3M – Prairie du Chien2013 SHWEC Internship
Kara Klubertanz
Outline
•Sustainability Background (3P)•Project Objectives•Water Reduction
▫Process A▫Process B
•Discharge Investigation•Site Wide Water Management
Pollution Prevention Pays (3P)
•Pollution Prevention Pays (3P) program in 1975. ▫Goal - eliminate or reduce sources of
pollution in 3M products and processes
•10,000 3p projects since 1975. ▫Prevented > 3.8 billion lbs of pollution ▫Saved > $1.7 billion in their first year.
Project Objectives
•Assess water management for potential reuse or reduction▫Noncontact and contact cooling water
Main focus Process A Process B
Water Reduction• Background
▫Two processes Process A
Extrudes resin to form very thin nylon or polyester fibers
Process B Extrudes resin to form
vinyl or Nylon/polyester webbing material
▫Significant opportunity to improve water management
Process A
Process A
•Current water usage▫Extruder
10 GPM▫Quench Tanks
1 tank = 6 GPM All 8 tanks = 48 GPM Each tank vol.= 45 Gal.
▫Orient Tank Volume = 278 Gal.
Gal/yr Ft3/yr
Extruder 2,764,800 369,654
Quench Tanks
13,271,040
1,744,338
Orient Tank
26,688 3,568
Total 16,062,528
2,117,560
Process A
•Suggestion▫Reduce flow rate in Quench Tanks by 15%▫Decrease each Quench Tank volume by 1/3
Evaluate tank design
Process A
•Water Reduced▫2,003,136 gal/yr
•CO2 Emission Reduction▫6.016 Tons CO2/yr
•Cost Savings▫$10,867/yr
Process A•Potential future projects
▫Automatic valves▫Reuse Quench Tank discharge to supply
Orient Tank
Process B
Process B
•Current water usage▫Extruders
44 GPM▫Quench Tank
6-12 GPM Temperature
dependent 435 gallon tank
Gal/yr Ft3/yr
Extruders 12,165,120
1,626,477
Quench Tank
1,658,880- 3,317,760
221,792- 443,585
Total 13,824,000-
15,482,880
1,848,269-2,070,062
Process B
•Replace non-contact cooling water with an Air Cooled Oil Cooler▫Cools oil in extruders
•Implement in 4.5” extruder
Process B – Heat Exchanger
•Water Reduction▫6,082,560 gal/yr
•CO2 Emission Reduction▫ 16.843 tons CO2/yr
•Average Cost Savings▫$10, 540/yr
Discharge Investigation•Problem
▫2Q water bill increased•Research Highlights
▫Discharge Monitoring Reports
▫Production Schedules Inconsistent with
chart recorder▫Maintenance
Preparing Fire Water Tanks for inspection
Discharge Investigation
•Conclusion▫Meter
Possible obstruction or mechanical upset▫Evaluate data more frequently▫Cost Savings
$43,181
Site Wide Water Management
•Accurately meter & evaluate usage•Improve as products and operations
expand