Art. 124 of the

General Accounting Regulation (Order No. 330-66 of April 21, 1967). TGR summarizes this data in its

“Monthly Statistical Bulletin for Public Finance,” published on its website. Through this TGR’s

statement, line ministries have access to detailed data on the execution of their budgets and main

ministries use this information to prepare a quarterly update of budget execution. Since GFMIS has been

rolled out, line ministries have now access to most data on their budget execution on a real time-basis.

73. At the end of the year, line ministries, in conjunction with the Budget Directorate, prepare each a

budget execution report on their expenditures. These reports indicate the budget commitments and the

related signed payment orders issued by budget chapter, article, paragraph and line. These reports, called

administrative accounts (compte administratif), are sent to the Court of Accounts for their report on the

budget review act. On the other hand, the TGR issues the set of accounts reflecting the commitments and

payment orders signed and registered for payment by the accounts (comptable assignataire). This set of

accounts also reflects the accounting centralization of the financial transactions of all central and local

entities through the treasury network all over the country. These accounts, called treasury accounts,

provide for statements of general ledgers on the basis of a monthly reconciliation. The recent roll-out of

GFMIS allows now for automated daily reconciliations. It is to be noted that the final financial statements

can take into account transactions for regularization until March 31 of the next budget year (période

complémentaire) at the initiative of the budget authorizing officers (ordonnateurs) and regional

treasurers.

74. The quality and timeliness of in-year reporting was reviewed by the 2009 PEFA, PI-24 with its

three dimensions (scope, timeliness, and quality) rated respectively A,B, and A. Since GFMIS has been

rolled-out, the timeliness of the budget reports should now most probably be upgraded to A. This is also

confirmed by audit reports produced in the country. Regarding the quality of accounting for INDH 1, the

audit report of the CAS, May 17, 2011 has highlighted the necessity to strengthen the accounting team at

the Prime minister level in order for him to produce more timely the consolidated financial statements

(compatibilité administrative consolidée de l’ordonnateur) that may be reconciled with the accounts of

the TGR.

6 PEFA 2009

Page 18: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

15

75. TGR’s organization. The organization of the TGR’s network and centralization of financial and

accounting data are as follows:

Local government level (municipality): a treasurer, public sector accounting officer and TGR

staff member, approves the commitments, and controls and executes the related payment orders,

records and books the transactions, and holds the accounting.

Regional level: each treasurer, TGR affiliated, receives from the regional representative of the

regional branch of the central bank a daily statement of debit and credit transactions for the single

treasury account where all public funds are hold and from which all expenditures are paid (and

resources collected). On this basis, the regional treasurer reconciles all expenditures made by his

regional office and on behalf of accounting office down the line; only the regional treasurer is

authorized to debit the single treasury account held at the central level at the central bank. The

regional treasurer operates the same kind of reconciliation for revenues.

Central level: the TGR centralizes the monthly statements of debit/credit transactions made by the

regional treasurer posts with the regional branch of the BAM. Until 2007, there was no proper

consolidation of public sector financial statement. Since then, the TGR has launched a program

for meeting such objective, in particular for consolidating local government expenditures.

76. Accounting system. The INDH 2 accounting system is based, as the INDH 1, on the same General

Accounting Regulation (Order No. 330-66 of April 21, 1967) than described above. Line ministries and

executive agencies of the INDH sub-programs will proceed in the same way for the bulk of the budget

expenditures. The executing agencies and accountants will maintain separate accounting systems, i.e.,

administrative accounting and treasury accounting, as described above. All these data will then be

recorded and reported in details and aggregated level in the INDH’s special purpose account (compte

d’affectation spéciale). As indicated above, there is no rigidity in the chart of accounts that would prevent

addition of new codes to keep track of program-related transactions (the codification includes a functional

and programmatic classification), nor major difficulties for keeping track of expenditures of main service

delivery units (Indicator PI-23 was rated B in 2009 PEFA). Regarding the ability of the accounting

system to issue accounting main documents in line with international standards, it is to be noticed that

Government accounts are not presented according to IPSAS or equivalent national standards. However,

the public sector chart of accounts refers to national standards approved by the National Accounting

Council adopted in 2002. In addition to that, the implementation in the next future of an accrual

accounting would comply with IPSAS. The related indicator of PEFA (PI-25, (iii)) was rated in 2009 C.

77. However, the financial certification of the INDH 1 aggregated account (Compte d’affectation

Speciale, CAS) by the General Inspection of Finances (2005-2008) stipulated that the regulations for

producing consolidated financial statements of the CAS needed to be improved, while no irregularities

were raised by the audit.

Strengths Areas for improvement

Reliability of CAS INDH financial statements Timeliness of information to Provinces and

Communes

Reliability of consolidated local government

expenditures

Adherence to international standards

Page 19: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

16

C.11 Treasury management and funds flow.

78. A Special Purpose Account (Compte d’Affectation Special- CAS) was introduced by the Decree of

19 July 2005 for the purpose of INDH1 with budget sub-headings for each component. The NGOs and

cooperatives also pay their contribution from funds transferred to them by the CAS. The CAS is a special

account, separated from the general budget for the line ministries, but fully transparent within the budget

law and ruled by the same financial regulations as for the general budget. The expenditures of INDH2

CAS, as for Phase 1, are authorized by the Prime Minister (authorizing officer, ordonnateur principal),

the Deputy authorizing officers (ordonnateurs secondaires) being the Governors of the provinces.

Provincial authorizing officers have provided during Phase 1 the bulk of the implementation of the

Program because of the low capacity of the communes. To this regard, the use of CAS by the local

municipalities has been below initial expectations.

