7901 EAST RIVERSIDE, BUILDING 2, SUITE 100 (512) 326-4223 WWW.BARTLETTCOCKE.COM HAYS CISD TRANSPORTATION (PROJECT 162090) WEEKLY PROGRESS REPORT: FEBRUARY 22, 2019 ANTICIPATED DATE OF SUBSTANTIAL COMPLETION: APRIL 23, 2019 Fuel Depot Canopies Bus Wash area graded. This Week’s Activities: Area B canopy erection Fuel Depot canopy erection Ceiling grid dropped throughout Area A PEMB trim, ridge cap, wall panels. Area B Mechanical and Electrical overhead. Overhead MEP devices in progress Area A Forming and reinforcement for 2 nd to last paving pour, grading in bus wash. Forming and reinforcing 2 nd to last paving pour. Area B canopy erection Upcoming Activities: Final 2 paving pours Flatwork Perimeter fencing Complete PEMB Area B mechanical and electrical Aluminum canopy installation Lighting and AV installation.

Upload: others

Post on 01-Jun-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: WEEKLY PROGRESS REPORT FEBRUARY ANTICIPATED DATE OF

7901 EAST RIVERSIDE, BUILDING 2, SUITE 100 ∙ (512) 326-4223

WWW.BARTLETTCOCKE.COM

HAYS CISD TRANSPORTATION (PROJECT 162090)

WEEKLY PROGRESS REPORT: FEBRUARY 22, 2019

ANTICIPATED DATE OF SUBSTANTIAL COMPLETION: APRIL 23, 2019

Fuel Depot Canopies

Bus Wash area graded.

This Week’s Activities:

• Area B canopy erection

• Fuel Depot canopy erection

• Ceiling grid dropped throughout Area A

• PEMB trim, ridge cap, wall panels.

• Area B Mechanical and Electrical overhead.

• Overhead MEP devices in progress Area A

• Forming and reinforcement for 2nd to last

paving pour, grading in bus wash.

Forming and reinforcing 2nd to last paving pour.

Area B canopy erection

Upcoming Activities:

• Final 2 paving pours

• Flatwork

• Perimeter fencing

• Complete PEMB

• Area B mechanical and electrical

• Aluminum canopy installation

• Lighting and AV installation.