7 ancillary services

Upload: fat

Post on 14-Jan-2016

221 views

Category:

Documents


0 download

DESCRIPTION

A chapter from a book, Fundamentals of Power System Economics

TRANSCRIPT

  • System Security andAncillary Services

    Daniel Kirschen

  • Daniel Kirschen 2005 2

    Introduction

    Electricity markets rely on the power system infrastructure

    Participants have no choice to use a different system

    Cost to consumers of outages is very high

    Consumer have expectations for continuity of service

    Cost of this security of supply must match its benefit

  • Daniel Kirschen 2005 3

    System security

    System must be able to operate continuously if situationdoes not change

    System must remain stable for common contingencies

    u Fault on a transmission line or other component

    u Sudden failure of a generating unit

    u Rapid change in load

    Operator must consider consequences of contingencies

    Use both:

    u Preventive actions

    u Corrective actions

  • Daniel Kirschen 2005 4

    Preventive actions

    Put the system in a state such that it will remain stable ifa contingency occurs

    Operate the system at less than full capacity

    Limit the commercial transactions that are allowed

  • Daniel Kirschen 2005 5

    Corrective actions

    Taken only if a disturbance does occur

    Limit the consequences of this disturbance

    Need resources that belong to market participants

    Ancillary services that must be purchased from themarket participants by the system operator

    When called, some ancillary services will deliver someenergy

    However, capacity to deliver is the important factor

    Remuneration on the basis of availability, not energy

  • Daniel Kirschen 2005 6

    Outline

    Describe the needs for ancillary servicesu Keeping the generation and load in balance

    u Keeping the security of the transmission network

    Obtaining ancillary servicesu How much ancillary services should be bought?

    u How should these services be obtained?

    u Who should pay for these services?

    Selling ancillary servicesu Maximize profit from the sale of energy and ancillary services

  • Needs for ancillary services

  • Daniel Kirschen 2005 8

    Balancing production and consumption

    Assume that all generators, loads and tie-lines areconnected to the same bus

    Only system variables are total generation, total load andnet interchange with other systems

    Generation Load Interchanges

  • Daniel Kirschen 2005 9

    Balancing production and consumption

    If production = consumption, frequency remains constant

    In practice:

    u Constant fluctuations in the load

    u Inaccurate control of the generation

    u Sudden outages of generators and interconnectors

    Excess load causes a drop in frequency

    Excess generation causes an increase in frequency

  • Daniel Kirschen 2005 10

    Balancing production and consumption

    Generators can only operate within a narrow range offrequencies

    u Protection system disconnects generators when frequency is toohigh or too low

    u Causes further imbalance between load and generation

    System operator must maintain the frequency withinlimits

  • Daniel Kirschen 2005 11

    Balancing production and consumption

    Rate of change in frequency inversely proportional tototal inertia of generators and rotating loads

    Frequency changes much less in large interconnectedsystems than in small isolated systems

    Local imbalance in an interconnected system causes achange in tie-line flows

    Inadvertent flow

  • Daniel Kirschen 2005 12

    Balancing production and consumption

    Inadvertent flows can overload the tie-lines

    Protection system may disconnect these lines

    Could lead to further imbalance between load andgeneration

    Each system must remain in balance

    Inadvertent flow

  • Daniel Kirschen 2005 13

    Balancing production and consumption

    Minor frequency deviations and inadvertent flows are notan immediate threat

    However, they weaken the system

    Must be corrected quickly so the system can withstandfurther problems

  • Daniel Kirschen 2005 14

    Example: load over 5 periods

    0

    50

    100

    150

    200

    250

    300

    1 2 3 4 5 Period

    Load [MW]

  • Daniel Kirschen 2005 15

    Example: energy traded

    0

    50

    100

    150

    200

    250

    300

    1 2 3 4 5 Period

    Load [MW]

  • Daniel Kirschen 2005 16

    Example: energy produced

    0

    50

    100

    150

    200

    250

    300

    1 2 3 4 5 Period

    Load [MW]

