yon tanner architecture p.c. a.i.a.€¦ · the hot water expansion tank and chilled water ... new...

47
YON TANNER ARCHITECTURE P.C. A.I.A. 2175 S. JASMINE ST. #217 DENVER, CO 80222 PH (303) 691-8000 FAX (303) 756-2332 Date: 10-09-2014 Project: DCSD Northeast Elementary School – Mechanical Upgrades ADDENDUM # 2 The Drawings, Specifications, and Contract documents on the project are modified, corrected, supplemented, and/or superseded as hereinafter described. It will be construed that each bidder’s proposal is submitted with full knowledge of all modifications and supplemental data specified herewith. This addendum may effect pricing. Failure to acknowledge this addendum may be cause for rejection of bid. GENERAL: Item 1: Architectural – Questions and Answers: 1. Sheet AD1.1. Where is Item # 13? / Answer: We labeled Item # 13, see sheet AD1.1 2. Sheet AD1.1. What is the description for demo item # 16? Answer: We added at demo notes. see sheet AD1.1 3. Sheet AD1.1. Where is demo item # 14? / Answer: We are not using this item # 14. 4. A1.1. Note # 6 @ 8 & E. Is that correct? / Answer: We delete that note from that location. 5. A1.1. Note # 9 @ 7.5 & J. Is that correct? / Answer: We delete that note from that location. 6. Is there a spec for the sprayed insulation and the Poly ISO? / Answer: See attached specifications # 061600 & # 072100. Sheathing replaces the existing section 061600. 7. The sheathing descriptions vary between the architectural and structural. Which prevails? / Answer: Structural uses OSB panels for shear applied directly on the metal studs and joists. Architectural uses plywood for installation of standing seam metal roof and panels, see the replaced sheathing specification section 061600. 8. What are the unit costs? /Answer: see section 012700- subgrade compaction if required for footings, helical piers have been removed from the project. 9. 13/A4.2. What happens at the 16” gap in the chain link fence? / Answer: see 12 & 13 at A4.2 dwg. Infill all openings with new chain link fence material. 10. Are the fence sleeves and right angle extensions galvanized? / Answer: Yes, galvanized match existing. 11. Where does note 12 apply on sheet AD2.1? / Answer: See sheet AD2.1 with new label. Item 2: Mechanical Questions and Answers: Mechanical Clarifications to plans dated September 24, 2014 1. Mechanical – Abatement contractor scope of work in the existing boiler room will include the removal of the existing boilers, pumps and connecting flanges. 2. Mechanical Clarification: HWCP 1-4 are the air handler hot water circulation pumps for AHU 1-4. 3. The air cooled chiller shall be provided with an integral pump package. Chiller manufacturer shall provide dual evaporator pumps, 170 GPM at 75 feet of head each, 30% propylene glycol and dual pump control output. Contractor shall ensure that an inlet strainer, P&T ports Page 1 of 4

Upload: hoangkhanh

Post on 05-Jun-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

YON TANNER ARCHITECTURE P.C. A.I.A. 2175 S. JASMINE ST. #217 DENVER, CO 80222 PH (303) 691-8000 FAX (303) 756-2332

Date: 10-09-2014 Project: DCSD Northeast Elementary School – Mechanical Upgrades

ADDENDUM # 2 The Drawings, Specifications, and Contract documents on the project are modified, corrected, supplemented, and/or superseded as hereinafter described. It will be construed that each bidder’s proposal is submitted with full knowledge of all modifications and supplemental data specified herewith. This addendum may effect pricing. Failure to acknowledge this addendum may be cause for rejection of bid. GENERAL: Item 1: Architectural – Questions and Answers:

1. Sheet AD1.1. Where is Item # 13? / Answer: We labeled Item # 13, see sheet AD1.1 2. Sheet AD1.1. What is the description for demo item # 16? Answer: We added at demo

notes. see sheet AD1.1 3. Sheet AD1.1. Where is demo item # 14? / Answer: We are not using this item # 14. 4. A1.1. Note # 6 @ 8 & E. Is that correct? / Answer: We delete that note from that

location. 5. A1.1. Note # 9 @ 7.5 & J. Is that correct? / Answer: We delete that note from that

location. 6. Is there a spec for the sprayed insulation and the Poly ISO? / Answer: See attached

specifications # 061600 & # 072100. Sheathing replaces the existing section 061600. 7. The sheathing descriptions vary between the architectural and structural. Which

prevails? / Answer: Structural uses OSB panels for shear applied directly on the metal studs and joists. Architectural uses plywood for installation of standing seam metal roof and panels, see the replaced sheathing specification section 061600.

8. What are the unit costs? /Answer: see section 012700- subgrade compaction if required for footings, helical piers have been removed from the project.

9. 13/A4.2. What happens at the 16” gap in the chain link fence? / Answer: see 12 & 13 at A4.2 dwg. Infill all openings with new chain link fence material.

10. Are the fence sleeves and right angle extensions galvanized? / Answer: Yes, galvanized match existing.

11. Where does note 12 apply on sheet AD2.1? / Answer: See sheet AD2.1 with new label. Item 2: Mechanical Questions and Answers: Mechanical Clarifications to plans dated September 24, 2014

1. Mechanical – Abatement contractor scope of work in the existing boiler room will include the removal of the existing boilers, pumps and connecting flanges.

2. Mechanical Clarification: HWCP 1-4 are the air handler hot water circulation pumps for AHU 1-4.

3. The air cooled chiller shall be provided with an integral pump package. Chiller manufacturer shall provide dual evaporator pumps, 170 GPM at 75 feet of head each, 30% propylene glycol and dual pump control output. Contractor shall ensure that an inlet strainer, P&T ports

Page 1 of 4

Page 2: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

4. The hot water expansion tank and chilled water expansion tank are to remain and be re-used.

5. The chilled water air separator is to be removed and replaced with a new B&G RL-4F Air Separator rated for 170 GPM.

6. The heating hot water air separator is to be removed and replaced with a new B&G RL-4F Air Separator rated for 178 GPM.

7. Provide new VFDs for HWP 1&2.

8. BCP-1&2 are the boiler circulation pumps as indicated in the pump schedule on sheet M7.1. The circ pumps shown on G-M-6.1 are the air handler hot water circulation pumps (HWCP - 1 -4).

9. The points of connection for the new chilled water piping will be at the outdoor location of the new chiller. Re the air cooled chiller piping schematic and control schematic on M5.1 and M2.1 for extent of the existing chilled water piping and the points of connection for new chilled piping.

10. The chiller is provided with circuit breakers for protection and the chiller is to be powered through a single point power connection.

11. The air handlers AHU-1 thru 4 will be provided with factory installed VFD’s as indicated in the air handler schedule on sheet M7.1.

12. The mechanical contractor shall provide VFD’s for return fans RF-1 thru 4 and the electrical contractor will install and provide power as indicated to them.

Mechanical Clarifications to specifications dated September 24, 2014

1. All interior supply air ducts, return air ducts and outside air plenums (rectangular or round) shall be insulated as follows (specification section 230700):

a. Mineral-Fiber Blanket: 1-1/2 inches thick, 1.5-lb/cu. ft. nominal density b. Vapor Retarder Required: Yes

2. All exterior supply air and return air ducts shall be lined as follows (specification section

233113):

a. Fibrous glass, Type I, 2 inch thick.

3. New Water-Tube Boiler specification is included, specification section 23 52 35. Disregard the previous in its entirety.

Item 3: Electrical responses to Contractor Questions: Item 1: Please confirm that free air plenum fire alarm cable is acceptable in accessible ceiling areas.

Response: Free air plenum fire alarm cable is acceptable. Install perpendicular to structure and properly supported per specification 28 31 00 3.3.

Page 2 of 4

Page 3: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

Item 2: What is the minimum conduit size and fitting types i.e. steel set screw or compression that can be used for this project?

Response: ½” minimum conduit size. Refer to 26 05 00 (2.3)(B) for conduit fitting requirements.

Item 3: Drawing E1.1 general note 7, E1.2 general note 6 and E2.1/E2.2, general note 5 indicated removed and reinstall of projectors. How many of these projector locations are there? Does this involve electrical and/or video cable as well?

Response: There is one projector, in fourth grade room #144, that will require relocation. The new location shall be coordinated with Architect. Both electrical and video cable shall be extended as required by site conditions.

Item 4: Please confirm that the new chiller will have a starter supplied and installed on unit and will have fused protection.

Response: The starter will be supplied. The fused disconnect shown on plan and fuses will still be required by the EC.

Item 5: Please confirm that AHU-1 thru 4 will have VFD’a provided and installed on units and will have fused protection with on/off switch. Will electrical subcontractor be required to install VFD’s?

Response: VFDs are integral with AHU units. The fused disconnect shown on plan and fuses will still be required by the EC.

Item 6: Please confirm that VFD’s are supplied and installed for RF1 thru 4. Will the electrical subcontractor need to install the VFD’s?

Response: VFDs are supplied loose with the fans and will need to be installed and wired by EC.

Item 7: Referencing panel M2 and mechanical schedule for the AHS’s on E0.2 should not all the breakers be 40 amp 3 pole? The panel schedule only indicated (1) 40 amp, 3 pole and the other three as 30 amp, 3 pole.

Response: Each breaker feeding an AHU unit shall be 40 amp 3 pole breaker. Refer to updated E0.2 for updated panel information.

Item 3: Is specification 26 51 00 – 01.03 applicable to this project?

Response: Specification 26 51 00 – 01.03 is not required for this project. Contractor is responsible for all relocated or reinstalled fixtures to be in working order at completion of project.

Item 9: In pre-bid meeting the approved fire alarm manufacturers mentioned was Simplex, Notifier and Firelite. Specification 28 31 0 2.1 indicates Siemens also. Is Siemens then an approved system to submit in electrical proposal?

Response: Siemens is not an approved system to submit in electrical proposal. Refer to updated specification section 28 31 00 2.1.

Electrical clarifications to plans dated September 24, 2014 1. Fire alarm device locations and quantities have been updated on sheets E2.1 and E2.2. Refer to updated drawing sheet sheets.

Page 3 of 4

Page 4: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

SPECIFICATIONS: Item 1: Description. Section 074113 - "Metal Wall and Roof Panels- Vertical Seam" standing seam panel. (To meet spec requirements) 16" coverage, 1.75" high. "Cee-Lock" standing seam panels. This product is an approved equal and can bid the project. Metal Sales Mfg. Corp. 2727 E. Trent, Spokane, WA 99202. Phone 800-572-6565 Item 2: Description. Section 061600 “Sheathing” replace the specification Section 061600. Item 3: Description. Added Section 072100 “Thermal Insulation”. Item 4: New Water-Tube Boiler specification is included, specification section 23 52 35. Disregard the previous in its entirety. Item 5: Updated 28 31 00 specification section with updated items underlined (Fire Detection and Alarm) DRAWINGS: Items 1: Modified Drawings Architectural – Sheets - AD1.1, AD2.1, A1.1 and A4.2. Description: all items have been replaced, see attached and FTP site. Item 2: Modified Drawings Electrical - Sheets E0.2, E2.1 and E2.2. ATTACHMENTS: Item 1: Revised Dwgs AD1.1, AD2.1, A1.1 and A4.2, revised Section 061600 “Sheathing” and Section 072100 “Thermal Insulation” Item 2: Revised Specification Mechanical - Description. Added Section 072100 “Thermal Insulation”. Item 3: Revised DWGs Electrical and Specification for Fire Detection and Alarm. Modified Drawings Electrical - Sheets E0.2, E2.1 and E2.2. Updated 28 31 00 specification section with updated items underlined

END OF ADDENDUM # 1

Page 4 of 4

Page 5: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

SECTION 061600 - SHEATHING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Wall sheathing. 2. Roof sheathing.

B. Related Requirements:

1. Section 061053 "Miscellaneous Rough Carpentry" for plywood backing panels.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of process and factory-fabricated product. Indicate component materials and dimensions and include construction and application details.

1. Include data for wood-preservative treatment from chemical treatment manufacturer and certification by treating plant that treated plywood complies with requirements. Indicate type of preservative used and net amount of preservative retained.

2. For products receiving a waterborne treatment, include statement that moisture content of treated materials was reduced to levels specified before shipment to Project site.

3. Include copies of warranties from chemical treatment manufacturers for each type of treatment.

1.4 QUALITY ASSURANCE

A. Testing Agency Qualifications: For testing agency providing classification marking for fire-retardant-treated material, an inspection agency acceptable to authorities having jurisdiction that periodically performs inspections to verify that the material bearing the classification marking is representative of the material tested.

1.5 DELIVERY, STORAGE, AND HANDLING

A. Stack panels flat with spacers beneath and between each bundle to provide air circulation. Protect sheathing from weather by covering with waterproof sheeting, securely anchored. Provide for air circulation around stacks and under coverings.

DCSD SHEATHING 061600 - Page 1

Page 6: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

PART 2 - PRODUCTS

2.1 WOOD PANEL PRODUCTS

A. Plywood: Either DOC PS 1 or DOC PS 2 unless otherwise indicated.

B. Oriented Strand Board: DOC PS 2.

C. Thickness: As needed to comply with requirements specified, but not less than thickness indicated.

D. Factory mark panels to indicate compliance with applicable standard.

2.2 PRESERVATIVE-TREATED PLYWOOD

A. Preservative Treatment by Pressure Process: AWPA U1; Use Category UC2 for interior construction not in contact with the ground, Use Category UC3b for exterior construction not in contact with the ground, and Use Category UC4a for items in contact with the ground.

1. Preservative Chemicals: Acceptable to authorities having jurisdiction and containing no arsenic or chromium.

B. Mark plywood with appropriate classification marking of an inspection agency acceptable to authorities having jurisdiction.

C. Application: Treat all plywood unless otherwise indicated.

2.3 WALL SHEATHING

A. Plywood Wall Sheathing: Exposure 1, Structural I sheathing.

1. Span Rating: Not less than 16/0. 2. Nominal Thickness: Not less than 1/2 inch (13 mm).

B. Oriented-Strand-Board Wall Sheathing: Exposure 1, Structural I sheathing.

1. Span Rating: Not less than 16/0. 2. Nominal Thickness: Not less than 1/2 inch (13 mm).

C. Foil-Faced, Polyisocyanurate-Foam Wall Sheathing: ASTM C 1289, Type I or Type II, Class 2, rigid, cellular, polyisocyanurate thermal insulation. Foam-plastic core and facings shall have a flame-spread index of 25 or less when tested individually.

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

a. Atlas Roofing Corporation. b. Dow Chemical Company (The). c. Rmax, Inc.

DCSD SHEATHING 061600 - Page 2

Page 7: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

2. Thickness: As indicated.

2.4 ROOF SHEATHING

A. Plywood Roof Sheathing: Exposure 1, Structural I sheathing.

1. Span Rating: Not less than 16/0. 2. Nominal Thickness: Not less than 1/2 inch (13 mm).

B. Oriented-Strand-Board Roof Sheathing: Exposure 1, Structural I sheathing.

1. Span Rating: Not less than 16/0. 2. Nominal Thickness: Not less than 5/8 inch (16 mm).

2.5 FASTENERS

A. General: Provide fasteners of size and type indicated that comply with requirements specified in this article for material and manufacture.

1. For roof and wall sheathing, provide fasteners with hot-dip zinc coating complying with ASTM A 153/A 153M.

B. Screws for Fastening Wood Structural Panels to Cold-Formed Metal Framing: ASTM C 954, except with wafer heads and reamer wings, length as recommended by screw manufacturer for material being fastened.

1. For wall and roof sheathing panels, provide screws with organic-polymer or other corrosion-protective coating having a salt-spray resistance of more than 800 hours according to ASTM B 117.

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. Do not use materials with defects that impair quality of sheathing or pieces that are too small to use with minimum number of joints or optimum joint arrangement. Arrange joints so that pieces do not span between fewer than three support members.

B. Cut panels at penetrations, edges, and other obstructions of work; fit tightly against abutting construction unless otherwise indicated.

