rohleder presentation

Post on 24-Oct-2014

16 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

Segmental Bridge Technology –Established and Evolving

W. Jay Rohleder, Jr, P.E., S.E. Senior Vice President / Project Development

FIGG

1

Segmental Bridge Topics Addressed

• Definition of concrete segmental bridge construction methods and related design considerations.

• The evolution of concrete segmental bridge technology over the past 30 years in the U.S.

• Design principles and practices that provide the economic and durability value for this structure type.

• Continuing evolution of the segmental bridge construction technology and related design concepts.

2

Definition of Segmental BridgesBridges, that are typically concrete box structure types, constructed using repetitive elements that are progressively connected together to form a completed structure. Construction Load Cases are particularly critical considerations in developing the design and building methods for segmental bridges.

3

CABLE STAYED BRIDGESCABLE STAYED BRIDGES

LONG SPAN BRIDGESLONG SPAN BRIDGES ENVIRONMENTALLY SENSITIVEENVIRONMENTALLY SENSITIVE

LONG BRIDGES OVER WATERLONG BRIDGES OVER WATER ARCHESARCHES

URBAN BRIDGESURBAN BRIDGES

SEGMENTAL BRIDGE APPLICATIONS

RAIL BRIDGESRAIL BRIDGES

4

Segmental Bridge Methods, Components and Evolution

of the Technique

5

Segmental Construction Methods• SPAN-by-SPAN (Precast)

• CANTILEVER (Precast or Cast-in-Place)> Balanced> Uni-Directional

• INCREMENTAL LAUNCH(Typically an Inefficient use of materials,

so Not commonly used –need tangent or constant curvature)

6

Segmental Construction Methods• Span by Span

JFK AirTrain, NY City

7

• Balanced Cantilever

Sagadahoc Bridge, ME

Segmental Construction Methods

8

• Uni-Directional Cantilever (shown)• Mixed Methods

Garcon Point Bridge, FL

Segmental Construction Methods

9

Precast Joints

• Keys (i.e. no reinforcing across joints)• Epoxy

– Temporary Clamping– Temperature

10

• Reinforcing Bars• Joint Preparation• Bulkheads

Cast-in-Place Joints

11

Post-Tensioning (PT) Arrangements

Layout Orientation• Longitudinal

– Span by Span– Cantilever

• Transverse• Vertical

Placement Type• Internal Tendons• External Tendons

12

• Internal Tendons– Transverse– Longitudinal

(Cantilever)

Post-Tensioning (PT) Arrangements

13

Post-Tensioning

Pre-Tensioning

Internal Transverse Pre-Stressing

14

• External Tendons, LongitudinalSingle Point Deviators

Post-Tensioning (PT) Arrangements

15

• External Tendons, LongitudinalMulti-Point Deviators

Post-Tensioning (PT) Arrangements

16

Post-Tensioning (PT) Arrangements

• Vertical Tendons(in Precast Piers)

17

Construction Engineering• Camber• Geometry Control• Prestressing Parameters• Erection Loads• Erection Equipment• Casting and Erection Manuals• Integrated Shop Drawings

18

Precasting Yard Operations

• Pre-Tied Reinforcing Cage Jigs• Casting Beds

> Long Line> Short Line

• Storage & Delivery

19

• Long Line Segment Casting

20

• Short Line Segment Casting

21

TYPICAL CASTING YARD LAYOUT

Batch Plant

Segment Storage

Rebar Jigs

Casting Beds

Segments in Storage

Possible Double Stack

22

JFK AirTrain, NY, NY

9 Miles of Elevated Precast Segmental Bridge

23

• 5,500 Segments• 14 Casting Cells

Precasting Facility - JFK AirTrain

24

Precasting Facility - JFK AirTrain

25

Segment DeliveryPrecasting Facility - JFK AirTrain

26

I-93 Viaducts & Ramps, Boston, MA

27

Precast plant 85 miles away by truckPrecasting Facility – I-93 Viaducts, Boston

85 Mile

s

28

• 15 Acres• 1250 Segments• Casting Cells

4 Typ., 1 Combined

Precast plant in Sanford, MEPrecasting Facility – I-93 Viaducts, Boston

29

Central concrete delivery - casting 3 beds / dayPrecasting Facility – I-93 Viaducts, Boston

30

• 1040 – Total Segments(958 Typical, 82 Specialty)

• 3 - Typical Casting Cells• 1 - Specialty Casting Cell

Precasting Facility – Susquahanna River, PA.