  • Daniel Kirschen 2005 17

    -150

    -100

    -50

    0

    50

    100

    1 2 3 4 5 Period

    Imbalance [MW]

    Example: imbalance

  • Daniel Kirschen 2005 18

    -150

    -100

    -50

    0

    50

    100

    1 2 3 4 5 Period

    Imbalance [MW]

    Example: imbalance with trend

    Random loadfluctuations

    Slower loadfluctuations Outages

  • Daniel Kirschen 2005 19

    Example (continued)

    Differences between load and energy traded:

    u Does not track rapid load fluctuations

    Market assumes load constant over trading period

    u Error in forecast

    Differences between energy traded and energy produced

    u Minor errors in control

    u Finite ramp rate at the ends of the periods

    u Unit outage creates a large imbalance

  • Daniel Kirschen 2005 20

    Balancing services

    Different phenomena contribute to imbalances

    Each phenomena has a different time signature

    Different services are required to handle thesephenomena

    Exact definition differ from market to market

  • Daniel Kirschen 2005 21

    Regulation service

    Designed to handle:

    u Rapid fluctuations in load

    u Small, unintended variations in generation

    Designed to maintain:

    u Frequency close to nominal

    u Interchanges at desired values

    Provided by generating units that:

    u Can adjust output quickly

    u Are connected to the grid

    u Are equipped with a governor and usually are on AGC

  • Daniel Kirschen 2005 22

    Load following service

    Designed to handle intra-period load fluctuations

    Designed to maintain:

    u Frequency close to nominal

    u Interchanges at desired values

    Provided by generating units that can respond at asufficient rate

  • Daniel Kirschen 2005 23

    Reserve services

    Designed to handle large and unpredictable deficitscaused by outages of generators and tie-lines

    Two main types:

    u Spinning reserve

    Start immediately

    Full amount available quickly

    u Supplemental reserve

    Can start more slowly

    Designed to replace the spinning reserve

    Definition and parameters depend on the market

  • Daniel Kirschen 2005 24

    Classification of balancing services

    Regulation and load following services:

    u Almost continuous action

    u Relatively small

    u Quite predictable

    u Preventive security actions

    Reserve services:

    u Use is unpredictable

    u Corrective security actions

    u Provision of reserve is a form of preventive security action

  • Daniel Kirschen 2005 25

    Example: Outage of large generating unit

    49.20

    49.30

    49.40

    49.50

    49.60

    49.70

    49.80

    49.90

    50.00

    50.10

    12:2

    4:00

    12:2

    4:30

    12:2

    5:00

    12:2

    5:30

    12:2

    6:00

    12:2

    6:30

    12:2

    7:00

    12:2

    7:30

    12:2

    8:00

    12:2

    8:30

    12:2

    9:00

    12:2

    9:30

    Primary response

    Secondary response

    Gas turbines

  • Daniel Kirschen 2005 26

    Network issues: contingency analysis

    Operator continuously performs contingency analysis

    No credible contingency should destabilize the system

    Modes of destabilization:

    u Thermal overload

    u Transient instability

    u Voltage instability

    If a contingency could destabilize the system, theoperator must take preventive action

  • Daniel Kirschen 2005 27

    Types of preventive actions

    Low cost preventive actions:

    u Examples

    Adjust taps of transformers

    Adjust reference voltage of generators

    Adjust phase shifters

    u Effective but limited

    High cost preventive actions:

    u Restrict flows on some branches

    u Requires limiting the output of some generating units

    u Affect the ability of some producers to trade on the market

  • Daniel Kirschen 2005 28

    Example: thermal capacity

    Each line between A and B is rated at 200 MW

    Generator at A can sell only 200 MW to load at B

    Remaining 200 MW must be kept in reserve in case ofoutage of one of the lines

    A B

    Load

  • Daniel Kirschen 2005 29

    Example: emergency thermal capacity

    Each line between A and B is rated at 200 MW

    Each line has a 10% emergency rating for 20 minutes

    If generator at B can increase its output by 20 MW in 20minutes, the generator at A can sell 220 MW to load at B

