    Projatech, Project Planning, Scheduling & Controls Using Primavera P6 & Microsoft Project; Consulting, Training & Workforce

    http://www.projatech.com/Knowledge.html[Mon 21/05/12 10:43:16 AM]

    Construction & Engineering Project Planning, Scheduling, and Controls. Consulting Services, Training, and Workforce Provider for Primavera,PertMaster & MS Project Software | Home | Training | Scheduling Services | Schedule Quality Assurance | Project Controls| Risk Analysis| Cost Estimates| Workforce| Experience| Clients | About Us | Contact Us|

    Project Management, Training & Contract Workforce

    Operator: 1-888-864-9849

    Click To Email

    Scheduling & Project Controls Knowledge

    Send an email to [email protected] ask a question not answered in the list below. We'll answer your question as soon as possible.

    Q: Microsoft Project schedule doesn't import properly in Primavera 6.??

    Always check to see there is no blank lines between list of activities in MS Project; check the same in resource list. Also make sure none of the resources have the first 10 character the same; as Primavera truncatesresource name and if the names are the same it doesn't import properly.

    Q: Minimally, what items should I check when I am performing schedule quality assurance?

    Cri ter ia Items To Be Ch eck ed

    Project Scope All project scope to be covered in the schedule.Provide Project Execution Plan.

    Completeness Schedule is complete with equipment lists, man-hour calculations, material take-offs, bid tabs,

    quotations from vendors, construction / fab yard

    labor productivity factors, etc.

    Development

    Basis

    It is developed with the help of work experts or

    based on previous experience; not based on

    information from a single person. Why Check These Items?

    Broken Logic N o B ro ke n L og ic Act iv it ie s w it h b ro ke n log ic do no t con tr ib ut e in d ri ving th e p ro je ct an d m ay su rp ri se yo u lat er byhindering the completion of a project. Only two activities, start and finish of the project may have broken

    logic. All other activities must have at least one predecessor and one successor. An activity having all

    its successor with "SS" relationship is l ike having no successor; such activity must have another

    successor with "FS" or "FF" relationship. If there are more than two activities with broken logic, pleaseensure there is a solid reason behind it. "SF" type relationships are rare; avoid or justify these

    relationships. If there are excessive number of relationships, clean up unnecessary relationship by

    observing "Relationship Free Float" and remove those relationships having very high "Relationship Free

    Float". Excessive use of SS or FF relationship makes the logic questionable. It may compress the

    schedule unnecessary and resource overload the schedule.

    No Activities with only SS successors

    No Activities with SF Relationships (rare

    exceptions)

    Avoid excessive number of predecessor or

    successors, and avoid excessive use of SS or FF

    relationships.

    Constraints No Hard Constra ints Hard constra ints defini te ly create a misleading longest path and a ll soft constraints, necessary or not ,may create a misleading longest path. Constraints should only be used if absolutely justifiable by work

    requirement and there is no other means of developing the logic. There should not be any constraint on

    the longest path. It makes it very difficult to see the entire path. Checking longest path is necessary to

    understand if schedule logic is designed properly. Where possible, try using activities with "Expected

    Finish" instead of a constraint.

    Minimal Soft Constraints

    No Constraints on Longest Path

    Lag Minimal number of Activities with Lag (NoUnnecessary Lag. Justify all Lag)

    If project work dictates lag, then having lag is perfectly fine otherwise it may create a misleading critical

    path or unnecessarily lengthen the project. Unnecessary lag is also difficult to find and correct. Where

    possible replace lag longer than 10 days with an activity.

    Longest Path To extend from Start to Finish of Project A critical path should extended from the beginning to the end of a project. A very long or short criticalpath indicates a poor work logic or a schedule not fully developed. Just having longest path is not

    enough, having correct sequence of work and verifying significance of work is also important..Verification of Sequence and Importance of

    activities

    Critical

    Activ ities

    Verification by stakeholders When a schedule contains constraints, there may be additional critical activities in the schedule other

    than the ones on the Critical Path. Verifying and monitoring these activities is very important.Critical, Near

    Critical,

    Longest, and

    Near Longest

    Paths

    Avoid having multiple critical paths. Also avoid

    several short near critical/Longest paths. Verify

    sequence and Importance of activities or Longest

    and Near Longest paths.

