1 beam plans for accelerator systems: the machine protection system jan uythoven on behalf of the...
TRANSCRIPT
1
Beam Plans for Accelerator Systems: The Machine Protection System
Jan UythovenOn behalf of the MPWG and the
MPS Commissioning WG
Special thanks to R.Schmidt, J.Wenninger, A.Macpherson
Jan Uythoven, AB /BT eLTC, 5 March 2008 2
Machine Protection System
Has to guarantee the Safe operation of the LHC under all circumstances
Hard work during all the different LHC ‘phases’: Design phase: done Construction phase of the individual equipment: almost done Individual System Testing (equipment): ongoing Global System Testing, MPS aspects
Talk Alick Macpherson, session 2 Hardware Commissioning Starting
Tests with beam Operation with beam
This Session
Jan Uythoven, AB /BT eLTC, 5 March 2008 3
Beam Interlock SystemBeam
Dumping System
Injection InterlockPowering
Interlockssc magnets
PoweringInterlocks
nc magnets
QPS(several 1000)
Power Converters
~1500
AUG
UPS
Power Converters
Magnets
Magnet Current Monitor
CryoOK
RFSystem
Movable Detectors
LHCExperiments
Beam LossMonitors
BCM
Experimental Magnets
CollimationSystem
CollimatorPositions
Environmentalparameters
Transverse Feedback
Beam ApertureKickers
BeamLifetimeFBCM
Screens / Mirrors
BTV
Access System
Doors EIS
VacuumSystem
Vacuumvalves
AccessSafetyBlocks
RF Stoppers
Beam loss monitors
BLM
SpecialBLMs
Monitorsaperture
limits(some 100)
Monitors in arcs
(several 1000)
Timing System (Post Mortem
Trigger)
Operator Buttons
CCC
SafeLHC
Parameter
SoftwareInterlocks
LHCDevices
Sequencer
LHCDevices
LHCDevices
Safe Beam Parameter
Distribution
SafeBeamFlag
Little beam dependence
View of the LHC - MPSCore Systems
Protection elements
Jan Uythoven, AB /BT eLTC, 5 March 2008 4
Tests with Beam
Some systems require ‘Machine Protection Tests’ with beam: Injection System and its Protection Elements Collimation System Beam Dump System and its Protection Elements Beam Loss Monitors FMCM
Generally not to test the hardware (done without beam) but to Check if the settings are ok Check if the assumptions – underlying the concepts used in
the ‘protection theory’ – is correct Check interdependency within systems
Treated by talks of the individual systems in this session Listed as tests in the procedures developed in the MPS Comm. WG
Jan Uythoven, AB /BT eLTC, 5 March 2008 5
The MPS hardware is working under nominal configuration: Beam dump request is only given when it is required No ‘false’ hardware interlocks via BIS No ‘false’ software interlocks via SIS Systems are brought into operation according to MPS commissioning plans
Depends on beam intensity and beam energy = commissioning phase Machine model is nominal, fitting to the corresponding phase :
Optics functions within tolerance (orbit, tunes etc.) properly corrected and within tolerances, beam intensity and energy within the pre-defined limits
Try to stick to ‘stable optics’ – avoid verification of MPS for new conditions Operational procedures related to Machine Protection ok:
Beam quality checks ok Post Mortem following beam dump fully understood Post Operational Checks (injection, beam dump) always ok
Daily Operation with BeamThe Ideal World
A system is required to restrict the operation within the well defined window:
• Clear procedures / limits known at all times: central place to keep this info!
• Software interlock on energy / intensity / optics? (e.g. limit operation at 2 TeV)
Be sure not to work outside the agreed upon conditions:
Jan Uythoven, AB /BT eLTC, 5 March 2008 6
Daily Operation with BeamThe Real World
Beam Dump, or no ‘green light’ to inject: operation Stopped
Safe, but degradation of the machine up-time: action desired
Not Safe to continue:Procedures – discipline of the operators, need clear limits and/or restrictionsCheck of MPS functionality under the different conditions / change interlock settings
Hardware malfunctioning or not available
Automatic Post Operational Checks stop operation
Produce interlock which needs resetting
No interlocks, but one does not fully understand what happened
Post Mortem Machine is not in nominal conditions
Different tunes, optical functions etc.
Previous Slide
Next Slide
Interlocks
No InterlocksUnsafe
Safe
Next Slide
Jan Uythoven, AB /BT eLTC, 5 March 2008 7
Beam Dump, or no ‘green light’ to inject: operation StoppedSafe, but degradation of the machine up-time: action desired
Can it be fixed within an acceptable delay
Y
Fix it
N
Possible toadjust the interlock level
or the settings to continue
Y
Acceptable?
Y
Adjust
Continue withDifferent beam conditions ?
(I , E, Optics)
Y
Acceptable?Useful?which?
Y
Adjust(SIS)
Disable the interlockY
Acceptable?
N
N
Y
Adjust
Follow-up
Follow-up
Follow-up
Stop the LHC,Restart after Repair
RBACMCS, …
RBACMCS, …
RBACMCS, …
N
Possible to mask?
