APPLICATION OF PRIMAVERA SOFTWARE FOR
SCHEDULING OF ROW HOUSE TO COMPLETE PROJECT
ON TIME Nisarg M. Mistry
1, Mayank A. Kanani
2, Dr. Neeraj D. Sharma
3, Rushabh A. Shah
4
PG. Student, SNPIT & RC, Umrakh, Gujarat, India1
PG. Student, SNPIT & RC, Umrakh, Gujarat, India2
Professor & HOD, Civil Engineering Dep. , SNPIT & RC, Umrakh, Gujarat, India3
Asst. Prof., , SNPIT & RC, Umrakh, Gujarat, India4
Abstract: In this project a case study is taken for our project situated at Tirupati society
Kadoli Road, Maroli of Sureshchandra Maganbhai Patel. By interviewing contractor we
knew that by conventional techniques of construction is very long due to no forecast of
how the whole project finish. In this case study we applied primavera P6 without resource
allocation to give the way to contractor to finish the project by arranging the whole
activities of project in step by step.
Keywords: Primavera P6, Schedule, Case Study, Activity relationship chart
INTRODUCTION
In the older days the software were not used in construction projects. No planning or
scheduling was done for small house it was directly executed by contractor and
planning was done manually. Now a day’s architectural planning is done on software
but the work execution schedules are not prepared so most of projects are delayed and
cost overrun occurs. This is the attempt made to achieve control over small residential
project with use of software. The present study is for optimizing plan of building to
reduce cost and decrease time of construction by scheduling. By working on a case
study of residential building. The aim of this project is to reduce the wastage of material
and manpower in a small construction project and reduce possibility of time and cost
overrun. Schedule of building execution will be prepared on the basis of planning and
specifications.
ORACLE SOFTWARE PRIMAVERA P6 & Autodesk AutoCAD
i. PRIMAVERA P6:
Primavera Systems is the brand name under which a range of software packages that
collectively form a comprehensive enterprise project portfolio management (EPPM)
solution are marketed. Primavera was launched in 1983 by Primavera Systems Inc. and was
acquired by Oracle Corporation in 2008.Primavera software includes project management,
collaboration and control capabilities and integrates with other enterprise software such
as Oracle or SAP’s ERP systems.
IJARESM
All rights reserved by www.ijaresm.net ISSN : 2394-1766 2
Primavera’s Project Management module is comprehensive, multi project planning and
control software, built on SQL, Oracle, and SQL Server Express server databases for
organization-wide project management scalability. The module can stand alone for project
and resource management, or it can be used with companion Primavera products to manage
your project portfolios.
ii. AutoCAD:
AutoCAD is a commercial software application for 2D and 3D computer-aided design
(CAD) and drafting available since 1982 as a desktop application and since 2010 as a mobile
web- and cloud-based app marketed as AutoCAD 360.
Developed and marketed by Autodesk, Inc., AutoCAD was first released in December 1982,
running on microcomputers with internal controllers. Prior to the introduction of AutoCAD,
most commercial CAD programs ran on mainframe computers or minicomputers, with each
CAD operator (user) working at a separate graphics.
AutoCAD is used across a wide range of industries, by architects, project managers,
engineers, designers, and other professionals. It is supported by 750 training centers
worldwide as of 1994.As Autodesk's flagship product, by March 1986 AutoCAD had become
the most ubiquitous CAD program worldwide. As of 2014, AutoCAD is in its twenty-ninth
generation, and collectively with all its variants, continues to be the most widely used CAD
program throughout most of the world.
CASE STUDY:
(TABLE 1: CASE STUDY DATA)
Case study: Residential Bungalow Residential Bungalow
Name of owner: Mr. Sureshchandra Maganbhai Patel
Address: At Tirupati society Kadoli Road, Marolibazar,
Maroli, Navsari Ubhrat road, Gujarat.
Plot area: 920 sq-ft
Built-up area: G.F.707.5 sq.ft.
F.F. 816.5 sq.ft.