    Critical path identifies those activities that determine finish of the project as of the day of review. If the

    project doesn't progress as planned, any of the near critical paths can become Critical soon. Thus,

    verifying and monitoring near critical paths is also essential. Properly sorted longest and near longest

    path helps verify quality of a schedule when verifying sequence and importance of activities on the path.

    Activ ity

    Duration

    No excessively long duration activities; Eng 7-21

    Days, Proc >3 Days, Const 3-14 Days

    Very long duration activities reflect an underdeveloped schedule. An underdeveloped schedule lacks

    efficiencies in work sequencing that can be achieved by breaking down activities to proper duration. A

    very short duration activities unnecessarily make a schedule cumbersome and unmanageable. It further

    reduces the effectiveness and utilization of a schedule. Ideally, activity duration should not be no more

    than 2-3 times schedule update cycle and no less than one update cycle.

    Free Float Minimal amount of activities with Free Float higherthan 30 days; otherwise good explanation for

    each (Procurement excluded)

    Excessive total float is a result of many activities with free float or a few activities with excessive free

    float. Too many activities with excessive free float is a sign of poor logic, broken logic, and/or schedule

    having too many parallel paths. Too many parallel paths indicates less likelihood of finishing the project

    on time.

    Total Float N o N eg at ive F lo at N eg at ive f lo at is a s ig n o f con st ra in t i n a sche du le th at ca n' t b e sat is fi ed as plan ne d. Wh en su chconstraint date is not met, negative float is created. Negative float means, work can't be performed per

    schedule logic. To correct the problem, you may take one or more of the following actions... 1. remove

    the constraint 2. Constraint date needs to be pushed into the future 3. Work needs to be expedited to

    cover negative float 4. Schedule logic needs to be changed to shorten the schedule 5. Work scope

    needs to be reduced 6. Split long duration activities to find work that can be performed in parallel 7.

    Assign more resources to shorten activity durations 8. Shorten activity duration by changing activity

    calendar for longer work-week.

    Activ ity &

    Resource Dist.

    Activ ity and Res Dist: Both similar bell-shaped

    curves

    Distribution of activities depict how well the schedule is developed. If the histogram is lopsided, it may

    mean the schedule is underdeveloped on one side or over developed on the other si de.

    http://www.alizar.com/http://www.bluecorndistribution.com/http://www.projatech.com/index.htmlhttp://www.projatech.com/Training.htmlhttp://www.projatech.com/Consulting.htmlhttp://www.projatech.com/Schedule_Quality_Assurance.htmlhttp://www.projatech.com/Project_Controls_Consultants.htmlhttp://www.projatech.com/Schedule_Risk_Analysis.htmlhttp://www.projatech.com/Estimate_Assurance.htmlhttp://www.projatech.com/Workforce.htmlhttp://www.projatech.com/Experience.htmlhttp://www.projatech.com/Client_List.htmlhttp://www.projatech.com/About_Us.htmlhttp://www.projatech.com/Contacts.htmlhttp://www.projatech.com/Contacts.htmlhttp://www.projatech.com/Contacts.htmlhttp://www.projatech.com/Contacts.htmlhttp://www.projatech.com/Contacts.htmlhttp://www.projatech.com/Contacts.htmlhttp://www.projatech.com/Contacts.htmlhttp://www.projatech.com/Contacts.htmlhttp://www.projatech.com/Contacts.htmlhttp://www.projatech.com/Contacts.htmlhttp://www.projatech.com/Contacts.htmlhttp://www.projatech.com/Contacts.htmlhttp://www.projatech.com/Contacts.htmlhttp://www.projatech.com/Contacts.htmlhttp://www.projatech.com/Contacts.htmlhttp://www.projatech.com/About_Us.htmlhttp://www.projatech.com/Client_List.htmlhttp://www.projatech.com/Experience.htmlhttp://www.projatech.com/Workforce.htmlhttp://www.projatech.com/Estimate_Assurance.htmlhttp://www.projatech.com/Schedule_Risk_Analysis.htmlhttp://www.projatech.com/Project_Controls_Consultants.htmlhttp://www.projatech.com/Schedule_Quality_Assurance.htmlhttp://www.projatech.com/Consulting.htmlhttp://www.projatech.com/Training.htmlhttp://www.projatech.com/index.htmlhttp://www.bluecorndistribution.com/http://www.alizar.com/
  • 8/12/2019 Good - Projatech, Project Planning, Scheduling & Controls Using Primavera P6 & Micr

