amats: mountain a rive extension
TRANSCRIPT
AMATS: MOUNTAIN AIR DRIVE
EXTENSION
Project No.: UAA CED 2021.02
DESIGN STUDY REPORT
ALASKA
DEPARTMENT OF TRANSPORTATION
AND PUBLIC FACILITIES
PREPARED BY: Engifar, Inc
2900 Spirit Dr
Anchorage AK 99508
April 2021
ALASKA
DEPARTMENT OF TRANSPORTATION AND PUBLIC FACILITIES
DESIGN AND ENGINEERING SERVICES – CENTRAL REGION
DESIGN STUDY REPORT
For
AMATS: Mountain Air Drive Extension
Project No.: UAA CED 2021.02
Written by: Erich Ramirez, Andrew Hwang, Shoshanna Johnson, Jasmine Langmann, Kadin
Yockey, Yamin Man
Prepared by:
__________________________________
Erich Ramirez Date
Project Engineer
Concur by:
__________________________________
Jasmine Langmann Date
Structural Lead
Concur by:
__________________________________
Andrew Hwang Date
Intersection Designer
NOTICE TO USERS
This report was created as part of a University of Alaska Anchorage Civil Engineering Department
project and reflects the thinking and design decisions at the time of publication. Changes frequently occur
during the evolution of the design process, so persons who may rely on information contained in this
document should check with the Alaska Department of Transportation and Public Facilities for the most
current design. Contact the Design Project Manager, Erich Ramirez at 907-785-25837, for this
information.
UAA CED 2021.02
AMATS: Mountain Air Drive Extension i Design Study Report
TABLE OF CONTENTS LIST OF FIGURES .................................................................................................................................... ii
LIST OF ACRONYMS ............................................................................................................................. iii
1.0 PROJECT DESCRIPTION ................................................................................................................. 1
1.1 Project Location and Description ...................................................................................................... 1 1.2 Existing Facilities and Land Use ...................................................................................................... 1 1.3 Purpose and Need ............................................................................................................................. 2
2.0 DESIGN STANDARDS AND GUIDELINES .................................................................................... 2
3.0 DISCUSSION OF ALTERNATIVES ................................................................................................. 3
3.1 Mountain Air Drive Alignment Alternatives .................................................................................... 3 3.2 Rabbit Creek Road / Mountain Air Drive Intersection Alternatives ................................................. 5
4.0 PREFERRED ALTERNATIVE .......................................................................................................... 8
4.1 Mountain Air Drive Preferred Alignment ......................................................................................... 8 4.2 Rabbit Creek Road / Mountain Air Drive Preferred Intersection ..................................................... 9
5.0 TYPICAL SECTIONS ......................................................................................................................... 9
6.0 HORIZONTAL AND VERTICAL ALIGNMENT ......................................................................... 10
6.1 Horizontal Alignment ..................................................................................................................... 10 6.2 Vertical Alignment .......................................................................................................................... 10
7.0 EROSION AND SEDIMENT CONTROL ....................................................................................... 10
8.0 DRAINAGE ......................................................................................................................................... 10
9.0 SOIL CONDITIONS .......................................................................................................................... 10
10.0 ACCESS CONTROL FEATURES ................................................................................................. 11
11.0 TRAFFIC ANALYSIS ...................................................................................................................... 11
12.0 SAFETY IMPROVEMENTS .......................................................................................................... 11
13.0 RIGHT-OF-WAY REQUIREMENTS ........................................................................................... 11
14.0 PEDESTRIAN AND BICYCLE FACILITIES .............................................................................. 12
15.0 UTILITY RELOCATION AND COORDINATION .................................................................... 12
16.0 PRELIMINARY WORK ZONE TRAFFIC CONTROL ............................................................. 12
16.1 Traffic Control Plan (TCP) ........................................................................................................... 13 16.2 Public Information Plan (PIP) ....................................................................................................... 13 16.3 Transportation Operations Plan (TOP) ......................................................................................... 13
17.0 STRUCTURAL SECTION AND PAVEMENT DESIGN ............................................................ 14
18.0 COST ESTIMATE ............................................................................................................................ 14
19.0 ENVIRONMENTAL COMMITMENTS AND CONSIDERATIONS ........................................ 14
20.0 BRIDGES........................................................................................................................................... 14
21.0 EXCEPTIONS TO DESIGN STANDARDS .................................................................................. 15
22.0 MAINTENANCE CONSIDERATIONS ......................................................................................... 15
23.0 ITS FEATURES ................................................................................................................................ 15
APPENDIX A Approved Design Criteria and Design Designation
APPENDIX B Typical Sections
UAA CED 2021.02
AMATS: Mountain Air Drive Extension ii Design Study Report
APPENDIX C 3R Analysis
APPENDIX D Traffic Analysis
APPENDIX E Material Recommendations
APPENDIX F VE Consideration
APPENDIX G Approved Environmental Document
APPENDIX H Approved Design Exceptions and Design Waivers
APPENDIX I ITS Systems Engineering Analysis
APPENDIX J Design Memos
APPENDIX K Bridge Analysis
APPENDIX L Alternative Analysis Memo
LIST OF FIGURES
Figure 1: Project Location and Vicinity Map – Courtesy of DOT&PF ....................................................... iv Figure 2: Alignment Alternatives (red box – approximate crossing locations) ............................................ 5 Figure 3: Rabbit Creek Road and Mountain Air Drive Intersection ............................................................. 6 Figure 4: Turn Lanes Example – Courtesy of USKH ................................................................................... 7 Figure 5: Roundabout Example – Courtesy of USKH .................................................................................. 8
UAA CED 2021.02
AMATS: Mountain Air Drive Extension iii Design Study Report
LIST OF ACRONYMS
AADT Annual Average Daily Traffic
AASHTO American Association of State Highway and Transportation Officials
AHDM Alaska Highway Drainage Manual
AMATS Anchorage Metropolitan Area Transportation Solutions
ATM Alaska Traffic Manual
ATMS Alaska Traffic Manual Supplement
BMP Best Management Practice
BVES Bear Valley Elementary School
DOT&PF Alaska Department of Transportation and Public Facilities
DOJ U.S. Department of Justice
ESCP Erosion and Sediment Control Plan
FHWA Federal Highway Administration
HMA Hot Mix Asphalt
HPCM Alaska Highway Preconstruction Manual
LOS Level of Service
MOA Municipality of Anchorage
MPH Miles per Hour
MUTCD Manual on Uniform Traffic Control Devices
PGDHS A Policy on Geometric Design of Highways and Streets
PIP Public Information Plan
PROWAG Proposed Accessibility Standards for Pedestrian Facilities in the Public Right-of-Way
RDG Roadside Design Guide
ROW Right-of-Way
SWPPP Storm Water Pollution Prevention Plan
TMP Traffic Management Plan
TOP Transportation Operations Plan
USGS United States Geological Survey
UAA CED 2021.02
AMATS: Mountain Air Drive Extension iv Design Study Report
Figure 1: Project Location and Vicinity Map – Courtesy of DOT&PF
UAA CED 2021.02
AMATS: Mountain Air Drive Extension 1 Design Study Report
1.0 PROJECT DESCRIPTION
1.1 Project Location and Description
The Alaska Department of Transportation and Public Facilities (DOT&PF), in cooperation with the
Federal Highway Administration (FHWA) and Anchorage Metropolitan Area Transportation
Solutions (AMATS), proposes to extend Mountain Air Drive from its intersection with Rabbit Creek
Road to 162nd Avenue. The project is located in Sections SW3040, SW3139, and SW3239, USGS
Topological Map Anchorage A-8 SE, Latitude 61.0812147°N, Longitude 149.751201°W, within the
Municipality of Anchorage (MOA), near Bear Valley Elementary School (BVES). See Figure 1 for
Location & Vicinity Map.
