a120 bypass (little hadham) - hertfordshire · 2018-08-22 · the project promoter will be required...

23
www.hertsdirect.org A120 Bypass (Little Hadham) Gateway & Business Case Presentation

Upload: others

Post on 24-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

A120 Bypass (Little Hadham)

Gateway & Business Case Presentation

Page 2: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

Overview of ProblemHighway issues:•Signal controlled staggered crossroads in village causes congestion (A120 is one-way through the signals).•Proximity of adjacent historic buildings limit online options.•Instances of vehicles hitting buildings within the village.

Other associated issue:•Flooding within the centre of the village (most recent in Feb 2014).

Signalised Cross Roads in Little Hadham

Little Hadham

Bishop’s Stortford

StanstedAirport

Page 3: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

Overview of FloodingAssociated issue:•Flooding within the centre of the village (most recent in Feb 2014).

Page 4: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

Overview of Scheme• 3.9km Single Carriageway Bypass• 3 Flood Attenuation/Storage Areas (delivered as part of the scheme

in collaboration with the Environment Agency)

Flood Storage Area

Roundabout Roundabout

Albury Road Overbridge

Agricultural Bridges

Page 5: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

Governance Framework

Page 6: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

HCC Project Stages and GatewaysStage Gateway

Stage 1 - InitiationGateway 1 - Inception

Stage 2 – Option TestingGateway 2 - Feasibility

Stage 3 – Preferred Option Business case

Gateway to be passed Gateway 3 – Programme EntryStage 4 -Design

Gateway 4 – Conditional ApprovalStage 5 -Procurement

Gateway 5 – Final ApprovalStage 6 – Delivery

Gateway 6 - CompletionStage 7 - Maintain & Operate

Page 7: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

Gateway 3 RequirementsThe project promoter will be required to provide evidence that the following criteria have been met within its request to pass through Gateway 3:

– Business Case approved following independent review– Updated Budget, Funding and Cashflow Requirements Identified for

Stage 4– Indicative Budget, Funding and Cashflow Requirements Identified for

Stages 5, 6 & 7– Approvals to Seek Statutory Powers Secured– All Legal Agreements Identified– Consultation and Communication Strategy for Stage 4 Identified– Post Completion Monitoring Regime Identified– Governance Framework Completed Quantitatively for Stage 4 and

Qualitatively for Stages 5, 6 &7

Page 8: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

Business CaseGateway 3 Requirement - Business Case approved following independent review

A120 Business Case structure:–Background–Strategic Case –Economic Case–Financial Case–Commercial Case–Management

Page 9: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

Business Case - ObjectivesObjectives:1. To decrease the journey time along the A120 between Bishop’s Stortford and the A10 by providing a local bypass at Little Hadham in scale with the other sections of the route by 2019.2. To reduce the risk of fluvial flooding in Little Hadham and communities to the south by working with the Environment Agency to deliver integral flood attenuation areas as part of the delivery of the bypass.3. To reduce severance in the centre of Little Hadham by removal of the majority of the through traffic congestion and, as a result,improving the overall well-being of residents in Little Hadham.

Page 10: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

Business Case – Key Outcomes

• Benefit to Cost Ratio– 9.1 (early schemes BCR 7.86)– Does not include Wider Economic Benefits or those

associated with the flood storage.• Total funding required for bypass scheme is £29.86m

including inflation.• Categorised as a Local Major Transport Scheme.• Contract strategy to be agreed, but likely to be a D&B.

Page 11: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

Key Issues and Risks• LEP funding not secured

– In SLGF Bid as high priority• Poor collaboration with Environment Agency

– MOU almost signed off– Collaboration Agreement being negotiated

• Required land not secured– Offer to acquire land - negotiations on-going

• Programme Risks due to unknown Issuese.g. Archaeology, Protected Species

– Robust assessment planned for 2014/15– Programme includes some capacity for delay

• Competition for Competent Contractors (Dam)– Begin engagement with Contractors once funding secured

Page 12: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

Key Scrutiny Outcomes• Stakeholder, Partners and Inter-dependencies Risk to Delivery

– MOU with EA developed, other stakeholder workshops and engagement planned.

• Reliance on previous Optioneering Work subject to challenge– Workshop already held to review previous work, further consideration will be

undertaken as required.

• Modelling Benefits and Journey Time Information deviation from process– Updated traffic modelling work planned and commissioned to be complete by

mid 2014.