    2/10

    Projatech, Project Planning, Scheduling & Controls Using Primavera P6 & Microsoft Project; Consulting, Training & Workforce

    http://www.projatech.com/Knowledge.html[Mon 21/05/12 10:43:16 AM]

    A sudden jump in resource requirement may be unrealistic in actual work situation. A lopsided

    distribution may also be unrealistic to achieve.

    Resource peak demands need to be verified. The question is if it realistic to acquire/have that many

    resource at one time at one location?

    Individual resource assignment and total resource assignment figures need to be verified with the

    Estimate provided by the contractor.

    Check Weekly & Monthly overall project and

    individual resource peak usage.

    Each Resource Max Limit (# of heads or crew

    size) to be verified

    Total resource units and Individual resource units

    to match the latest estimate. Provide latest

    summary estimate.

    Milestones &

    LOE Activities

    All critical and contractual milestone and LOE

    activities depicted in the top WBS (Eng, Proc,

    Const, T/A, etc)

    Proper use of milestones help summarize a schedule and monitor its progress properly. Milestones

    should be used for start of something significant, mark major accomplishments, monitor contractual

    dates or track procurement items or watch for major deliverables. Milestones can also be used to

    determine physical progress of the project, determine Earn Value and Performance Indexes. Physical

    progress can be determined within each group of activities where activities are grouped by work

    package, work area, unit, etc.

    Milestones should never be used in place of work activities!

    Not too few or too many milestone (3%-5%). No

    milestone is to replace any task activity

    Predecessors to all major milestones are verified

    to be correct

    WBS Structure Structure matching Company recommendations orprovide a good explanation

    A good WBS should follow Company recommendations and structured to match with how actual work is

    planned, such as, civil, mechanical, piping, etc. Both Cost Estimate format and Cost Breakdown

    Structure should match the WBS. The purpose of WBS is to break work down into smaller segments for

    easy progress monitoring and reporting. WBS structure is determined before schedule development

    starts in early Ph-3

    Must match cost structure & Estimate

    Primavera

    Setups

    Project Calculat ion Tab Primavera is a very flexib le and robust scheduling application. It has many defaults and configurations --

    if not properly configured it gives incorrect results. Before schedule development starts, all Primavera

    defaults should be set according to Company recommendations. These items can also be fixed later if

    not set initially.

    Project Default Tab

    Resource defaults

    Task Dependent Activity defaults and duration

    type assignment

    Risk Register Provide Updated Risk Register A risk register should be developed on Company recommended template in Ph-2 and then updatedmonthly. It helps avoid many issues that can potentially delay the project. It also helps determine

    schedule and cost contingency and provides justification for your contingency figures. It also set's

    correct expectation for project success.

    Activ ity

    Description

    To contain a Verb and enough detail for it to make

    sense when viewed by others outside its WBS

    structure

    Frequently even the people involved in schedule development don't understand description of an activity

    when reviewing schedule or providing updates; especially if the activity is observed outside its WBS.

    Thus, all activity description must contain a verb and enough detail that even an outsider could

    understand the task when outside its WBS. Shorten long description by using common acronyms or by

    removing vowels from some words, such as, "Construction" can be stated as "Cnstrctn"

    Others

    Q: Minimally, what item in a schedule should I keep an eye on during project execution?