Is this sufficient(I, E) Mask
Follow-upN
N
N
Y
Y
N
N
Jan Uythoven, AB /BT eLTC, 5 March 2008 8
Protection andBookkeeping
When Settings or Interlock Levels ’can be changed’, protection against ‘anybody’ doing this and errors in transmission. Talk V.Kain on Friday: Role Based Access Control
(RBAC) Management of Critical
Settings (MCS) Coherent list of equipment
where this is required Coherent list of people for the
specific equipment Need to do the bookkeeping of all
changes
RBACMCS, …
Change of Settings,Interlocks Disabled
Change of Settings,Interlocks DisabledTOOL
Jan Uythoven, AB /BT eLTC, 5 March 2008 9
Maskable InterlocksSafe Machine Parameters
Selected set of BIS interlocks or maskable: First step if unexpected interlock – during the beam commissioning
phase: can the interlock be masked? Agreed upon procedures, decided upon before the beam
commissioning started Foreseen especially for the commissioning phase Should be rather straight forward – done by EIC However: bookkeeping
Software Interlock System: Do we need to have maskable interlocks for the SIS (disabled with
safe beam)? Also ‘ RBAC like system’ on SIS? SIS talk by J.Wozniak on Friday
If we don’t trust our definition of ‘safe beam’ – Sector
test session: provoke quench – then we should NOT
use any maskable interlocks…
Jan Uythoven, AB /BT eLTC, 5 March 2008 10
Beam Dump, or no ‘green light’ to inject
Automatic protection, but degradation of the machine up-time: actions desired
Can it be fixed within an acceptable delay
Y
Fix it
N
Possible toadjust the interlock level
or the settings to continue
Y
Acceptable?
Y
Adjust
Continue withDifferent beam conditions ?
(I , E, Optics)
Y
Acceptable?Useful?which?
Y
Adjust(SIS)
Disable the interlockY
Acceptable?
N
N
Y
Adjust
Follow-up
Follow-up
Follow-up
Stop the LHC,Restart after Repair
RBACMCS, …
RBACMCS, …
RBACMCS, …
N
Possible to mask?
Is this sufficient(I, E) Mask
Follow-upN
N
N
Y
Y
N
N
Jan Uythoven, AB /BT eLTC, 5 March 2008 11
Beam Dump, or no ‘green light’ to inject
Automatic protection, but degradation of the machine up-time: actions desired
Y
Fix it
N
Possible toadjust the interlock level
or the settings to continue
Y
Y
Adjust
Continue withDifferent beam conditions ?
(I , E, Optics)
Y
Adjust
Disable the interlockY Adjust
Follow-up
Follow-up
Follow-up
Stop the LHC,Restart after Repair
RBACMCS, …
RBACMCS, …
RBACMCS, …
Possible to mask?
Mask
Follow-up
N
N
Y
Can it be fixed within an acceptable delay
Acceptable?
Acceptable?Useful?which?
Acceptable?
Is this sufficient(I, E)
Decision increasingly complicated to take
Advise / Discussion / Green light required
EIC can decide by
him/her-self
Advice from equipment specialist
Advice from ‘LHC
Protection Panel’
RBACMCS, …
+ ….
Jan Uythoven, AB /BT eLTC, 5 March 2008 12
Responsibilities
Engineer In Charge
Machine Coordinator Commissioner in Charge
Equipment Experts
Magnet Performance PanelIn place for ‘magnet protection’,
Already used during Hardw. Comm.
LHC Protection PanelConcerning MachineProtection System
A.Siemko, MPP meeting 21/09/2006
J. Uythoven, ‘Chamonix’ 2006
Jan Uythoven, AB /BT eLTC, 5 March 2008 13
Group of experts who have an overview of The nominal MPS
MPS MPSi
The actual state of the MPS The bookkeeping
Can’t foresee all permutations, can’t write procedures in case of failures beforehand, need experience with the actual systems and flexibility to adjust
See ‘Chamonix’ 2006 New: LPP members MPS Comm WG
This group of experts exists!
LHC Protection Panel
JET is operating since many years with a Machine Protection System Panel
Jan Uythoven, AB /BT eLTC, 5 March 2008 14
Examples BIS problem
STOP Asynchronous beam dump
Analysis by BT group of XPOC data If the result of the BT analysis is not clear:
Fix / replace doubtful equipment Series of runs of LBDS without beam Series of test dumps with low intensity beam Check interface to other equipment: RF, timing, …
BLM crate not working Repair If not possible, can change ‘Master Table’ (RBAC etc.) to continue with:
Safe beam? Pilot at 450 GeV? No beam
dIbeam/dt interlock available in a later stage, so been running with limited beam power without this interlock
If this system has a hardware problem: gives an interlock and stops operation Do we need to stop until it is fixed? Can we continue, but with limited beam power? Can we just continue?
BLM signals behind collimators giving higher values than normal When do we stop operation (only at interlock level?) How much time do we take to re-optimise collimator settings What do we do if we can’t get back in the old situation
Suddenly no losses measured on BLM collimators any more…!
Can take 10’s of hours out of physics: so cannot be decided on by individuals but needs support/weight of LPP BG
No interlocks or RBAC, but here LPP should be of help as well!
Jan Uythoven, AB /BT eLTC, 5 March 2008 15
The aim is to have a fully operational MPS, functioning under nominal conditions, all the time.
In all circumstances the state of the MPS should be known Inventory of ‘hardware’ which is not standard
Settings Interlock Levels Masking Disabling
In all circumstances the operational limits and conditions of the machine should be clear
For the standard conditions, depending on the commissioning phase
If one is allowed to only run under special conditions:
An LHC Protection Panel should be used to advise the EIC when significant changes to MPS systems and their settings need to be made to continue or optimise operation
This is at least the case when RBAC is required to make the change Once agreed upon to make a change to MPS (settings): procedures for doing this
Clear definitions of applying RBAC and MCS – coherent approach Who can make hardware changes? Obvious?
Do we need a kind of RBAC on the Software Interlock System? Maskable interlocks with Safe Beam on SIS?
Conclusions
Tool(s) required for keeping track of MPS conditions
Tool(s) required for keeping track of allowed machine conditions