79. Regarding more specifically the predictability of funds for commitments for the Program

expenditures, there is:

No specific cash problem in Morocco that would prevent INDH disbursements to be made on

time. The treasury single account provides for the required funds in due time. Cash forecasts are

reconciled on a daily basis with the Treasury account balances at the central bank and at least on a

weekly basis with the balances of others local government or public enterprises (the indicator PI-

16, (i) of 2009 PEFA was rated A);

No specific obstacles that would hamper the spending units to commit for their expenditure

within a reasonable horizon in advance in accordance with their budget appropriations. The

indicator PI-16, (ii) of 2009 PEFA, has evaluated this horizon at 6 months in advance, which

equals a rate A.

Strengths

Areas for Improvement

Robustness of CAS financial regulations and practices. Lack of trained bookkeeper and treasurer for

communes NGOs

Unpredictability of funds availability

C.12 Internal controls and audit

80. The Morocco PFM system is based on:

An internal ex ante control by both the financial controller and the accountant, both affiliated to

the TGR, but each under specific statute for warranting their independence from the authorizing

officer.

An internal audit both at MoF and line ministry level, respectively the General Inspection of

finance (IGF) and General Inspection of Interior (IGAT).

An external audit, performed by the Auditor General (Court of Accounts, Cour des Comptes) who

operated as a judicial institution.

Page 20: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

17

81. With respect to audit and control, INDH is submitted to some specificity:

TGR: since 20097, the ex ante control of expenditures of local governments is still performed by

the TGR but only on a limited scope (availability of appropriations and classification of the

expenditure) and the bulk of the control is made by the authorizing officer under the ex post

control by the Court of Accounts. Furthermore, since 20088 a major PFM reform is the gradual

adoption of an ex post control system tailored to the capacity of the commitment officers to

implement it (controle modulé de la dépense). Several ministries have been assessed to

implement this risk-based approach and the reform is on-going.

Provincial Internal Auditors. During Phase 1, provincial internal auditors have been recruited

and deployed to improve the control framework. However those internal auditors have not been

appointed in all provinces due to resources constraints. In some cases, internal auditors perform

incompatible tasks such as procurement specialists and merely do not use professional audit

methods, including risk assessment techniques.

Effectiveness of internal control to prevent or detect serious irregularities, misuse, and

inefficient use of Program funds. The indicator PI 20, first dimension (i) was rated A, especially

for its efficient commitment control system, however the two other dimensions, (ii) for other

procedures of control than those for processing and recording transactions, meaning procedure

for management control, performance control/audit and assets safeguards, and (iii) for

procedures of control of simplified or emergency situations were rated C. Overall, the indicator

was rated C+. Since the PEFA has been issued, an important reform of the internal control has

begun to be implemented consisting in some devolution of ex ante control to line ministries

according to their capacity (controle modulé de la dépense). Moreover, for the INDH

specifically, some upgraded procedures of control have been put in place, in particular the joint

audit of the IGF and IGAT with proper performance-oriented procedures. Both these evolutions

should lead to improve the rate C of the second dimension of the PEFA indicator PI-16

mentioned above.

Capacity of the internal audit to provide assurance on the robustness of and compliance with

internal controls. The indicator PI-21 which measures this ability was rated B for its first

dimension, especially for the ability to perform at least 50 % of systemic audit and its

compliance with international standards. The two other dimensions, related to the distribution of

the audit reports and follow up by management, were rated C.

Strengths Areas for Improvement

INDH regulations have introduced a significant

measure of flexibility at the commitment stage of

expenditures: approval by the controller cannot be

withheld unless funds are not available and the

qualified approval cannot entail suspension of these

disbursements.

Comprehensive expenditure commitment controls are

in place and effectively limit

commitments to actual cash availability and approved

budget allocations

A few budget authorization units (Ordonnateurs) have

prepared a risk matrix

Internal auditors have not been appointed in all

provinces due to resources constraints

Appointed internal auditors perform

incompatible tasks such as procurement

specialists and do not use professional audit

methods, including risk assessment techniques

Audit recommendations are not always

followed-up

7 February 18, 2009 local Finance Act

8 Decree November 4, 2008 related to financial control of expenditure

Page 21: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

18

C.13 Program Audit

82. The Court of Accounts and the Regional Courts of Account established in 2004 are the main

institutions in charge of external audit within the Morocco PFM system. The scope of their mission was

broadened to include management audit by the promulgation of the Code of Financial Jurisdictions on

June 13, 2002 (Law. No. 62-99). The Courts’ audit officers are granted with a judicial statute (magistrats)

and tasked with jurisdictional audit under the 1996 Constitution. They also have the requisite

prerogatives and independence in the performance of their extra-judicial powers that are specified in

INTOSAI and IFAC international standards.

83. The CDC includes 9 regional Court of Accounts to ensure the control of accounts and management

of the “territorial communities” (Collectivites territoriales i.e Local Governments) and their affiliated

public entities.

84. The Court of Accounts’ audit reports on central government’s general account, which form the

basis for the draft budget review act, may be prepared only after the Secretary General of Government

(SGG) has handed over the account details as drawn up by the Finance Minister (TGR). The 2009 PEFA

(indicator PI-25, ii) reviewed the significant delays, more than 18 months after the end of the fiscal years,

in issuing the audited annual financial statements for 2004, 2005, and 2006. These delays were mostly

imputable, at the time, to the difficulties of the MoF in issuing the annual financial statements. Delays

have improved since then, though still insufficiently (12 months), and do not put at question the quality of

the audit work of the Court. The quality of audit work and methodology of the Court was rated by the

2009 PEFA (indicator PI-26 dimension (i)) as B, which is a good rating, and has improved since then.

CDC reports are available to the public on their website. Their quality is satisfactory, with respect to the

application of international standards and the scope of their missions. The CDC goal is to no longer focus

control on compliance but to review the regularity, efficiency, economy, efficiency, and ethics. Even

though the CDC has indicated that it cannot express a separate opinion on the Program or any other Bank-

financed project but also that INDH falls under its scope and could be audited in the context of its work

program. The Bank will continue country level dialogue with the CDC to explore their involvement in the

external audit oversight of the Program which would complement internal audit function.