31

Susquehanna River Bridge, PA

• Assembly Line – Reinforcing Cage Jig

32

• Assembly Line – Casting Bed Set-Up

Susquehanna River Bridge, PA

33

Match CastSegment

Wet CastSegment

34

• Assembly Line – Segment Pour

35

• Assembly Line – Steam Cured Segments

Susquehanna River Bridge, PA

36

• Segment Storage Handling,Lifting with Strap under Wing

Susquehanna River Bridge, PA

37

• Segment Handling

Lifting with Bars through Lifting Holes

38

1

2

3

• Segment Storage

Three Point Supports

39

• Segment Storage

Double Stacking

40

PRECAST SUPERSTRUCTUREComparison Table

Project: Susq. I-93 JFK Victory Sagadahoc(Pa.) (Ma.) (NY) (NJ) (Maine)

No. Segments - 1040 1250 5409 927 202 Max. Wt. (Tons) - 105 80 38 82 100 No. Typical Beds - 3 4 11 8 1 Casting Yard Size - 20 A 15 A N/A N/A 12 A

Cast 1 Segment / Day / Bed

41

Precast SegmentalSpan-by-Span Construction

42

SECTION A-AA

A

Typical Span-by-Span Erection

43

•Advance Truss to Next Span

Typical Span-by-Span Erection

44

•Deliver Segments•Set Segments

Typical Span-by-Span Erection

45

•Deliver Segments•Set Segments

Typical Span-by-Span Erection

46

•Epoxy Joints•Join Segments

•Deliver Segments•Set Segments

Typical Span-by-Span Erection

47

•Epoxy Joints•Align Pier Segm.

•Deliver Segments•Set Segments

Typical Span-by-Span Erection

48

•Align Pier Segm.•Thread Tendons•Cast Closure

•Deliver Segments•Set Segments•Epoxy Joints

Typical Span-by-Span Erection

49

•Stress Tendons•Lower Truss andRepeat Process

SECTION A-AA

A

Typical Span-by-Span Erection

50

- Underslung Trusses- Overhead Gantry- Falsework Supports

Precast Span-by-SpanSegments Erected using:

51

ERECTION TRUSSES – Under Bottom Soffit

52

Deck Designed for Support ConditionERECTION TRUSSES – Under Wings

53

ERECTION with OVERHEAD GANTRY

54

• Tower on FoundationERECTION TRUSS SUPPORTS

55

• Pier BracketERECTION TRUSS SUPPORTS

56

Delivery of Segments from AboveSpecialized Erection Equipment

WMATA, VA

57

SPAN-BY-SPAN CONSTRUCTION EXAMPLEMay 2007

Susquehanna River Bridge, PA

58

Casting Yard

Pennsylvania Turnpike

Commission

Bridge –East Approach

Susquehanna River Bridge, PA

59

West EndCalverIslandEast End

Casting Yard

New WB

New EB

Existing Bridge

Twin Bridges with each:• 5,910’ Long by 57’ Wide• 40 Spans – 35 @ 150’, 5 @ 132’• 21 River Piers• 18 Land Piers

Susquehanna River Bridge, PA

60

ONE

THREE

TWO

ERECTION PHASES

Susquehanna River Bridge, PA

61

Casting YardCasting Yard

Segment Segment ErectionErection

Access RoadAccess Road

Susquehanna River Bridge, PA

62

Susquehanna River Bridge, PA

Segments Delivered from Storage

63

Segments Delivered from Above

Susquehanna River Bridge, PA

64

Susquehanna River Bridge, PA

65

Susquehanna River Bridge, PA

66

Susquehanna River Bridge, PA

67

Susquehanna River Bridge, PA

Segment Alignment

68

Susquehanna River Bridge, PA

69

Susquehanna River Bridge, PA

70

Susquehanna River Bridge, PA

ELEVATION

SECTION VIEWS

71

Susquehanna River Bridge, PA

72

Susquehanna River Bridge, PA

Activities Off the Critical Path

73

Achieved Typical Span x Span

Erection Rate of 2 Spans per Week

Susquehanna River Bridge, PA

74

VERTICAL CLEARANCES

RAILROAD LINESLOCAL AIRPORT

Susquehanna River Bridge, PA

75

November 2004 - NTPMay 2007 - New Bridge Complete

Susquehanna River Bridge, PA

76

• Quick, Simple Erection (2 - 3 Spans / Week)• Easy Geometry Control• Savings from less MOT• Minimum User Delays• Cost Effective• Simple Design• Durable Structures

ADVANTAGES OF SPAN-BY-SPAN

Beautiful Bridges

77

Precast SegmentalBalanced Cantilever Construction

78

Balanced Cantilever Erection

ERECTION SEQUENCE I

79

Balanced Cantilever Erection

ERECTION SEQUENCE II

80

ERECTION SEQUENCE IV

ERECTION SEQUENCE III

Balanced Cantilever Erection

81

- Barge-mounted cranes- Ground based cranes- Beam and Winch- Overhead Gantry

Precast Balanced Cantilever Segments Erected using:

82

BALANCED CANTILEVER EXAMPLE

September 2007

Victory Bridge, NJ

• Twin 3,971’ Long Bridges• Main Span Unit 330’, 440’, 330’• 100’ Tall Precast Piers• SxS Appr., B.C. Main Span Unit

83

Victory Bridge, NJ

84

Victory Bridge, NJ

85

Victory Bridge, NJ

86

Victory Bridge, NJ

87

Victory Bridge, NJ

88

Victory Bridge, NJ

89

Victory Bridge, NJ

90

Average production:4 to 6 segments/day (45 ft)

Balanced Cantilever Erection

Victory Bridge, NJ

91

Victory Bridge, NJ

1st Bridge Open to Traffic in 15 mo.2nd Bridge Completed in 9 mo.