    Criteria Description Reasoning

    (Please Do Not Edit)

    How often is project updated? During engineering: Once or Twice per month.During construction: every week or every other week.

    Is There Any Out of Sequence

    Progress?

    If there are more than 10% completed or in-progress activities

    with out-of-sequence progress, question the contractor or ;

    consider revising logic per Company schedule change

    management procedures and then update Primary baseline.

    Any significant number of Out Of Sequence progress indicates that schedule logic was not

    designed appropriately and it is not being followed. In this case, remaining logic needs to be

    improved so that it reflects a realistic work plan. Most current baseline should be updated

    accordingly.

    Has there been any modification in

    the schedule since latest baseline?

    For example: change of logic,

    addition or deletion of activities,

    changes in constraints or constraint

    date, etc.

    If any of the following is observed in comparison to the current

    Baseline, follow Company schedule change management

    procedures and update primary baseline: (Logic changes,

    Original Duration, Budgeted Units, Constraints, New Activities,

    Deleted Activities, Activity Description Change.) Also conduct

    schedule quality assurance and complete "Structural Quality"

    worksheet in this workbook.

    Any modification in the schedule may make a schedule unsuitable for comparison with the

    baseline if the baseline wasn't updated accordingly; thus making progress monitoring difficult. Any

    modification in the schedule may have major affect on finish of the entire project, or finish of one

    or more milestones. It may also reduce Total Float for many activities. Thus such modification

    may not only delay project finish date, but also make it more risky. That is why, all modification

    should be approved by stakeholders after analyzing a what-if scenario of those changes.

    Are th ere exces sive n umber of

    activities starting or finishing on

    Data Date?

    There should not be more than 2% of activities starting or

    finishing on Data Date, except when following original SS logic.

    If there are, then it means we are lagging behind in work.

    If activities are not completing or starting as scheduled they will end up on the data date. This

    reflects that either logic or activity durations weren't planned properly.

    Are th ere mor e than 5% o f remain ing

    activities In-Progress and Actual

    Duration of most of these activities

    is higher than the Original duration?

    At any time there should be approximately 5% of remaining

    activities in progress; except near project completion. It is

    especially concerning if most of these "In Progress" activities'

    actual duration is higher than original duration.

    Too many activities in progress points toward two things. 1. Contractor starts too many activities,

    claims that most of the work is completed for each activity, but the last portion of activity takes

    extremely long to complete. The contractor may do so to show better than actual performance

    and to earn more hours than actual accomplishment to get paid higher than what contractor

    deserves. 2. On the other hand, there may be issues with safety, procurement, engineering, etc.,

    that is keeping the contractor from completing those activities. If it is reason # 2, the activities

    need to be "Suspended" to keep Primavera from adding to "Actual Duration" and efforts need to

    be directed towards resolving root cause of delays.

    Is Data Date being changed and

    progress updated on regular

    intervals based on agreed timetable?

    Is schedule being updated and data date changed on regular

    intervals based on agreement with Company? If not, the

    procedures need to be established.

    Sometimes many other projects are dependent on a single project; while other times many types

    of reporting is dependent on update cycle. Thus it is important to have update cycle and data

    date changes coordinated with all other parties. For linked projects; all projects should have the

    same data date at all times.

    The value in activity field "Original

    Duration" has not been modified for

    any activity since baseline.

    1. For activities Not Started, Original Duration to Match

    Remaining and At Complete Durations; if not, correct these

    figures and change project default setting by checking "Link

    Budget and At Completion for not started activities" in Project

    "Calculations" tab.2.Activity Original Duration should not be modified in Current or

    Baseline Schedules without following Change Management

    Process and appropriate approvals. (Original Baseline is never

    modified once approved)

    The original duration is designed to keep this duration available for comparison with actual

    duration. Changing original duration makes it difficult to judge progress.