85. IGAT and IGF: IGAT and IGF conducted audits for INDH I. An audit charter, signed by these

two entities, defines the objectives and methods of the joint audit that covers FM and procurement. IGAT

and IGF are not independent from the executive but have proven their credibility. Overall, these audits

have been accepted by the Bank and the same arrangement will be maintained. Audit reports have

identified the main shortcomings in the implementation of INDH I and have made relevant

recommendations. However IGF and IGAT TORs will be reviewed, in collaboration with the Bank, IGF

and IGAT, in line with ISA international audit rules applicable to the Program, in order to address the

need to: a) issue a consolidated audit on the Program Financial Statements; b) including coverage of

Procurement activities with sufficient details; c) identify priority recommendations.

86. IGAT and IGF. During Phase 1, transactions and programs of INDH1 were audited and certified

by IGAT and IGF. An audit Charter, signed by these two entities, defined the objectives and methods of

the joint audit. Furthermore, a manual of audit of the account of the special assignment has been

developed. Its methodology ensures that: (i) the financial statements of the programs financed by the

"CAS- INDH" comply with the laws, regulations and accounting repository that are applicable, and (ii)

the audit provides reasonable assurance that these financial statements do not contain significant

anomalies. The audit arrangements included (i) Annual audit of INDH accounts, (ii) Ex-post controls of

sub-projects, (iii) Annual performance audit.

Page 22: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

19

87. In reality, IGAT/IGF issued the following reports:

Opinion on Program financial statements of each implementing (provinces and prefectures)

Summaries of the executing entities annual audit reports published on INDH website.

Report on internal controls

Opinion on the Special Purpose Account (CAS-INDH)

88. From 2005 to 2010, the audit opinions of executing agencies can be classified as the following:

Year Number of Executing

agencies

Unqualified

Opinion

Qualified

Opinion

Adverse

Opinion

Disclaimer

2005 69 54 15 0 0

2006 70 56 14 0 0

2007 70 67 3 0 0

2008 70 67 3 0 0

2009 70 64 6 0 0

2010 83 74 8 1 0

89. In 2010, qualified opinions were mainly due to ineligibility of sub-projects, the adverse opinion

was motivated by a conflict of interest between CPDH, CLDH and a beneficiary in one prefecture.

90. It is to be noted that these audits demonstrated candid and independent assessment of the

program. However the audit performance needs improvement in the following areas:

The opinion on the main SRA account at the Central level was not issued timely. The reports

covering 2009 and 2010 were shared with the Bank in May 2012. The delay is also caused by the

late completion of the CAS financial statements Main activities that will be covered by these

reports are studies, technical assistance and capacity building activities managed at the Central

level.

Capacity to conduct a Program Financial Statements audit and provide an overall opinion on the

program instead of 83 opinions for each Program’s implementing entity

Lack of prioritization and follow-up of audit findings and recommendations

Synergy with Provincial Internal Auditors

91. The Bank has taken several steps to resolve this non-compliance including formal communication

to the Borrower and the receipt of the report as negotiation condition

92. To ensure that such noncompliance does not occur under INDH2, the Bank is working with

IGAT/IGF to define clear guidance and standard s on Program Financial Statements Audit, Technical

audit, and to include the coverage of Procurement activities with sufficient details.

Page 23: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

20

93. To improve the implementation of audit recommendations, the auditors will identify priority

recommendations which should be addressed urgently. These include, inter alia: (i) internal controls are

lacking or not applied regularly, (ii) Major shortcomings lead to significant risk of errors, (iii)

irregularities or fraud, (iv) The risk could jeopardize the reliability of Program’s financial information,

efficient and economic use of funds for intended purposes and (v) compliance with laws and regulations

including loan agreement.

Strengths Areas of Improvement

The SAI (Cour des Comptes) also has the

requisite prerogatives and independence under the

Constitution in the performance of their extra-

judicial powers that are specified in INTOSAI

and IFAC international standards.

Moreover, since 2005, the Regional Courts of

Account have been auditing local governments

and their local public enterprises

9 Regional Courts had 153 staff of which 99 are

auditors

The scope of CDC was broadened to include

management audit

Not in line with national accountability

legal framework

Audit reports are submitted to the legislature

more than 12 months from the end of the

period covered (for audit of financial

statements from their receipt by the

auditors); audited financial statements are

presented to Parliament more than 12

months following the receipt of the

statements by the external audit body

C.14 Fiduciary performance monitoring

94. In order to monitor properly fiduciary performance, each indicator should have its baseline

information known at the beginning of Program implementation. The considered fiduciary indicators and

their baselines are as follows (related Program Action Plans (PAPs), results indicators and DLIs from

PAD and Annexes 2-4 are in brackets). In addition, an important improvement of the program systems

has been discussed with the CN during appraisal, which is the new systematic and periodic production by

the Information System (MIS) under INDH2 of Key Fiduciary Statistic Performance Indicators (listed in

Appendix 2), among which consensus was reached for a selection of 12 most significant and

representative procurement performance indicators extracted from the national TGR Data Base for

homogeneity and comparability with the national system. Among the FM ones, three would be produced

by MIS, the others, more qualitative than statistically measurable, would be included in Audit reports.