• Scheme Costs and Affordability Risk– Funding routes identified and approval of funding by LTB, LEP and EA being

sought.

Page 13: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

Programme

2014 2015 2016 2017 2018 2019 2020

Gateway 3 – Programme Entry

Stage 4 – Preliminary Design & Planning ApplicationGateway 4 – Conditional Approval

Stage 5 – Procurement

Gateway 5 – Final Approval

Stage 6 – Delivery (D&B)

Gateway 6 – Completion

Stage 7 – Maintain and Operate

Page 14: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

Budget, Funding and Cashflow

2014/15 2015/16 2016/17 2017/18 2018/19

Stage 4 – Preliminary Design & Planning Application

£0.65m £1.13m

Stage 5 – Procurement £0.76m

Stage 6 – Delivery (D&B) £10.93m £16.26m

Stage 7 – Maintain and Operate

Programme of costs 2015-19

Page 15: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

Funding SourcesFunding Source Amount (£m)

Project Sponsor (HCC) £1.55m

Growth Fund (LTB) £18.5m

Environmental Agency sources

£1.0m

Stansted Airport Ltd/S106 £0.33m

Growth Fund (LEP) £8.48m

Total £29.86m

Page 16: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

Cost Profile (including inflation)Financial

Year2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total

HCC £0.12m £0.65m £0.68m £0.10m £0 £0 £1.55m

LTB £0 £0 £0.45m £0.66m £10.93m £6.45m £18.50m

LEP £0 £0 £0 £0 £0 £9.81m £9.81m

Total £0.12m £0.65m £1.13m £0.76m £10.93m £16.26m £29.86m

Page 17: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

Statutory ProcessCompleted:• Preferred Route identification process undertaken in 2008. • “Authorisation to proceed with Statutory Processes including applying for Planning Permission, Side Roads Orders and Compulsory Purchase Orders to enable delivery of the A120 LittleHadham Bypass” obtained via

– H&WM Panel endorsement (18 March 2014) and

– Cabinet authorisation (24 March 2014).

Page 18: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

Statutory ProcessTo be completed:•Side Road Orders / TROs•Rights of Way diversions•Compulsory Purchase Orders (if required)•Joint Planning Permission Application to HCC for bypass and for flood storage area•SUDS Approval (following consultation in early stages to be completed formally by D&B Contractor)

Page 19: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

Legal Agreements• Memorandum of Understanding in place with

Environment Agency• Collaboration Agreement with EA (to set out detail under

MoU) to be developed during Stage 4• Any associated agreements following potential land

purchase will be developed as appropriate.

Page 20: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

Stakeholder Engagement Strategy (Stage 4)• Public Consultation Events undertaken as part of previous schemes• Business Case Identifies:

– Public and stakeholder engagement will be a key part of the delivery of the project.

– Statutory Consultees and other key stakeholders will be engaged throughout the scheme assessment and delivery process.

– We will hold Environmental Liaison Group Meetings (ELG) throughout the environmental assessment process.

– Public information events and one-to-one meetings with potentially directly affected landowners and other interested parties

• Stakeholder Mapping Exercise undertaken i/c EA• Stakeholder Engagement Activity Plan to be produced in Q1 14/15• Letters have already been sent to landowners and Councillors

about environmental surveys and project website set up with FAQ.

Page 21: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

Post Completion Monitoring RegimeStrategy developed in accordance with DfT guidance in order to measure the effectiveness of the intervention in meeting the scheme objectives. Strategy based upon two elements:•Assessment of data that is already collected by the county council on a before and after basis; and•Collection and assessment of data collected specifically for the purpose of developing and appraising the scheme.The results will be reported in a Before and After Study to be produced one year after full scheme opening. Evaluation of the scheme based upon the monitored impacts and outcomes will be reported in the study.

Further specific monitoring arrangements for each objective detailed within the Business Case.

Page 22: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment

www.hertsdirect.org

Stage 4 Programme/Milestones2014 2015

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Gateway 3 – Programme Entry

Flood Modelling Work (EA)

Traffic Model Update

Preliminary Scheme Design

Environmental Surveys

Environmental Assessments

Preparation of Planning Application

Submission of Planning Application

Planning Process

Public Inquiry (if required)

Gateway 4 – Conditional Approval

Page 23: A120 Bypass (Little Hadham) - Hertfordshire · 2018-08-22 · The project promoter will be required to provide evidence that the ... (ELG) throughout the environmental assessment