C. Securely attach to substrate by fastening as indicated, complying with the following:

1. Table 2304.9.1, "Fastening Schedule," in ICC's "International Building Code." 2. Table R602.3(1), "Fastener Schedule for Structural Members," and Table R602.3(2),

"Alternate Attachments," in ICC's "International Residential Code for One- and Two-Family Dwellings."

D. Coordinate wall and roof sheathing installation with flashing and joint-sealant installation so these materials are installed in sequence and manner that prevent exterior moisture from passing through completed assembly.

DCSD SHEATHING 061600 - Page 3

Page 8: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

E. Do not bridge building expansion joints; cut and space edges of panels to match spacing of structural support elements.

F. Coordinate sheathing installation with installation of materials installed over sheathing so sheathing is not exposed to precipitation or left exposed at end of the workday when rain is forecast.

3.2 WOOD STRUCTURAL PANEL INSTALLATION

A. General: Comply with applicable recommendations in APA Form No. E30, "Engineered Wood Construction Guide," for types of structural-use panels and applications indicated.

B. Fastening Methods: Fasten panels as indicated below:

1. Wall and Roof Sheathing:

a. Screw to cold-formed metal framing. b. Space panels 1/8 inch (3 mm) apart at edges and ends.

3.3 FOAM-PLASTIC SHEATHING INSTALLATION

A. Comply with manufacturer's written instructions.

B. Foam-Plastic Wall Sheathing: Install vapor-relief strips or equivalent for permitting escape of moisture vapor that otherwise would be trapped in stud cavity behind sheathing.

END OF SECTION 061600

DCSD SHEATHING 061600 - Page 4

Page 9: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

SECTION 072100 - THERMAL INSULATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Spray polyurethane foam insulation.

B. Related Sections:

1. Section 042000 "Unit Masonry" for insulation installed in cavity walls and masonry cells. 2. Section 061600 "Sheathing" for foam-plastic board sheathing over wood or steel framing. 3. Section 075323 "Ethylene-Propylene-Diene-Monomer (EPDM) Roofing" for insulation

specified as part of roofing construction. 4. Section 078446 "Fire-Resistive Joint Systems" for insulation installed as part of a

perimeter fire-resistive joint system.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

1.4 QUALITY ASSURANCE

A. Surface-Burning Characteristics: As determined by testing identical products according to ASTM E 84 by a qualified testing agency. Identify products with appropriate markings of applicable testing agency.

1.5 DELIVERY, STORAGE, AND HANDLING

A. Protect insulation materials from physical damage and from deterioration due to moisture, soiling, and other sources. Store inside and in a dry location. Comply with manufacturer's written instructions for handling, storing, and protecting during installation.

DCSD THERMAL INSULATION 072100 - Page 1

Page 10: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

PART 2 - PRODUCTS

2.1 SPRAY POLYURETHANE FOAM INSULATION

A. Closed-Cell Polyurethane Foam Insulation: ASTM C 1029, Type II, with maximum flame-spread and smoke-developed indexes of 75 and 450, respectively, per ASTM E 84.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. BASF Corporation. b. BaySystems; Bayer MaterialScience. c. Dow Chemical Company (The); STYROFOAM Spray Polyurethane Foam

Insulation. d. ERSystems. e. Gaco Western LLC. f. Henry Company. g. NCFI Polyurethanes; a division of Barnhardt Manufacturing Company. h. SWD Urethane Company. i. Volatile Free, Inc.

2. Minimum density of 1.5 lb/cu. ft. (24 kg/cu. m), thermal resistivity of 6.2 deg F x h x sq. ft./Btu x in. at 75 deg F (43 K x m/W at 24 deg C).

PART 3 - EXECUTION

3.1 PREPARATION

A. Clean substrates of substances that are harmful to insulation or that interfere with insulation attachment.

3.2 INSTALLATION, GENERAL

A. Comply with insulation manufacturer's written instructions applicable to products and applications indicated.

B. Install insulation that is undamaged, dry, and unsoiled and that has not been left exposed to ice, rain, or snow at any time.

C. Extend insulation to envelop entire area to be insulated. Cut and fit tightly around obstructions and fill voids with insulation. Remove projections that interfere with placement.

D. Provide sizes to fit applications indicated and selected from manufacturer's standard thicknesses, widths, and lengths. Apply single layer of insulation units to produce thickness indicated unless multiple layers are otherwise shown or required to make up total thickness.

3.3 INSTALLATION OF INSULATION FOR FRAMED CONSTRUCTION

A. Apply insulation units to substrates by method indicated, complying with manufacturer's written instructions. If no specific method is indicated, bond units to substrate with adhesive or use mechanical anchorage to provide permanent placement and support of units.

DCSD THERMAL INSULATION 072100 - Page 2

Page 11: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

3.4 PROTECTION

A. Protect installed insulation from damage due to harmful weather exposures, physical abuse, and other causes. Provide temporary coverings or enclosures where insulation is subject to abuse and cannot be concealed and protected by permanent construction immediately after installation.

END OF SECTION 072100

DCSD THERMAL INSULATION 072100 - Page 3

Page 12: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

SECTION 235235 – FLEX WATER-TUBE BOILERS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes packaged, flex water-tube boilers, trim, and accessories for generating hot water with the following configurations, burners, and outputs:

1. Factory assembled heat exchanger. 2. [Forced-draft gas] [Oil] [Combination gas and oil] burner.

1.3 ACTION SUBMITTALS

A. Product Data: Include performance data, operating characteristics, furnished specialties, and accessories.

B. Shop Drawings: For boilers, boiler trim, and accessories. Include plans, elevations, sections, details, and attachments to other work.

1. Design calculations and vibration isolation base details.

1. Design Calculations: Calculate requirements for selecting vibration isolators and seismic restraints and for designing vibration isolation bases.

2. Vibration Isolation Base Details: Detail fabrication including anchorages and attachments to structure and to supported equipment.

2. Wiring Diagrams: Power, signal, and control wiring.

1.4 INFORMATIONAL SUBMITTALS

A. Manufacturer Seismic Qualification Certification: Submit certification that boiler, accessories, and components will withstand seismic forces defined in Section 230548 "Vibration and Seismic Controls for HVAC Piping and Equipment." Include the following:

1. Basis for Certification: Indicate whether withstand certification is based on actual test of assembled components or on calculation.

1. The term "withstand" means "the unit will remain in place without separation of any parts from the device when subjected to the seismic forces specified."

2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate and describe mounting and anchorage provisions.

3. Detailed description of equipment anchorage devices on which the certification is based and their installation requirements.

DCSD WATER-TUBE BOILERS 23 52 35-1

Page 13: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

B. Source quality-control test reports.

C. Field quality-control test reports.

D. Warranty: Special warranty specified in this Section.

E. Other Informational Submittals:

1. ASME "H" Stamp Certification and Report: Submit "H" stamp certificate of authorization as required by authorities having jurisdiction, and document hydrostatic testing of piping external to boiler.

2. Startup service reports.

1.5 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For boilers, components, and accessories to include in emergency, operation, and maintenance manuals.

1.6 QUALITY ASSURANCE

A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use.

B. ASME Compliance: Fabricate and label boilers to comply with ASME Boiler and Pressure Vessel Code.

C. ASHRAE/IESNA 90.1 Compliance: Boilers shall have minimum efficiency according to "Gas and Oil Fired Boilers - Minimum Efficiency Requirements."

D. UL Compliance: Test boilers for compliance with UL 726, Oil-Fired Boiler Assemblies, and UL 795 Commercial-Industrial Gas Heating Equipment, or UL 795 Commercial-Industrial Gas Heating Equipment as applicable. Boilers shall be listed and labeled by a testing agency acceptable to authorities having jurisdiction.

1.7 COORDINATION

A. Coordinate size and location of concrete bases. Cast anchor-bolt inserts into bases. Concrete, reinforcement, and formwork requirements are specified with concrete.

1.8 WARRANTY

A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace heat exchangers damaged by thermal shock and boilers that fail in materials or workmanship within specified warranty period. 1. Warranty Period for Drums, Tubes, Cabinets, and Burner: One year from date of Substantial

Completion, pro rata. 2. Warranty Period for Pressure Vessel: Twenty Five (25) years from date of Substantial

Completion for thermal shock.

DCSD WATER-TUBE BOILERS 23 52 35-2

Page 14: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

PART 2 - PRODUCTS

2.1 FLEXIBLE WATER-TUBE BOILERS

A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to the following:

1. Bryan Steam 2. Unilux

B. Description:

1. Boilers shall be UL Listed and Labeled. It is the contractor’s responsibility to insure that the packaged boilers comply with any / all local, state and city codes.

C. Pressure Vessel Design – Heat Exchanger:

1. Boiler(s) shall be of the dual drum industrial style bent water tube type with a 4-sided tangent

water wall furnace. Water walls shall be on the top, bottom and both sides. No refractory or insulation shall be used on any sidewall.

2. Top, bottom and sides of the furnace shall be made up of water-cooled surfaces and shall be comprised of straight tube runs only. No furnace seal shall be made by the meeting of two tube hairpin bends.

3. The fireside of the boiler shall have five (5) longitudinal gas passes, travelling the full length of

the boiler, separated with tangential water wall tubes to insure maximum linear gas travel, increased gas side velocities and improved gas side heat transfer coefficients. Products of combustion shall flow horizontally through the boiler across boiler tubes.

4. Stainless steel cross flow turbulating baffles shall be installed in the second and fourth passes to

provide increased hot gas turbulence, increased furnace pressure and improved flue outlet temperature control.

5. All tubes shall be exposed to radiant luminous heat in the boiler furnace to create high water flow

rates at all loads and substantially increase heat transfer in the convection zones outside the furnace.

6. Boiler tubes shall be SA 178 Grade A and shall be no less than 1 ½” dia., .095 wall thickness,

made of only domestic U.S. steel and shall be easily removed and replaced if necessary without need for any welding or rolling. Tubes directly beneath the flue gas outlet shall be easily removable without the need to disconnect, move or modify the flue outlet cover arrangement or raise / remove any part of the boiler roof panels. There shall no more than one (1) 180 deg. bend in any single boiler tube. All tube bends shall be made with a mandrel type industrial bender to insure maximum I.D. opening at each bend.

7. Boiler vessel design shall insure that total boiler tube lengths shall be equal on each side of the

vessel to maintain balanced flow through boiler.

8. A large down comer shall be located external to the boiler housing. This down comer shall provide natural internal circulation without requiring external pumping sources. Down comers located within the boiler housing shall not be acceptable.

DCSD WATER-TUBE BOILERS 23 52 35-3

Page 15: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

9. Boiler shall have an air vent connection located at the highest point of the vessel and one (1) hand

hole type inspection opening at each end of each drum with yolk type covers. Threaded pipe type openings will not be accepted. Lower drum shall have a 90 deg. threaded drain opening at the rear of the vessel at the lowest point as standard.

10. The furnace heat release shall not exceed 45,000 BTU/hr per square foot of heating surface

exposed directly to the radiant flame. For boilers with heat releases greater than 45 000 BTU/hr per square foot of heating surface, then a minimum of 5 square feet of total heating surface per boiler horsepower shall be required. The furnace volumetric heat release shall not exceed 67,000 BTU/hr per cubic foot of furnace volume.

D. Housing and Jacket Construction:

1. The boiler base shall be constructed of heavy gauge steel. Base shall be poured with one layer of

1900 deg. F insulating refractory to cover all base plate steel contact points. An additional 2 inch layer of 2700 deg.F castable refractory shall then be poured covering the insulating refractory. The high temperature refractory shall have no contact points with the boiler base steel. Boiler bases insulated with mineral fiber wool type insulation shall not be acceptable.

2. The rear target wall shall be of industrial grade heavy-duty construction. Wall shall be constructed of no less than 4” of 1900 deg. F insulating poured refractory, 1” of high temperature mineral board and 4” of 2700 deg. F castable refractory. The high temperature refractory shall have no contact points with the boiler furnace wall steel. Total thickness of the rear furnace wall shall be not less than nine (9) inches. Stainless steel stays shall be permanently welded to the steel rear wall enclosure in intervals of at least every ten (10) square inches. Rear wall shall be warranted against “hot spotting” failure on the outside enclosure for a period of not less than five (5) years. Rear wall shall incorporate burner observation sight glass.

3. The front wall shall be constructed of the same industrial grade materials as the rear wall described

above. Total wall thickness shall be no less than seven (7) inches. Blanket or fiber wool insulated type front and rear walls are not acceptable.

4. Boiler inner casing shall be fabricated of not less than 11 gauge reinforced steel. Entire boiler

casing shall be comprised of “bolt on” type panels. Each panel shall be independently insulated with a minimum of three (3) inches of 2400 deg. F fiber wool insulation. Each panel shall be easily removable and replaceable with standard hand tools.

5. Roof panels shall be constructed of not less than 11 gauge reinforced steel and insulated with not

less than one (1) inch of high temperature insulating fiber board. Board shall be affixed to the roof panel by stud nails and 1 ½” collar stays at four (4) inch seam intervals. Roof panel shall be supplied with a factory installed round flanged smoke outlet with top outlet position located on the centerline of the boiler at the rear.

6. Entire inner housing shall be fully sealed with industrial grade ½” bolts, washers and nuts, at a

maximum spacing or 8 inches and gaskets to insure that the products of combustion are contained within the boiler up to 5” w.c. pressure.

7. Boiler outer jacket shall be constructed of 20 gauge insulated steel panels. Overall boiler inner /

outer housing design shall allow for a two (2) inch insulating air space between the inner and outer panels. Outer panels shall be finished with a rust resistant, polyester paint impregnated powder coat finish.

DCSD WATER-TUBE BOILERS 23 52 35-4

Page 16: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

8. The overall heat losses through boiler housing and jacket panels shall not exceed 0.50% of maximum input rating. Outer skin temperatures of the jacket panels shall be no greater than 20 degrees Fahrenheit above ambient room temperature.

9. The combustion chamber shall be easily accessed via a hinged, tapered refractory burner plate for

inspection and required maintenance. All boiler and jacket panels shall be easily removed and replaced, using only standard hand tools, for access to all boiler tube surfaces.

E. Boiler Trim & Controls:

1. Shall comply with the requirements of ASME CSD-1 and FM, IRI requirements. 2. Safety relief valve(s) shall be in accordance with the appropriate ASME code and local require-

ments.

3. Boiler operating trim shall consist of not less than the following:

A) Operating aquastat control with well; B) Modulating aquastat control with well; C) High limit aquastat control with well, manual reset type; D) Independently mounted 3” dial thermometer; E) Independently mounted 4 ½” pressure gauge; F) Probe type Low Water Cutoff, manual reset type;

Above listed boiler controls shall be factory piped and wired. Operating, Modulating and High Limit Controls shall be furnished as a flush mounted factory control package, model CP1-V160W by Unilux and affixed to the front of the boiler in plain view. All trim and control wiring shall be routed to the clearly marked strip in the panel. All trim and control wiring shall be housed in an approved casement.

F. Burner:

1. Horizontal Burner Assembly:

1. Burner shall be a separate UL listed and approved assembly for burning natural gas as noted on the plans. Burner shall be mounted on the boiler assembly once in place on permanent supporting base.

2. Burner shall be supplied and approved by boiler manufacturer for insertion and firing within boiler at maximum combustion efficiency without flame impingement while firing with a zero smoke rating.

3. For boilers less than 8000 MBH input, burner shall be mounted on a swing out style door for easy access to all fireside components. For boilers of 8000 MBH input and greater, burner shall be mounted directly to front wall of combustion chamber, with a supporting leg for burners extended weight.

4. Burner shall have a viewing port for observation of burner operation.

5. Fan shall be controlled to pre-purge and post-purge the combustion chamber before firing.

DCSD WATER-TUBE BOILERS 23 52 35-5

Page 17: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

2. Gas Train: Control devices and [on-off] [low-high-low] control sequence shall comply with requirements of ASME CSD-1. In addition to these requirements, include shutoff cock, pressure regulator, and control valve for incoming fuel supply pressures noted and for utility requirements having jurisdiction.