(i) Availability of a credible program and /or decentralized level complaint mechanism: Baseline :

no (provincial/central) database for monitoring complaint mechanism is in place at the end of

INDH1 (PAP #8);

(ii) Procurement and financial management capacity building: Baseline : capacity assessment

template to assess project sponsors /procuring entities capacity does not exist; provincial capacity

building plans are not developed (PAP #10; )

(iii) Documentary tools to simplify preparation of bidding documents and contract management

(simplified manuals, standard contracts, guides, templates, forms, etc.) Baseline: the tools are not

available nor prepared for INDH2 version (RFI 13)

(iv) Expansion of Audit TORs t cover procurement aspects with more details, and Development of

effective and timely follow-up/implementation mechanism for audit recommendations (DLI 7 and

8). Baseline: see DLIs

Page 24: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

21

(v) Effectiveness of the external audit function

(vi) Technical Support : Use of technical design studies for each works contract (construction, rural

roads, water supply, power grids etc..) as a prerequisite to contracting or systematic possibility to

rely on technical support of provincial /external services contractual clause (% in partnership

contracts). Baseline: No formalized technical support clause in partnership agreements. (RFI #13)

(vii) Involvement of external services in developing (or reviewing) CPS (Cahier des Prescriptions

speciales) as improvement of BDs/quality and technical supervision of works contracts. Number

of completed infrastructure contracts complying with technical CPS specification. (RFI # 6 and

RFI # 13). Baseline: see RFI #6

(viii) Improvement of the former Fiduciary Innovation ad-hoc team replaced with permanent and

strengthened Fiduciary Coordination Committee (FCC) with clear TORs, role and responsibilities

to oversee and monitor fiduciary performance, and review manuals, guides and reports. Baseline:

Fiduciary Innovation Team intervened punctually and faded out/was dissolved before end of

INDH1 (PAP # 12).

(ix) Systematic production and periodic review of Key Fiduciary Statistic Performance Indicators

(KFSPI) and aggregate on 77/83 provinces, see Appendix 2. Baseline: At the end of INDH1, the

new MIS could not produce representative and exhaustive statistic aggregated procurement

performance indicators (less than 45 provinces data available).Therefore, the operational baseline

will be the first set of KFSPI produced at the beginning of INDH2 implementation for the

aggregate of 77/83 provinces. (They will be reflected in the yearly activity report and reviewed

during Bank supervision missions and in each joint Audit –see new expanded Audit TORs-). (RFI

#12, third target for year 2012)

D. FIDUCIARY RISK

D.1 Overall risk

95. The overall fiduciary risk for INDH 2 is rated “substantial”. Risk mitigation, capacity building

activities and other mitigation measures have been proposed as described earlier and below, notably those

inserted in the Program Action Plan or annexes 2-3 to address identified risks.

96. The findings of this assessment highlight firstly the national procurement system related risk, those

related to the capacity of implementing agencies, and finally those related to the organization of the

Program. Identified risks include the following:

The contractual imbalance of power between partners (employers - bidders) and lack of

transparency in the procurement process due to lack of independence of the entity to which

complaints and claims are made, the lack of monitoring of complaints and the non-disclosure of

their outcomes.

Implementing agencies are relatively respectful of formal rules of procurement. Control is also

restricted to formal compliance. The risk is mainly related to the capacity of staff to execute

procurement properly, and this capacity is often low especially in remote rural or difficult to

access communities and Associations / NGOs.

Matrix structure of the institutional arrangement under INDH1: the Coordination Nationale did

not have any power in terms of procurement control or oversight; and procurement technical

oversight was under the responsibility of Ministry of Finance (TGR and IGF). The Fiduciary

Page 25: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

22

Innovation Team which was put in place for INDH-1 was a good mitigation measure for this risk

but unfortunately it did not work efficiently for the first phase, partly because it was not

empowered to enforce its proposals and partly because it was not permanent and faded out in the

last years of INDH1. Hence the improvements to be brought in the creation of the INDH2

permanent “Fiduciary Coordination Committee” (see above its roles, provision for TORs and

mission letter, and composition).

The main risks are due to: (i) the lack of an independent procurement appeals system and clear

process for handling complaints; (ii) quality and timeliness of annual audited financial

statements; (iii) effectiveness of internal audit function and follow-up of audit recommendations,

(iv) a heavy reliance on Management Information Systems (MIS) for DLIs verification protocol,

(v) low capacity of small or remote entities procurement staff which often leads to low quality of

technical specifications, ToR, bidding documents, infrastructure works; (vi) lack of thoroughness

of bid evaluation linked to choice of criteria or scoring system; and (vii) occurrences of

questionable quality (not timeliness) of works or services delivered to small or remote entities

often due to lack of local technically skilled supervision. The procedures and control framework

are adequate, but the risks persist because of the large number of small contracts and sponsors,

often with low capacity, dispersed over more than 20 000 activities or locations.

D.2 Risk mitigation measures

97. General Risk mitigation and capacity building activities have been proposed to address the main

identified risks. Mitigations measures that should be addressed include (i) improving audit TORS, (ii)

providing clear guidance and standard s on Program Financial Statements Audit, procurement, and

Technical audit, in order to improve assurance framework. Additional measures are (i) ensuring that the

MIS is robust and effective so that quick disbursement is not jeopardized and which will enable better

procurement reporting; (ii) monitoring KFSPI during implementation support, (iii) mainstreaming anti-

corruption efforts by strengthening the borrower’s systems by creating a central system data base for

allegations collection and follow-up, with periodic reviews; (v) disseminating a revised and simplified

procurement Operational Manual; (vii) providing new guidance tools for Manuals, bidding documents

preparation and contract templates; (viii) implementing fiduciary training program (s); (ix) establishing a

Fiduciary Coordination Committee to oversee fiduciary performance; (x) strengthening grievance

mechanisms procedures which include the handling of procurement-related complaints; and (xi)

providing formalized technical support through a systematic clause in project sponsor partnership

agreements.