The proposed extension will connect a 450-foot segment of Mountain Air Drive that intersects with
Rabbit Creek Road in the north of the Project Area to another 2,200-foot segment of Mountain Air
Drive that intersects with Sandpiper Drive in the south.
Additional considerations include:
• Intersection improvements at Rabbit Creek Road
• Structural crossing over Little Rabbit Creek
• Separated pathways and ADA pedestrian facilities
• Roadside ditches and drainage culverts
• Guardrails, signage, and striping
• Relocating utilities
• ROW acquisition
• Vegetation clearing and grubbing
• Soil stabilization
1.2 Existing Facilities and Land Use
The existing north and south separated segments of Mountain Air Drive are two-lane Rural Collectors
with 60-feet of ROW. Both segments lack a posted speed limit, curb and gutter, pedestrian facilities,
or striping.
The north segment of Mountain Air Drive is a 450-foot-long, 36-foot-wide, paved facility, and
provides access to BVES and Anchorage Fire Department Fire Station No. 10. While the Anchorage
Hillside area is often classified as rolling or mountainous terrain, the existing northern segment of
Mountain Air Drive is relatively flat. Drainage is provided by culverts and roadside ditches. The north
segment of Mountain Air Drive ends in a cul-de-sac at the entrance to BVES. A foot trail continues
where the pavement ends and primarily follows the platted ROW of Mountain Air Drive around the
outside of BVES until it connects with the platted ROW of Hillside Drive, near the SE corner of
BVES.
The south segment of Mountain Air Drive is a 2,200-foot long, 30-foot wide, paved facility on rolling
terrain, and slopes down from its intersection with Sandpiper Drive as it snakes north until it ends at a
cul-de-sac. Drainage is provided by cross culverts and roadside ditches. For the first several hundred
feet, there are developed or in-development private properties on both sides of Mountain Air Drive,
then it is undeveloped until the cul-de-sac.
UAA CED 2021.02
AMATS: Mountain Air Drive Extension 2 Design Study Report
The T-intersection with Rabbit Creek Road is stop-controlled only from Mountain Air Drive. There
are no turn lanes, medians, or traffic signals at the intersection. There is one luminaire at the
intersection, on Rabbit Creek Road across from Mountain Air Drive. Rabbit Creek Road is a
residential collector at this intersection with a posted speed of 45 mph. Currently, the intersection
experiences delays during AM and PM peak hours that coincide with the start and end of the school
day for BVES.
Land use in the project area, aside from BVES and Fire Station 10, is mostly undeveloped residential
parcels. Platted ROW for Hillside Drive, Mountain Air Drive, and 155th Avenue are located in the
vicinity. A network of community trails can be found on platted ROW. Little Rabbit Creek is located
at the bottom of a 50-foot ravine and crosses the project area draining east to west. MOA-classified
wetlands of high and moderate valuation are present and are especially clustered to the south and east
of the project area. A MOA Heritage Land Bank is to the east of the Hillside Road ROW. An MOA
Heritage Land Bank is east of the project vicinity.
Utilities in the project vicinity are underground and overhead and include electric and communication
lines from Chugach Electric Association and Alaska Communications. A transformer is just off the
foot path to the west of BVES. Hanging utilities are adjacent and parallel to the Hillside Drive ROW.
A Section Line is located just east of the Hillside Drive ROW.
1.3 Purpose and Need
The purpose and need of the AMATS: Mountain Air Drive Extension project is to address safety
concerns for the surrounding communities and to spur development in this region of Anchorage,
including providing a secondary means of egress for residents and access for emergency services.
Other considerations include improving active transportation in the community, to provide
connectivity to a large undeveloped area in SE Anchorage, and to increase circulation in the Rabbit
Creek / Goldenview area.
2.0 DESIGN STANDARDS AND GUIDELINES
Design standards and guidelines that apply to the AMATS: Mountain Air Drive are contained in the
following publications:
Standards:
• A Policy on Geometric Design of Highways and Streets (PGDHS), 6th Edition, AASHTO, 2011.
• Roadside Design Guide (RDG), 4th Edition, AASHTO, 2011.
• Alaska Highway Preconstruction Manual (HPCM), DOT&PF, 2005 as amended.
• Alaska Highway Drainage Manual (AHDM), DOT&PF, 2006.
• The Alaska Traffic Manual (ATM), consisting of the Manual on Uniform Traffic Control Devices
(MUTCD), 2009 as amended, U.S. DOT, FHWA) and the Alaska Traffic Manual Supplement
(ATMS), DOT&PF, 2016.
• ADA Standards for Transportation Facilities, DOT, 2006.
• ADA Standards for Accessible Design, DOJ, 2010.
UAA CED 2021.02
AMATS: Mountain Air Drive Extension 3 Design Study Report
• Guide for the Development of Bicycle Facilities, 4th Edition, AASHTO, 2012.
• Recommended Practice for Roadway Lighting (RP-8-14), ANSI / IES, 2014.
• Highway Capacity Manual (HCM), 5th Edition, TRB, 2010.
• Design Criteria Manual (DCM), MOA, Project Management & Engineering Department, 2007
with 2018 revision.
Guidelines:
• Proposed Accessibility Standards for Pedestrian Facilities in the Public Right-of-Way
(PROWAG), U.S. Access Board, 2011.
• Guide for the Planning, Design, and Operation of Pedestrian Facilities, 1st Edition, AASHTO,
2004.
Appendix A contains the Project Design Criteria and Design Designation.
3.0 DISCUSSION OF ALTERNATIVES
Alternatives for an extension of Mountain Air Drive through the project area and intersection
improvements at Rabbit Creek Road were considered separately. Three build options were considered for
each. Beginning of Project (BOP) is the intersection of Mountain Air Drive with Rabbit Creek Road, and
End of Project (EOP) is Sandpiper Drive, beyond the cul-de-sac at the end of the southern segment of
Mountain Air Drive. BOP and EOP are labelled in Figure 2.
To review the Criteria Matrix for both the Mountain Air Drive extension and the Mountain Air Drive and
Rabbit Creek Road intersection, and a discussion of the evaluation criteria, see Alternative Memo in
Appendix L.
3.1 Mountain Air Drive Alignment Alternatives
The alignment alternatives were evaluated according to Project Costs, Future Maintenance Costs,
Environmental Impact, Mobility, Accessibility, and Public Opinion. Of the criteria, Project Costs was
given the most weight, then Mobility, given the importance of purpose and need.