  • 8/12/2019 Good - Projatech, Project Planning, Scheduling & Controls Using Primavera P6 & Micr

    3/10

    Projatech, Project Planning, Scheduling & Controls Using Primavera P6 & Microsoft Project; Consulting, Training & Workforce

    http://www.projatech.com/Knowledge.html[Mon 21/05/12 10:43:16 AM]

    There has been no modifications in

    Resource Budgeted Units for any

    activity or any resource since

    baseline.

    1. For activities Not Started, Budgeted Units to Match

    Remaining and At Complete Units; if not, correct these figures

    and change project default setting by checking "Link Budget

    and At Completion for not started activities" in Project

    "Calculations" tab.

    2. Budgeted Units should not be modified in Current or Primary

    Baseline Schedules without following Change Management

    Process and appropriate approvals. (Original Baseline is never

    modified once approved)

    Once cost estimate is approved, resource budgeted units are assigned to activities, and baseline

    is established, there should not be any changes to Budgeted Units. Any change would make it

    difficult to judge productivity accurately.

    Were there any new activities added

    to replace Placeholder activities in

    the schedule to provide work detail?

    After formal schedule quality assurance and formal approval,

    activities can only be added to replace any placeholder activity.

    The new activities should not span beyond the original

    placeholder activity's time span. After replacing placeholder

    activities with detailed work activities, a schedule quality

    assurance is needed and baseline updated.

    Adding new activities means there is a need to check schedule for quality to ensure the new

    logic is created properly and it is interfacing with the rest of the schedule appropriately.

    For completed activities are you

    noticing a trend that most of activity

    "At-Complete" Durations are largerthan Original Durations?

    If more than 10% of In-Progress or Completed activities have

    At Complete durations higher than Original Duration, then

    discuss the plan with stakeholders and see if there is a need to

    revise durations for the rest of the schedule following Companyschedule change management procedures. Update the

    baseline, when done.

    If most of the completed activities are showing "At-Complete" duration larger than original

    duration, it means it is taking longer to do work than planned. It also means that initial estimate

    of work duration was not correct. It would be advantageous at this point to revise durations for

    remaining work to come up with a realistic plan with a realistic finish date. Update most currentbaseline with revised plan. (Never change original approved baseline)

    For completed activities, are you

    noticing a trend that most of

    activities' "At-Complete" resource

    units are higher th at Budgeted

    Units?

    (Applicable only if you are i nputting Actual

    units in Primavera)

    If too many In-Progress and Completed activities have At

    Complete resource units higher than Budgeted Units, then

    discuss the plan with stakeholders and see if there is a need to

    revise activities' resource units following Company schedule

    change management procedures and then update baseline..

    If most of the completed activities are showing "At-Complete" Units more than Budgeted Units, it

    means it is taking more labor hours to do work than planned. It also means that initial estimate

    of work labor units was not correct. It would be advantageous at this point to revise labor units

    for remaining work to come up with a realistic plan. Update your cost estimate accordingly as

    well as your most current baseline. (Never change original approved baseline)

    In comparison to the latest baseline,

    during each update cycle, are you

    noticing a trend where Total Float

    Variance is growing?

    If more than 25% of major milestones are having significant

    Total Float variance from Project Baseline, have the schedule

    reviewed by stakeholders. If necessary revise plan according to

    Company schedule change management procedures and

    update baseline.

    If Total Float is reducing, it means that it is taking longer to complete work than planned. Such

    delay is reducing Total Float for remaining activities and slowly bringing them near critical. It is

    also likely that project will not finish as planned. It would be advantageous at this point to revise

    durations or labor units for remaining work to come up with a realistic plan with a realistic finish

    date. Update most current baseline with revised plan. (Never change original approved baseline)

    In comparison to the latest baseline,

    during each update cycle, are you

    noticing a trend where activity Finish

    Date Variance is growing?

    If more than 25% of activities are having significant Finish date

    variance from Project Baseline, have the schedule reviewed by

    stakeholders. If necessary revise durations for the remaining

    activities by following Company schedule change management

    procedures and update baseline.

