HAYS CISD TRANSPORTATION (PROJECT 162090)

WEEKLY PROGRESS REPORT: FEBRUARY 22, 2019

ANTICIPATED DATE OF SUBSTANTIAL COMPLETION: APRIL 23, 2019

Fuel Depot Canopies

Bus Wash area graded.

This Week’s Activities:

• Area B canopy erection

• Fuel Depot canopy erection

• Ceiling grid dropped throughout Area A

• PEMB trim, ridge cap, wall panels.

• Area B Mechanical and Electrical overhead.

• Overhead MEP devices in progress Area A

• Forming and reinforcement for 2nd to last

paving pour, grading in bus wash.

Forming and reinforcing 2nd to last paving pour.

Area B canopy erection

Upcoming Activities:

• Final 2 paving pours

• Flatwork

• Perimeter fencing

• Complete PEMB

• Area B mechanical and electrical

• Aluminum canopy installation

• Lighting and AV installation.