    A B

    Load

  • Daniel Kirschen 2005 30

    Example: transient stability

    Assumptions:

    u B is an infinite bus

    u Transient reactance of A = 0.9 p.u., inertia constant H = 2 s

    u Each line has a reactance of 0.3 p.u.

    u Voltages are at nominal value

    u Fault cleared in 100 ms by tripping affected line

    Maximum power transfer: 108 MW

    A B

    Load

  • Daniel Kirschen 2005 31

    Example: voltage stability

    No reactive support at Bu 198 MW can be transferred from A to B before the voltage at B

    drops below 0.95 p.u.

    u However, the voltage collapses if a line is tripped when powertransfer is larger than 166 MW

    The maximum power transfer is thus 166 MW

    A B

    Load

  • Daniel Kirschen 2005 32

    Example: voltage stability

    25 MVAr of reactive support at Bu 190 MW can be transferred from A to B before the outage of a

    line causes a voltage collapse

    A B

    Load

  • Daniel Kirschen 2005 33

    Voltage control and reactive support services

    Use reactive power resources to maximize active powerthat can be transferred through the transmission network

    Some of these resources are under the control of thesystem operator:

    u Mechanically-switched capacitors and reactors

    u Static VAr compensators

    u Transformer taps

    Best reactive power resources are the generators

    Need to define voltage control services to specify theconditions under which the system operator can usethese resources

  • Daniel Kirschen 2005 34

    Voltage control and reactive support services

    Must consider both normal and abnormal conditions

    Normal conditions:u 0.95 p.u. V 1.05 p.u.

    Abnormal conditions:u Provide enough reactive power to prevent a voltage collapse

    following an outage

    Requirements for abnormal conditions are much moresevere than for normal conditions

    Reactive support is more important than voltage control

  • Daniel Kirschen 2005 35

    Example: voltage control under normal conditions

    Load at B has unity power factor

    Voltage at A maintained at nominal value

    Control voltage at B?

    A B

    Load

    X=0.6 p.u.R=0.06 p.u.

    B=0.2 p.u. B=0.2 p.u.

  • Daniel Kirschen 2005 36

    -40

    -20

    0

    20

    40

    60

    80

    0 20 40 60 80 100 120 140 160 180 200 220

    Active Power Transfer [MW]

    Reac

    tive

    Pow

    er In

    ject

    ion

    [MV

    Ar]

    0.9

    0.95

    1

    1.05

    1.1

    Vol

    tage

    [p.

    u.]

    Example: voltage control under normal conditions

    Reactive injection at BVoltage at B

  • Daniel Kirschen 2005 37

    Example: voltage control under normal conditions

    Controlling the voltage at B using generator at A?

    Local voltage control is much more effective

    Severe market power issues in reactive support

    A B

    Load

    Power Transfer [MW] VB [p.u.] VA [p.u.] QA [MVAr]49.0 1.05 0.95 -68.3

    172.5 0.95 1.05 21.7

  • Daniel Kirschen 2005 38

    Example: reactive support following line outage

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    0 20 40 60 80 100 120 140

    Power Transfer [MW]

    Post

    -con

    tinge

    ncy

    reac

    tive

    pow

    er in

    ject

    ion

    at b

    us B

    [M

    VA

    r]

    A B

  • Daniel Kirschen 2005 39

    Example: pre- and post-contingency balance

    A B

    130 MW0 MVAr

    68 MW

    13 MVAr 0.6 MVAr136 MW

    26 MVAr

    68 MW

    13 MVAr

    65 MW

    0.6 MVAr

    65 MW

    1.2 MVAr

    0 MW

    1.0 p.u.1.0 p.u.

    A B

    130 MW0 MVAr

    145 MW

    40 MVAr

    145 MW

    40 MVAr 67 MVAr

    130 MW

    67 MVAr

    0 MW

    1.0 p.u.1.0 p.u.

