3 project management project crashing
TRANSCRIPT
-
7/28/2019 3 Project Management Project Crashing
1/4
1
3 1
33 CHAPTER THREE
ProjectProjectManagement:Management:
Project CrashingProject Crashing
ProjectProjectManagement:Management:
Project CrashingProject Crashing
3 2
A project that your company has undertaken has the followingactivities, which are listed below:
ActivityPreceding
ActivityNormal time
(weeks)Normal cost
($)Crash time
(weeks)Crash cost
($)
ABC
DEFGHJ
--
A
CB, CD, E
FE, G
H
465
8108953
400060004000
300015006000200060003000
25-
47-7--
60006500
-
78003600
-6000
--
The normal costs shown for each activity are the costs to complete eachactivity by working under normal conditions. The crash time represents theshortest time in which the activity can be completed given the use of costlymethods of completion. Assume that it is possible to reduce the normal timeto crash time in steps of one week and that the extra cost will be proportionalto the time saved. In addition, there is a site cost of $1,500 per week.
Problem
-
7/28/2019 3 Project Management Project Crashing
2/4
2
3 3
1.1. Compute the crash cost per time period.Compute the crash cost per time period.
Crash costCrash costper periodper period ==
(Crash cost(Crash cost Normal cost)Normal cost)
(Normal time(Normal time Crash time)Crash time)
ActAct AA BB CC DD EE FF GG HH JJ
CCCC 10001000 500500 -- 12001200 700700 -- 20002000 -- --
MaxMax 22 11 -- 44 33 -- 22 -- --
2.2. Using normal activity times, find the criticalUsing normal activity times, find the criticalpath and identify the critical activities.path and identify the critical activities.
Determine the minimum cost of undertaking this
project and state its associated time of completion
3 4
A
4
40
B
6
60
Start
0
00
C
5
94D
8
179
E
10
199 F
8
2719 G
9
3627
H
5
4136J
3
4441
44414136
36272719199
19119440
93
Critical path:
A-C-E-F-G-H-J
Project Duration = 44 weeks
Total cost = $35,500+(44x1500)=$101,500
Network Diagram
-
7/28/2019 3 Project Management Project Crashing
3/4
3
3 5
Network Diagram - Crashing
A1000
2
4
40
B5001
6
60
Start
0
00
C--5
94D
12004
8
179
E7003
10
199F--8
2719G
20002
9
3627
H--5
4136J--3
4441
44414136
36272719199
19119440
93
OBJECTIVE minimize totalcost
One critical path min. crashcost per week on this criticalpath $700 (activity E) thencrash activity E by 2 weekswhy 2 weeks?
3 6
Network Diagram - Crashing
A1000
2
4
40
B5001
6
60
Start
0
00
C--5
94D
12004
8
179
E7001
8
179 F--8
2517 G20002
9
3425
H--5
3934J--3
4239
42393934
34252517179
1799440
93
Duration: 42
New Total Cost =101500+(700x2) (2x1500) =$99,900
Now two critical paths:ACDFGHJ & ACEFGHJ min.crash cost per week for both
paths$1000 (activity A) thencrash activity A by 2 weeks.
-
7/28/2019 3 Project Management Project Crashing
4/4
4
3 7
Network Diagram - Crashing
A1000
0
2
20
B5001
6
60
Start
0
00
C--5
72D
12004
8
157
E7001
8
157F--8
2315G
20002
9
3223
H--5
3732J--3
4037
40373732
32232315157
1577220
71
Duration: 40
New Total Cost =99,900+(1000x2) (2x1500) =$98,900
Two critical paths:ACDFGHJ &ACEFGHJSTOPsince min.crash cost per week for both
paths ($1200+$700) (D & E)greater than $1500site cost.