3. Pilot: Intermittent-electric-spark pilot ignition with 100 percent main-valve and pilot-safety

shutoff with electronic supervision of burner flame.

1. Motors: Comply with requirements specified in Section 230513 "Common Motor Requirements for HVAC Equipment."

G. Controls:

1. Refer to Section 230900 "Instrumentation and Control for HVAC."

2. Boiler operating controls shall include the following devices and features:

1. Control transformer 2. Temperature Adjustment: Operating temperature shall be adjustable. 3. Sequence of Operation: Upon activation by the Building Automation System, the boiler

plant shall maintain water temperature as adjusted. 4. Include automatic, alternating-firing sequence for multiple boilers to ensure maximum

system efficiency throughout the load range and to provide equal runtime for boilers.

3. Burner Operating Controls: To maintain safe operating conditions, burner safety controls limit burner operation. 1. Sequence of Operation: Electric controls and field-installed to control burner firing rate to

maintain a constant steam pressure. Maintain pressure set point plus or minus 10 percent. 2. Alarm contacts: SPST N.O. Factory mounted on control panel shall close alarm for above

conditions.

4. Building Automation System Interface: Factory install hardware and/or software to enable building automation system to monitor, control, and display boiler status and alarms.

1. Monitoring: On/off status, common trouble alarm, and low water level alarm 2. Control: On/off operation

2.2 ELECTRICAL POWER

A. Controllers, Electrical Devices, and Wiring: Electrical devices and connections are specified in electrical Sections.

2.3 SOURCE QUALITY CONTROL

A. Burner and Hydrostatic Test: Field adjust burner to eliminate excess oxygen, carbon dioxide, oxides of nitrogen emissions, and carbon monoxide in flue gas and to achieve combustion efficiency; perform hydrostatic test.

DCSD WATER-TUBE BOILERS 23 52 35-6

Page 18: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

B. Allow Owner access to source quality-control testing of boilers. Notify Architect 14 days in advance of testing.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Before boiler installation, examine roughing-in for concrete equipment bases, anchor-bolt sizes and locations, and piping and electrical connections to verify actual locations, sizes, and other conditions affecting boiler performance, maintenance, and operations.

1. Final boiler locations indicated on Drawings are approximate. Determine exact locations before roughing-in for piping and electrical connections.

B. Examine mechanical spaces for suitable conditions where boilers will be installed.

C. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 BOILER INSTALLATION

A. Install boilers level on concrete base. Concrete materials and installation requirements are specified with concrete.

B. Install gas-fired boilers according to NFPA 54.

C. Assemble and install boiler trim.

D. Install electrical devices furnished with boiler but not specified to be factory mounted.

E. Install control wiring to field-mounted electrical devices.

3.3 CONNECTIONS

A. Piping installation requirements are specified in other Sections. Drawings indicate general arrangement of piping, fittings, and specialties.

B. Install piping adjacent to boiler to allow service and maintenance.

C. Connect gas piping as applicable to boiler gas-train inlet with union. Piping shall be at least full size of gas train connection. Provide a reducer if required.

D. Connect oil piping as applicable full size to burner inlet with shutoff valve and union.

E. Connect steam and condensate piping to supply-, return-, and blowdown-boiler tappings with shutoff valve and union or flange at each connection.

F. Install piping from safety valves to drip-pan elbow to nearest floor drain.

G. Install piping from equipment drain connection to nearest floor drain. Piping shall be at least full size of connection. Provide an isolation valve if required.

DCSD WATER-TUBE BOILERS 23 52 35-7

Page 19: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

H. Boiler Flue Venting: 1. Connect full size to boiler connections. Comply with requirements in Section 235100 Breechings,

Chimneys, and Stacks

I. Connect breeching to full size of boiler outlet. Comply with requirements in Section 235100 Breechings, Chimneys, and Stacks for venting materials.

J. Ground equipment according to Section 260526 Grounding and Bonding for Electrical Systems

K. Connect wiring according to Section 260519 Low-Voltage Electrical Power Conductors and Cables

3.4 FIELD QUALITY CONTROL

A. Perform tests and inspections and prepare test reports.

1. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect components, assemblies, and equipment installations, including connections, and to assist in testing.

B. Tests and Inspections:

1. Perform installation and startup checks according to manufacturer's written instructions. 2. Operational Test: Start units to confirm proper motor rotation and unit operation. 3. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and

equipment.

1. Burner Test: Adjust burner to eliminate excess oxygen, carbon dioxide, oxides of nitrogen emissions, and carbon monoxide in flue gas and to achieve combustion efficiency.

2. Check and adjust initial operating set points and high- and low-limit safety set points of fuel supply, water level, and steam pressure.

3. Set field-adjustable switches and circuit-breaker trip ranges as indicated.

C. Remove and replace malfunctioning units and retest as specified above.

D. Performance Tests:

1. Engage a factory-authorized service representative to inspect component assemblies and equipment installations, including connections, and to conduct performance testing.

2. Boilers shall comply with performance requirements indicated, as determined by field performance tests. Adjust, modify, or replace equipment in order to comply.

3. Perform field performance tests to determine the capacity and efficiency of the boilers. 1. Test for full capacity.

4. Repeat tests until results comply with requirements indicated. 5. Provide analysis equipment required to determine performance. 6. Provide temporary equipment and system modifications necessary to dissipate the heat produced

during tests if building systems are not adequate. 7. Notify Architect in advance of test dates. 8. Document test results in a report and submit to Architect.

DCSD WATER-TUBE BOILERS 23 52 35-8

Page 20: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

3.5 DEMONSTRATION

A. Engage a factory-authorized service representative to train Owner's maintenance personnel to adjust, operate, and maintain boilers. Video training sessions.

END OF SECTION 235235

DCSD WATER-TUBE BOILERS 23 52 35-9

Page 21: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

DCSD FIRE DETECTION AND ALARM 28 31 00 - 1

SECTION 28 31 00 - FIRE DETECTION AND ALARM

PART 1 - GENERAL 1.1.1 SUMMARY

A. This Section Includes:

1. Delegated Design requirements for system design. 2. Fire-alarm control unit (panel). 3. Remote annunciator. 4. Manual fire-alarm boxes. 5. System smoke detectors. 6. Nonsystem smoke detectors. 7. Heat detectors. 8. Notification appliances. 9. Device Guards. 10. Magnetic door holders. 11. Addressable interface devices. 12. Digital alarm communicator transmitter.

1.2 DEFINITIONS

A. Definitions in NFPA 72 apply to fire alarm terms used in this Section B. CPVC: Chlorinated Poly Vinyl Chloride C. EPO: Emergency Power Off System. D. FAAP: Fire Alarm Annunciator Panel (Remote Annunciator). E. FACP: Fire Alarm Control Unit (Panel). F. FSCS: Firefighters' Smoke Control Station (panel). G. IDC: Initiating Device Circuit H. LED: Light-emitting diode I. NAC: Notification appliance circuit. J. NICET: National Institute for Certification in Engineering Technologies. K. NRTL: Nationally Recognized Testing Laboratory L. SLC: Signaling Line Circuit

1.3 SYSTEM DESCRIPTION

A. Noncoded, UL-certified addressable system, with automatic sensitivity control of certain smoke detectors and multiplexed signal transmission, dedicated to fire-alarm service only. The system shall detect fire conditions, alarm the building occupants of a fire condition, control the necessary systems to suppress fire and smoke and shall summon the local Fire Department automatically without the need for human

Page 22: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

DCSD FIRE DETECTION AND ALARM 28 31 00 - 2

intervention/human action.

B. The fire alarm system shall be a microprocessor based network system.

1.4 PERFORMANCE REQUIREMENTS

A. Delegated Design: These specifications and the accompanying Drawings define the intent of the fire alarm system to be provided. In addition to the system as specified herein and shown on the Drawings, provide all planning, design, calculations, equipment, devices, raceways, boxes, cabling, system programming and any other component or service required for a complete, fully operational and code compliant system. 1. Premises protection includes Construction Type IIB and Occupancy E.

B. System Zoning: Fire-alarm control system and all associated circuits shall be arranged to comply with

zoning requirements of NFPA 72 and the following: 1. The entire building is an evacuation signaling zone for this Project. 2. Display each intelligent addressable device at the main fire alarm control panel in accordance with

the following: a. Use a unique alphanumeric label identifying each device location. b. Include a descriptive reference with alphanumeric label that corresponds to devices’

specific location and zone.

C. Voltage Drop Calculations: Design system for a maximum of 10 percent voltage drop for each notification appliance circuit.

D. Seismic Performance: Fire-alarm control unit and raceways shall withstand the effects of earthquake motions determined according to SEI/ASCE 7. 1. The term "withstand" means "the unit will remain in place without separation of any parts from the

device when subjected to the seismic forces specified and the unit will be fully operational after the seismic event."

1.5 SUBMITTALS

A. Submit product data and shop drawings in accordance with Division 01 and Division 28 Section “Common Work Results for Electronic Safety and Security” for products specified under PART 2 - PRODUCTS.

B. General Submittal Requirements:

1. Submittals shall be approved by Architect prior to submitting them to authorities having jurisdiction.

2. Comply with recommendations in the "Documentation" Section of the "Fundamentals of Fire Alarm Systems" Chapter in NFPA 72.

C. Simultaneous Action Submittals: Product Data, Delegated-Design Submittal, and Delegated-Design Shop

Drawings submittal shall be submitted simultaneously.

D. Product Data: For each type of product indicated, include the following: 1. Supervisory power usage. 2. Alarm power usage. 3. Physical dimensions of equipment.

Page 23: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

DCSD FIRE DETECTION AND ALARM 28 31 00 - 3

4. Finish. 5. Mounting requirements. 6. Performance parameters and installation details for each type of detector. 7. Performance parameters for duct-mounted detectors verifying that each detector is listed for

complete range of air velocity, temperature, and humidity possible when air-handling system is operating.

E. Delegated-Design Submittal: For fire-alarm system. Signed and sealed by the qualified professional responsible for their preparation. Include the following: 1. Circuit loading and voltage drop calculations for each circuit. Include voltage drop calculations for

notification appliance circuits. 2. Battery-size calculations in a spreadsheet type format with a complete listing of all devices,

quantities, individual component supervisory current and alarm current. Indicate the total supervisory and alarm currents, hours of backup, minutes in alarm and total battery amp-hour rating.

3. Calculations for selecting the spacing and sensitivity of detection devices.

a. Include calculations for area and duct-mounted detectors. 4. Mathematical justification for audible notification device placement to meet code required sound

dB levels. 5. Complete sequence of operation of the fire alarm system. 6. System Input-Output Matrix.

F. Delegated-Design Shop Drawings: For fire-alarm system. Signed and sealed by the qualified professional

responsible for their preparation. Include the following: 1. Plans, elevations, sections, details, and attachments to other work. Include floor plans to indicate

final outlet locations showing address of each addressable device. a. Prepare shop drawings using symbols and notes as recommended in NFPA 170 “Standard

for Fire Safety and Emergency Symbols.” b. Include location of each smoke and heat detector, ratings of each, and installation details

as needed to comply with listing conditions of the detector. c. Include location of each audible notification device, ratings of each, and installation

details as needed to comply with NFPA 72 sound dB level requirement. Annotate to correspond with mathematical calculations.

d. Include location of each visible notification device, ratings of each, and installation details as needed to comply with NFPA 72. Annotate coverage patterns to show placement meets coverage requirements of NFPA 72.

e. Show size and route of cable and conduits.

2. Dimensional drawings and elevations of all system enclosures including but not limited to the following: a. Fire Alarm Control Unit (panel), b. Remote Annunciators.

3. One-line riser drawing for the entire system network indicating panel-to-panel conductors including type, size, quantity and specific function.

4. System address and labeling methodology 5. System wiring diagrams indicating interfaces to equipment supplied by others. 6. Device "typical" wiring diagrams. These drawings shall indicate specific termination details for all

peripheral equipment and/or interface devices.

Page 24: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

DCSD FIRE DETECTION AND ALARM 28 31 00 - 4

G. Coordination Drawings: Submit Coordination Drawings in accordance with Division 26 Section “Common

Work Results for Electronic Safety and Security”. Include the following:

1. Enlarged Equipment Room layouts. 2. Reflected Ceiling Plans. 3. Heating, ventilating, and air-conditioning duct drawings, drawn to scale and coordinating

installation of duct smoke detectors and access to them. Show critical dimensions that relate to placement and support of sampling tubes, detector housing, and remote status and alarm indicators.

H. Qualification Data: For qualified Designer and Installer.

1. Copy of State license showing the fire alarm contractor to be certified in the layout and installation of fire alarm systems.

2. Copy of NICET certification showing the fire alarm contractor to be certified in the layout, equipment selection, installation, acceptance testing, trouble-shooting, servicing and sales of fire alarm systems.

I. Seismic Qualification Certificates: For fire-alarm control unit, accessories, and components, from manufacturer.

1. Basis for Certification: Indicate whether withstand certification is based on actual test of

assembled components or on calculation.

2. Dimensioned Outline Drawings of Equipment Unit: Identify center of gravity and locate and describe mounting and anchorage provisions.

3. Detailed description of equipment anchorage devices on which the certification is based and their installation requirements.

J. Field quality-control reports.

K. Operation and Maintenance Data: For fire-alarm systems and components to include in emergency,

operation, and maintenance manuals. In addition to items specified in Division 01 Section "Operation and Maintenance Data," include the following: 1. Comply with the "Records" Section of the "Inspection, Testing and Maintenance" Chapter in

NFPA 72. 2. Provide "Record of Completion Documents" according to NFPA 72 article "Permanent Records"

in the "Records" Section of the "Inspection, Testing and Maintenance" Chapter. 3. Record copy of site-specific software. 4. Provide "Maintenance, Inspection and Testing Records" according to NFPA 72 article of the same

name and include the following: a. Frequency of testing of installed components. b. Frequency of inspection of installed components. c. Requirements and recommendations related to results of maintenance. d. Manufacturer's user training manuals.

5. Manufacturer's required maintenance related to system warranty requirements. 6. Abbreviated operating instructions for mounting at fire-alarm control unit. 7. Copy of NFPA 25 “Standard for the Inspection, Testing, and Maintenance of Water-Based Fire

Protection Systems”.

Page 25: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

DCSD FIRE DETECTION AND ALARM 28 31 00 - 5

L. Graphic map: Plans shall be of durable construction, easily readable in normal lighting, protected by a smooth, transparent, plastic surface and shall include every building level including mezzanines and roofs. Plans shall contain the following information as applicable: 1. Building name 2. Building address 5. North orientation arrow 6. “You Are Here” in contrasting and bold font 7. Latest date plans were drawn/revised 8. Floor plans 9. Concealed spaces below floors and above ceilings; e.g., crawl spaces and attics 10. Site plan 11. Adjacent streets 13. Major uses, e.g., kitchens, restaurant, offices, Gymnasium, parking, etc. 15. Utility areas, e.g., electrical/telephone rooms/closets, water entry 16. All stair enclosures with distinct designation for each, matching floor signage 17. All elevators with distinct designation for each and associated machine rooms 20. All interior and exterior utility (communication, electricity, gas, water, etc.) shutoff locations 21. Locations of hazardous materials such as:

a. Control areas b. Fuel storage c. Battery rooms e. Emergency and standby power equipment locations

22. Sprinkler zones 23. All control valve locations including elevators and paint booths 24. Standpipe outlet locations 25. Special suppression systems; e.g., FM-200; UL-300; pre-action specialized fire protection

equipment; e.g., water tanks 27. Fire pump location 30. Fire department connections 31. Pump test headers 32. Wall hydrants as applicable 33. Smoke control zones 34. All initiating and addressable devices including water flow and control modules 35. Fire alarm zones 36. FACP/DACT/NAC power extender locations

M. Software and Firmware Operational Documentation:

1. Software operating and upgrade manuals. 2. Program Software Backup: On magnetic media or compact disk, complete with data files. 3. Device address list.