98. Specific measures will be as follow:

Planning and budgeting. A critical risk is delays in project implementation. A set of measures

has been taken by the Ministry of Finance to improve the transfer to spending units. There was a

lack of procurement planning under Phase 1. The new Public Procurement Decree will address this

deficiency by making the elaboration and dissemination of procurement plans mandatory for Local

Governments. Under the INDH 2 Program, the updated Operational Manual will also mandate the

completion of Procurement Plans as the first step of procurement cycle.

Bidding and contracting. Mitigation measures include one specific to technical quality of

preparation, BDs, and technical works supervision Formalized technical support will become

systematically available through a standard and customized clause in project sponsors partnership

agreements. This measure is described in RFI # 13 – see PAD, Annex 2-3.

Page 26: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

23

Program accounting and financial reporting. The current Program information system has been

developed to optimize the use of financial information; however it does not provide adequate

standard procurement and fiduciary reporting. The ongoing upgrade of the INDH information

system would allow better functionality of the tool, provide regular reports on procurement and

contract progress, and provide the ability to extract customized synoptic data including selected

Key fiduciary statistic performance indicators (KFSPI). The IS upgrade is tracked by RI 12 – see

PAD, Annex 2.

Internal controls and internal audit. The ex ante control of expenditures of local governments is

still performed by the TGR but only on a limited scope (availability of appropriations and

classification of the expenditure) and The Coordination Nationale plays a facilitating role vis-à-

vis the DAS with respect to procurement control or oversight. The technical procurement oversight

is under the responsibility of Finance Ministry (TGR). The mitigation measures will be to: (i) set-

up Fiduciary Coordination Committee (FCC) that will provide Program oversight, and develop

standard tools and documents, and (ii) design and implement a capacity building program. This is

Program Action Plan # 10 and # 12– see PAD, Annex 4.

Technical supervision of works contract: Technical design and technical supervision by external

services are not used systematically for works contracts. Under Phase II, the revised procurement

OM will provide for systematic use of (simplified) technical design studies for each works

contract, and technical review and supervision by external services or consultants will be required.

The Bank will monitor the system performance.

Provincial Internal Auditors (PIT). During Phase 1, Provincial Internal Auditors have been

designed and deployed to improve the control framework. However PITs have not been appointed

in all provinces due to resource constraints. In some cases, they perform incompatible tasks such

as also acting as procurement specialists, or do not use professional audit methods, including risk

assessment techniques. Under Phase II, the capacity of these auditors will be built into the

provincial action plans. This is Program Action and RFI 14 – see PAD, Annex 4. To improve

fiduciary performance monitoring of the Program, the multidisciplinary Fiduciary Coordination

Committee will be reinstated with clearer TORs, scope and authority.

Program Audit. During Phase1, the synergy with PIT, prioritization, follow-up and monitoring of

those recommendations were not optimal. Under Phase II, acceptable action plans will be developed

following IGF/IGAT audits (see DLI #7 RI #14 in PAD, Annexes 2- 4). Follow up and

implementation of key audit recommendations will be tracked by indicators (see RI #14 & #15, DLI

#8 in PAD, Annexes 2 and 3).

Improvement of Program fiduciary systems linked to RFI/DLI indicators and Program Action

Plan: During preparation, consensus was reached with Moroccan counterparts on the following:

- On the principle of two fiduciary DLIs : (i)DLI No 7 (RFI# 14), formalizing the gradual

elaboration by provinces of Action Plans reflecting Audits recommendations, and (ii) DLI No

8 (RFI #15), measuring yearly implementation of (priority one) audits recommendations or

incorporation of longer term ones in implemented action plans

- On two other specific fiduciary results framework indicators: (i) RFI No 13: related to

elaboration and dissemination of updated simplified procurement and fiduciary manuals, and

to contractual institutionalization of technical support by administrative services to project

sponsors through incorporation of a special clause in partnership contracts/agreements, and (ii)

RFI No 16 focused on procurement capacity and yearly measuring fiduciary capacity of

project sponsors.

Page 27: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

24

- Fiduciary sub-set of improvements will also be incorporated into cross-sectoral indicators

and multi-disciplinary actions of PAP: (i) One set of procurement complaints handling set

measures/mechanisms in the GRM Grievance Redress Mechanism/indicator (see paras. 54-

57) and (ii) two fiduciary modules (procurement and FM) including the systematic and

periodic production of key fiduciary statistic performance indicators (KFSPIs) – which are

detailed in Appendix2- in the improvement of the Program Information System.

99. Implementation Support. During Program implementation, a tripartite Assurance Framework

will be instated and ramped up, with adequate balance between controls and support provided by:

The client ( financial controllers, IGF, IGAT, Provincial Internal Auditors, the Court of

Accounts);

Third parties e.g. social accountability mechanisms9, EU audit reports on rural activities

The Bank through fiduciary implementation support with FM, PR and other technical

specialists associated in supervision missions.

100. The Key Fiduciary Statistics Performance Indicators (KFSPI’s) will be produced and monitored,

including monitoring of payment related complaints and end use audits (see Appendix2).