Figure 2 displays the Mountain Air Drive extension alternatives from BOP to EOP.
NO BUILD
The No Build alternative would not construct a roadway connecting the existing northern and
southern segments of Mountain Air Drive. With the immediate need for egress and emergency access,
the No Build option was considered for the Mountain Air Drive extension but was rejected because it
did not meet the purpose and need for the project.
ALIGNMENT 1
This alternative is the westernmost build alternative. From BOP, it follows the existing Mountain Air
Drive, continues through the foot path on the Mountain Air Drive ROW until it reaches the border at
the SW corner of BVES property, then continues primarily south-south east through the project area.
UAA CED 2021.02
AMATS: Mountain Air Drive Extension 4 Design Study Report
A 150-foot single-span bridge will cross the Little Rabbit Creek valley. After the crossing, the
alignment continues primarily between large existing drainage paths until connecting with the cul-de-
sac and continuing on the existing southern segment of Mountain Air Drive until EOP.
Alignment 1 meets purpose and need of the project by prioritizing mobility through the project area.
The alternative needs a single-span bridge but has the least length of the alternatives.
ALIGNMENT 2
This alternative is slightly east of Alignment 1. From BOP, it follows the existing Mountain Air
Drive, continues through the foot path on the Mountain Air Drive ROW, around the SW corner of
BVES, until coming to a stop-controlled intersection alongside the southern BVES property border.
The alignment then proceeds south. A multi-plate arch culvert will cross the Little Rabbit Creek
valley. After the crossing, the alignment continues southwest until connecting with the cul-de-sac and
continuing on the existing southern segment of Mountain Air Drive until EOP.
Alignment 2 meets purpose and need by providing a balance of mobility and accessibility through the
project area. The alignment has a stop-controlled intersection and has a small turning radius around
the southwest corner of BVES. The alternative needs a multi-plate arch culvert and is approximately
500 feet longer than Alignment 1.
ALIGNMENT 3
This alternative is the easternmost alternative. From BOP, it follows the existing Mountain Air Drive,
continues through the foot path on the Mountain Air Drive ROW until coming to a stop-controlled
intersection as it meets with the Hillside Drive ROW to the SE of BVES, then continues south on the
ROW. Two multi-plate arch culverts will cross Little Rabbit Creek and a tributary stream. After the
crossings, the alignment will continue south until coming to a stop-controlled intersection with the
ROW for 155th Avenue. The corridor continues west on the 155th ROW, comes to a stop-controlled
intersection, then continues due south until connecting with the cul-de-sac and continuing on the
existing southern segment of Mountain Air Drive until EOP.
Alignment 3 meets purpose and need for the project by providing connectivity through the project
area for future development. The alternative needs two multi-plate culverts, has three stop-controlled
intersections and is approximately 1,800 feet longer than Alignment 1.
UAA CED 2021.02
AMATS: Mountain Air Drive Extension 5 Design Study Report
Figure 2: Alignment Alternatives (red box – approximate crossing locations)
3.2 Rabbit Creek Road / Mountain Air Drive Intersection Alternatives
Figure 3 displays an aerial of the existing intersection.
UAA CED 2021.02
AMATS: Mountain Air Drive Extension 6 Design Study Report
Figure 3: Rabbit Creek Road and Mountain Air Drive Intersection
NO BUILD
The no-build alternative was considered for the intersection, but would fail to meet future capacity if
the Mountain Air Drive extension was constructed. Significant traffic delays will occur in this
intersection should the Mountain Air Drive extension be built. USKH, now Stantec, conducted a
traffic study (memorandum dated January 2011) and found that during both peak AM and PM hours,
the level of service (LOS) will be unacceptable should the extension be built. Of the LOS levels, LOS
D (approaching unstable flow) is the minimum acceptable condition for intersections per MOA
standards. Per the USKH traffic study report, the existing LOS as of September 1, 2009 was at LOS B
(stable flow). However, should the Mountain Air Drive extension be built, the intersection would
experience an LOS F (forced flow) should no improvements be done on the intersection.
UAA CED 2021.02
AMATS: Mountain Air Drive Extension 7 Design Study Report
TRAFFIC SIGNAL without TURN LANES
This alternative is to install a traffic signal on Mountain Air Drive and Rabbit Creek Road without the
installation of a turn lane. The Manual on Uniform Traffic Control Devices, or MUTCD, sets nine
possible warrants for the installation of a traffic signal based on traffic studies of the intersection. In
its existing condition, the intersection of Mountain Air Drive and Rabbit Creek Road only meets one
of the warrants, which concerns peak hour volume. Meeting only one of the nine possible warrants is
not ideal in its consideration of selecting this alternative. A traffic signal would allow for an easier
and more understandable pedestrian crossing, considering the intersection is located near a school.
However, the improper usage of a traffic signal would be detrimental to the flow of traffic and causes
delays outside of the current peak traffic hours. Traffic signals are also monetarily costly, as the
maintenance for a traffic signal costs approximately $10,000 a year.
TURN LANES
This alternative is the construction of a turn lane on Mountain Air Drive and Rabbit Creek Road. The
National Cooperative Highway Research Program (NCHRP) Report 457 sets a volume threshold for
the consideration of a turn lane, which this intersection meets. A turn lane is more ideal in terms of
allowing emergency access vehicles to travel and cross at, while also providing a specific lane for
through traffic on Rabbit Creek Road. Should the turn lane not be adequate when traffic volume
increases in the future, the turn lane allows for the installation of a traffic signal to accommodate for
the increase in traffic volume. This alternative will require reallocation of its existing pavement or
widening the cross-section of the roads, resulting in additional right of way needs. Installations
necessary for a future traffic signal would need to be constructed as well, as the USKH traffic study
states the additional lanes would increase the level of service to an acceptable LOS D. Per the USKH
traffic study, the level of service with a turn lane during the peak AM hour would be an LOS F, which
is the lowest LOS. The installation of a traffic signal will be necessary along with the turn lanes due
to the peak AM hour LOS. The combination of the traffic signal and turn lanes would accrue a
significant amount of cost involved with the project.
Figure 4: Turn Lanes Example – Courtesy of USKH
UAA CED 2021.02
AMATS: Mountain Air Drive Extension 8 Design Study Report
ROUNDABOUT
This alternative is the construction of a single-lane roundabout at the intersection of Rabbit Creek
Road and Mountain Air Drive. A roundabout does not require electricity or any special maintenance
like a traffic signal requires, thus having lower overall maintenance costs than the installation of a
traffic signal. Roundabouts have historically reduced the frequency and severity of crashes, as well as
reducing the delay in traffic when traffic volumes do not exceed the roundabout capacity. The
intersection of Rabbit Creek Road and Mountain Air Drive has an overall intersection grade of 1%,
which is desirable as it is less than 4% as stated in the NCHRP report 672. On February 11, 2021, the
Department of Transportation and Public Facilities conducted a public meeting with the Rabbit Creek
Community Council regarding the Mountain Air Drive extension. It was found that the public was in
favor of a roundabout. The roundabout would require an additional right of way acquisition, as the
single-lane roundabout would require an inscribed circle diameter of 90 feet to 150 feet. Roundabouts
also require the drivers to slow down for the entry of a roundabout regardless of any other vehicles
being present. Per the NCHRP report 457, roundabouts are not as conductive to serving pedestrian
and bicycle traffic.
