ado-po / tc meeting 05th july2018

21
ADO - PO / TC meeting 05 th July2018 ATLAS Design Office Raphael Vuillermet

Upload: others

Post on 09-May-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ADO-PO / TC meeting 05th July2018

ADO-PO / TC meeting05th July2018

ATLAS Design Office

Raphael Vuillermet

Page 2: ADO-PO / TC meeting 05th July2018

• Raphaël Vuillermet Design office supervisor & Project Engineer

• Giancarlo Spigo RSO & Project Engineer• Tatiana Klioutchnikova Integration & Project Engineer• Joffrey Malaquin Opening operations & Project Engineer• Claudio Bortolin ATLAS cooling activities & Project Engineer• Marco Ciapetti EAM, Services• Tomasz Blaszczyk Fellow• Julien Migne• Wim Van Emden• Vit Zahradnik 50% TC / 50% ITK• Alexander Seletskiy• Lorenzo Quercia Fellow• Shuvay Singh Project Associate• Peter Kulka Project Associate

• Jamie Pinnell Workshop and Design Office• Gevorg Akhperjanyan Workshop and Design Office• Didier Bertet Logistic support and safety

Resources in ATLAS Design Office

05th of July 2018

Page 3: ADO-PO / TC meeting 05th July2018

• LS2 preparation

– nJD/nSW

– BIS7&8

– ITK trial test for transport

• LS3

– Muon BI project

– ITK

– ID decomissioning

Activities Overview

05th of July 2018

Page 4: ADO-PO / TC meeting 05th July2018

LS2 - nJD/nSW

05th of July 2018

• Since November – Scaffolding has been installed

– Services has been installed on HO and IP faces

• TC has followed the production of:– the Hub (Giancarlo)

– The KM (Raphael)

– The service bracket (Raphael)

• TC has assembled (Christian, Jamie)– The 2 hubs main part

– The 2 hubs extension

• TC has installed – The piping for the movement system

(Armen, Fred)

– The hub (Christian, Armen, Raphael)

Page 5: ADO-PO / TC meeting 05th July2018

LS2 - nJD/nSW

05th of July 2018

• NSW production follow-up (Raphael)

– The production of the NSW is going-on in Georgie

– The first Small Sector assembly was done last week

– Delivery for transport is organised

o Picking on 10th of July for the first 4 Small Sector Spokes

o Picking on 20th of July for the remaining 4 Small Sector Spokes

o Picking on 7th of August of the second Small Sector set

– Delivery of the 2 Large Sector Spokes beginning of September

• NSW installation (Christian, Jamie)

– The assembly will start on 23rd of July, NSW-A followed by NSW-C up to the end of September

– The assembly will involved several teams

o Alignment bar

o services team (fixation of cable tray)

o TC members for the mechanical assembly

Page 6: ADO-PO / TC meeting 05th July2018

1. Injection of the resign for the shear pin of the hub (August 20th) (Julien)

2. Installation of the IP tagger disk (Christian, Jamie, Raphael)

3. Repositioning of the service brackets once the Small Sector spokes are assembled (Christian, Jamie + services team)

4. Design / production drawings (Julien)

– IP face stoppers

– Organise and finalise the CAD model in the Smart Team database

LS2 - nJD/nSW

05th of July 2018

Page 7: ADO-PO / TC meeting 05th July2018

LS2 - nJD/nSW

05th of July 2018

NSW + services envelope

5. Envelope (Alexandre, Tatiana)

– Check and control that the assembly of services and mechanical parts are within defined and approved envelops

6. Movement system (Tomasz, Michel)

– Produce the new Z- bracket for traction

Page 8: ADO-PO / TC meeting 05th July2018

7. nSW – design access platform in sector 3 (Alexander)

o To access the nSW LV patch panel in

8. Design platform on sector 11 and 15 (Gevorg)

To access

o NSW electronics ,

o feet of JD

o calorimeter access

LS2 - nJD/nSW

05th of July 2018

Page 9: ADO-PO / TC meeting 05th July2018

LS2 - nJD/nSW other production

05th of July 2018

• The design and production of the different tooling is finished.

9. Assembly procedure shall be prepared for (Julien, Raphael)

– Small sector spokes

– Small Sector chambers installation

– Large sector spokes

– Large sector chamber installation

item sub-item Delivery date(s) Satus

nJD steel structure, tagger, Jul 17 - Sep 17 Delivered

nSW nSW 01/07/18 production

Stainless steel envelop 01/12/17 Delivered

Copper disk 01/02/17 Delivered

A-plate stainless steel 05/12/17 Delivered

steel parts 15/07/17 Delivered

polyboron and PE parts 06/10/17 Delivered

Lead parts 15/07/17 Delivered

fixation screw 01/09/17 Delivered

Springs 15/09/17 Delivered

Services brackets flexible chain support 15/02/18 Delivered

LS spherical joint proto 01/03/17 Delivered

LS 15/06/18 Delivered

SS 15/06/18 Delivered

Alignement bar KM 01/09/17 Delivered

Air pad extension 29/09/17 Delivered

Hub

Shielding elements

KM

Page 10: ADO-PO / TC meeting 05th July2018

10. Assembly work in b191 (Christian, Jamie, Armen)

– Hub

– nSW spokes (Small Sector)

– Services brackets

– Small Sector assembly

11. MM + sTGC mechanical connection (Louis)

12. Cooling (Claudio, Piotr, Peter, Marco)

– Integrate the cooling lines from flexible chain up USA15

– Installation and commissioning of a cooling set up in BB5

13. Assembly follow-up and scheduling (Raphael & Ana)

LS2 - nJD/nSW

05th of July 2018

Page 11: ADO-PO / TC meeting 05th July2018

12. Transport FDR review took place at the end of April and the procurement process of the different tooling is progressing

– nJD/nSW (Pavel, Raphael)o Launch the procurement of The Resting frame+ covering structure

o Follow up the procurement and production of the lifting tool

o Follow up the internal production of the transport frame (Jamie, Alain, etc.)