E. GOVERNANCE, ANTI-CORRUPTION AND ACCOUNTABILITY

E.1 FM and Procurement

101. The Bank is currently supporting IGF to build its capacity with respect to Fraud and corruption. A

first training was provided by MNAFM in collaboration with INT. The Bank will continue to provide

support to improve IGF performance in monitoring F&C.

102. The existing PPD provides the list of standard evaluation committee’s permanent members: three

representative of the project owner, one representative of TGR and one representative from Ministry of

finances if the amount of contract is above 30 million MAD. The committee must invite a representative

of Ministry of commerce if contract amount is above one million MAD per the decree’s provision for

increased transparency and to double check fairness of access to contracts complying with bilateral or

multilateral trade agreements signed by Morocco.

103. The “statute of civil servants” (Governments staff regulation) contains general provisions on the

obligations of officials and civil servants and stipulates penalties for misconduct. Accountability for

decision-making and disclosure of financial information is detailed in the Law on responsibilities of

authorizing officers and public accountants. The consequences for misconduct are of administrative or

criminal liability nature.

104. The PPD clearly describes the decision process for the award and contract management. Open

competitive bidding is the default procurement method; all other methods are exceptional. Procurement

processes allowed by the PPD are well known by the administrative staff. It is very often the case in the

municipalities.

9 Social accountability tools have been developed to monitor rural and urban program (participatory M&E)

Page 28: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

25

105. For NGOs / associations there is rarely a formal organization and responsibilities are not defined

clearly. All procurement related laws and regulations are publicly available as they are published on

TGR's public procurement portal. They are also available (paper version) in the services of the provinces /

prefectures and in most municipalities. The simplified procurement manuals and training programs under

INDH2 would ensure dissemination of appropriate procedures to other small procuring entities such as

remote communities, NGOs and associations.

E.2 Arbitration and measures to fight Fraud and Corruption

106. The arbitration system is required by law but has not been reflected in the existing General

Contract Conditions (GCCs). GCCs for Goods contracts, which are the ones missing, should be prepared

and disseminated under the program at the beginning of implementation of INDH2, as part of the

Fiduciary guide if the up to date National GCCs are not yet ready.

107. Past experience has justified in the ongoing reforms to include measures to fight fraud and

corruption in the new Constitution, which is an enhancement very few countries have enacted to date.

However until the new anticorruption framework included in the new Constitution will trickle down with

the elaboration and enactment of the full set of necessary decrees and regulations, old behaviors and

malpractices will persist, including bidders behaviors akin to fear of retaliation which are reflected in the

very low number of complaints filed, and low frequency of whistle blowing or red flags signaling by

other actors (see para.109)

108. In addition, the country has taken a number of measures to promote ethics and fight against fraud

and corruption including the creation of an institution for the prevention of fraud and corruption (Central

Institution for the Prevention of Corruption - ICPC) and an agency to fight against money laundering. The

ICPC has established an electronic system of anonymous reporting of corruption and fraud, although no

mechanism of investigation or sanction, other than judicial, is in place. In the spirit of the new

constitutional reform, the ICPC should see an evolution of its independence and be in charge of new

missions to enhance the fight against these scourges (investigations, sanctions etc.) with new powers

which will be enforceable once the set of corresponding law/decrees is enacted.

109. The number of anonymous whistle blowing cases declared by ICPC is still small even after the

launch of the secured electronic site (about 100 allegations on national level over the first year). During

the implementation of INDH I, no fraud and corruption case was declared at all. In certain cases, auditors

reported situations of conflict of interest and several contracts awarded to the same firm. These red flags

had not stimulated any complaint. It is therefore more likely that the absence of complaint and the limited

number of whistle blowing cases is a sign of lack of bidders’ confidence in the systems with regard to

appeal mechanisms or judicial process, and of their fear to be penalized. More generally, the fear of

retaliation is so deeply entrenched in Moroccan contractors’ minds that very few cases of corruption are

signaled, flagged or raised to attention. This is most probably because in the current system complaints

have to be filed with the same procuring authority which carries out the procurement process, and not

with an independent authority which would have the power to suspend the ongoing procurement

procedure (This body will be created as “Commission de la Commande Publique” within the above

mentioned second decree under preparation), and the judicial decision, when courts are involved, is

usually made after contract execution. Moreover the judicial system, which is currently considered for

reform with support from the Bank under a DPL, and is still characterized by very lengthy and dubious

outcome practices, is not really trusted by bidders who are victims of flawed or biased award processes.

Page 29: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

26

110. The existing Public Procurement Decree provides that any entity engaged in fraud may be

excluded from award of contracts with a given department or from all public contracts procured by the

State by decision of the concerned minister in the first case and of the Head of Government in the second

case. In both cases the decision must be submitted to the opinion of the national Central Procurement

Tender Board (CPB).

E.3 Improvement of program systems to fight fraud and corruption

111. The Program mainstreams a range of measures at fiduciary and technical design level to mitigate

fraud and corruption risks. Key measures include: a) the strengthening of the control framework through

the introduction of prioritization of audit recommendations and provincial action plans for IGAT-IGF

audits; b) the establishment of a Fiduciary Coordination Committee, replacing the previous Fiduciary

Innovation Team (Equipe d’Innovation Fiduciaire –EIF) to provide oversight to the Program fiduciary

system; c) the strengthening of the INDH Grievance Redress Systems through the upgrading of local level

GRM and the introduction of a central database for monitoring the submission and treatment of

complaints and facilitating reporting d) the enhancement of the existing MIS in order to produce relevant

and representative procurement related information enabling to assess performance; e) the introduction of

peer selection of CSOs representatives within the Governance bodies, which will increase transparency of

decision making within INDH governance bodies; f) the introduction of social accountability processes at

local level, in order to enhance scrutiny of decisions and mitigate the risk of elite capture; g) the

clarification of procedures for validation of the ILDH by provincial authorities, to increase transparency

and reduce patronage risks. Lastly, in addition to the internal control framework, the Program is subject to

external audits by other financial partners such as the EU.10

112. The Government: (i) will use its own systems to the fullest extent in order to take all appropriate

measures to prevent F&C in connection with the Program; and (ii) has agreed to use the PforR

Anticorruption Guidelines (ACGs), including giving the Bank the rights to access information in a non

intrusive way. The Government has developed experience on this with the EU Anti Fraud Office (OLAF).

