6) Torque box assembly jig – 2 nos. (1 no. on each bay)
7) SCE assembly jig – 2 nos (1 no. on each bay)
8) SCE Upside down stand – 2 nos. (1 no. on each bay)
9) Front and Rear end Support stand – 2 nos. (1 no. on each bay)
10) Photogrametry (Q-Foto) – 2 nos. ( 1 no. on each bay)
11) Mirror pit (for mirror assembly) – 2 nos. (1 no. on each bay)
12) Balancing unit – 2 nos. (1 no. on each bay)
13) Trailers (SCA) – 8 nos to transport thro’ tractors to Solar field
14) Mirror storage bay – 2nos. (1 no on North & South side of SCA Building
15) Hydra cranes – 2 nos. to feed torque box frames on both bays
16) Fork Lift – 2 nos. to shift from main storage to both bays’ mirror pit
17) SCA building put up in 135 working days
18) Workmen – 120 (60 on each bay) for one 12 hrs shift
19) 5 engineers on each bay
In the month Sep ’12 Installation of Solar Collecting Element work started (Trial)
In the month Mar ’13 Solar field ready for generating Steam
In the month Mar ’13 Visit of Top Executives
In the month Mar ’13 Solar field ready for generating Steam
In the month Mar ’13 Solar field ready for generating Steam
In the month Mar ’13 Solar field ready for generating Steam
In the month Apr ’13 Steam blow on 28-04-2013
In the month Apr ’13 Top View for Power Block
In the month June ’13 Top View for Power Block
In the month June ’13 Power Block
In the month June ’13 Power Block
In the month June ’13 Water treatment plant
In the month June ’13 SWAS system in Power Block
In the month June ’13 Pipe rack
In the month June ’13 Ullage system in PB
In the month June ’13 Expansion Vessel Structure in PB
In the month June ’13 Expansion Vessel Structure in PB
In the month June ’13 View from Evaporation Pond
In the month June ’13 View from Evaporation Pond
In the month June ’13 View from North
In the month June ’13 Cross Over (Carrying HTF)
In the month June ’13 Cross Over (Carrying HTF)
In the month June ’13 Cross Over (Carrying HTF)
In the month June ’13 Nitrogen Skid in PB
In the month June ’13 Top of Pipe rack
In the month June ’13 Top of Pipe rack
In the month June ’13 Electrical building & Battery room
In the month June ’13 inside Electrical building
In the month June ’13 inside Battery room
In the month June ’13 1500 KVA DG Set
In the month June ’13 SST & UAT
In the month June ’13 Cooling Tower
In the month June ’13 Ware house and maintenance (50m * 25m*12m)
In the month June ’13 Raw Water Pond (450 m * 200 m * 8 m)
In the month June ’13 Condenser
In the month June ’13 Dearator
In the month June ’13 Turbine building
In the month June ’13 Solar Turbine supplied by Siemens
In the month June ’13 10.5 Switch gear room
In the month June ’13 GSU
In the month June ’13 132 KV Switch yard
In the month June ’13 Plantation of SCAs to Generate Heat in turn Electricity in Desert Like area
In the month June ’13 Plantation of SCAs to Generate Heat in turn Electricity in Desert Like area
In the month June ’13 Plant Model
In the month June ’13 Plant Model
In the month June ’13 Plant Model
In the month June ’13 Team Executed the task
In the month June ’13
After commissioning Team kept for attending operational issues
Lauren Jyoti., GGEL., 50 Mwe CSP., Nokh Rajasthan
Synopsys about the project
1) Area upgraded – 2000 m * 1000 m
2) No. of piling – 6000 (900mm dia * 3500 to 4000 mm depth)
3) Solar Structural Erection – 16039 MT
4) Solar Collecting assembly installed -5760 5) No. of mirrors erected – 161280 6) No. of Heat Conducting Elements (HCE tubes) transported and installed – 19280 of 4.2 m long. (SS tube surrounded
by Glass) – 72 KM 7) Total piping fabricated and erected – 52 KM 8) Equipment erected – 2750 MT 9) Other structures fabricated and erected – 600 MT 10) Total manpower deployed 1200 excluding civil labourers
11) Worked 24 * 7 for 14 months
Thus got commissioned on 19-06-13 as first CSP in India (Completed by 20 months from earth