    Pre-contingency:

    Post-contingency:

  • Daniel Kirschen 2005 40

    Other ancillary services

    Stability services

    u Intertrip schemes

    Disconnection of generators following faults

    u Power system stabilizers

    Blackstart restoration capability service

  • Obtaining ancillary services

  • Daniel Kirschen 2005 42

    Obtaining ancillary services

    How much ancillary services should be bought?

    How should these services be obtained?

    Who should pay for these services?

  • Daniel Kirschen 2005 43

    How much ancillary services should be bought?

    System Operator purchases the servicesu Works on behalf of the users of the system

    Services are used mostly for contingenciesu Availability is more important than actual usage

    Not enough servicesu Cant ensure the security of the system

    u Cant maintain the quality of the supply

    Too much servicesu Life of the operator is easy

    u Cost passed on to system users

  • Daniel Kirschen 2005 44

    How much ancillary services should be bought?

    System Operator must perform a cost/benefit analysisu Balance value of services against their cost

    Value of services: improvement in security and servicequality

    Complicated probabilistic optimization problem

    Should give a financial incentive to the operator toacquire the right amount of services at minimum cost

  • Daniel Kirschen 2005 45

    How should services be obtained?

    Two approaches:

    u Compulsory provision

    u Market for ancillary services

    Both have advantages and disadvantages

    Choice influenced by:

    u Type of service

    u Nature of the power system

    u History of the power system

  • Daniel Kirschen 2005 46

    Compulsory provision

    To be allowed to connect to the system, generators maybe obliged to meet some conditions

    Examples:

    u Generator must be equipped with governor with 4% droop

    All generators contribute to frequency control

    u Generator must be able to operate from 0.85 lead to 0.9 lag

    All generators contribute to voltage control and reactive support

  • Daniel Kirschen 2005 47

    Advantages of compulsory provision

    Minimum deviation from traditional practice

    Simplicity

    Usually ensures system security and quality of supply

  • Daniel Kirschen 2005 48

    Disadvantages of compulsory provision

    Not necessarily good economic policy

    u May provide more resources than needed and causeunnecessary investments

    Not all generating units need to help control frequency

    Not all generating units need to be equipped with a stabilizer

    Discourages technological innovation

    u Definition based on what generators usually provide

    Generators have to provide a costly service for free

    u Example: providing reactive power increases losses and reducesactive power generation capacity

  • Daniel Kirschen 2005 49

    Disadvantages of compulsory provision

    Equityu How to deal with generators that cannot provide some services?

    Example: nuclear units cant participate in frequency response

    Economic efficiencyu Not a good idea to force highly efficient units to operate part-

    loaded to provide reserve

    u More efficient to determine centrally how much reserve is neededand commit additional units to meet this reserve requirement

    Compulsory provision is thus not applicable to allservices

    How to deal with exceptions that distort competition?

  • Daniel Kirschen 2005 50

    Market for ancillary services

    Different markets for different services

    Long term contracts

    u For services where quantity needed does not change and availabilitydepends on equipment characteristics

    u Example: blackstart capability, intertrip schemes, power systemstabilizer, frequency regulation

    Spot market

    u Needs change over the course of a day

    u Price changes because of interactions with energy market

    u Example: reserve

    System operator may reduce its risk by using a combination of spotmarket and long term contracts

  • Daniel Kirschen 2005 51

    Advantages of market for ancillary services

    More economically efficient than compulsory provision

    System operator buys only the amount of service needed

    Only participants that find it profitable provide services

    Helps determine the true cost of services

    Opens up opportunities for innovative solutions

  • Daniel Kirschen 2005 52

    Disadvantages of market for ancillary services

    More complex

    Probably not applicable to all types of services

    Potential for abuse of market power

    u Example: reactive support in remote parts of the network

    u Market for reactive power would need to be carefully regulated

  • Daniel Kirschen 2005 53

    Demand-side provision of ancillary services

    Creating a market for ancillary services opens up anopportunity for the demand-side to provide ancillaryservices