Figure 5: Roundabout Example – Courtesy of USKH
4.0 PREFERRED ALTERNATIVE
4.1 Mountain Air Drive Preferred Alignment
Beyond addressing purpose and need, Alignment 1’s most prominent characteristic is the mobility of
the thoroughfare. Two other nearby collectors were used as comparables for the Mountain Air Drive
Extension, Goldenview Drive to the west and Clarks Road to the northeast. Both Goldenview and
Clarks primarily provide direct passage to local roads that service residential neighborhoods.
Alignment 1 meets the purpose and need of the project and scored the highest using the Evaluation
Criteria. The alignment has a comparable construction and maintenance costs with the other
UAA CED 2021.02
AMATS: Mountain Air Drive Extension 9 Design Study Report
alternatives, has less environmental impact, and constructs a collector with high mobility through the
project area.
Key Alignment 1 features for the public and client include:
• Creates a highly mobile thoroughfare that directly addresses purpose and need for the project.
• Minimal environmental impact throughout the corridor.
• Difference in capital costs with Alignment 2 are expected to be minimal with fewer linear
feet of road and less structural material needed for Little Rabbit Creek crossing and fewer
utility conflicts.
• Difference in maintenance costs with Alignment 2 are expected to be minimal with fewer
linear feet of road, no intersections, and bridge maintenance only required every two years.
• Alignment 1 also avoids a major constraint for the other two alignments: the curve around the
SW corner of BVES. To fit a DOT&PF desirable radius of 550 feet, there would need to be a
property acquisition from BVES. A DOT&PF minimum radius of 380 feet does fit, but the
right side of the Mountain Air Drive corridor ROW slopes down into the Little Rabbit Creek
valley south of BVES, requiring significant fill to support the right side of the roadway for
Alignments 2 and 3.
4.2 Rabbit Creek Road / Mountain Air Drive Preferred Intersection
The preferred alternative for the improvements at the intersection of Rabbit Creek Road and
Mountain Air Drive is to construct a single-lane roundabout. The roundabout has a lower overall cost
compared to the other alternatives, a higher public opinion, and provides less delay in traffic at the
intersection. Per the USKH traffic study, the roundabout has a higher level of service than the turn
lane or the traffic signal. Should both a turn lane and traffic signal be installed, the level of service
would exceed the level of service of a roundabout slightly but would be significantly more expensive
to implement. While roundabouts require more right of way acquisition at the intersection, turn lanes
have a more longitudinal right of way impact.
5.0 TYPICAL SECTIONS
The typical section is derived from DCM Figure 1-12, a typical section for a Rural Collector, with:
• 2 11-foot lanes with 4-foot shoulders, paved, with a 2% cross-slope crowned at the roadway
centerline.
• 1-foot gravel shoulders between the paved shoulder and ditch.
• ‘V’ shaped roadside ditches, with a recoverable foreslope of 4:1 that is 14-feet wide and 3.5-feet
deep and a backslope of 2:1 that is 7-feet wide.
• 2-foot sodded shoulders between the ditches and the pedestrian facilities.
• On the east side of the roadway, a 5-foot paved pathway (1.5% cross-slope), and on the west side,
an 8-foot gravel shared-use pathway (3% cross-slope).
• Outside of the pedestrian facilities, 2-feet of spacing, then 2:1 cut and fill slopes to existing
ground.
The typical section for Mountain Air Drive was adapted for the bridge crossing over Little Rabbit Creek,
with:
• 9 bulb-tee prestressed concrete girders forming the deck.
• 2 11-foot lanes with 4-foot shoulders and a 2% cross-slope.
• 3-tube railing on both sides separating the roadway from pedestrian facilities (width of 1’-8”).
UAA CED 2021.02
AMATS: Mountain Air Drive Extension 10 Design Study Report
• On the east side of the roadway, a 5’-6” paved pathway (2% cross-slope), and on the west side, an
8-foot paved pathway (2% cross-slope).
• Pedestrian railing outside of the pedestrian facilities (width of 1’-0”)
The alignment and bridge typical sections are provided in Appendix B.
6.0 HORIZONTAL AND VERTICAL ALIGNMENT
6.1 Horizontal Alignment
From BOP, the first horizontal curve, in front of Fire Station 10 (Station 1 + 20), has a radius of 210
feet, a value below the minimum value in Table 1-9 of the DCM. With the proximity of the curve to
the yield-controlled single-lane roundabout intersection preferred in Section 4.2, the radius is
acceptable.
All other horizontal curve radii from the Rabbit Creek Road intersection to the cul-de-sac on the
southern segment of Mountain Air Drive are greater than the minimum limit of 600 feet for collector
roads as displayed in Table 1-9 of the DCM.
6.2 Vertical Alignment
The profile of the new alignment will match existing segments of Mountain Air Drive at the north and
south ends of the project area. Through the undeveloped area, sag curves will be present on both sides
of the valley to come down to the Little Rabbit Creek bridge. Mountain Air Drive will be designed for
a speed of 35 mph, and profile grades for the new alignment segment will not exceed 5%. The
existing southern segment of Mountain Air Drive has grades up to 8%.
The single-span bridge over Little Rabbit Creek has a + 0.70% slope moving from north to south.
7.0 EROSION AND SEDIMENT CONTROL
Outside of scope.
8.0 DRAINAGE
Outside of scope.
9.0 SOIL CONDITIONS
A geotechnical report was developed by Shannon & Wilson, Inc. in June of 2010 for the previous
Mountain Air Drive Extension project. Eleven boreholes were drilled between February 24 to March 3,
2010, along the USKH preferred alternative, with one boring being near the Rabbit Creek Road
intersection, four to the west of BVES, and six borings (three to the north and three to the south)
investigating the soils at the Little Rabbit Creek valley, at the approximate locations for the bridge
approaches and foundations. The locations of the first five borings follow the same path as this DSR’s
UAA CED 2021.02
AMATS: Mountain Air Drive Extension 11 Design Study Report
new alignment. The borings along the Little Rabbit Creek valley range from 150 to 300 feet east of the
new alignment. There were no boreholes drilled south of the 155th Avenue ROW.
The report found medium dense to very dense soils. Soils were frozen from 2 to 7 feet below ground
surface. Groundwater should be expected between 20 and 35 feet below ground surface.
The Shannon & Wilson report recommends that the project does not use native soils in any structural
section.
10.0 ACCESS CONTROL FEATURES
New access to the roadway will be managed through driveway permits and future project evaluation.
Mountain Air Drive is classified as a collector, but minimal future driveway access is anticipated.