Given the nature of INDH2 activities, involving mostly local and national contractors, compliance with

the Bank debarment list is not expected to pose significant problems. The INDH National Coordination

will notify Program’s executing entities of the persons and entities debarred by the Bank, and verify

periodically that such persons and entities do not participate in the Program, through the M&E

arrangements and Program’s audit, and with Bank information provided through permanently updated

debarment list on the web site. Reporting to the Bank on allegations occurring under the Program and

their handling will be carried out by CN through the annual reports on Program implementation. The

Government will collaborate with the Bank on the investigations of allegations which the Bank intends to

pursue. Program participants (including executing entities, suppliers, contractors and subcontractors) will

be notified of the potential to be subjected by an investigation of their books and accounts through a

standard clause inserted in the bidding documents and contracts.

E.4 Transparency

113. Transparency and information disclosure: Bidding documents are free of charge and they can

be downloaded from the procurement portal. The bids opening sessions are public, but the openings of

administrative and financial envelopes are not simultaneous. However, in most cases, these openings are

held on the same day (same meeting) because of the simplicity of related operations. Under INDH2, both

the INDH website as well as the national procurement portal maintained by the TGR should be used for

publishing of advertisements and awards disclosure.

10

The Technical Assessment, Environmental and Social Assessment and the Fiduciary Assessment all contain

extensive treatments of mitigating measures to address Fraud and Corruption risk, as well as a description of the

Government anti-corruption framework.

Page 30: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

27

114. As outlined earlier, procurement plans when available and bidding opportunities are well

advertised. Bidding documents are free of charge and they can be downloaded from the procurement

portal and bid opening sessions are public. The list of attendees during bid-opening is not systematically

established ("because it is not required by the decree" according to interviewees), however publishing the

results of the award is made by posting and sending letters to all candidates. They often are invited at the

same time to come to withdraw their bid securities. Among the improvements of MIS under INDH2, the

number of participants in each bidding process will be measured within the KFPI indicators.

E.5 Accountability

115. Program execution is based on administrative structures and existing provincial or municipal staff

and associations or NGOs will be involved. Responsibilities within the administrative structures are

clearly defined.

116. The involvement of each administrative office and each project in the INDH is defined by the

Manual of Procedures. Project implementation is delegated to the Governors who may delegate to the

decentralized services of the state, municipalities or NGOs / Associations whenever the entity has the

management capacity. But the level of capacity required is not defined anywhere and no evaluation

mechanism is established. In the INDH2, systematic assessment of fiduciary capacity will be undertaken

to trigger specific training and mentoring programs/actions as well as provincial services support.

117. FM risk management measures will be enhanced during this second phase to include measures to

detect error and possible misuse of funds and review: (i) the fiduciary guide will clarify procedures

related to segregation of duties in order to minimize conflict of interest of job functions, (ii) history of

complaints to assess if there is a systemic risk and ensuring that FM relate controls are tightened in

response, (iii) history of complaints to assess if they relate to possible wrong doing and referring them to

INT.

118. Public procurement decree provides the list of evaluation committee’s permanent members: three

representative of the project owner, one representative of TGR and one representative from Ministry of

finances if the amount of contract is above 30 million MAD. The committee should invite a representative

of Ministry of Commerce if contract amount is above one million MAD.

F. INPUTS TO IMPLEMENTATION SUPPORT PLAN

119. In providing Implementation Support, the fiduciary team will monitor overall performance

(improvement) of financial management and procurement systems. Specifically the team will: (i) check

progress of the fiduciary reform at country level, (ii) assess the efficiency of fiduciary oversight system,

(iii) support design, implementation and evaluation of fiduciary capacity building plan, (iv) provide

technical assistance and training complaints mechanisms (v) check implementation in the Program

grievance redress initiatives, (vi) assess the impact of the introduction of the Organic Budget Law, and

(vii) monitor achievement of key fiduciary DLIs.

120. Key Performance Indicators (KPI’s) in Annex 2-3 will be used to monitor fiduciary performance.

KPIs will be checked and analyzed by the Bank twice a year during implementation support missions and

appropriate follow-up will be undertaken when red flags arise from analysis of these indicators.

Page 31: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

28

G. APPENDICES

G.1 Appendix 1: Improvements in the new draft PPD

121. Many improvements remain to date conditional upon the enactment of the new PPD. Examples

of these improvements include:

Procurement regulation would be extended to local governments’ contracts.

Reform of the Procurement Regulatory Body (Commission Supérieure des Marchés) would

provide more autonomy and independence from the Ministries, and would improve

participation with the inclusion of representatives from the private sector and civil society;

Reinforcement of integrity in public procurement (internal control, fight against fraud and

corruption).

Amendment of the “General Conditions of Contracts (GCC)” for Works and preparation of

GCC for Goods and services for public sector contracts consistent with national requirements

and, when applicable, international requirements to harmonize the performance of public

contracts.