    Unfortunately, definition of ancillary services often stillbased on traditional practice

    In a truly competitive environment, the system operatorshould not favour any participant, either from the supply-or demand-side

  • Daniel Kirschen 2005 54

    Advantages of demand-side provision

    Larger number of participants increases competition andlowers cost

    Better utilization of resources

    u Example:

    Providing reserve with interruptible loads rather than partly loadedthermal generating units

    Particularly important if proportion of generation from renewablesources increases

    Demand-side may be a more reliable provider

    u Large number of small demand-side providers

  • Daniel Kirschen 2005 55

    Opportunities for demand-side provision

    Different types of reserve

    u Interruptible loads

    Frequency regulation

    u Variable speed pumping loads

  • Daniel Kirschen 2005 56

    Who should pay for ancillary services?

    Not all users value security and quality of supply equally

    u Examples:

    Producers vs. consumers

    Semi-conductor manufacturing vs. irrigation load

    Ideally, users who value security more should get moresecurity and pay for it

    With the current technology, this is not possible

    u System operator provides an average level of security to all users

    u The cost of ancillary services is shared by all users on the basisof their consumption

  • Daniel Kirschen 2005 57

    Who should pay for ancillary services?

    Sharing the cost of ancillary services on the basis ofenergy is not economically efficient

    Some participants increase the need for services morethan others

    These participants should pay a larger share of the costto encourage them to change their behaviour

    Example: allocating the cost of reserve

  • Daniel Kirschen 2005 58

    Who should pay for reserve?

    Reserve prevents collapse of the system when there is alarge imbalance between load and generation

    Large imbalances usually occur because of failure ofgenerating units

    Owners of large generating units that fail frequentlyshould pay a larger proportion of the cost of reserve

    Encourage them to improve the reliability of their units

    In the long term:

    u Reduce need for reserve

    u Reduce overall cost of reserve

  • Selling ancillary services

  • Daniel Kirschen 2005 60

    Selling ancillary services

    Ancillary services are another business opportunity forgenerators

    Limitations:

    u Technical characteristics of the generating units

    Maximum ramp rate

    Reactive capability curve

    u Opportunity cost

    Cant sell as much energy when selling reserve

    Need to optimize jointly the sale of energy and reserve

  • Daniel Kirschen 2005 61

    Example: selling both energy and reserve

    Generator tries to maximize the profit it makes from thesale of energy and reserve

    Assumptions:

    u Consider only one type of reserve service

    u Perfectly competitive energy and reserve markets

    Generator is a price-taker in both markets

    Generator can sell any quantity it decides on either market

    u Consider one generating unit over one hour

    Dont need to consider start-up cost, min up time, min down time

    u No special payments for exercising reserve

  • Daniel Kirschen 2005 62

    pi1

    pi 2

    x2

    x1

    Pmin

    Pmax

    Rmax

    C1(x1)

    C2 (x2 )

    Notations

    : Market price for electrical energy (/MWh)

    : Market price for reserve (/MW/h)

    : Quantity of energy bid and sold

    : Quantity of reserve bid and sold

    : Minimum power output

    : Maximum power output

    : Upper limit on the reserve (ramp rate x delivery time)

    : Cost of producing energy

    : Cost of providing reserve (not opportunity cost)

  • Daniel Kirschen 2005 63

    Formulation

    f (x1, x2 ) = pi1x1 + pi 2x2 C1(x1)C2 (x2 )

    x1 + x2 Pmax

    x1 Pmin

    Objective function:

    Constraints:

    x2 Rmax Rmax < Pmax Pmin(We assume that )

    l(x1, x2 , 1, 2 , 3 ) = pi1x1 + pi 2x2 C1(x1)C2 (x2 )+ 1(P

    max x1 x2 ) + 2 (x1 Pmin ) + 3(R

    max x2 )

    Lagrangian function:

  • Daniel Kirschen 2005 64

    Optimality conditions

    lx1

    pi1 dC1dx1

    1 + 2 = 0

    lx2

    pi2 dC2dx2

    1 3 = 0

    l1

    Pmax x1 x2 0

    l2

    x1 Pmin 0

    l3

    Rmax x2 0

  • Daniel Kirschen 2005 65

    Complementary slackness conditions

    1 (Pmax x1 x2 ) = 0

    2 (x1 Pmin ) = 0

    3 (Rmax x2 ) = 0

    1 0; 2 0; 3 0

  • Daniel Kirschen 2005 66

    Case 1:

    No binding constraints

    Provide energy and reserve up to the point wheremarginal cost is equal to price

    No interactions between energy and reserve

    1 = 0; 2 = 0; 3 = 0

    lx1

    pi1 dC1dx1

    1 + 2 = 0 dC1dx1

    = pi1

    lx2

    pi2 dC2dx2

    1 3 = 0!!!!dC2dx2

    = pi2

  • Daniel Kirschen 2005 67

    Case 2:

    Generation capacity fully utilized by energy and reserve:

    Marginal profit on energy equal to marginal profit on reserve

    1 > 0; 2 = 0; 3 = 0

    lx1

    pi1 dC1dx1

    1 + 2 = 0

    lx2

    pi2 dC2dx2

    1 3 = 0

    x1 + x2 = Pmax

    pi1 dC1dx1

    = pi2 dC2dx2

    = 1 0

  • Daniel Kirschen 2005 68

    Case 3:

    Unit operates at minimum stable generation

    Marginal profit on reserve

    Marginal loss on energy minimized by operating at minimum

    KKT conditions guarantee only marginal profitability, not actual profit

    1 = 0; 2 > 0; 3 = 0

    lx1

    pi1 dC1dx1

    1 + 2 = 0

    lx2

    pi2 dC2dx2

    1 3 = 0

    x1 = Pmin

    dC1dx1

    pi1 = 2

    dC2dx2

    = pi2

  • Daniel Kirschen 2005 69

    Cases 4 & 5: 1 > 0; 2 > 0; 3 = 0 1 > 0; 2 > 0; 3 > 0

    Rmax < Pmax PminSince we assume that these cases are not interesting because the upper and lower limits cannot be binding at the same time

    x1 + x2 Pmax1 :

    x1 Pmin2 :

    x2 Rmax3 :

  • Daniel Kirschen 2005 70

    Case 6:

    Reserve limited by ramp rate

    Maximum profit on energy

    Profit on reserve could be increased if ramp rate constraint could berelaxed

    1 = 0; 2 = 0; 3 > 0

    lx1

    pi1 dC1dx1

    1 + 2 = 0

    lx2

    pi2 dC2dx2

    1 3 = 0

    dC1dx1

    = pi1

    pi2 dC2dx2

    = 3

    x2 Rmax

  • Daniel Kirschen 2005 71

    Case 7:

    Maximum capacity and ramp rate constraints are binding

    Sale of energy and sale of reserve are both profitable

    Sale of reserve is more profitable but limited by the ramp rateconstraint

    1 > 0; 2 = 0; 3 > 0

    lx1

    pi1 dC1dx1

    1 + 2 = 0

    lx2

    pi2 dC2dx2

    1 3 = 0

    pi1 dC1dx1

    = 1

    pi2 dC2dx2

    = 1 + 3

    x2 = Rmax

    x1 + x2 = Pmax

    x1 = Pmax Rmax

  • Daniel Kirschen 2005 72

    Case 8:

    Generator at minimum output and reserve limited by ramp rate

    Sale of reserve is profitable but limited by ramp rate constraint

    Sale of energy is unprofitable

    Overall profitability needs to be checked

    1 = 0; 2 > 0; 3 > 0

    lx1

    pi1 dC1dx1

    1 + 2 = 0

    lx2

    pi2 dC2dx2

    1 3 = 0

    pi1 dC1dx1

    = 2

    pi2 dC2dx2

    = 3

    x2 = Rmax

    x1 = Pmin