11.0 TRAFFIC ANALYSIS
The USKH traffic study was conducted on January 12, 2011, which analyzed the alternatives for the
intersection improvements between Mountain Air Drive and Rabbit Creek Road. USKH used the
Intersection LOS (level of service) Criteria to analyze the flow of traffic at the intersection using a
projected traffic volume of 1,570 trips per day with a design year set at 2029. The improvement options
were ranked with a LOS between A and F. A single-lane roundabout was found to have a LOS B in the
AM peak hour and LOS A in the PM peak hour using the projected 2029 traffic volume. The only other
alternative that reaches the roundabout’s LOS was the combination of the traffic signal and turn lanes.
12.0 SAFETY IMPROVEMENTS
Studies have shown that roundabouts reduce the severity of crashes at an intersection. The NCHRP report
672 states that intersections allow safer merging of traffic and provides more time for drivers to correct
any mistakes due to lower vehicle speeds.
The illumination of the roundabout will use a perimeter illumination design. This design has the
illumination poles along the side of the roundabout, as opposed to installing the poles on the central
island.
With the proximity to BVES, separated pedestrian facilities will be provided on both sides of the
roadway. A paved 5-foot ADA sidewalk is to be constructed on the east side of the roadway, and a gravel
8-foot multi-use pathway will be installed on the west side.
Signage and striping will be addressed later in the design process.
13.0 RIGHT-OF-WAY REQUIREMENTS
This project will require ROW acquisitions throughout the corridor. According to the OSHP, Mountain
Air Drive is a Type 1B Neighborhood Collector, and prescribes a minimum ROW width of 70 feet. To
integrate the roadside ditches and separated pedestrian facilities, the Mountain Air Drive extension will
require a minimum of 95 feet of ROW. With the cut sections for the roadway to meet the bridge,
additional ROW will be needed at the valley crossing.
UAA CED 2021.02
AMATS: Mountain Air Drive Extension 12 Design Study Report
At the Rabbit Creek Road intersection, two partial acquisitions, one from Fire Station 10 and another
from a residential parcel, will be necessary for the roundabout and to achieve sight distances. West of
BVES, a strip acquisition of approximately 40 feet is needed for Mountain Air Drive ROW. On the north
ridge of the valley at Little Rabbit Creek, two full-parcel acquisitions are necessary. South of Little Rabbit
Creek, strip acquisitions from unsubdivided parcels are required for Mountain Air Drive ROW that range
from approximately 95 to 160 feet until connecting with the cul-de-sac on the southern segment of
Mountain Air Drive.
To maintain consistency along the full Mountain Air Drive corridor, strip acquisitions of approximately
20 feet on both sides of the roadway will be needed along the southern Mountain Air Drive segment for
pedestrian facilities.
14.0 PEDESTRIAN AND BICYCLE FACILITIES
With the new alignment’s proximity to BVES, pedestrian and bicycle facilities have been designed into
Mountain Air Drive’s ROW. Starting at BOP, the east side of the road, the same side that BVES is on,
features a 5-foot paved separated sidewalk, and the west side has an 8-foot gravel separated multi-use
pathway. The pedestrian facilities are separated from the roadway by 21-foot ditches. For bicyclists, the
4-foot shoulders meet the AASHTO recommendation for bicycle facilities according to the Guide for
Development of Bicycle Facilities. A cross-slope of 1.5% is designed for the paved pathway to
accommodate wheel chair users.
Pedestrian facilities are planned for the southern segment of Mountain Air Drive, but further design work
needs to take place to integrate the pathways with existing driveways.
15.0 UTILITY RELOCATION AND COORDINATION
Utility companies with facilities in the project limits include Chugach Electric Association and Alaska
Communications. Utilities will require relocation and agreements will need to be developed, at select
locations throughout the project, to address conflicts. A transformer is located near the SW corner of
BVES and will require relocation. Underground communication cables are presumed to be under the foot
path west and south of BVES, but further investigation is necessary.
16.0 PRELIMINARY WORK ZONE TRAFFIC CONTROL
Section 1400.2 of the HPCM lists the criteria for deciding if a project is ‘significant’ for purposes of
determining the level of effort required in developing a Traffic Management Plan (TMP). Significant
projects meet either the Category 1 or Category 2 classification.
Category 1
• Project occupies a location for more than three days with either intermittent or continuous land
closures on Interstate Highways within a Transportation Management Area – CRITERIA NOT
MET
Category 2
UAA CED 2021.02
AMATS: Mountain Air Drive Extension 13 Design Study Report
• Project occupies a location for more than three days with either intermittent or continuous lane
closures on arterials, expressway, or freeways with Average Annual Daily Traffic (AADT) of
30,000 or more – CRITERIA NOT MET
• Project fully closes an arterial for more than one hour at a time with no practical alternate route –
CRITERIA NOT MET
• Any other project that, alone or in combination with other concurrent projects nearby, is
anticipated to require greater than normal attention to traffic control to eliminate sustained work
zone impacts greater than what would be considered acceptable – CRITERIA MET
Therefore, the project is considered a Category 2 “Significant Project” and a full TMP, including a Traffic
Control Plan, a Public Information Plan, and a Transportation Operations Plan, must be developed.
16.1 Traffic Control Plan (TCP)
The contractor will develop a TCP during construction, to safely guide and protext the traveling
public in work zones, in accordance with the Alaska Traffic Manual (ATM) and the project
specifications. The plan will be assessed and approved by the Construction Project Engineer and
Traffic Control Engineer.
The contractor is responsible for providing advance notice to the public, including local businesses,
residents, and road travelers, of construction activities that could cause delays, detours, or affect
access to adjacent properties.
16.2 Public Information Plan (PIP)
A PIP will be developed prior to beginning construction that will specify the ways and means that the
contractor will use to inform the public of upcoming activities that will impact local stakeholders, the
roadway users and public entities. The PIP will contain measures to inform stakeholders of project
scope, expected work zone impacts, closure details, and recommended action to avoid impacts and
changing conditions during construction. Measures to distribute information include:
• Contractor’s Worksite Traffic Supervisor
• DOT&PF’s Construction Section thru the DOT&PF’s 511 system
• DOT&PF’s Navigator website
• Television, radio, and/or newspaper advertisements
• Other location-specific communication tools
16.3 Transportation Operations Plan (TOP)
No large construction projects are anticipated within the vicinity of this project site so cumulative
traffic delay impacts are not expected. If unanticipated work is ongoing concurrently with the project,
the contractor must develop a TOP that will specify coordination effects from creating undue
impediment to the traveling public.
UAA CED 2021.02
AMATS: Mountain Air Drive Extension 14 Design Study Report
17.0 STRUCTURAL SECTION AND PAVEMENT DESIGN
The pavement for the existing north segment of Mountain Air Drive will be removed. The existing south
segment will remain as is south of the cul-de-sac.
For the new Mountain Air Drive alignment, the structural section and pavement design will consist of 36
inches of Selected Material, Type A, 2 inches of Aggregate Base Course, Grading D-1, 3 inches of
Asphalt Treated Base Course, and 2 inches of Hot Mix Asphalt (HMA).
The sidewalk structural section on the left side of the roadway will consist of 24 inches of Selected
Material, Type A, 4 inches of Aggregate Base Course, Grading D-1, and 2 inches of Hot Mix Asphalt.