Rooms: Ground floor: 2BHK
First floor: 2BHK
Parking: Two-wheeler parking
Contractor:
(Surat)
Here an above mentioned case study is taken and plans from contractor are taken for further
process. By applying Primavera P6 we can made schedule of all activities which include
starting to finish the project. This attempt had a power that reduce the time of completion of
project
IJARESM
All rights reserved by www.ijaresm.net ISSN : 2394-1766 3
Figure 1: Ground Floor Contractor Plan
IJARESM
All rights reserved by www.ijaresm.net ISSN : 2394-1766 4
Figure 2: First Floor Contractor Plan
IJARESM
All rights reserved by www.ijaresm.net ISSN : 2394-1766 5
SCHEDULE OF PLANNING BY PRIMAVERA P6 :
(TABLE 2: SCHEDULE OF PLANNING)
Activity
ID Activity Name WBS Name
Ori
gin
al
Du
rati
o
n
Start Finish
A1000 SITE
CLEARANCE
SUB
STRUCTURE 1 11-Nov-14 11-Nov-14
A1010 LAYOUT
MARKING
SUB
STRUCTURE 1 11-Nov-14 12-Nov-14
A1020 EXCAVATION SUB
STRUCTURE 2 12-Nov-14 14-Nov-14
A1030 PCC FORMWORK 1 14-Nov-14 15-Nov-14
A1040 PCC CASTING WORK 1 15-Nov-14 16-Nov-14
A1050 FOOTING FORMWORK 1 16-Nov-14 17-Nov-14
A1060 FOOTING STEEL WORK 2 17-Nov-14 18-Nov-14
A1070 FOOTING CASTING WORK 1 19-Nov-14 19-Nov-14
A1080 COLUMN UP TO
G.L. FORMWORK 1 19-Nov-14 20-Nov-14
A1090 COLUMN UP TO
G.L. STEEL WORK 2 20-Nov-14 22-Nov-14
A1100 COLUMN UP TO
G.L. CASTING WORK 1 22-Nov-14 23-Nov-14
A1110 BACK FILLING SUB
STRUCTURE 1 23-Nov-14 24-Nov-14
A1120 G.B. PCC SUPER
STRUCTURE 1 25-Nov-14 26-Nov-14
A1130 GROUND BEAM FORMWORK 1 26-Nov-14 26-Nov-14
A1140 GROUND BEAM STEEL WORK 2 27-Nov-14 28-Nov-14
A1150 GROUND BEAM CASTING WORK 1 28-Nov-14 29-Nov-14
A1160 PLINTH G.B. TO
P.B. MASONARY 2 29-Nov-14 01-Dec-14
A1170 PLINTH G.B. TO
P.B. PLASTER 1 01-Dec-14 02-Dec-14
A1180 COLUMN UP TO
G.B. TO P.B. FORMWORK 1 02-Dec-14 03-Dec-14
A1190 COLUMN UP TO
G.B. TO P.B. STEEL WORK 2 03-Dec-14 04-Dec-14
A1200 COLUMN UP TO
G.B. TO P.B. CASTING WORK 1 05-Dec-14 05-Dec-14
A1210 PLINTH BEAM FORMWORK 1 05-Dec-14 06-Dec-14
A1220 PLINTH BEAM STEEL WORK 2 06-Dec-14 08-Dec-14
A1230 PLINTH BEAM CASTING WORK 1 08-Dec-14 09-Dec-14
A1240 GRADE SLAB FORMWORK 1 11-Dec-14 12-Dec-14
IJARESM
All rights reserved by www.ijaresm.net ISSN : 2394-1766 6
Activity
ID Activity Name WBS Name
Ori
gin
al
Du
rati
o
n
Start Finish
A1250 GRADE SLAB STEEL WORK 2 12-Dec-14 13-Dec-14
A1260 GRADE SLAB CASTING WORK 1 13-Dec-14 14-Dec-14
A1270 BACK FILLING G.B.
TO P.B.
SUPER
STRUCTURE 1 09-Dec-14 10-Dec-14
A1280
A1290
COLUMN UP TO
P.B. TO GROUND
SLAB
COLUMN UP TO
P.B.