1.6 QUALITY ASSURANCE

A. Designer Qualifications: Shop Drawings shall be prepared and signed by personnel with the following qualifications: 1. Trained and certified by manufacturer. 2. Certified by NICET as Level III or a qualified professional engineer. 3. Licensed by authorities having jurisdiction.

B. Installer Qualifications: Personnel shall be trained and certified by manufacturer and be certified by NICET

Page 26: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

DCSD FIRE DETECTION AND ALARM 28 31 00 - 6

as follows: 1. Supervisor: Level III or higher. 2. Technician: Level II or higher.

C. Source Limitations for Fire-Alarm System and Components: Obtain fire-alarm system from single source from single manufacturer.

D. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70, by a qualified testing agency, and marked for intended location and application.

E. NFPA Certification: Obtain certification according to NFPA 72 by a UL-listed alarm company. F. Comply with NFPA 70 G. Comply with NFPA 72 H. Comply with the Americans with Disabilities Act (ADA); including local amendments, modifications and

additional accessibility requirements of the authorities having jurisdiction.

I. Comply with International Standards Organization (ISO)

1. ISO-9000 2. ISO-9001

1.7 DELIVERY, STORAGE, AND HANDLING

A. Prepare products for shipment.

1. Provide suitable packaging materials, crating, blocking, and supports so equipment will withstand expected domestic shipping and handling shocks and vibration.

2. Weatherproof packaging for shipment. Close connection openings to prevent entrance of foreign material during shipment and storage.

B. Store products indoors in clean dry space with uniform temperature in accordance with manufacturer’s requirements to prevent condensation. Protect products from exposure to dirt, fumes, water, corrosive substances, and physical damage.

C. Handle product components according to manufacturer's written instructions.

1.8 COORDINATION

A. Coordinate installation and operational requirements for automatic elevator recall, including but not limited to the recall signal time frame, with Division 14 and with authorities having jurisdiction.

B. Coordinate installation and operational requirements for fire-protection systems, including but not limited to water-based sprinkler system, with Division 21.

C. Coordinate installation and operational requirements for duct mounted smoke detectors with Division 21 and 23.

1.9 SOFTWARE SERVICE AGREEMENT

Page 27: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

DCSD FIRE DETECTION AND ALARM 28 31 00 - 7

A. Comply with UL 864.

B. Technical Support: Beginning with Substantial Completion, provide software support for two years.

C. Upgrade Service: Update software to latest version at Project completion. Install and program software upgrades that become available within two years from date of Substantial Completion. Upgrading software shall include operating system. Upgrade shall include new or revised licenses for use of software. 1. Provide 30 days' notice to Owner to allow scheduling and access to system and to allow Owner to

upgrade computer equipment if necessary.

1.10 MAINTENANCE AGREEMENT

A. Initial Maintenance Service: Beginning at Substantial Completion, provide full inspection and maintenance by skilled employees of manufacturer's designated service organization during the Warranty period, including any special warranty period specified.

1.11 EXTRA MATERIALS

A. Furnish extra materials described below that match products installed and that are packaged with protective covering for storage and identified with labels describing contents. 1. Lamps for Remote Indicating Lamp Units: 1 for every 100 of each type and rating installed.

Furnish at least one of each type. 2. Lamps for Strobe Units: 1 for every 100 of each type and rating installed. Furnish at least one of

each type. 3. Smoke Detectors and Heat Detectors: 10 for every 100 of each type and rating installed. Furnish

at least (2) two of each type. 4. Detector Bases: 2 for every 100 of each type installed. Furnish at least one of each type. 5. Keys and Tools: One extra set for access to locked and tamper-proofed components. 6. Audible and Visible Notification Appliances: 2 for every 100 of each type installed. Furnish at

least (2) two of each type. 7. Fuses: Three of each type installed in the system.

PART 2 – PRODUCTS 2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. FireLite; a Honeywell company. 2. NOTIFIER; a Honeywell company. 3. SimplexGrinnell LP; a Tyco International company.

2.2 SYSTEMS OPERATIONAL DESCRIPTION

A. Alarm signals:

1. Fire-alarm signal initiation (General Alarm) shall be by one or more of the following devices and systems:

Page 28: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

DCSD FIRE DETECTION AND ALARM 28 31 00 - 8

a. Manual Fire-Alarm Boxes. b. Heat detectors. c. Smoke detectors. d. Duct-Mounted smoke detectors. e. Automatic sprinkler system water flow. f. Heat detectors in elevator shaft and pit.

2. Supervisory signal initiation (Supervisory Alarm) shall be by one or more of the following devices and actions: a. Valve supervisory switch. (Operation of a fire-protection system valve tamper switch.) b. Elevator shunt-trip supervision.

3. System trouble signal initiation (Trouble Alarm) shall be by one or more of the following devices and actions: a. Open circuits, shorts, and grounds in designated circuits. b. Opening, tampering with, or removing alarm-initiating and supervisory signal-initiating

devices. c. Loss of primary power at fire-alarm control unit. d. Ground or a single break in fire-alarm control unit internal circuits. e. Abnormal ac voltage at fire-alarm control unit. f. Break in standby battery circuitry. g. Failure of battery charging. h. Abnormal position of any switch at fire-alarm control unit or annunciator.

B. Alarm Actions:

1. Fire alarm signal (General Alarm) shall initiate the following actions:

a. Continuously operate alarm notification appliances as indicated. Notification of a General Alarm conditions within the protected premises shall be similar to the following methodology: 1) Notification: Activate audible and visible indicating devices throughout the

entire facility.

b. Identify alarm at fire-alarm control unit and remote annunciators. Indication, notification and acknowledgement of alarm conditions at the fire-alarm control unit shall be similar to the following methodology:

1) When the system control panel goes into alarm condition the normal indicator

light shall extinguish and an alarm indicator light shall illuminate, a control panel audible alert (buzzer) shall pulsate.

2) Visually indicate, via the system control panel LCD display, all applicable information associated with the status condition including; the real time, the number of messages waiting, the type of alarm, the alarm zone number, the device type, the device location, the time/date the alarm occurred and any user specified message(s).

3) The operator shall acknowledge the alarm/message by pressing an acknowledge button, and the buzzer shall silence providing there isn't an additional alarm pending. If there are additional alarms waiting the operator must acknowledge all pending alarms/messages before the buzzer will silence.

4) To silence audible devices and stop visible devices from flashing the operator may press the alarm silence button; a new alarm shall cause the audible and visible devices to resound/flash. The visible devices shall stop operating when

Page 29: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

DCSD FIRE DETECTION AND ALARM 28 31 00 - 9

the "Alarm Silence" button is pressed, failure to do so could result in confusion of hearing impaired occupants.

5) To reset the system the operator shall press the reset button. 6) Any remote or local annunciator LCD/LED's associated with the status zone

shall be illuminated.

c. Transmit an alarm and water flow signal to the remote alarm supervising station.

1) Operate alarm relay contacts to initiate the transmission of an alarm and water flow to the following:

a) A Central Monitoring Station retained by the Owner via an auto-dialer

or within the system control panel.

d. Release fire and smoke doors held open by magnetic door holders.

1) Door hold-open devices that are controlled by smoke detectors at doors in smoke barrier walls shall be connected to fire-alarm system.

e. Interface with Security System to include but not limited to Lock Down Functions. f. Record events in the system memory. g. Comply with additional sequences specified under the “Additional Specialized Alarm

Actions” paragraph in Part 2 of this section.

2. System Trouble and Supervisory Signal Actions shall initiate the following actions:

a. Notification appliance and annunciate at the FACP and remote annunciators. b. Record events in the system memory. c. Transmit alarm signal to the remote supervising station.

1) Operate alarm relay contacts to initiate the transmission of an alarm to the following:

a) A Central Monitoring Station retained by the Owner via an auto-dialer

or within the system control panel.

d. Comply with additional sequences specified under the “Additional Specialized Alarm Actions” paragraph in Part 2 of this section.

C. Additional Specialized Alarm Actions:

1. Elevator Recall: Activate elevator recall system to start in accordance with ANSI Standard A17.1 and NFPA 72. Comply with the following: a. Alarm-initiating devices, except those listed, shall not start elevator recall. Smoke

detectors in locations indicated below shall initiate automatic elevator recall:

1) Elevator lobby detectors. 2) Smoke detector in elevator machine room. 3) Smoke detectors in elevator hoistway.

b. Smoke detectors designated for Elevator Recall shall be connected to fire-alarm system. Initiate a General Alarm upon detection of smoke.

c. Actuation of the elevator lobby detector located on the designated primary recall floor shall signal the cars to move to the alternate recall floor.

Page 30: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

DCSD FIRE DETECTION AND ALARM 28 31 00 - 10

2. Elevator Shunt-Trip Operation: Heat detectors designated for elevator power removal shall be connected to fire-alarm system. Alarm-initiating devices, except those listed, shall not start elevator power removal. a. Actuation of heat detectors in the locations indicated below shall shut down power, via a

shunt trip operator, to the elevators associated with the location without time delay: 1) Heat detector in elevator machine room; locate detector within two feet of each

sprinkler head. 2) Heat detectors in elevator hoistway; locate detector within 18 inches of each

sprinkler head. 3) Upon elevator power shut down, fire alarm shall send a supervisory signal for

elevator power loss.

3. Duct-mounted smoke detector: Duct-mounted smoke detector shall initiate the following functions:

a. Initiate a Supervisory. b. Shutdown the associated air-handling unit. c. Provide for an adjustable time delay, initially set at 20 seconds, to delay the transmission

of close signal to the dampers. The intent of this time delay is to allow the air-handling unit fan(s) to receive the stop signal and slow down before closing any dampers in order to avoid a high static-pressure alarm/trip on the air-handling system.

2.3 FIRE-ALARM CONTROL UNIT (PANEL)

A. General Requirements for Fire-Alarm Control Unit:

1. The system shall have the capability of being activated into alarm, supervisory and trouble modes of operation from both manual and automatic devices.

2. Field-programmable, microprocessor-based, modular, power-limited design with electronic modules, complying with UL 864 and listed and labeled by an NRTL. a. System software and programs shall be held in flash electrically erasable programmable

read-only memory (EEPROM), retaining the information through failure of primary and secondary power supplies.

b. Include a real-time clock for time annotation of events on the event recorder and printer.

3. Addressable initiation devices that communicate device identity and status.

a. Smoke sensors shall additionally communicate sensitivity setting and allow for adjustment of sensitivity at fire-alarm control unit.

b. Temperature sensors shall additionally test for and communicate the sensitivity range of the device.

4. Addressable control circuits for operation of mechanical equipment.

B. Alphanumeric Display and System Controls: Arranged for interface between human operator at fire-alarm control unit and addressable system components including annunciation and supervision. Display alarm, supervisory, and component status messages and the programming and control menu. 1. Annunciator and Display: LCD Touchscreen or Liquid-crystal type, with minimum of 2 line(s) of

40 characters. 2. Keypad: Arranged to permit entry and execution of programming, display, and control

Page 31: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

DCSD FIRE DETECTION AND ALARM 28 31 00 - 11

commands and to indicate control commands to be entered into the system for control of smoke detector sensitivity and other parameters.

C. Elevator Recall: Provide an output signal using an addressable relay to start elevator recall sequence in accordance with sequence of operation.

D. Transmission to Remote Supervising Station: Automatically transmit alarm, supervisory, trouble, and water flow signals to a remote alarm station.

E. Primary Power: 24-V dc obtained from 120-V ac service and a power-supply module. Initiating devices, notification appliances, signaling lines, trouble signals, supervisory signals, supervisory and digital alarm communicator transmitters, where provided, shall be powered by 24-V dc source. 1. Alarm current draw of entire fire-alarm system shall not exceed 80 percent of the power-supply

module rating.

F. Secondary Power: 24-V dc supply system with batteries, automatic battery charger, and automatic transfer switch. 1. Batteries: Sealed lead calcium.

G. Instructions: Computer printout or typewritten instruction card mounted behind a plastic or glass cover in a

stainless-steel or aluminum frame. Include interpretation and describe appropriate response for displays and signals. Briefly describe the functional operation of the system under normal, alarm, and trouble conditions.

1.4 REMOTE ANNUNCIATOR

A. Description: Annunciator functions shall match those of fire-alarm control unit for alarm, supervisory, and trouble indications. Manual switching functions shall match those of fire-alarm control unit. 1. Mounting: Flush cabinet, NEMA 250, Type 1.

B. Display Type and Functional Performance: Alphanumeric display and LED indicating lights shall match

those of fire-alarm control unit.

1.5 MANUAL FIRE-ALARM BOXES

A. General Requirements for Manual Fire-Alarm Boxes: Comply with UL 38. Boxes shall be finished in red with molded, raised-letter operating instructions in contrasting color; shall show visible indication of operation; and shall be mounted on recessed outlet box. If indicated as surface mounted, provide manufacturer's surface back box. 1. Double-action mechanism requiring two actions to initiate an alarm, pull-lever type; with integral

addressable module arranged to communicate manual-station status (normal, alarm, or trouble) to fire-alarm control unit.

2. Station Reset: Key- or wrench-operated switch. 3. Indoor Protective Shield: Factory-fabricated clear plastic enclosure hinged at the top to permit

lifting for access to manual fire alarm box to initiate an alarm. Lifting the protective shield actuates an integral battery-powered audible horn intended to discourage false-alarm operation.

1.6 SYSTEM SMOKE DETECTORS

Page 32: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

DCSD FIRE DETECTION AND ALARM 28 31 00 - 12

A. General Requirements for System Smoke Detectors:

1. Comply with UL 268; operating at 24-V dc, nominal. 2. Detectors shall be two-wire type. 3. Base Mounting: Detector and associated electronic components shall be mounted in a twist-lock

module that connects to a fixed base. Provide terminals in the fixed base for connection to building wiring.

4. Self-Restoring: Detectors do not require resetting or readjustment after actuation to restore them to normal operation.

5. Integral Visible-Indicating Light: LED type indicating detector has operated and power-on status.

B. Photoelectric Smoke Detectors:

1. Detector address shall be accessible from fire-alarm control unit and shall be able to identify the detector's location within the system and its sensitivity setting.

2. An operator at fire-alarm control unit, having the designated access level, shall be able to manually access the following for each detector:

a. Primary status. b. Device type. c. Present average value. d. Present sensitivity selected. e. Sensor range (normal, dirty, etc.).

C. Duct-Mounted Smoke Detectors: Two-wire Photoelectric type complying with UL 268A.

1. Detector address shall be accessible from fire-alarm control unit and shall be able to identify the detector's location within the system and its sensitivity setting.

2. An operator at fire-alarm control unit, having the designated access level, shall be able to manually access the following for each detector:

a. Primary status. b. Device type. c. Present average value. d. Present sensitivity selected. e. Sensor range (normal, dirty, etc.).

3. Each sensor shall have multiple levels of detection sensitivity. 4. Sampling Tubes: Design and dimensions as recommended by manufacturer for specific duct size,

air velocity, and installation conditions where applied. 5. Provide relay at each duct-mounted detector for Fan Shutdown, Smoke Damper actuation or

Fire/Smoke Damper actuation. Contacts rated to interrupt control circuit. 6. Provide relay at each detector located at an air-handling unit to interface with the Facility

Management System (FMS) and communicate the device address and status.

1.7 HEAT DETECTORS

A. General Requirements for Heat Detectors: Comply with UL 521. B. Heat Detector, Combination Type: Actuated by either a fixed temperature of 135 deg F (57 deg C) or a

rate of rise that exceeds 15 deg F (8 deg C) 1. Mounting: Twist-lock base interchangeable with smoke-detector bases.

per minute unless otherwise indicated. 2. Integral Addressable Module: Arranged to communicate detector status (normal, alarm, or trouble)

to fire-alarm control unit.