The multi-use pathway on the right side of the roadway will consist of 24 inches of Selected Material,
Type A, and 4 inches of Aggregate Base Course, Grading D-1.
18.0 COST ESTIMATE
The project cost estimate is as follows:
Preliminary Engineering $ 200,000
Right-of-Way $ 708,120
Utility Relocation $ 500,000
Construction $ 6,873,758
Total $ 8,281,878
19.0 ENVIRONMENTAL COMMITMENTS AND CONSIDERATIONS
The proposed project does not anticipate any unusual circumstances or significant environmental impacts.
The contractor will be required to prepare and implement a SWPPP.
The contractor will be required to dispose of solid waste at a DEC approved landfill. The contractor will
be responsible for obtaining all necessary permits and clearances for materials sites, disposal sites, and
staging areas unless DOT&PF has obtained the necessary permits.
20.0 BRIDGES
The proposed Little Rabbit Creek crossing on Mountain Air Drive is a single span 148' long precast
concrete decked-bulb tee bridge over alignment 1. The bridge will have approaches that are
approximately 50’ long on each end of the bridge.
Appendix K provides a bridge analysis for the three alternative alignments.
UAA CED 2021.02
AMATS: Mountain Air Drive Extension 15 Design Study Report
21.0 EXCEPTIONS TO DESIGN STANDARDS
There are no exceptions to design standards for this project.
22.0 MAINTENANCE CONSIDERATIONS
Future maintenance will be the responsibility of the Municipality of Anchorage.
23.0 ITS FEATURES
All NHS and non-NHS highway projects receiving federal funding and incorporating Intelligent
Transportation System (ITS) elements are required to be developed in conformance with 23 CFR 940
National Intelligent Transportation System Architecture and Standards.
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
APPENDIX A
Approved Design Criteria and Design Designation
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
PROJECT DESIGN CRITERIA Page 1 of 3
Project Name: AMATS: Mountain Air Drive Extension
State Project No.:
UAA CED 2021.02 Federal Project No.: N/A
Functional Classification:
Rural Neighborhood Collector Terrain: Rolling
Segment: Rabbit Creek Rd. to Sandpiper Dr
Present ADT (2021): N/A Mid-Design ADT (2038): N/A Design ADT (2048): 3416
DHV (%): N/A Trucks (%): N/A Directional Split (%/%): N/A
Pavement Design Year: 20 Pavement Design ESAL: N/A
Design Turning Vehicle: WB-67
Project Type: New Construction/Reconstruction NHS: ☐ Non-NHS: ☐
FHWA 10 CONTROLLING DESIGN CRITERIA
SOURCE
STA
ND
AR
D
AS
PR
OP
OSE
D
EXC
EPTI
ON
1
Design Speed1 MOA DCM Table 1-4, Pg. 1-25 35 mph 35mph No
Lane Width Travel MOA DCM Table 1-4, Pg. 1-25 10-11 ft 11 ft No
Auxiliary MOA DCM Table 1-4, Pg. 1-25 10-11 ft 11 ft No
Shoulder Width
Outside MOA DCM Table 1-4, Pg. 1-25 3.5-5 ft 5 ft No
Inside N/A N/A ft N/A N/A
Auxiliary N/A N/A ft N/A N/A
Horizontal Curve Radius, min MOA DCM Table 1-9, Pg. 1-51 600 ft > 600 ft No
Superelevation Rate, e, max MOA DCM Table 1-10, Pg. 1-
55 6% ≤ 6% No
Stopping Sight Distance (SSD), min
MOA DCM Fig. 1-20, Pg. 1-54 250 ft > 250 ft No
Grade Min. MOA DCM Pg. 1-45 1% 1% No
Max. MOA DCM Table 1-8 Pg. 1-47 ≤ 8% 5% No
Cross Slope MOA DCM Pg. 1-47 2-3% 2% No
Vertical Clearance, Overhead Utilities
HPCM Table 1130-1, Pg. 1130-5
20 ft – 6 in 20 ft – 6 in No
Design Loading Structural Capacity1 GB Pg 6-7, Sec. 6.2.3 HL 93 HL 93 No
1 On low speed roadways (<50 mph) on the NHS, only Design Speed and Design Loading Structural Capacity require a Design Exception; all other criteria require a Design Waiver. For projects off the NHS, all criteria require a Design Waiver.
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
Page 2 of 3
OTHER DESIGN CRITERIA
SOURCE
STA
ND
AR
D
AS
DES
IGN
ED
WA
IVER
Superelevation Transition, Δ GB Table 3-15 Pg. 3-61 0.62% 0.62% No
Bridge Clear-Roadway Width HPCM Pg. 1160-15, Sec.
1160.3.5 N/A N/A N/A
Vertical Curvature (min)
K (crest) GB Table 3-34 Pg. 3-155 29.0 29 No
K (sag) GB Table 3-36 Pg. 3-161 49.0 49 No
Lateral Offset to Obstruction RDG Pg. 10-1 4-6 ft 4 ft No
Surfacing Material HPCM Pg. 1180-1, Sec.
1180.3 Paved Paved No
Clear Zone
Slope (fill)
HPCM Pg. 1130-6, Table
1130-2
4:1 or flatter
4:1 or flatter
No
Width (fill) 14-16 ft 19 ft No
Slope (cut) N/A N/A N/A
Width (cut) N/A N/A N/A
Bicycle Lane Width N/A N/A N/A N/A
Sidewalk/Pathway Width MOA DCM Table 1-4, Pg. 1-
25 5 ft/8 ft 5/8 ft No
Intersection Sight Distance, Passenger Car
Left Turn (GB Case B1)
GB Table 9-6 Pg. 9-38 385.9 ft 390 ft No
Right Turn (GB Case B2)
GB Table 9-8 Pg. 9-41 334.4 ft 335 ft No
Crossing (GB Case B3)
GB Table 9-8 Pg. 9-41 334.4 ft 335 ft No
Passing Sight Distance GB Table 3-4 Pg. 3-9 550 ft 550 ft No
Degree of Access Control GB 2.5.4 Pg. 2-73 Driveway regulations No
Median
Treatment
N/A
N/A N/A
Width N/A N/A N/A
Illumination DCM 5.4H Pg. 5-9 Intersection illumination No
Curb Type N/A N/A N/A
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
Page 3 of 3
Notes: GB = Green Book, DCM = Design Criteria Manual, HPCM= Highway Preconstruction Manual, RDG = AASHTO Roadside Design Guide Proposed by: Date: Designer (Consultant or Staff) Recommended by: Date: Engineering Manager Accepted by: Date: Regional Preconstruction Engineer
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
APPENDIX B
Typical Sections
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
APPENDIX C
3R Analysis
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
APPENDIX D
Traffic Analysis
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
The information in this report is compiled for highway safety planning purposes. Federal law prohibits its
discovery or admissibility in litigation against state, tribal or local government that involves a location or
locations mentioned in the collision data. 23 U.S.C. § 409; 23 U.S.C. § 148(g); Walden v. DOT, 27 P.3d
297, 304-305 (Alaska 2001).