– JD/SW (Pavel, Joffrey)o Update and refresh the procedure to extract and prepare SW for the transport

– Transport operation (Pavel, Raphael)o Prepare technical specification for the transport of the SW and nSW in partner ship with

EN-HE

LS2 - nJD/nSW

05th of July 2018

Lifting tool Covering structure

Resting frame

Transport frame

13. nSW logistic (Didier)Organise the transport of component between BB5 and b180/b191Organise the reception of material and delivery up to the assembly/storage hallOrganise expedition of material to institutes

Page 12: ADO-PO / TC meeting 05th July2018

LS2 - nJD/nSW assembly schedule up to end of 2018

05th of July 2018

Installation of small sectors on end of 2018 ?

Pre-assembled hub extension

Hub installation on NJD-A

Small sector spokes installation on NJD-A

Hub installation on NJD-C

Small sector spokes installation on NJD-C

Page 13: ADO-PO / TC meeting 05th July2018

• Tooling already manufactured

– Transport frame

• Tooling to produce

– Test frame

LS2 - Installation BIS78

05th of July 2018

Page 14: ADO-PO / TC meeting 05th July2018

LS2 - Installation BIS78

05th of July 2018

• Preparations for the installation of 16x BIS78 chambers: (Tatiana)

1. Removal of the Force Transfer Bracket

o Finalise the design the tool, control all interfaces (Wim)

o Launch the production of the tooling and organise the reception test (Wim)

o Design new support for the rubber plates (Tomasz)

o Prepare ECR (Tatiana)

2. Remaining production for the installation :

o Produce rails reinforcement

o Produce reinforced brackets

o Produce rail extension for installation

Page 15: ADO-PO / TC meeting 05th July2018

LS2 - Installation BIS78 – access IP side

05th of July 2018

Page 16: ADO-PO / TC meeting 05th July2018

LS2 - Installation BIS78 – access HO side

05th of July 2018

3. Prepare access procedure studied by Lorenzo, Gevorg, Tatiana, Michel

Page 17: ADO-PO / TC meeting 05th July2018

4. Prepare and update integration drawings and services routing(on the chamber).(Alexandre)

5. Identify BIS78 services routing from chamber to rack in USA15 (Peter, Marco)

o Prepare intervention

6. Schedule the intervention (Tatiana, Michel)

o June 2019 for side A and June 2020 for side C but depend on the readiness of the nSW

LS2 - Installation BIS78

05th of July 2018

Page 18: ADO-PO / TC meeting 05th July2018

1. Installation tooling – for “dry run” lowering during LS2 to validate installation paths (Julien, Joffrey)

1. Finalise the design and prepare production drawings

2. Launch procurement process

3. Follow up production (internally or externally)

LS2 - ITK

05th of July 2018

1- BT vacuum pipe

2- Forward platform S3

BT vacuum pipe

Forward platform S1

Arches stair

1. ITk Outer Cylinder Mockup 2. Lifting device 3. Platform on top of Ext. Barrel

Page 19: ADO-PO / TC meeting 05th July2018

2. Baby Demo - Cooling mock-up (Claudio, Piotr, Michal, Lukasz)

– Finish the installation of

o The Manifold box

o The Warm nose

o The new pump

– Reinforce the Truss structure and move the vertical pillar to allow mock-up activities for ID decommissioning

– Commission the cooling plant

– Perform test for the ITK (start in August)

o With Ø 60mm flexible concentric line

o With detector structure prototype test

– Optimise the performance …

LS2 - 2018

05th of July 2018

Cooling plant

Page 20: ADO-PO / TC meeting 05th July2018

1. Integration of ITK PP2 boxes (Vit)

– Integration activities in the area, design, connectivity, etc…

2. ID decommissioning (Vit)

– VI extraction tooling - prepare production drawings for the tooling

– IBL interface with extraction tooling – prepare production drawings

LS3- ITK

05th of July 2018

Page 21: ADO-PO / TC meeting 05th July2018

• Design activity for BIL (Lorenzo, Tatiana)

– Define RPC layout

These chambers will be installed on the external face of the BIL During LS3

o Define envelope and layout such that installation is feasible.

o Definition of the installation scenario

– Preliminary design of the RPC frame for BIL

• Study the EIL4 translation and rotation (Shuvay)

– Check the accessibility during the operations and propose solution

– Study the EIL4 movement (translation and rotation)

o Study the rail extension and its external support

o Check that safe working access exists or is possible

LS3 - BIL

05th of July 2018