Page 33: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

DCSD FIRE DETECTION AND ALARM 28 31 00 - 13

1.8 NOTIFICATION APPLIANCES

A. General Requirements for Notification Appliances: Connected to notification appliance signal circuits, zoned, equipped for mounting and with screw terminals for system connections. 1. Combination Devices: Factory-integrated audible and visible devices in a single-mounting

assembly, equipped for mounting and with screw terminals for system connections.

B. Visible Notification Appliances: Xenon strobe lights comply with UL 1971, with clear polycarbonate lens mounted on an aluminum faceplate. The word "FIRE" is engraved in minimum 1-inch- (25-mm-) high letters on the device faceplate. 1. Rated Light Output: 15/30/75/110 cd, selectable in the field. 2. Mounting: Wall mounted unless otherwise indicated. 3. For units with guards to prevent physical damage, light output ratings shall be determined with

guards in place. 4. Flashing shall be in a temporal pattern, synchronized with other units. 5. Strobe Leads: Factory connected to screw terminals. 6. Mounting Faceplate: Factory finished, red with white lettering.

C. Horns: Electric-vibrating-polarized type, 24-V dc; with provision for housing the operating mechanism behind a grille. Comply with UL 464. Horns shall produce a sound-pressure level of 90 dBA, measured 10 feet (3 m) from the horn, using the coded signal prescribed in UL 464 test protocol.

1.9 CONDUCTORS AND CABLES

A. RS-232 Cable

1. Plenum-Rated Cable: NFPA 70, Type CMP.

a. Paired, 2 pairs, No. 22 AWG, stranded (7x30) tinned copper conductors. b. Plastic insulation. c. Individual aluminum foil-polyester tape shielded pairs with 100 percent shield coverage. d. Plastic jacket. e. Pairs are cabled on common axis with No. 24 AWG, stranded (7x32) tinned copper drain

wire. f. Flame Resistance: Comply with NFPA 262.

B. Fire Alarm Wire And Cable

1. Available Manufacturers: Provide products from manufacturers offering products that comply with requirements.

2. General Wire and Cable Requirements: Plenum-Rated NRTL listed and labeled as complying with NFPA 70, Article 760.

3. Signaling Line Circuits: Twisted, shielded pair, size as recommended by system manufacturer. 4. Non-Power-Limited Circuits: Solid-copper conductors with 600-V rated, 75 deg C, color-coded

insulation. a. Low-Voltage Circuits: No. 16 AWG, minimum. b. Line-Voltage Circuits: No. 12 AWG, minimum.

5. Multiconductor Armored Cable: NFPA 70, Type MC, copper conductors, Type TFN/THHN conductor insulation, copper drain wire, copper armor with outer jacket with red identifier stripe,

Page 34: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

DCSD FIRE DETECTION AND ALARM 28 31 00 - 14

NTRL listed for fire alarm and cable tray installation, plenum rated, and complying with requirements in UL 2196 for a 2-hour rating.

C. Circuit Class and Style:

1. Initiating Device, Notification Appliance, and Signaling Line Circuits: NFPA 72, Class B.

1.10 DEVICE GUARDS

A. Description: Welded wire mesh of size and shape for the manual station, smoke detector, gong, or other device requiring protection.

1. Factory fabricated and furnished by manufacturer of device. 2. Finish: Paint of color to match the protected device.

1.11 MAGNETIC DOOR HOLDERS

A. Description: Units are equipped for wall or floor mounting as indicated and are complete with matching doorplate. 1. Electromagnet: Requires no more than 3 W to develop 25-lbf (111-N) 2. Wall-Mounted Units: Flush mounted unless otherwise indicated.

holding force. Rating: 24-V ac or dc.

C. Material and Finish: Match door hardware. 2.12 ADDRESSABLE INTERFACE DEVICE

A. Description: Microelectronic monitor module, NRTL listed for use in providing a system address for alarm

initiating devices for wired applications with normally open contacts.

B. Integral Relay: Capable of providing a direct signal to the following:

1. Elevator controller to initiate elevator recall. 2. Circuit-breaker shunt trip for elevator power shutdown. 3. Door hold open devices

2.13 DIGITAL ALARM COMMUNICATOR TRANSMITTER

A. Digital alarm communicator transmitter shall be acceptable to the remote central station and shall comply with UL 632 and be listed and labeled by an NRTL.

B. Functional Performance: Unit shall receive an alarm, supervisory, or trouble signal from fire-alarm control unit and automatically capture two telephone line(s) and dial a preset number for a remote central station. When contact is made with central station(s), signals shall be transmitted. If service on either line is interrupted for longer than 45 seconds, transmitter shall initiate a local trouble signal and transmit the signal indicating loss of telephone line to the remote alarm receiving station over the remaining line. Transmitter shall automatically report telephone service restoration to the central station. If service is lost on both telephone lines, transmitter shall initiate the local trouble signal.

C. Local functions and display at the digital alarm communicator transmitter shall include the following:

Page 35: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

DCSD FIRE DETECTION AND ALARM 28 31 00 - 15

1. Verification that both telephone lines are available. 2. Programming device. 3. LED display. 4. Manual test report function and manual transmission clear indication. 5. Communications failure with the central station or fire-alarm control unit.

D. Digital data transmission shall include the following:

1. Alarm. 2. Supervisory. 3. Trouble 4. Water Flow 5. Loss of ac supply or loss of power. 6. Low battery. 7. Abnormal test signal. 8. Communication bus failure.

E. Secondary Power: Integral rechargeable battery and automatic charger. F. Self-Test: Conducted automatically every 24 hours with report transmitted to central station.

PART 3 – EXECUTION

3.1 APPLICATION A. Fire-Alarm Control Unit (FACP) Locations: Provide control units and/or annunicators in the following

locations, unless otherwise indicated:

1. Fire Sprinkler Room 2. Lobby 3. Main Office

3.2 EQUIPMENT INSTALLATION A. Comply with NFPA 72 for installation of fire-alarm equipment.

B. Comply with NECA 305 “Standard for Fire Alarm System Job Practices” as published by the National

Electrical Contractors Association.

C. Equipment Mounting: Install wall-mounted equipment, with tops of cabinets not more than 72 inches (1830 mm) above the finished floor. 1. Comply with requirements for seismic-restraint devices specified in Division 26 Section

"Vibration and Seismic Controls for Electrical Systems."

D. Smoke- or Heat-Detector Spacing:

1. Comply with NFPA 72, "Smoke-Sensing Fire Detectors" Section in the "Initiating Devices" Chapter for smoke-detector spacing.

2. Comply with NFPA 72, "Heat-Sensing Fire Detectors" Section in the "Initiating Devices" Chapter, for heat-detector spacing.

3. Smooth ceiling spacing shall not exceed the listing of the detector.

Page 36: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

DCSD FIRE DETECTION AND ALARM 28 31 00 - 16

4. Spacing of detectors for irregular areas, for irregular ceiling construction, and for high ceiling areas shall be determined according to Appendix A in NFPA 72.

5. HVAC: Locate detectors not closer than 5 feet (1.5 m) from air-supply diffuser or 3 feet (1 m) from return-air opening.

6. Lighting Fixtures: Locate centerline of detectors not closer than 12 inches (300 mm) from any part of a lighting fixture.

E. Duct-Mounted Smoke Detectors: Comply with NFPA 72 and NFPA 90A. Install sampling tubes so they

extend the full width of duct with support by other side of duct regardless of size. F. Heat Detectors in Elevator Shafts: Coordinate temperature rating, thermal response characteristic and

location with sprinkler rating and location.

G. Remote Status and Alarm Indicators: Install near each smoke detector and each sprinkler water-flow switch and valve-tamper switch that is not readily visible from normal viewing position.

H. Notification Devices: Install devices with appropriate backbox and raceway according to room finish (i.e. flush mounted devices in recessed backboxes with concealed conduit in finished spaces; surface mounted boxes with exposed conduit in unfinished spaces. Refer to Architectural Documents for room finish types.

I. Device Location-Indicating Lights: Locate in public space near the device they monitor.

J. No panels shall be mounted above ceiling.

K. All modules located above ceiling shall have identification on ceiling grid with address. 3.3 WIRING INSTALLATION

A. Install wiring according to the following:

1. NECA 1. 2. TIA/EIA 568-A. 3. Cables, raceways, and support pathways, including but not limited to j-hooks and cable tray, that

are used for fire alarm circuits and equipment control wiring associated with the fire alarm system shall not contain any other wire or cable.

4. Signaling Line Circuits: Power-limited fire alarm cables shall not be installed in the same cable or raceway as signaling line circuits.

B. Comply with mounting and support requirements specified in Division 26 Section "Hangers and Supports for Electrical Systems."

C. Wiring Method for vertical risers penetrating floor slabs: Install wiring in metal raceway according to Division 26 Section "Raceways and Boxes for Electrical Systems.”

D. Wiring Method for circuits concealed in Walls, Partitions, and Inaccessible Ceilings: Install wiring in metal raceway according to Division 26 Section "Raceways and Boxes for Electrical Systems.”

E. Wiring Method for surface mounted and other exposed circuits, including in Crawlspaces: Install wiring in metal raceway according to Division 26 Section "Raceways and Boxes for Electrical Systems.”

F. Wiring Method for circuits concealed in accessible ceilings, install plenum-rated fire alarm cables supported on j-hooks, cable tray or bridal rings. All supports shall be red or painted red. One hole zip-ties not accepted for support. 1. For wall mounted devices: Install recessed device back boxes with conduit extended to above

Page 37: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

DCSD FIRE DETECTION AND ALARM 28 31 00 - 17

accessible ceiling according to Division 26 Section "Raceways and Boxes for Electrical Systems.”

G. Wiring within Enclosures:

1. Separate power-limited and non-power-limited conductors as recommended by manufacturer. 2. Install conductors parallel with or at right angles to sides and back of the enclosure. 3. Bundle, lace, and train conductors to terminal points with no excess. 4. Connect conductors that are terminated, spliced, or interrupted in any enclosure associated with

the fire alarm system to terminal blocks. 5. Mark each terminal according to the system's wiring diagrams. 6. Make all connections with approved crimp-on terminal spade lugs, pressure-type terminal blocks,

or plug connectors.

H. Cable Taps: Use numbered terminal strips in junction, pull, and outlet boxes, cabinets, or equipment enclosures where circuit connections are made.

I. Wiring to Remote Alarm Transmitting Device: Provide 1-inch (25-mm) conduit between the FACP and the transmitter. Install number of conductors and electrical supervision for connecting wiring as needed to suit monitoring function.

J. Conductors: Size according to system manufacturer's written instructions unless otherwise indicated. K. General Requirements for Cabling:

1. Comply with TIA/EIA-568-B.1. 2. Comply with BICSI ITSIM, Ch. 6, "Cable Termination Practices." 3. Terminate all conductors; no cable shall contain un-terminated elements. Make terminations only

at indicated outlets, terminals, and cross-connect and patch panels. 4. Cables may not be spliced. Secure and support cables at intervals not exceeding 30 inches (760

mm) and not more than 6 inches (150 mm) from cabinets, boxes, fittings, outlets, racks, frames, and terminals.

5. Bundle, lace, and train conductors to terminal points without exceeding manufacturer's limitations on bending radii, but not less than radii specified in BICSI ITSIM, "Cabling Termination Practices" Chapter. Install lacing bars and distribution spools.

6. Do not install bruised, kinked, scored, deformed, or abraded cable. Do not splice cable between termination, tap, or junction points. Remove and discard cable if damaged during installation and replace it with new cable.

7. Cold-Weather Installation: Bring cable to room temperature before dereeling. Heat lamps shall not be used for heating.

8. Pulling Cable: Comply with BICSI ITSIM, Ch. 4, "Pulling Cable." Monitor cable pull tensions.

L. Color-Coding: Color-code fire alarm conductors differently from the normal building power wiring. Use one color-code for alarm circuit wiring and another for supervisory circuits. Color-code audible alarm indicating circuits differently from alarm-initiating circuits. Use different colors for visible alarm-indicating devices. Paint fire alarm system junction boxes and covers red.

3.4 CONNECTIONS

A. Make addressable connections with a supervised interface device to the following devices and systems. Install the interface device less than 3 feet (1 m) from the device controlled. Make an addressable confirmation connection when such feedback is available at the device or system being controlled. 1. Alarm-initiating connections to the following:

a. Elevator Recall system and components.

Page 38: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

DCSD FIRE DETECTION AND ALARM 28 31 00 - 18

2. Supervisory connections to the following:

a. Valve supervisory switches. b. Elevator shunt trip breaker.

B. Where fire-protection systems are specified in Division 08 Section "Door Hardware” to be integral to doors in fire-rated walls and partitions and to doors in smoke partitions, comply with requirements in Division 08 Section and Connect hardware and devices to fire-alarm system. 1. Verify that hardware and devices are NRTL listed for use with fire-alarm system in this Section

before making connections.

1.12 IDENTIFICATION

A. Identify system components, wiring, cabling, and terminals. Comply with requirements for identification specified in Division 26 Section "Identification for Electrical Systems." 1. Paint junction box cover plates using red paint. Stencil the letters “FA” in white paint over red

background. 2. For all components of the fire alarm system requiring 120VAC power, provide a permanent

engraved label at the component indicating the panel and circuit number from which it is fed.

B. Install framed instructions in a location visible from fire-alarm control unit.

C. Color-Coding:

1. Color-code fire alarm conductors differently from the normal building power wiring. 2. Use one color-code for alarm circuit wiring and a different color-code for supervisory circuits. 3. Color-code audible alarm-indicating circuits differently from alarm-initiating circuits. Use

different colors for visible alarm-indicating devices.

D. Provide a red marking on all circuit breakers feeding any fire alarm control system in accordance with NFPA 72. Provide a permanent engraved label next to the circuit breaker(s) feeding the system that reads “Fire Alarm Control Circuit”.

1.13 GROUNDING

A. Ground fire-alarm control unit and associated circuits; comply with IEEE 1100. Install a ground wire from main service ground to fire-alarm control unit.

1.14 FIELD QUALITY CONTROL

A. Field tests shall be witnessed by authorities having jurisdiction, as required.

1. Provide 14 days' advance notice of tests and opportunity for observation of tests by Engineer and Owner's representative.

B. Manufacturer's Field Service: Engage a factory-authorized service representative to inspect, test, and adjust components, assemblies, and equipment installations, including connections.

C. Tests and Inspections:

Page 39: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

DCSD FIRE DETECTION AND ALARM 28 31 00 - 19

1. Visual Inspection: Conduct visual inspection prior to testing.

a. Inspection shall be based on completed Record Drawings and system documentation that is required by NFPA 72 in its "Completion Documents, Preparation" Table in the "Documentation" Section of the "Fundamentals of Fire Alarm Systems" Chapter.

b. Comply with "Visual Inspection Frequencies" Table in the "Inspection" Section of the "Inspection, Testing and Maintenance" Chapter in NFPA 72; retain the "Initial/Reacceptance" column and list only the installed components.

2. System Testing: Comply with "Test Methods" Table in the "Testing" Section of the "Inspection, Testing and Maintenance" Chapter in NFPA 72.

3. Test audible appliances for the public operating mode according to manufacturer's written instructions. Perform the test using a portable sound-level meter complying with Type 2 requirements in ANSI S1.4.

2. Test visible appliances for the public operating mode according to manufacturer's written instructions.

5. Factory-authorized service representative shall prepare the "Fire Alarm System Record of Completion" in the "Documentation" Section of the "Fundamentals of Fire Alarm Systems" Chapter in NFPA 72 and the "Inspection and Testing Form" in the "Records" Section of the "Inspection, Testing and Maintenance" Chapter in NFPA 72.

D. Reacceptance Testing: Perform reacceptance testing to verify the proper operation of added or replaced devices and appliances.

E. Fire-alarm system will be considered defective if it does not pass tests and inspections. F. Prepare test and inspection reports.