FORMWORK
STEEL WORK
1
2
19-Dec-14
20-Dec-14
20-Dec-14
21-Dec-14
A1300
GROUND SLAB
COLUMN UP TO
P.B. TO
CASTING WORK 1 21-Dec-14 22-Dec-14
A1310 GROUND SLAB
GROUND SLAB FORMWORK 3 22-Dec-14 25-Dec-14
A1320 GROUND SLAB STEEL WORK 2 25-Dec-14 27-Dec-14
A1330 GROUND SLAB CASTING WORK 1 27-Dec-14 28-Dec-14
A1340 COLUMN UP TO
G.S. TO F.S. FORMWORK 1 01-Jan-15 02-Jan-15
A1350 COLUMN UP TO
G.S. TO F.S. STEEL WORK 2 02-Jan-15 04-Jan-15
A1360 COLUMN UP TO
G.S. TO F.S. CASTING WORK 1 04-Jan-15 05-Jan-15
A1370 FIRST SLAB FORMWORK 3 05-Jan-15 07-Jan-15
A1380 FIRST SLAB STEEL WORK 2 07-Jan-15 09-Jan-15
A1390 FIRST SLAB CASTING WORK 1 09-Jan-15 10-Jan-15
A1400 GROUND FLOOR MASONARY 5 14-Dec-14 19-Dec-14
A1410 GROUND FLOOR
1ST COAT PLASTER 1 26-Jan-15 27-Jan-15
A1420 FIRST FLOOR MASONARY 5 28-Dec-14 01-Jan-15
A1430 FIRST FLOOR 1ST
COAT PLASTER 1 27-Jan-15 28-Jan-15
A1440 GROUND FLOOR
2ND COAT PLASTER 2 28-Jan-15 29-Jan-15
A1450 FIRST FLOOR 2ND
COAT PLASTER 2 30-Jan-15 31-Jan-15
A1460 COLUMN FOR
STAIR CABIN FORMWORK 1 10-Jan-15 11-Jan-15
A1470 COLUMN FOR
STAIR CABIN STEEL WORK 2 11-Jan-15 13-Jan-15
A1480 COLUMN FOR
STAIR CABIN CASTING WORK 1 13-Jan-15 13-Jan-15
IJARESM
All rights reserved by www.ijaresm.net ISSN : 2394-1766 7
ACTIVITY RELATIONSHIP CHART WITH DATE
Activity
ID Activity Name WBS Name
Ori
gin
al
Du
rati
on
Start Finish
A1720 SLAB OF STAIR
CABIN
STEEL
WORK 2
16-
Jan-15
18-Jan-
15
A1730 SLAB OF STAIR
CABIN
CASTING
WORK 1
18-
Jan-15
19-Jan-
15
A1740
A1750
G.F. FRAME OF DOOR
& WINDOW
F.F. FRAME OF DOOR &
FLOORIN
G
FLOORING
2
2
03-
Feb-15
05-Feb-15
05-Feb-
15
06-Feb-15
A1760
WINDOW
FITTING OF DOOR &
WINDOW
SUPER
STRUCTURE 2
26-
Feb-15
28-Feb-
15
IJARESM
All rights reserved by www.ijaresm.net ISSN : 2394-1766 8
IJARESM
All rights reserved by www.ijaresm.net ISSN : 2394-1766 9
TIME COMARISON
(TABLE 2: TIME COMPARISON)
Sr. no. Contractor (days) Optimized(days)
Sub structure 37 28
Super structure 71 54
Finishing work 54 41
Total 162 123
CONCLUSION
By interviewing Contractor working without softwares we found the problems in
construction, design, planning etc. like improper co-ordination between contractor and on site
working peoples, wastage of materials etc. after working on case study and applying different
softwares for applying modular coordination & optimizing for maximum benefit. The
optimized plan with software has more carpet area compared to contractor plan and the cost
for both are nearly equal to same very less cost difference is observed.
By applying primavera for arranging all activities which include in construction work
at starting to finish the project on time. We could manage to save time in all phases of
construction as we see in table 2.
IJARESM
All rights reserved by www.ijaresm.net ISSN : 2394-1766 10
REFERENCES
[01] Aline da Silva Ramos “The technique of modular coordination as policy design tool”
National Association of Technology of the Built Environment, ISSN 1678-8621 © 2005
[02] Ron Winter, “The History of Primavera Scheduling Software”, Published in February
10, 2013
[03] Alan Griffith., and Paul Wilson., “Construction Management, Principles and Practice.”
Palgrave Macmillan. pp115-180. 2004
[04] Burke, R., “Project Management, Planning and Control Techniques.” Chichester, John
Wiley and Sons.Inc. 2003
[05] Chan, J.P., JuHyung Kim, Jae-Jun Kim, and Yong, C.Y., “Management of Daily
Progress in a Construction Project of Multiple Apartment.” 2007
[06] Daniel, C.L., Gursel, A.S., Julian Gonzalez, and Yates, J.K., “Construction Project
Scheduling with Time, Cost, and Material Restrictions Using Fuzzy Mathematical
Models and Critical Path Method.” Journal of Construction Engineering and
Management. 135(10), pp1096–1104. 2009
[07] Gary, H.R., “Project Management”, McGraw Hill publication. year 2002
[08] George Alukal., and Anthony Manos., “Lean Kaizen.”ASQ quality press. 2006
[09] Hans Sommer., “Project Management for Building Construction.” Springer-
VerlagBerlin Heidelberg, London.
[10] Harold Kerzner. “Strategic Planning for Project Management using a Project
Management Maturity Model.” John Wiley and sons, Canada, pp109-139. 2001
[11] James, L.P., “Mastering Project Management.” McGraw Hil publication l,pp269-355.
2008
[12] Jason Westland., “The Project Management life Cycle.” Cambridge university press,
Great Britain. 2006
[13] Jeffrey, S.R., Edward, J.J., and Samuel, P.L., “Continuous Assessment of Project
Performance.” Journal of Construction Engineering and Management, 123(1), 64-71.
1997
[14] Kaura Mohinder, N., “Management Control and Reporting Systems”, Sage
Publications India Private Ltd., Kolkata. 2002