    A one time Finish date variance could just be an indication that project started later than

    planned, but an increasing variance indicates that it is taking longer to complete work than

    planned. Such delay is pushing remaining activities to a later finish date. It is likely that project

    will not finish as planned. It would be advantageous at this point to revise durations or labor

    units for remaining work to come up with a realistic plan with a realistic finish date. Update mostcurrent baseline with revised plan. (Never change original approved baseline)

    If you are following Company

    recommended rule of credit for Earn

    Value management system, do all In-

    Progress Activities have 25%

    duration completion?

    Check to make sure all in-progress activities have a "Duration

    Percentage Complete" equal to 25%

    If you are following Company recommended rules of credit then all In-Progress activities should

    have 25% duration percentage complete to credit 25% of labor units as earned. The remaining

    75% will be marked earned when activity completes.

    Is there any Actual Start or Actual

    Finish Date After the Data Date?

    No activity should have such activities after the data date. Any activities having Actual Start or Actual Finish date after data date means actual work started

    or finished in the future; which is not realistic. Such information should be corrected immediately.

    Misc. Comments or Exceptions

    Q: What items should I minimally check when I am performing a baseline comparison.

  • 8/12/2019 Good - Projatech, Project Planning, Scheduling & Controls Using Primavera P6 & Micr

    4/10

    Projatech, Project Planning, Scheduling & Controls Using Primavera P6 & Microsoft Project; Consulting, Training & Workforce

    http://www.projatech.com/Knowledge.html[Mon 21/05/12 10:43:16 AM]

    Q: What items should I minimally check when I am performing an schedule quality assurance.

  • 8/12/2019 Good - Projatech, Project Planning, Scheduling & Controls Using Primavera P6 & Micr

    5/10

    Projatech, Project Planning, Scheduling & Controls Using Primavera P6 & Microsoft Project; Consulting, Training & Workforce

    http://www.projatech.com/Knowledge.html[Mon 21/05/12 10:43:16 AM]

  • 8/12/2019 Good - Projatech, Project Planning, Scheduling & Controls Using Primavera P6 & Micr

    6/10

    Projatech, Project Planning, Scheduling & Controls Using Primavera P6 & Microsoft Project; Consulting, Training & Workforce

    http://www.projatech.com/Knowledge.html[Mon 21/05/12 10:43:16 AM]

  • 8/12/2019 Good - Projatech, Project Planning, Scheduling & Controls Using Primavera P6 & Micr

    7/10

    Projatech, Project Planning, Scheduling & Controls Using Primavera P6 & Microsoft Project; Consulting, Training & Workforce

    http://www.projatech.com/Knowledge.html[Mon 21/05/12 10:43:16 AM]

    Q: What is the best method of assigning Float contingency in a schedule among different contractors/disciplines?

    Q: What is the best method of assigning schedule contingency among different contractors/disciplines?

  • 8/12/2019 Good - Projatech, Project Planning, Scheduling & Controls Using Primavera P6 & Micr

    8/10

    Projatech, Project Planning, Scheduling & Controls Using Primavera P6 & Microsoft Project; Consulting, Training & Workforce

    http://www.projatech.com/Knowledge.html[Mon 21/05/12 10:43:16 AM]

    Q: How can I assign a constraint and still be able to see the entire longest path in Primavera?

  • 8/12/2019 Good - Projatech, Project Planning, Scheduling & Controls Using Primavera P6 & Micr

    9/10

    Projatech, Project Planning, Scheduling & Controls Using Primavera P6 & Microsoft Project; Consulting, Training & Workforce

    http://www.projatech.com/Knowledge.html[Mon 21/05/12 10:43:16 AM]

  • 8/12/2019 Good - Projatech, Project Planning, Scheduling & Controls Using Primavera P6 & Micr

    10/10

    Projatech, Project Planning, Scheduling & Controls Using Primavera P6 & Microsoft Project; Consulting, Training & Workforce

    htt // j t h /K l d ht l[M 21/05/1210 43 16 AM]