3.8 ADJUSTING

A. Occupancy Adjustments: When requested within 12 months of date of Substantial Completion, provide

on-site assistance in adjusting system to suit actual occupied conditions. Provide up to two visits to Project outside normal occupancy hours for this purpose.

3.9 CLEANING

A. Clean components according to manufacturer's written instructions.

B. On completion of device box installation but before any wiring devices are installed, inspect interior of boxes and perform the following: 1. Vacuum dirt and debris; do not use compressed air to assist in cleaning.

C. On completion of initiation and notification devices installation, inspect exterior surfaces and perform the

following: 1. Remove paint splatters and other spots. 2. Remove all temporary markings and labels. 3. Wipe down all devices with approve cleaning agent to remove fingerprints and dust.

3.10 DEMONSTRATION

A. Engage a factory-authorized service representative to train Owner's personnel to adjust, operate, and

Page 40: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

DCSD FIRE DETECTION AND ALARM 28 31 00 - 20

maintain fire-alarm system. Refer to Division 01 Section "Demonstration and Training."

END OF SECTION

Page 41: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

5TH GR. C.R. 1515TH GR. C.R. 1525TH GR. C.R. 154 6TH GR. C.R. 166 6TH GR. C.R. 162 6TH GR. C.R. 161

6TH GR. C.R. 165 6TH GR. C.R. 163 6TH GR. C.R. 160

HALLW

AY 1

64

HALLWAY 1695TH GR. C.R. 1505TH GR. C.R. 1535TH GR. C.R. 155 HALLWAY 156

CORRIDOR 103

MECH. 120MEDIA OFF. 121

BOYS 167 GIRLS 168

TEACHERS LOUNGE 106

STAFF TOILET 108

SPECIAL EDUCATION 110

CUST. SUPPLY 111

MAIN CUSTODIAL 112

BRT 123

TOILET 113

COMPUTER ROOM 124

LOUNGE VEST. 105

MEDIA CENTER 122

CORRIDOR 101

CO

RR

IDO

R 1

02

CO

RR

IDO

R 1

00

BOYS 157

BOYS 158STORAGE 146

CUST. 119

CUST. 118

4TH GR. C.R. 145

4TH GR. C.R. 144TEACHER WORK CENTER & SUPPLY 128 4TH GR. C.R. 143 4TH GR. C.R. 142 4TH GR. C.R. 141 4TH GR. C.R. 140

STAFF TOILET 107 TELEPHONE 109

CO

RR

IDO

R 2

02

CO

RR

IDO

R 2

03

GIRLS 132

COAT CLOSET 133COAT CLOSET 135

BOYS 136GIRLS 137

COAT CLOSET 138

MATCH L

INE S

EE 1

/ AD

1.2

MATCH L

INE S

EE 1

/ AD

1.1

33 3 3 3

33333

3

3

3

3

3 3 2 3 3 32 222

2

2

2

2

2 2 2 2 2

2222

11111

1

1

1

1

1 1 1 1 1

77

815

5

8

MATCH L

INE S

EE 1

/ AD

1.2

MATCH L

INE S

EE 1

/ AD

1.1

2

4

8

10

COAT CLOSET 130

BOYS 131

MATCH L

INE S

EE 1

/ AD

1.1

MATCH L

INE S

EE 2

/ AD

1.2

MATCH L

INE S

EE 1

/ AD

1.1

MATCH L

INE S

EE 2

/ AD

1.2

12

7

7 7 7

7

7

7

7 7

7

6

12

5

15

5 510105 105 10

10 101010 10 10

10

1010 10101010

10

1216 1613 13

13

ALL DEMO FLOOR PLANS

1. REMOVE MECHANICAL GRILL ASSEMBLY COMPLETE. PREPARE OPENING FORPATCH, MATCH (E) BRICK AND (E) GROUT COLOR AND SIZE.

2. REMOVE UNI VENT ASSEMBLY COMPLETE. PREPARE OPENING FOR PATCH-TOMATCH (E) CMU WALL, PAINT FULL WALL CORNER TO CORNER.

3. TRIM EXISTING CARPET TO STRAIGHT EDGE. APPROXIMATE AREA SHOWN.PATCH WITH SOLID DARK CARPET, COLOR BY ARCHITECT.

4. REMOVE (E) PUMPS, INSTALL NEW PUMPS ON (E) HOUSEKEEPING PAD, RE:MECHANICA.L.

5. (E) CASEWORK TO REMAIN. PROTECT DURING CONSTRUCTION PROCESS.

6. CAREFULLY REMOVE CASEWORK, SALVAGE AND SCRIBE TO FIT AROUND NEWCOLUMNS, REINSTALL.

7. REMOVE (E) FLOORING, SAW CUT (E) CONC. FOOTING AND/ OR (E) WALL ASREQ'D FOR INSTALL NEW SPREAD FOOTINGS AND STL COLUMNS, RE:STRUCTURAL.

8. CAREFULLY REMOVE BUILT-IN TABLE/COUNTER TOP AS REQUIRED FOR NEWCONSTRUCTION, SALVAGE FOR COLUMN ALTERATION, SCRIBE AROUND COLUMNFOR REINSTALLATION.

9. REMOVE (E) BOILER, RE: MECHANICAL. LEAVE (E) HOUSEKEEPING PAD.

10. REMOVE (E) THERMOSTAT, RE: MECHANICAL FOR FULL EXTENT. PATCH TOMATCH (E) AS REQ'D.

11. REMOVE/DEMO (E) CHILLER. RE: MECHANICAL DRAWINGS FOR FURTHERINFORMATION. LEAVE (E) CONCRETE PAD TO RECEIVE (N) MECHANICALEQUIPMENT.

12. REMOVE (E) MARKER BD., SALVAGE FOR REINSTALLATION.

13. REMOVE (E) SCREEN, SALVAGE FOR RELOCATION.

14. NOT USED.

15. REMOVE (E) CASEWORK, SALVAGE FOR REINSTALLATION.

16. REMOVE (E) CARPET AS REQ'D TO INSTALL (N) WALL.

DEMO NOTES:

ALL FLOOR DEMO PLANSGENERAL DEMO NOTES:FOR GENERAL DEMO NOTES SEE GENERAL DEMO NOTES SHEET A1.0

2175 S. JASMINE ST.

DENVER CO 80222SUITE 217

FX: (303) 756-2332PH: (303) 691-8000

YON TANNERARCHITECTURE

MEC

HA

NIC

AL

UPG

RA

DE

FOR

:

PROJECT NO: 13121

ISSUE:

DATE: SEP 24, 2014

CHECKED:

DRAWN:

FILE NAME:

DWG NAME:

SHEET NO:

DO

UG

LAS

CO

UN

TY S

CH

OO

L D

ISTR

ICT

NO

RTH

EAST

ELE

MEN

TAR

Y S

CH

OO

L

PAR

KER

, CO

LOR

AD

O 8

0134

CONSTRUCTIONDOCUMENTS

6598

N. H

IGH

WA

Y 8

3

LZ-KS

RET

DEMOLITIONFLOOR PLAN- AREA 1

AD1.1_DFPA1

NORTH

1 SCALE: 1/8" = 1'-0"

DEMOLITION FLOOR PLAN- AREA 1

AREA 1

AREA 2

AREA 3

KEY PLAN

2

2

REVISIONS:

ADDENDUM # 22

Page 42: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

5TH GR. C.R. 1515TH GR. C.R. 1525TH GR. C.R. 154

6TH GR. C.R. 166 6TH GR. C.R. 162 6TH GR. C.R. 161

6TH GR. C.R. 165 6TH GR. C.R. 163 6TH GR. C.R. 160HALLWAY 164HALLWAY 1695TH GR. C.R. 1505TH GR. C.R. 1535TH GR. C.R. 155

HALLWAY 156

CORRIDOR 103

MECH. 120MEDIA OFF. 121 BOYS 167 GIRLS 168 TEACHERS LOUNGE 106

STAFF TOILET 108

SPECIAL EDUCATION 110

CUST. SUPPLY 111

MAIN CUSTODIAL 112

BRT 123 TOILET 113

COMPUTER ROOM 124LOUNGE VEST. 105

MEDIA CENTER 122

CORRIDOR 101

CO

RR

IDO

R 1

02

CO

RR

IDO

R 1

00

BOYS 157

BOYS 158MECHANICAL 146

CUST. 119 CUST. 118

4TH GR. C.R. 145

4TH GR. C.R. 144TEACHER WORK CENTER & SUPPLY 128 4TH GR. C.R. 143 4TH GR. C.R. 142 4TH GR. C.R. 141 4TH GR. C.R. 140

STAFF TOILET 107 TELEPHONE 109 CORRIDOR 202

CORRIDOR 203

MATCH L

INE S

EE 1/ A

D2.2

MATCH L

INE S

EE 1/ A

D2.1

MATCH L

INE S

EE 1/ A

D2.3

MATCH L

INE S

EE 1/ A

D2.1

TYP.

TYP.

4TYP.

TYP.

GIRLS 132

COAT CLOSET 133COAT CLOSET 135

BOYS 136GIRLS 137

COAT CLOSET 138 COAT CLOSET 130

BOYS 131

1 1 1

1 7 7

1

2

44 4

7TYP.

6

TYP.

4

TYP.

4

TYP.

4

TYP.

4

TYP.

4

TYP.

4

TYP.

4

TYP.

1

1

1

1

1

1

2 2 2 2

2

4

4

4

2

TYP.

1 1 1 111

2

TYP.

7TYP.

7

3 TYP.3 TYP.

3 TYP.3TYP.

3

TYP.

3 TYP.3

TYP.

3

TYP.3 TYP.

3TYP.

3

TYP.

TYP.

3

TYP.

3

TYP.

TYP.

3

TYP.TYP.

3

TYP.

3

TYP.

3

3

31

1 1

11

1

1 1 1 1 1 7 1 1 1

1

7 7 7

1 1 17 7 7

2

TYP.

4

TYP.

4

4TYP.

4

4

TYP.

4

TYP.

4

4

TYP.

4

TYP.

4

TYP.

8888

9

8

9

1

1

3

2

2

10

10 10

10

10

10

10

10

10

10

11 11

11 11

11 11

11 11

11 11

11 11

1

10

1 10

10TYP.

10

10

10

10

3

10

10 10

13

10

2

2

2

2

2

2

2

1

2

14 14 14

TYP.

1

1

1

1

1

1

1

1

1

1

1

1 1

1

14

14

14

10

10TYP.

TYP.

10

10

10

10

10

10

1010

10

1

10

10

10

10

10

10

10

12

TYP.

DOUBLE FACE EXIT SIGN

WALL MOUNTED STROBE

LIGHT FIXTURESURFACE MOUNTED FLUORESCENT

MANUAL PULL STATION

WALL MOUNTED FIRE HORN W/STROBE

SINGLE FACE EXIT SIGN

(E) CEILING MOUNTED SPEAKER

SMOKE DETECTOR

(E) TUBULAR DAYLIGHT DEVICE

LEGEND: ALL REFLECTED CEILING PLANS

(E) RECESSED FLUORESCENTLIGHT FIXTURE RELOCATED

NEW SUPPLY AIR GRILLE, RE: MECH.

NEW RETURN AIR GRILLE, RE: MECH.

(E) SUSPENDED ACOUSTICAL CEILING TILE AND GRID TOBE REMOVED AND SALVAGE FOR REINSTALLATION ASREQUIRED FOR NEW MECHANICAL.

EXIT LIGHT

XX'-XX"A.F.F.

CEILING HEIGHT

EXISTING SUPPLY AIR GRILLE, RE: MECH.

EXISTING RETURN AIR GRILLE, RE: MECH.

(E) SUSPENDED ACOUSTICAL CEILING TILE AND GRID-PROTECT DURING CONSTRUCTION

NEW SUSPENDED ACOUSTICAL CEILING TILE AND GRID

(E) RECESSED FLUORESCENTLIGHT FIXTURE TO BE REMOVED AND SALVAGEFOR REINSTALLATION.

(E) GYP. BD. CEILING TO BE DEMOLISH AS REQ'DFOR STRUCTURAL & MECHANICAL WORK

(N) GYP. BD. CEILING MATCH (E), PATCH AND PAINTAS ORIGINAL CONDITIONS AFTER PERFORMEDSTRUCTURAL & MECHANICAL WORK

S

(E) GYP. BD. CEILING WITH POSSIBLE ASBESTOS, TOBE REMOVED AS REQ'D TO PROVIDE NEW MECH.DUCT ROOF PENETRATIONS.

ALL DEMO RCP'S

1. DEMO OR REMOVE (E) SUSPENDED ACOUSTICAL CEILING ASSEMBLY ASREQUIRED TO INSTALL NEW MECHANICAL OR WALLS. RE: MECHANICAL,STRUCTURAL & ELECTRICAL DWGS.

2. REMOVE (E) LIGHT FIXTURE ASSEMBLY AS REQUIRED FOR NEWMECHANICAL WORK. SALVAGE FOR REINSTALLATION. RE: ELECTRICALDWGS.

3. REMOVE MECHANICAL DEVICE, ETC. RE: MECHANICAL DWGS FOR FULLEXTENT OF DEMOLITION.

4. REMOVE (E) ALL FIRE ALARM ASSEMBLY COMPLETE: SMOKE DETECTORS.WIRING, PANEL AND DEVICES. RE: ELECTRICAL FOR FULL EXTENT OFDEMOLITION AND NEW INSTALLATION.

5. NOT USED.

6. REMOVE EXISTING GYP BD. ASSEMBLY AND (E) WD JOIST AS REQ'D TOINSTALL ROOF HATCH ACCESS. PROVIDE SHORING AS REQ'D . RE:STRUCTURAL. 2/A3.4 & 1/A3.3 - BID ALTERNATE #2.

7. REMOVE (E) CLG ASSEMBLY AS REQ'D TO INSTALL NEW STRUCTURALWORK. RE: STRUCTURAL DWGS.

8. (E) SINK VENT TO REMAIN, REMOVE COVER IF POSSIBLE TO HOLD DUCTTIGHT TO WALL, RE: PLUMBING.

9. REMOVE AND SALVAGE (E) CLOCK FOR REINSTALLATION. RE:ELECTRICAL.

10. ABATEMENT CONTRACTOR TO DEMOLISH AS REQ'D TO INSTALL (N)MECHANICAL DUCTS. RE: MECH. DWGS. FIELD VERIFY LOCATIONS (BYOWNER).

11. (E) SAC AND ALL OTHERS (E) DEVICES, (E) SOLATUBE TO BE RESET IN (N)CLG ELEVATION. RE: MECH AND ELECT DWGS.

12. CAREFULLY REMOVE PROJECTION EQUIPMENT COMPLETE TO INSTALL NEWDUCTWORK, REINSTALL. RE: ELECTRICAL DWGS.

13. REMOVE AND SALVAGE MAP ASSEMBLY FOR REINSTALLATION.

14. (E) SOLATUBE ASSEMBLY TO BE RELOCATED, CHECK WITH MECH. ELECT.AND FIELD VERIFICATION PRIOR TO BE REMOVED.

RCP DEMO NOTES:

2175 S. JASMINE ST.

DENVER CO 80222SUITE 217

FX: (303) 756-2332PH: (303) 691-8000

YON TANNERARCHITECTURE

MEC

HA

NIC

AL

UPG

RA

DE

FOR

:

PROJECT NO: 13121

ISSUE:

DATE: SEP 24, 2014

CHECKED:

DRAWN:

FILE NAME:

DWG NAME:

SHEET NO:

DO

UG

LAS

CO

UN

TY S

CH

OO

L D

ISTR

ICT

NO

RTH

EAST

ELE

MEN

TAR

Y S

CH

OO

L

PAR

KER

, CO

LOR

AD

O 8

0134

CONSTRUCTIONDOCUMENTS

6598

N. H

IGH

WA

Y 8

3

LZ-KS

RET

DEMOLITIONREFLECTEDCEILINGPLAN- AREA 1

AD2.1_DRCPA1

NORTH

1 SCALE: 1/8" = 1'-0"

DEMOLITION REFLECTED CEILING PLAN- AREA 1

AREA 1

AREA 2

AREA 3

KEY PLAN

REVISIONS:

ADDENDUM # 22

2

Page 43: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

ALL FLOOR PLANS

1. PATCH WALLS TO MATCH EXISTING -PAINT FULL WALL.

2. PATCH CARPET, SOLID DARK COLOR- COLOR BY ARCHITECT.

3. EXISTING FLOORING TO REMAIN, PROTECT DURING CONSTRUCTION.

4. PATCH OLD THERMOSTAT LOCATION AS REQ'D, IF NEW THERMOSTAT ISNOT LOCATED IN SAME LOCATION RE: MECHANICAL, MATCH EXISTING-PAINT FULL WALL.