92

Cast-in-Place SegmentalBalanced Cantilever Construction

93

Wabasha Street Bridge, MN

1,248’ Long Twin Bridgeswith 398’ Main Spans

94

Wabasha Street Bridge, MN

95

Wabasha Street Bridge, MN

Continue through the Winter

96

Blending shapes, texture and color Wabasha Street Bridge, MN

97

Segmental BridgesMixing Construction Erection

Methods

98

Sagadahoc Bridge, ME

3,000’ Bridge with420’ Main Span

over Kennebec River

99

68’ Roadway with2 Cell Box Girder

Cast-in-Place Approach Units, with Precast

Main Span Unit Sagadahoc Bridge, ME

100

520,000 sf of Structures - Completed Nov. 2002

I-93 Ramps & Viaducts, Boston MA

101

I-93 Ramps & Viaducts, Boston MA

Span-by-Span Construction

102

I-93 Ramps & Viaducts, Boston MA

Balanced Cantilever Construction

103

Mid-Bay Bridge, FL

• Span-by-Span Approaches• One-Directional Cantilever Main Span

CIP low level piers

P/C high level piers

104

Precast Segmental Piers

105

Precast Piers

Directionof Erection

Erect 1 Segment an Hour,Approximately 1 Pier per Day

106

Victory Bridge, NJ

107

First segment cast6 weeks after NTP

Precast Piers

Victory Bridge, NJ

108

Precast Piers Casting Bed

Victory Bridge, NJ

109

Typical Precast Pier Details

110

Precast Pier Erection

Victory Bridge, NJ

111

Precast Pier Erection

Victory Bridge, NJ

112

Precast Pier Erection

Victory Bridge, NJ

113

Precast Pier Erection

Victory Bridge, NJ

114

Precast Pier Erection

Victory Bridge, NJ

115

Precast Pier Erection

Victory Bridge, NJ

116

First pier erected5 months after NTP

Completed Precast Piers

Victory Bridge, NJ

117

Cable StayedSegmental Superstructure

118

U.S. Senator William V. Roth Jr. Bridge over C&D Canal, DE

1st concrete cable-stayed bridge in the Northeast – 1995

119

Entirely Precast Segmental Bridge

U.S. Senator William V. Roth Jr. Bridge over C&D Canal, DE

120

Segmental Cable-Stay BridgesI-280 Veterans’ Glass City Skyway, Ohio

1,225’ main span (2 @ 612’-6”)

Penobscot Narrows Bridge& Observatory, Maine (1,161’ main span)

Open Dec. 2006

Open June 2007

121

Veterans’ Glass City SkywayPrecast SuperstructureCompleted in 8 Months

New Penobscot Narrows BridgeCast-in-Place SuperstructureCompleted in 15 Months

122

Penobscot Narrows Bridge & Observatory, ME

123

CIP Balanced Cantilever Construction

FormTraveler

FormTraveler

Penobscot Narrows Bridge & Observatory, ME

124

Penobscot Narrows Bridge & Observatory, ME

125

Penobscot Narrows Bridge & Observatory, ME

126

Carbon Fiber Composite Strand Demonstration Project

Penobscot Narrows Bridge & Observatory, ME

127

Veteran’s Glass City Skyway, Ohio

Veteran’s Glass City Skyway, OH

128

Typical Pre-Cast Cross-Sections: Main SpanVeteran’s Glass City Skyway, OH

129

Main Span Precast Segmental Construction

• Backspans: Span-by Span• Mainspan: One-Directional Cantilever

Veteran’s Glass City Skyway, OH

130

• 3 pairs of segmentserected in cantilever– Epoxied segment joints– Segments post-tensioned

Veteran’s Glass City Skyway, OH

131

Segmental Bridge Construction Benefits• Rapid Construction• Segments Delivered over Completed Spans

– No Need for Barge Delivery• Maintained Shipping Lanes at All Times

– Access to Port of Toledo

Veteran’s Glass City Skyway, OH

132

Review Questions• Define a segmental concrete bridge structure type?• List 3 methods for constructing segmental bridges? • List benefits during construction that result from

using a segmental bridge construction technique?• List permanent bridge site layout benefits resulting

from using a segmental box girder bridge type?• What structural benefits apply to using a closed cell

box girder for a segmental bridge?• What segmental bridge technological advances offer

the most immediate benefits?

133

Open-ended Assignment Questions

Can you identify a viable candidate location for a segmental bridge given your understanding of the potential benefits from using this structure type?

What new innovative applications of the segmental bridge construction technique can you envision?

134

America Deserves Beautiful

Bridges

135

top related