    :: Home :: Services:: Experience:: Client List :: About Us:: Contact Us :: Employment::Useful Links :: Knowledge::Partner's Links :: Privacy Policy ::

    :: Scheduling & Planning Services :: Scheduling Training :: Schedule Quality Assurance :: Project Risk Analysis :: Scheduling Workforce ::

    Copyright 2006. Projatech. All rights reserved.Construction and IT Project Management, Consulting, Training, and Workforce Provider for Primavera P3e, Primavera 5.0, SureTrak and Related Software

    Construction and IT Project Management, Consulting, Training, and Workforce Provider for Primavera P3e, Primavera 5.0, SureTrak and Related Software

    Construction and IT Project Management, Consulting, Training, and Workforce Provider for Primavera P3e, Primavera 5.0, SureTrak and Related Software

    Speed of light

    http://www.1stgrand.com/http://www.projatech.com/index.htmlhttp://www.1stgrand.com/index.htmlhttp://www.projatech.com/Services.htmlhttp://www.1stgrand.com/links/links.htmlhttp://www.projatech.com/Experience.htmlhttp://www.1stgrand.com/links/Manual_Link_Exchanges.htmlhttp://www.projatech.com/Client_List.htmlhttp://www.1stgrandrealty.com/home.htmlhttp://www.projatech.com/About_Us.htmlhttp://www.1stgrandrealty.com/links/links.htmlhttp://www.projatech.com/Contacts.htmlhttp://www.projatech.com/1stGrand%20Website/index.htmlhttp://www.projatech.com/Employment.htmlhttp://www.projatech.com/Privacy_Policy.htmlhttp://www.projatech.com/useful_links.htmlhttp://www.projatech.com/Privacy_Policy.htmlhttp://www.projatech.com/links/links.htmhttp://www.projatech.com/1stGrand%20Website/MyProfile.htmlhttp://www.projatech.com/useful_links.htmlhttp://www.projatech.com/Privacy_Policy.htmlhttp://www.projatech.com/Consulting.htmlhttp://www.projatech.com/Training.htmlhttp://www.projatech.com/Schedule_Quality_Assurance.htmlhttp://www.projatech.com/Schedule_Risk_Analysis.htmlhttp://www.projatech.com/Workforce.htmlhttp://www.projatech.com/http://www.projatech.com/http://www.alizar.com/http://www.bluecorndistribution.com/http://www.speed-light.info/http://www.speed-light.info/http://www.bluecorndistribution.com/http://www.alizar.com/http://www.projatech.com/http://www.projatech.com/Workforce.htmlhttp://www.projatech.com/Schedule_Risk_Analysis.htmlhttp://www.projatech.com/Schedule_Quality_Assurance.htmlhttp://www.projatech.com/Training.htmlhttp://www.projatech.com/Consulting.htmlhttp://www.projatech.com/Privacy_Policy.htmlhttp://www.projatech.com/useful_links.htmlhttp://www.projatech.com/1stGrand%20Website/MyProfile.htmlhttp://www.projatech.com/links/links.htmhttp://www.projatech.com/Privacy_Policy.htmlhttp://www.projatech.com/useful_links.htmlhttp://www.projatech.com/Privacy_Policy.htmlhttp://www.projatech.com/Employment.htmlhttp://www.projatech.com/1stGrand%20Website/index.htmlhttp://www.projatech.com/Contacts.htmlhttp://www.1stgrandrealty.com/links/links.htmlhttp://www.projatech.com/About_Us.htmlhttp://www.1stgrandrealty.com/home.htmlhttp://www.projatech.com/Client_List.htmlhttp://www.projatech.com/Client_List.htmlhttp://www.1stgrand.com/links/Manual_Link_Exchanges.htmlhttp://www.projatech.com/Experience.htmlhttp://www.1stgrand.com/links/links.htmlhttp://www.projatech.com/Services.htmlhttp://www.1stgrand.com/index.htmlhttp://www.projatech.com/index.htmlhttp://www.1stgrand.com/