5. PROVIDE J-MOLD AND CONTINUOUS SEALANT WHERE GYP. BD. MEETSEXISTING DISSIMILAR MATERIAL. (TYP.)

6. ALTERNATE #1, INSTALL NEW WALLS, 25 GA. 3 5/8" MTL. STUDS AT 16" O.C.WITH TOP AND BOTTOM TRACK. 5/8" TYPE 'X' GYP. BD. EACH SIDE.STUDS TO EXTEND TO UNDERSIDE OF EXISTING STRUCTURE. GYP. BD. TOEXTEND MIN. 4" ABOVE CEILING. FINISH, TEXTURE, AND PAINT TO MATCHEXISTING RE. DTL. 14/A4.2.

7. (N) TUBE STEEL COLUMN RE: STRUC. - PAINT- MATCH (E) WALL PAINTCOLOR.

8. PATCH CONC. SLAB, INSTALL # REBAR DOWELS. DRILL INTO (E) SLAB MIN4" AS REQ'D FOR 12" O.C. EPOXY GROUT DOWEL INTO SLAB., RE:STRUCTURAL- PATCH MATCH EXISTING FLOORING FINISHES AS REQ'D.

9. INSTALL (N) WALL 25 GA. 3 5/8" MTL. STUDS AT 16" O.C. WITH TOP ANDBOTTOM TRACK . 5/8" TYPE 'X' GYP. BD. ONE SIDE. STUDS TO EXTEND4" ABOVE (E) CLG, BRACING AS REQ'D. FINISH, TEXTURE, AND PAINT TOMATCH EXISTING BLOCKING FOR M.B. REQ'D.

10. REINSTALL SALVAGED CASEWORK, SCRIBE AROUND NEW COLUMNS.

11. ALT #3, NEW BOOKSELF, RE: DTL 5/A4.2.

12. REINSTALL SALVAGED BUILT-IN TABLE TOP. SCRIBE TABLE TOP TO WRAPAROUND NEW COLUMNS.

13. PATCH AND PAINT WALL AT OLD FIRE STROBE/HORN LOCATION, RE:ELECT.

14. NEW PUMPS, RE: MECHANICAL, ON (E) 4" CONCRETE HOUSEKEEPING PAD.

15. (E) 4" CONC. HOUSEKEEPING PAD TO REMAIN, ADD ADDITIONAL PADS TO(E) TO MEET NEW SIZE REQUIREMENTS. SIZES ARE FOR REFERENCE ONLY,RE: MECH & MFGR REQUIREMENTS FOR PROPER SIZING AND LOCATION.

16. 4" HIGH HOUSEKEEPING PAD FOR NEW BOILER, RE: MECH. DRILL INTO (E)PAD MIN 4" AS REQUIRED FOR 12" EPOXY GROUT DOWEL INTO (E) PAD.

17. (E) 4" CONC. HOUSEKEEPING PAD TO REMAIN.

18. INSTALL NEW CHILLER EQUIPMENT ON (E) CONCRETE PAD.

19. MODIFY (E) FENCE TO MAKE ROOM FOR (N) CHILLER MECHANICAL. RE:DTL. 12 & 13/A4.2

20. ALT #2, INSTALL NEW HATCH ROOF LADDER AND ROOF HATCH, RE: DTL.1& 2/A3.3.

21. REINSTALL (E) MARKER BD. BOARD TO BE MOUNTED WITH BOTTOM OFBOARD @ 30" ABOVE FINISHED FLOOR.

22. PROVIDE TWO NEW POWER OUTLETS, RE: ELECTRICAL

23. PROVIDE TWO (N) 3 WAYS SWITCHES AND MODIFY AS REQ'D EXISTINGLIGHTING CIRCUIT TO THIS NEW ROOM. (ALTERNATE # 1)

KEY NOTES:

WALLNORTHFLOOR BASE WALL

SOUTHEAST

WESTWALL

WALL

FINISH SCHEDULE

F.1 (E) FLO0RING TO REMAIN - PROTECT DURING CONSTRUCTIONF.2 (E) FLOORING TO REMAIN - PATCH TO MATCH EXISTING, OR AS

NOTED,AS REQUIRED FOR NEW CONSTRUCTIONF.3 PATCH CARPET- SOLID DARK COLOR, COLOR BY ARCHITECT.

B.1 (E) BASE TO REMAIN - PROTECT DURING CONSTRUCTIONB.2 (E) BASE TO REMAIN - PATCH TO MATCH EXISTING AS REQUIRED FOR

NEW CONSTRUCTIONB.3 4" BASE- MATCH EXISTING

C.1 (E) CEILING TO REMAIN - PROTECT DURING CONSTRUCTIONC.2 (E) CEILING TO REMAIN - PATCH CEILING ASSEMBLY TO MATCH (E)C.3 (E) GYPSUM CEILING TO REMAIN - PATCH & PAINT CEILING ASSEMBLY TO

MATCH (E)

W.1 (E) WALL TO REMAIN - PROTECT DURING CONSTRUCTIONW.2 (E) WALL TO REMAIN - MATCH (E) FINISH -PATCH & PAINT FULL WALLW.3 GYPSUM BOARD - PAINT

CEILING

ALL FLOOR PLANSGENERAL NOTES:FOR GENERAL NOTES SEE GENERAL NOTES SHEET A1.0

5TH GR. C.R. 151F.2 B.3 C.2 W.2

W.2W.2W.2

5TH GR. C.R. 152F.2 B.3 C.2 W.2

W.2W.2W.2

5TH GR. C.R. 154F.2 B.3 C.2 W.2

W.2W.2W.1

6TH GR. C.R. 166F.2 B.3 C.2 W.2

W.2W.2W.2

6TH GR. C.R. 162F.2 B.3 C.2 W.2

W.2W.2W.2

6TH GR. C.R. 161F.2 B.3 C.2 W.2

W.2W.2W.2

6TH GR. C.R. 165F.2 B.3 C.2 W.2

W.2W.1W.2

6TH GR. C.R. 163F.2 B.3 C.2 W.1

W.2W.2

W.2

6TH GR. C.R. 160F.2 B.3 C.2 W.2

W.2W.1W.2

HALLW

AY 1

64

F.1

B.1

C.2

W.2

W.2

W.2

W.25TH GR. C.R. 150

F.2 B.3 C.2 W.1W.2

W.2W.2

5TH GR. C.R. 153F.2 B.3 C.2 W.2

W.2W.1W.2

5TH GR. C.R. 155F.2 B.3 C.2 W.2

W.2W.2W.2

MECH. 120F.2 B.2 C.1 W.1

W.2W.1W.2

MEDIA OFF. 121F.2 B.2 C.1 W.1

W.1W.1W.2

BOYS 167F.1 B.1 C.1 W.2

W.1W.1

W.1

GIRLS 168F.1 B.1 C.1 W.1

W.1W.2

W.1

TEACHERS LOUNGE 106F.2 B.2 C.2 W.2

W.1W.1W.2

STAFF TOILET 108F.1 B.1 C.1 W.1

W.1W.1

W.2

SPECIAL EDUCATION 110F.1 B.1 C.1 W.1

W.1W.1W.1

CUST. SUPPLY 111F.1 B.1 C.1 W.1

W.1W.1

W.1

MAIN CUSTODIAL 112F.1 B.1 C.1 W.1

W.1W.1

W.1

BRT 123F.1 B.1 C.1 W.1

W.1W.1W.1

TO

ILET 1

13F.1

B.1

C.1

W.1

W.1

W.2

W.1

COMPUTER ROOM 124F.2 B.2 C.2 W.2

W.2W.2

W.1

LOUNGE VEST. 105F.1 B.1 C.1 W.1

W.1W.1

W.1

MEDIA CENTER 122F.2 B.2 C.2 W.1

W.1W.1

W.1

CORRIDOR 101F.2 B.2 C.2 - W.2

W.1W.2

CO

RR

IDO

R 1

02

F.1

B.1

C.2

W.1

-W

.1-

BOYS 157F.1 B.1 C.1 W.1

W.1W.1

W.2

GIRLS 158F.1 B.1 C.1 W.1

W.2W.1W.1

MECHANICAL 146F.1 B.1 C.1 W.1

W.1W.1

W.1

CUST. 119F.1 B.1 C.1 W.1

W.1W.1W.1

CUST. 118F.1 B.1 C.1 W.1

W.1W.1W.1

4TH GR. C.R. 145F.2 B.3 C.2 W.2

W.2W.1

W.1

4TH GR. C.R. 144F.2 B.3 C.2 W.2

W.1W.2

W.2

TEACHER WORK & SUPPLY 128F.2 B.3 C.2 W.1

W.2W.1W.2

4TH GR. C.R. 143F.2 B.3 C.2 W.1

W.2W.2W.2

4TH GR. C.R. 142F.2 B.3 C.2 W.2

W.2W.1W.2

4TH GR. C.R. 141F.2 B.3 C.2 W.2

W.2W.2W.2

4TH GR. C.R. 140F.2 B.3 C.2 W.2

W.2W.1W.2

STAFF TOILET 107F.1 B.1 C.1 W.1

W.2W.1

W.1TELEPHONE 109F.1 B.1 C.1 W.1

W.1W.1

W.1

CO

RR

IDO

R 2

03

COAT CLOSET 138F.1 B.1 C.1 W.1

W.1W.1

W.1

2

1

2

1

2

1

2

1

2

1

2

1

2

1

2

1

2

1

1

2

1

2

1

2

1

2

1

2

2

1

2

1

2

1

21

HALLW

AY 1

69

F.1

B.1

C.2

W.2

W.2

W.2

W.2

HALLW

AY 1

56

F.1

B.1

C.2

W.2

W.2

W.2

W.2

CO

RR

IDO

R 1

00

F.1

B.1

C.1

W.1

W.1

W.2

W.1

GIRLS 137F.1 B.1 C.1 W.1

W.1W.1

W.1

BOYS 136F.1 B.1 C.1 W.1

W.1W.1W.1

COAT CLOSET 135F.1 B.1 C.1 W.1

W.1W.1

W.1

COAT CLOSET 130F.1 B.1 C.1 W.1

W.1W.1

W.1

COAT CLOSET 133F.1 B.1 C.1 W.1

W.1W.1

W.1

GIRLS 132F.1 B.1 C.1 W.1

W.1W.2

W.1BOYS 131F.1 B.1 C.1 W.2

W.1W.1

W.1

CORRIDOR 103F.2 B.2 C.2 - W.2

W.1W.2

MATCH L

INE S

EE 1

/ A1.2

MATCH L

INE S

EE 1

/ A1.1

MATCH L

INE S

EE 1

/ A1.2

MATCH L

INE S

EE 1

/ A1.1

5/A4.25/A4.2

6/A4.2 6/A4.2

2

1

7

CUST. 117F.2 B.2 C.2 W.1

W.1W.1

W.2

LINE OF NEW MECHANICAL ABOVE

LINE OF NEW MECHANICAL ABOVE

5/A4.2

6/A4.2

5/A4.2

6/A4.2

5/A4.2

6/A4.2

5/A

4.2

6/A

4.2

5/A

4.2

6/A

4.2

5/A

4.2

6/A

4.2

5/A

4.2

6/A

4.2

6/A4.2

5/A4.2

6/A4.2

5/A4.2

6/A4.2

5/A4.2

6/A4.2

5/A4.2

6/A4.2

5/A4.2

5/A4.25/A4.2

4/A4.1 5/A4.1

5/A4.2

1210

2/A4.1

4

13

4

13

4 44

44

44 4 44 4

1/A4.1

LINE OF TUNNEL BELOW

LINE OF TUNNEL BELOW

LINE OF TUNNEL BELOW

LINE OF TUNNEL BELOW

12

MATCH L

INE S

EE 1

/ A1.1

MATCH L

INE S

EE 2

/ A1.2

MATCH L

INE S

EE 1

/ A1.1

MATCH L

INE S

EE 2

/ A1.2

20

8' M.B.8' M.B. 8' M.B.

2121

ALTERNATE #2

LINE OF TUNNEL BELOW

LINE OF TUNNEL BELOW

LINE OF NEW MECHANICAL ABOVE

3/A4.1

7 7

7 7 7

7

7

7

7

7

7

8

8

8

8

8

8

TYP.

8

8TYP. 8

8

8

TYP.

TYP.

TYP.

TYP. TYP.

TYP. TYP.

8

4

10

8' M.B.9

11

11 11 11 11 11

1111111111

11

11

11

11 11 11 11

ALTERNATE #3(BOOKSHELVES)TYPICAL ALLCLASSROOMS

22922

2175 S. JASMINE ST.

DENVER CO 80222SUITE 217

FX: (303) 756-2332PH: (303) 691-8000

YON TANNERARCHITECTURE

MEC

HA

NIC

AL

UPG

RA

DE

FOR

:

PROJECT NO: 13121

ISSUE:

DATE: SEP 24, 2014

CHECKED:

DRAWN:

FILE NAME:

DWG NAME:

SHEET NO:

DO

UG

LAS

CO

UN

TY S

CH

OO

L D

ISTR

ICT

NO

RTH

EAST

ELE

MEN

TAR

Y S

CH

OO

L

PAR

KER

, CO

LOR

AD

O 8

0134

CONSTRUCTIONDOCUMENTS

6598

N. H

IGH

WA

Y 8

3

LZ-KS

RET

FLOOR PLAN-AREA 1

A1.1_FPA1

NORTH

1 SCALE: 1/8" = 1'-0"

FLOOR PLAN- AREA 1

AREA 1 AREA 2

AREA 3

KEY PLAN

1

REVISIONS:

ADDENDUM # 1

ADDENDUM # 2

1

2

2

2

Page 44: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

1 SCALE: 1-1/2" = 1'-0"

H.M. HEAD DETAIL

DOOR ( RE: DOORSCHEDULE)

H.M. FRAME -PAINT

DOUBLE 20 GA. STUDHEADER W/ TRACK TOP ANDBOTTOM TO MATCH (E) WALLTHICKNESS

MTL. STUDS AT 16" O.C. W/ ONELAYER 5/8" TYPE 'X' GYP. BD.ON EA. SIDE -PAINT

5 3/4"DOOR ( RE: DOORSCHEDULE)

H.M. FRAME -PAINT

5 3

/4"

METAL STUD JAMBANCHORS, MIN. (3) PERJAMB

DOUBLE 20 GA. MTL. STUDS ATEA. JAMB W/ ONE LAYER 5/8"TYPE 'X' GYP. BD. ON EA. SIDE-PAINT

2 SCALE: 1-1/2" = 1'-0"

H.M. JAMB DETAIL

3-1/2" ACOUSTICAL BATT.INSULATION TO MATCH EXISTING

3-1/2" ACOUSTICAL BATTINSULATION TO MATCH EXISTING

BID ALTERNATE #1 BID ALTERNATE #1

SCALE: 1" = 1'-0"TYP MECHANICAL @ SOFFIT 9

REMOVE (E) STEEL ANGLEAND CUT 12" (E) TUBESTEEL

SCALE: 1" = 1'-0"CAGE DETAILS12

(N) TUBE STEEL MATCH (E)W/ SLAVE (4" DIA.APPROX. - F.V.)

