Pool Schedule Delay

Pool DelaysPool phase began as scheduled on June 1st. Removal of plaster revealed concrete

degradation of the shell.Walls have deteriorated in multiple areas.Rebar inside the walls have rusted.Existing wall has been determined to be

unfit.N0 indication of this condition was evident

prior to removal of the plaster coat.

FindingsRe-plastering began our final phase of

renovations.Project was proceeding on schedule with best

efforts put forth to re-open July 1st. Structural Engineer, Soil testing agency, and Pool

Builder were consulted for opinions and recommendations.

Although this delay is unavoidable, we are working diligently to finalize the change in scope and deliver an exceptional amenity for our residents and guests.

About GuniteA mixture of cement, sand, and water applied

through a pressure hose, producing a dense hard layer of concrete .

It is mixed on site and sprayed into a form creating a pool shell.

Gunite provides structural stability and is the base to which plaster is applied.

Deteriorated wall section

Rusted rebar inside wall

Degraded shell section

Water intrusion through wall

Water seeping through wall

Next StepsConstruction plans are now being developed.Permit for constructing new pool is required.Other renovation work is near completion.Build new pool.Reopen indoor pool as soon as possible.