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
APPENDIX E
Material Recommendations
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
APPENDIX F
VE Consideration
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
APPENDIX G
Approved Environmental Document
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
APPENDIX H
Approved Design Exceptions and Design Waivers
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
APPENDIX I
ITS Systems Engineering Analysis
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
APPENDIX J
Design Memos
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
APPENDIX K
Bridge Analysis
An alternatives analysis was developed for all three alternative alignments. Possible structures to cross
Little Rabbit Creek include a single-span 148' or two-span 260' precast concrete decked bulb-tee bridges,
multi-plate culverts, and concrete culverts. Each alternative alignment crossing structure was tailored to
accommodate the respective alignment location elevations and 100-year flood plain levels for Little
Rabbit Creek.
ALIGNMENT 1 – PREFERRED ALTERNATIVE
Alignment 1 crossing alternatives included both the single-span 150' precast concrete decked bulb tee
bridge and the two-span 260' precast concrete decked bulb tee bridge. Bridges were considered at this
location because of the steep slopes above the creek. A bridge would allow the road to have a less steep
grade on the approach by raising the deck elevation in comparison to a culvert. The bridges that were
considered are 260’ and 148’ long. The girders on the single-span bridge would be 145’ long and two
130’ long on the two-span bridge. The 148' bridge has longer and more expensive girders but requires less
fill material and eliminates the need for a pier. The 260' bridge requires shorter girders and are less
expensive but require a larger amount of fill material and a pier to be placed in the middle of Little Rabbit
Creek. Another option is a steel bridge, but it would be more expensive than the single or two-span
precast concrete bridge. The single span 148' long precast concrete deck bulbed-tee bridge is the preferred
alternative. The quantities and cost of materials for the single span 148’ long bridge is in the table below.
Item No. Item Est Unit
Total Quantity
Cost/ Unit Cost
205.0006.0000 Structural Fill CY 1,300 35 $45,500
501.0001.000 Class A Concrete CY 180 1,500 $270,000
501.0007.0000 Precast Concrete Member, 145'-0" Decked Bulb-Tee EA 9 65,000 $585,000
503.0001.0000 Reinforcing Steel LBS 12,000 1.75 $21,000
503.0002.0000 Epoxy-Coasted Reinforcing Steel LBS 24,000 2 $48,000
503.2000.0000 Waterproofing Membrane, Spray Applied SY 910 100 $91,000
505.0005.1417 Furnish Structural Steel Piles, HP 14x117 LF 900 80 $72,000
505.2005.1417 Install Structural Steel Piles, HP14x117 EA 14 10,000 $140,000
504.0001.0002 Steel Bridge Railing, 3-Tube LF 380 200 $76,000
507.0001.0002 Steel Bridge Railing, Pedestrian Rail LF 380 200 $76,000
511.0001.0000 Mechanically Stabilizing Earth Wall SF 1,840 65 $119,600
606.0016.0000 Transition Rail EA 4 2,500 $10,000
611.0001.0002 Riprap, Class II CY 800 75 $60,000
TOTAL $1,614,100
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
This alignment has steep slopes with a ravine approximately 40' deep. The 100-year flood has a flood
plain that is about 38' wide and about 4' high. The bridge is supported by an approximately 20' tall MSE
walls at the abutments with a 2.5:1 slope on each side of the approach. The area under the bridge is large
enough that flooding that would impact the bridge and debris buildup are unlikely to ever be a concern
and there is plenty of space for wildlife crossing. The height of the MSE walls were decided to balance
increasing costs and engineering after a 20' tall cut was required to bring the road down to bridge deck
elevation. The approaches are longer and the bridge deck elevation lower to balance the cost between the
roadway and structural components. This bridge will have H-piles that are installed 50’ below ground
level at the abutments creating a deep foundation.
The longitudinal slope of the bridge is 0.7% to allow proper drainage of the bridge deck. The pavement,
both the roadway, pathway, and sidewalk and paved and have a 2% cross slope to allow for drainage.
A 3-tube pedestrian railing is between the roadway and the pathways which has a height of 3’-8” and
pedestrian rail is on the outside of each pathway, which is 4’-6” tall. The roadway has 4’ shoulders and
11' wide lanes. The sidewalk is 5’-6” wide and the pathway is 8’-0” wide. The new standard thrie-beam
transition rail will be installed in each corner of the bridge and will provide adequate distance and
protection for pedestrians as their pathways near the roadway during the roadway-bridge transition.
ALIGNMENT 2
Alignment 2 crossing alternatives included the 148’ single-span precast concrete decked bulb tee bridge
and a low-profile multi-plate culvert. The 148’ bridge considerations are the same as those indicated for
Alignment 1. The multi-plate culvert would be 18’-8” tall and 45' wide to accommodate the 100-year
flood plain level.
The culvert would be manufactured out-of-state and shipped up and would require a large amount of fill
material. However, the existing ground slopes on either side the creek at Alignment 2 are less steep than
Alignment 1 requiring shorter fill and side slopes. Although the multiplate culvert would be considerably
large, require a great deal of fill material, and be manufactured out-of-state, the cost analysis of the
multiplate culvert versus the single-span 148’ precast concrete decked bulb tee bridge determined the
multiplate culvert to be less expensive. Additionally, because the culvert would be very wide, it poses less
of a concern for debris or ice buildup than that of smaller culverts during a flood event. Though not a
requirement for this area, this culvert is also tall enough to be considered a wildlife passage.
ALIGNMENT 3
Alignment 3 crosses two branches of Little Rabbit Creek which requires two crossings. Alignment 3
considers two types of culverts: a concrete box culvert and a steel multiplate culvert. The stream crossings
are a shorter horizontal and vertical distance, and the streams are smaller than in comparison to
Alignments 1 and 2. The recommended structure are two multi-plate culverts are 20’ long and 10’ tall.
Due to the shorter spans, a bridge is not recommended for this alignment.
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
During construction, the streams would need to be diverted since a sheet pipe foundation would be
installed. A sheet pile foundation was preferred over a spread footing foundation because of ease of
construction and resilience in seismic events. The multiplate structures would need to be shipped up while
precast culverts could be constructed locally. In the case of a flood event, the water would rise above the
foundation and while it is unlikely to overflow the culvert, debris and ice could create problems in the
future. A concrete box culvert would have similar advantages and disadvantages.
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
APPENDIX L
Alternative Analysis Memo
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
MOUNTAIN AIR DRIVE ALIGNMENT ALTERNATIVES
A weighted-average matrix was used to select the preferred alternative alignment consisted of the
following criteria: capital costs, future maintenance costs, environmental impact, mobility and
accessibility, and public opinion. With the direct and indirect budgets involved with the project, capital
costs were the most heavily weighted, and future maintenance costs were also considered. Other criteria
were weighted according to their relation with primary and secondary purpose and needs for the project,
and their anticipated value for the public and client.
Table 1 displays the criteria matrix and rankings for the Alternative Alignments.
The No Build alternative was considered and was assigned values for each criterion.