Some additional improvements are still needed to make the administrative review of bidders

‘complaints more independent and efficient. The procedures for complaint are enumerated by

the draft new decree for the “Commission Supérieure des Marchés” which would become an

enhanced “Commission de la Commande Publique” with more powers and independence,

however this draft, has not been modified or updated since 2010.

122. Moreover, some potential improvements might already be obsolete to a certain extent because of

the new requirements imposed by the Constitution enacted in July 2011.

123. Audit and oversight: The new Constitution enumerates the functions of the “Cour des Comptes”

and “Cours Regionales des Comptes” as the main bodies in charge of controlling the management of

public funds. According to articles 149 and 150 they will be in charge of sanctioning any misuses of

public funds however a new law is required to specify their attributions. Other provisions reiterate the

necessity to oversee public funds’ management by Public Services and a dedicated “Charte of the Public

Services” will be enacted to organize their obligations. It is therefore of great importance that the

Procurement activity will be also targeted by these controls and their mandatory publication (which is not

the case in the current draft Procurement decree).

124. On the anti-corruption policy, the new Constitution may require to go further than what was

initially accepted by the Government in the draft Decree. The latter contains only one article against

Conflict of Interests and Fight against Corruption with a rather imprecise definition, and no specific

individual sanction attached to these cases other than annulment of the decisions taken by the award

Box 1. Fiduciary inputs to Implementation Support Plan

Support and monitor achievement of the two key fiduciary DLIs # 7 and # 8 and of actions mentioned

between brackets twice a year (DLI 7 and 8 with ref. to verification procedure, RFI #13-16, PAP # 8, 10

and 12).Monitor overall financial management and procurement systems including KFSPIs, RFI

#13(during each supervision mission).Check progress on the fiduciary environment at country level (in

procurement reform and in program missions).

Check effects on the Program of anti-corruption and grievance redress initiatives (during program

supervision missions).

Assess the impact of the introduction of the Organic Budget Law. (legal expert/FM mission).

Page 32: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

29

commissions. According to article 36 of the new Constitution a Law will be needed to establish the

sanctions to reprimand misconducts occurring before or after the award of the contract, during its

performance, and a new Anti-Corruption body (Instance Nationale de la probité et de lutte contre la

corruption) will replace the current ICPC -Instance Centrale de Prevention de la Corruption-, aiming to

cover anti-competitive behaviors as well. However issues including debarment of convicted companies

and individual sanctions of fraud or conflict of interests remain only partially addressed in the current

draft Procurement decree.

G.2 Appendix 2A: Key Procurement Performance Indicators

Procurement

Stage

Reference of

Indicators Indicators Definitions

Preparation

IC10 Number of invitations to bid

or calls for proposals or

requests for quotation, with

contract awarded

Number of invitations to bid or calls for proposals

or request for quotations that ends up with award

of contract

IC12 Total amount for bidding

processes resulting in

contract award

Total amount of awarded contracts after

invitations to bid or calls for proposals or request

for quotations - that end up with award of

contract-

IC14 Number of bidders having

submitted an offer

Number of bidders that submitted their bids

(average= Number of bidders that submitted their

bids/ Number of invitations to bid or calls for

proposals or requests for bids or quotations, with

bids opened and contracts awarded)

IC18 Time period for award of

contract following an

invitation to bid/ a call for

proposals/ a request for

quotations

Time period for award of contract following an

invitation to bid or a call for proposals or a

request for quotations ([Sum of (award date- bid

opening date)] / Number of invitations to bid or

calls for proposals or requests for quotations, with

bids or proposals or quotations opened and

contracts awarded)

Award/ contract IC19 Time period for contract

commitment

Time period for contract commitment

([Sum of (arrival date of draft contract – Approval

date)] / Number of request for commitment

related to call for proposals or request for

quotations, with bids opened and contracts

awarded)

IC27 Number of contracts awarded

on direct contracting basis

Number of contracts awarded on direct

contracting basis

IC28 Total amount for direct

contracting

Total amount for direct contracting

IC33 Number of contracts

completed and closed

Number of contracts completed and closed

IC44 Ratio of contracts (awarded

following a call for

proposals, an invitation to

bid or request for quotations)

in compliance with the time

frame set in the provisions of

procurement regulatory

framework

Ratio of contracts awarded in compliance with

time frame set in the provisions of procurement

regulatory framework

Page 33: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

30

Payment

IC58 Time period for payment of

invoice

Time period for payment of invoice

IC59 Time elapsed between

submission of evaluation

report and contract signature

Time elapsed between submission of evaluation

report and contract signature

IC63 Delay measured between

planned and actual dates of

contract completion

Delay measured between planned and actual dates

of contract completion

Page 34: World Bank Document · expected to encompass “high-value” contracts as defined in para. 5 of BP9.00. 13. Based on the information furnished during the preliminary assessment,

31

G.3 Appendix 2 B: Key FM Performance Indicators

Description

INDH111

INDH2

1. Variance: Budget expenditure vs. actual expenditure 37% (2011)

2. Quality of information received from the service delivery

unit: quality is defined by timeliness, completeness and

accuracy of the financial reports

3. Financial statements of the provinces prepared within 60

days of the end of the fiscal year

4. Financial statements of the Program prepared within 90

days of the end of the fiscal year

5. Unqualified opinions rendered for Provinces

6. Unqualified opinion rendered for the Program

7. Audited financial statements for the Program received

within 6 months of the end of the fiscal year

8. Audit reports accepted by the Bank and National

Coordination

9. Controls over fixed end-users

10. Number of audit recommendations that have been

implemented

11

Available KPI data is reflected in sections B, C, and D of this assessment. Quantitative baseline will be

established during the first year of implementation, following first IGF/IGAT audit mission.