1'-0"

CUT (E) POST ANDPROVIDE 16" SPACER ASREQ'D TO EXTEND 16"HEIGHT ABOVE (E)CONCRETE SLAB

1'-0"6"

(N) TUBE STEEL MATCH (E)

SCALE: 1" = 1'-0"CAGE DETAILS13

6"RELOCATED STANDARDSTEEL PIPE FENCEASSEMBLY SYSTEM

(E) STEEL CHAIN LINKFENCE TO REMAIN

(E) STEEL POSTRELOCATED AT 16" UPPER

(N) 16" LENGTH TUBESTEEL SPACER MATCH (E)DIAMETER (F.V.)

CONT. SMOOTH WELDED

CONT. SMOOTH WELDED

1'-4

" -

F.V

. W

ITH

MECH E

QUIP D

IMS

(N) 4x4 STEEL ANGLEWELDED TO TUBESUPPORT ANCHOR TOCMU W/ (2) 1/2" BOLT ATSAME LOCATIONS

(E) CMU WALL TO REMAIN

1'-4

"

CONT. SMOOTH WELDED

(E) CONCRETE SLAB TOREMAIN1'

-0"

(E) GLUE LAM BEAM TOREMAIN

1'-9

1/2

" (F

.V.)

(E) ROOFINGCONDITIONS TO REMAIN

(E) 2x10 JOIST @ 16" O.C.TO REMAIN (F.V.)

(E) PLYWOOD DECK TOREMAIN

10" Ø MAXMECHANICAL DUCT ,RE: MECH DWGS

(E) SUSP. CLG TILE TO REMAIN

9 1/

2" F.V

.

JOIS

T

SCALE: 1" = 1'-0"TYP MECHANICAL @ CLG15

1" INSULATION

(E) WALL TO REMAIN

(E) GLUE LAM BEAM TOREMAIN

1'-3

1/2

" (F

.V.)

(E) ROOFING CONDITIONS TOREMAIN

(E) 2x10 JOIST @ 16" O.C.TO REMAIN (F.V.)

(E) PLYWOOD DECK TOREMAIN

(E) SUSP. CLG TILE TO REMAIN

9 1/

2" F.V

.JO

IST

6"

SCALE: 1" = 1'-0"TYP MECHANICAL DUCTS @ P-LAM BEAMS17

10x8 TO 10" Ø MECH DUCTTRANSITION, RE: MECH. DWGSFOR LOCATIONS, TYP.

(E) SUSP. CLG TILE TO REMAIN

AIR SUPPLY DIFFUSER PERMECHANICAL

2'-1"

F.V

.

10" FLEXIBLE SUPPLY DUCT AIR,RE: MECH. DWGS, TYP.

1'-6"

PROVIDE 2X10 BLOCKING ASREQ'D @ MODIFIED JOISTSFRAMING, RE: STRUCT. DWGS

PROVIDE ENGINEERING SHORING AS REQ'DBEFORE TO PERFORM ANY STRUCTURALMODIFICATION, RE: SPECS

(E) WALL TO REMAIN

(E) GLUE LAM BEAM TOREMAIN

1'-3

1/2

" (F

.V.)

(E) ROOFINGCONDITIONS TO REMAIN

(E) 2x10 JOIST @ 16" O.C.TO REMAIN (F.V.)

(E) PLYWOOD DECK TOREMAIN

10" Ø MAX MECHANICAL DUCT ,RE: MECH DWGS

(E) SUSP. CLG TILE TO REMAIN

9 1/

2" F.V

.

JOIS

T

6"

1" INSULATION

AIR SUPPLY DIFFUSERPER MECHANICAL

SEE MECH DWGSFOR DUCTS SIZINGAND LOCATIONS

SEE MECH DWGSFOR DUCTS SIZINGAND LOCATIONS

SEE MECH DWGSFOR DUCTS SIZINGAND LOCATIONS

DO NOT INSULATE DUCT@ TRANSITION POINTWHERE DUCT PASSOVER BEAM IN ORDERTO FIT UNDER 2X4FRAMING.

PROVIDE (N)CHAIN LINK FENCEMATCH (E)

PROVIDE AS REQUIRED (16" HEIGHT APPROX ALL AROUND FENCE,[FIELD VERIFY SIZE]) STEEL CHAIN LINK FENCE (MATCH EXISTING)AS REQUIRED TO PRESERVE SECURITY OF MECHANICAL UNIT.

PROVIDE AS REQUIRED (16" HEIGHT APPROX ALL AROUND FENCE,[FIELD VERIFY SIZE]) STEEL CHAIN LINK FENCE (MATCH EXISTING) ASREQUIRED TO PRESERVE SECURITY OF MECHANICAL UNIT.

DOOR SCHEDULE

Jam

b

Typ

e

Mat

eri

al

Colo

r

Fin

ish

Typ

e

Mat

eri

al

Fin

ish

Colo

r

Head

DOOR SIZE#

FRAMEDOOR

Thr

esho

ld

Har

dwar

e

Mul

lion

Lab

el

Remarks

DETAILS MISC.

01 20 MIN * DOOR AND DOOR FRAME COLOR MATCH (E) ADJACENT, F.V. (ALTERNATE # 1)**FFWDA3'-0" X 7'-0" X 1-3/4" PTHM1 1/A4.2 2/A4.2 - 01

ROOM

BOOK ROOM 206

FACTORY FINISHFIRE RESISTANTHOLLOW METALPAINTWOOD - MATCH (E)

FFFRHMPTWD

DOOR SCHEDULE ABBREVS:DOORS:

2"

2"

FRAMES:

02 20 MIN**FFWDA3'-0" X 7'-0" X 1-3/4" PTHM1 1/A4.2 2/A4.2 - 01BOOK ROOM 206

03 20 MIN ** DOOR AND DOOR FRAME COLOR MATCH COLOR FINISHES FROM SIDING ****PTHMA4'-0" X 7'-0" X 1-3/4" PTHM1 - 02MECH. PENTHOUSE WEST

HARDWARE

01 SEE HARDWARE SPECIFICATIONS

02 SEE HARDWARE SPECIFICATIONS

2'-10

"

5 CLASSROOM BOOKSHELF

FINISH END

SCALE: 1/4" = 1'-0"

100048-34-13

FINISHED END

NOTE:-SECURE UNIT TO EXISTINGWALL-INSTALL OVER PATCHEDFLOOR FINISHES

(1) ADJUSTABLESHELF

100048-34-13

04 20 MIN****PTHMA4'-0" X 7'-0" X 1-3/4" PTHM1 - 02MECH. PENTHOUSE EAST

3/A4.2 4/A4.2

3/A4.2 4/A4.2

F. F. ATPENTHOUSE

ALUM.WINDOWLOUVER

8 WINDOW LOUVERSSCALE: 1/4" = 1'-0"

(ALTERNATE # 3)

** DOOR AND DOOR FRAME COLOR MATCH COLOR FINISHES FROM SIDING

10A4.2

2'

2'-6"

10A4.2

11A4.2

SIM.

A

4'-6"

* DOOR AND DOOR FRAME COLOR MATCH (E) ADJACENT, F.V. (ALTERNATE # 1)

1-1/2" TALLHELVETICA MEDIUMLETTERS RAISEDTEXT 1/32" HIGH

NOTE:CONTRASTINGBACKGROUNDCOLORS AND SIGNCOLORS TO BEDETERMINED

1" TALL HELVETICAMEDIUM LETTERSRAISED TEXT 1/32"HIGH

1/2" RADIUS-TYP.

7"

BRAILLE

NOTE:ALL ROOM DESIGNATION LETTERINGTO BE REVIEWED AND APPROVED BYOWNER PRIOR TO FABRICATION &INSTALLATION.

1"1"

1 1/

2"

1"

7"

2"

1 1/

2"

7 SCALE: 3" = 1'-0"

ROOM SIGN

H.M. DOOR ( RE:DOOR SCHEDULE)-PAINT

H.M. FRAME -PAINT

3" POLYISO.INSULATION

BLDG. WRAP ON 1/2" PLYWD

METAL SIDING PANEL

DOUBLE 6" 18 GA. MTL.STUDS AT EA. JAMB W/ONE LAYER EXTERIOR7/16" OSB ONEXTERIOR SIDE.

METAL STUD JAMBANCHORS, MIN. (3)PER JAMB

CHANNEL CLOSURE 4"ENDS LAP W/ CONT.CAULK AT LAPS

H.M. DOOR ( RE:DOOR SCHEDULE)-PAINT

H.M. FRAME -PAINT

DOUBLE 18 GA.STUD HEADER W/TRACK TOP ANDBOTTOM.

3" POLYISOC.INSULATION

BLDG. WRAP ON1/2" PLYWDSHEATHING

METAL SIDINGPANEL

10 1/2"

METAL DRIPFLASHING

10 1

/2"

CONT. SEALANT ANDBAKER ROD

CONT. SEALANT

3 SCALE: 3" = 1'-0"

H.M. HEAD DETAIL 4 SCALE: 3" = 1'-0"

H.M. JAMB DETAIL

METAL SIDINGPANEL

WALL SUPPORTSCALE: 3" = 1'-0'14

3 5/8" STUDSSECURED TO HEADOF STUD WALL @4'-0" O.C.

STAGGERED

4"

MIN

.

45°

MAX.

SUSPENDEDACOUSTICAL CLG

5/8" TYPE 'X' GYP.BD. BOTH SIDES ONMTL. STUDS @ 16"O.C.

3-1/2" ACOUSTICALBATT INSULATION

4"2"

DOUBLE 18 GA. STUDHEADER W/ TRACKTOP AND BOTTOM.

6" MTL. STUDS AT 16"O.C. W/ ONE LAYEREXTERIOR 7/16" OSBON EXTERIOR SIDE.

BLDG WRAP ON 1/2"PLYWD SHEATHING

MTL DRIP FLASHING

ALUMINUM EXTRUDEDLOUVERS, PERMECHANICAL

CONT. SEALANT

ALUM. SCREEN, TYP.

CONT. SEALANT

4 1/2"

10 SCALE: 3" = 1'-0"

LOUVER HEAD DETAIL

4"2"

CONT. SEALANT

ALUMINUM EXTRUDEDLOUVERS, PERMECHANICAL

ALUM. SCREEN, TYP.

TREATED WDBLOCKING

11 SCALE: 3" = 1'-0"

LOUVER SILL DETAIL

BID ALTERNATE #1

BID ALTERNATE #1

MTL TRIM CLOSURE

TREATED WOODBLOCKING

METAL FLASHINGSLOPE

6" MTL. STUDS AT 16"O.C. W/ ONE LAYEREXTERIOR 7/16" OSBON EXTERIOR SIDE.

6" MTL. STUDS AT 16"O.C. W/ ONE LAYEREXTERIOR 7/16" OSBON EXTERIOR SIDE.

MTL SIDING PANEL

BLDG WRAP ON 1/2"PLYWD SHEATHING

SCALE: 3/4" = 1'-0"FOUNDATION DETAIL16

(E) CMU WALL TOREMAIN

(E) CONCRETESLAB TO REMAIN

1'-8

" F.V

.1'-0

"STEEL COLUMNS,RE: STRUCTURALDWGS

1/2" GAP

(E) FOUNDATION

SEE STRUCTURALDWGS FOR SIZINGAND LOCATIONS

PATCH CONCRETESLAB AS REQ'D

4'-10

" F.V

.

2'-0" OR 3'-0"RE: STRUCTURAL

6"

F.V

.

TOOTH BRICK TO MACTH (E),MATCH (E) GROUT COLOR

FIELD VERIFY OPENING (E) BRICK

SCALE: 1/2" = 1'-0"EXTER. PATCH ELEVATION6

2175 S. JASMINE ST.

DENVER CO 80222SUITE 217

FX: (303) 756-2332PH: (303) 691-8000

YON TANNERARCHITECTURE

MEC

HA

NIC

AL

UPG

RA

DE

FOR

:

PROJECT NO: 13121

ISSUE:

DATE: SEP 24, 2014

CHECKED:

DRAWN:

FILE NAME:

DWG NAME:

SHEET NO:

DO

UG

LAS

CO

UN

TY S

CH

OO

L D

ISTR

ICT

NO

RTH

EAST

ELE

MEN

TAR

Y S

CH

OO

L

PAR

KER

, CO

LOR

AD

O 8

0134

CONSTRUCTIONDOCUMENTS

6598

N. H

IGH

WA

Y 8

3

LZ-KS

RET

DOORSCHEDULE &DETAILS

A4.2_SCH&DTL

MODEL #

HEIGHTDEPTHWIDTH

ALL CASEWORK BASED ON MODELNUMBERS AND SIZES FROM LSI CORP.

XXXX XX-XX-XX

REVISIONS:

ADDENDUM # 22

2

2

2

Page 45: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

2175 S. JASMINE ST.

DENVER CO 80222SUITE 217

FX: (303) 756-2332PH: (303) 691-8000

YON TANNERARCHITECTURE

REM

OD

EL F

OR

:

PROJECT NO: 13121

ISSUE:

DATE: OCT 10, 2014

CHECKED:

DRAWN:

FILE NAME:

DWG NAME:

SHEET NO:

DO

UG

LAS

CO

UN

TY S

CH

OO

L D

ISTR

ICT

NO

RTH

EAST

ELE

MEN

TAR

Y S

CH

OO

L

PAR

KER

, CO

LOR

AD

O 8

0134

CONSTRUCTIONDOCUMENTS

6598

N. H

IGH

WA

Y 8

3

(W) 303.936.1633

(F) 303.934.3299

[email protected]

6402 S. Troy Circle

Centennial, CO 80111

www.mep-eng.com

ELECTRICAL

SCHEDULES

JBP

DGM

Page 46: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

2175 S. JASMINE ST.

DENVER CO 80222SUITE 217

FX: (303) 756-2332PH: (303) 691-8000

YON TANNERARCHITECTURE

REM

OD

EL F

OR

:

PROJECT NO: 13121

ISSUE:

DATE: OCT 10, 2014

CHECKED:

DRAWN:

FILE NAME:

DWG NAME:

SHEET NO:

DO

UG

LAS

CO

UN

TY S

CH

OO

L D

ISTR

ICT

NO

RTH

EAST

ELE

MEN

TAR

Y S

CH

OO

L

PAR

KER

, CO

LOR

AD

O 8

0134

CONSTRUCTIONDOCUMENTS

6598

N. H

IGH

WA

Y 8

3

(W) 303.936.1633

(F) 303.934.3299

[email protected]

6402 S. Troy Circle

Centennial, CO 80111

www.mep-eng.com

ELECTRICAL

DEMOLITION

FLOOR PLAN-

AREA 2

JBP

DGM

AREA 1 AREA 2

AREA 3

Page 47: YON TANNER ARCHITECTURE P.C. A.I.A.€¦ · The hot water expansion tank and chilled water ... new chilled piping. 10. The chiller is provided ... Include data for woodpreservative

2175 S. JASMINE ST.

DENVER CO 80222SUITE 217

FX: (303) 756-2332PH: (303) 691-8000

YON TANNERARCHITECTURE

REM

OD

EL F

OR

:

PROJECT NO: 13121

ISSUE:

DATE: OCT 10, 2014

CHECKED:

DRAWN:

FILE NAME:

DWG NAME:

SHEET NO:

DO

UG

LAS

CO

UN

TY S

CH

OO

L D

ISTR

ICT

NO

RTH

EAST

ELE

MEN

TAR

Y S

CH

OO

L

PAR

KER

, CO

LOR

AD

O 8

0134

CONSTRUCTIONDOCUMENTS

6598

N. H

IGH

WA

Y 8

3

(W) 303.936.1633

(F) 303.934.3299

[email protected]

6402 S. Troy Circle

Centennial, CO 80111

www.mep-eng.com

ELECTRICAL

FLOOR PLAN-

AREA 2

JBP

DGM

AREA 1 AREA 2

AREA 3