For capital costs, the higher the value, the cheaper the alternative. When comparing between the
alternatives, assigned values were primarily balanced between total linear feet of roadway, the type of
structural crossing, potential right-of-way (ROW) acquisitions, and potential utility conflicts.
When analyzing the considerations, for total feet of roadway, Alignment 1 has the shortest potential
roadway through the project area, with Alignment 2 being only a few hundred feet longer. Alignment 3 is
much longer than the other two. For the crossing, Alignment 1 is designed with a single-span bridge,
Alignment 2 has a multi-plate arch culvert, and Alignment 3 has two multi-plate arch culverts. For ROW,
Alignments 1 and 2 project to acquire a significant amount of ROW. Alignment 3 primarily follows
Municipality of Anchorage (MOA) platted ROW around the project area, although will need additional
ROW. For potential utility conflicts, Alignment 1 and 2 have similar utility impacts. For several hundred
feet of Alignment 3, hanging utilities are next to the designed corridor. Further investigation is needed to
determine if the hanging utilities will need to be relocated.
For future maintenance costs, the higher the value, the cheaper the alternative. When comparing the
alternatives, assigned values were primarily between total linear feet of roadway to be maintained, and the
type of structural crossing.
When analyzing the considerations, for total feet of roadway to be maintained, especially in the winter,
Alignment 1 has the shortest potential roadway through the project area, with Alignment 2 being only a
few hundred feet longer. Alignment 3 is much longer than the other two. For the structural crossings, the
single-span bridge for Alignment 1 would require biennial inspections. The culverts designed for
Alignment 2 and 3 do not require inspections.
For environmental impact, the higher the value, the greater the impact. When comparing between
alternatives, assigned values were primarily balanced between proximity to MOA-classified wetlands,
presence with respect to the floodplain of Little Rabbit Creek, and potential impacts with wildlife.
When analyzing the considerations, for proximity to wetlands, Alignment 1 avoids all area defined
wetlands. Alignment 2 does not encroach, but comes near some wetlands that are to the east of the
alternative. Alignment 3 crosses through wetlands on the east side of the project area and passes next to
other wetlands before reaching the cul-de-sac. For the impact on Little Rabbit Creek, the retaining wall
for the single-span bridge does not enter the 100-year floodplain. The culverts for Alignments 2 and 3 will
be installed in the 100-year floodplain. For wildlife impacts, the single-span bridge for Alignment 1
would not impact the game trails along Little Rabbit Creek. The culverts for Alignments 2 and 3 need
further analysis to consider potential interactions with area wildlife, including bull moose and
anadromous fish.
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
For mobility and accessibility, the higher the value, the stronger the perception that alternative meets the
characteristic. Other collector roads in the area, Goldenview Drive to the west, and Clarks Road to the
northeast, were used as comparables for the new Mountain Air Drive alignment.
When analyzing the characteristics over the undeveloped project area, for mobility, Alignment 1 does not
have any stop-controlled intersections, and all curve radii are larger than the DCM recommended
minimum of 600 feet (Table 1-9). It was designed to perform similarly to the comparables and directly
address the purpose and need of the project, secondary egress and secondary access for emergency
services, and serves as a mainline thoroughfare through the project area. Alignment 2 has one stop-
controlled intersection. Alignment 3 has three stop-controlled intersections. Alignment 2 and 3 are
constrained by the corner at the southwest corner of Bear Valley Elementary School (BVES). To avoid
acquiring school property, the alignments were designed with a curve radius less that the DCM
recommended minimum. For accessibility throughout the vicinity, Alignment 1 does not project to
provide direct access to future residents, and local roads would need to be installed to develop the area.
Alignment 2 projects to serve slightly more parcels than Alignment 1. Following MOA platted ROW
around the project area, Alignment 3 addresses a secondary purpose and need of the project for future
development with its route.
For public opinion, alternatives were assigned values from public feedback. At the time of ranking, public
opinion data showed an interest in moving forward with the project, but no data existed in differentiating
the alternative alignments.
Table 1: Alignment Criteria Matrix Rankings
RABBIT CREEK ROAD / MOUNTAIN AIR DRIVE INTERSECTION ALTERNATIVES
The intersection matrix used the following criteria to determine the selection of the preferred alternative:
the cost, maintenance, public opinion, traffic flow, safety, and flexibility.
Table 2 displays the criteria matrix and rankings for the Alternative Alignments.
The cost is regarding the initial cost of the alternative and the maintenance is regarding the cost over time
to maintain that alternative. The higher the value, the cheaper the alternative is. The no-build option has
the highest rating for these two criteria, as it will have need minimal cost to maintain the current
condition. The traffic signal is the lowest rated amongst the other alternatives, as the initial cost of the
traffic signal is the highest amongst the others. Traffic signals would require the multi-conductor cables to
be installed and signal wiring to be implemented underneath the roads. The maintenance cost of the traffic
signal is also approximately $10,000.00 per year. The roundabout and turn lanes alternative were rated in
the middle, as it is not as expensive as traffic signals, but still requires a significant cost. Turn lanes would
require an additional ROW acquisition and reallocation of the cross-section to include additional turn
UAA CED 2021.02
AMATS: Mountain Air Drive Extension Design Study Report
lanes on the road. In order to account for a traffic signal to be installed in the future when traffic volumes
increase, signal wiring should be installed in preparation. The roundabout has a higher upfront cost due to
the installation of the roundabout design but would not require any special maintenance cost like a traffic
signal would.
The public opinion was based on the Rabbit Creek Community Council meeting. The public was in favor
of improvements being done and preferred a roundabout to be placed at the intersection between Rabbit
Creek Road and Mountain Air Drive. Thus, the roundabout was rated higher than the other alternatives
due to the community’s opinion.
The traffic flow is in regard to how stable the flow of traffic is due to these improvements. In its current
condition, should the Mountain Air Drive extension be built, the level of service would go from a rating
of B (Stable Flow, slight delays) to F (Forced flow, jammed) based on the USKH study. An acceptable
level of service is a minimum of rating D (Approaching unstable flow). The roundabout was rated highest
in the design criteria matrix, as the level of service would exceed the others. The turn lane would have an
acceptable flow of traffic, but would require a traffic signal to be installed when traffic volumes increase.
The improper usage of a traffic signal would cause delays at the intersection, so it must be used in
conjunction with a turn lane.
The safety criteria is in regards to the safety of both the drivers and pedestrians. Studies have shown that
roundabouts are the safest in terms of preventing crashes. Turn lanes were the next highly rated
alternative, as providing an additional lane specifically for through-traffic prevents the severity of crashes
at the intersection. Traffic signal, while provides an easier understanding for pedestrian crossing, does not
prevent the severity of crashes as much as the other alternatives do.
The flexibility criteria was based on its usefulness in the future should further expansion be done in the
area. Turn lanes allow the intersection to also install a traffic signal should traffic volumes increase. A
single-lane roundabout can later be upgraded to a multilane roundabout to accommodate for an increase
in traffic volume. A traffic signal installed in its existing condition would require the installation of turn
lanes, as it would be a detriment to the traffic flow and can cause further delays during the peak AM and
PM hours.
Table 2: Intersection Criteria Matrix Rankings