Applied KanbanA success: the introduction of Kanban as planning,
monitoring and process-control tool in a small team.
Tuesday 14 June 2011
![Page 2: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/2.jpg)
OpenmindsB2B webhosting // Managed servers
Scalable solutions // Personal approachQuality & guarantees
[email protected] // www.openminds.be // +32 9 225 82 91
Tuesday 14 June 2011
![Page 3: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/3.jpg)
The problem
Tuesday 14 June 2011
![Page 4: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/4.jpg)
Openminds
•Hosting (support, installations, ...)
•Development
•Sales/marketing
•Administration
•8 people (5 sysadmin, 2 development, 1 sales, but overlap)
Tuesday 14 June 2011
![Page 5: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/5.jpg)
Before
•Planning was hard
•Tickets got “lost”
•Hard to delegate a task to a colleague
•No overview
Tuesday 14 June 2011
![Page 6: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/6.jpg)
Overview
•Each had his own todo method
•Support: “master in-pile” & “todo”
•Sales: Kristofs book
•Development: All over the place
•Other: when (if) it came to mind
Tuesday 14 June 2011
![Page 7: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/7.jpg)
Kanban: what
Tuesday 14 June 2011
![Page 8: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/8.jpg)
Goal
•Visualizing the workload
•Planning
•Limit the WIP
•Optimalisation
Tuesday 14 June 2011
![Page 9: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/9.jpg)
Standard IT kanban
Tuesday 14 June 2011
![Page 10: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/10.jpg)
Standard IT kanban
•Backlog, Ready, Work In Progress, Done
Tuesday 14 June 2011
![Page 11: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/11.jpg)
Standard IT kanban
•Backlog, Ready, Work In Progress, Done
•Task goes from left to right
Tuesday 14 June 2011
![Page 12: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/12.jpg)
Standard IT kanban
•Backlog, Ready, Work In Progress, Done
•Task goes from left to right
•WIP is limited
Tuesday 14 June 2011
![Page 13: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/13.jpg)
Standard IT kanban
•Backlog, Ready, Work In Progress, Done
•Task goes from left to right
•WIP is limited
•Refill of the backlog through meetings
Tuesday 14 June 2011
![Page 14: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/14.jpg)
How we did it
Tuesday 14 June 2011
![Page 15: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/15.jpg)
Investing
•Board
•Markers
•Post-its
•Planning poker
•Magnets
•Time
Tuesday 14 June 2011
![Page 16: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/16.jpg)
Board location
Tuesday 14 June 2011
![Page 17: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/17.jpg)
Board location
Tuesday 14 June 2011
![Page 18: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/18.jpg)
Board location
Tuesday 14 June 2011
![Page 19: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/19.jpg)
Board layout
•Todo
•Work in progress
•Done
•Waiting for ...
Tuesday 14 June 2011
![Page 20: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/20.jpg)
Special area’s
TriageSupport
Datacenter-todoUrgent
Tuesday 14 June 2011
![Page 21: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/21.jpg)
TeamsColors
Tuesday 14 June 2011
![Page 22: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/22.jpg)
Meetings
•Monday: “planning”
•Tuesday till Friday: “standup”
Tuesday 14 June 2011
![Page 23: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/23.jpg)
Planning
•First working day of the week
•Overview of last week
•Selection of workload for this week
•Discussion about each todo-item
•Rating the item
Tuesday 14 June 2011
![Page 24: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/24.jpg)
Planning poker
•Fibonacci-series
•? en coffee
•Complexity, not time
•Discussion when the difference is big
Tuesday 14 June 2011
![Page 25: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/25.jpg)
Each morningStandup
5 minutes
Tuesday 14 June 2011
![Page 26: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/26.jpg)
Delegate
Tuesday 14 June 2011
![Page 27: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/27.jpg)
Extra
•Priority is from top to bottom (todo)
•“Pair” for training / difficulties
•Ping-pong: stick the tickets together
•Three magnets per person
Tuesday 14 June 2011
![Page 28: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/28.jpg)
Introduction
•No major issues...
•Team wanted some change
•We will evaluate after 2 months
Tuesday 14 June 2011
![Page 29: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/29.jpg)
Result
Tuesday 14 June 2011
![Page 30: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/30.jpg)
Result
•Planning: major improvement
Tuesday 14 June 2011
![Page 31: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/31.jpg)
Result
•Planning: major improvement
•Monitoring: nothing gets forgotten
Tuesday 14 June 2011
![Page 32: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/32.jpg)
Result
•Planning: major improvement
•Monitoring: nothing gets forgotten
•Overview: very clear
Tuesday 14 June 2011
![Page 33: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/33.jpg)
Result
•Planning: major improvement
•Monitoring: nothing gets forgotten
•Overview: very clear
•Workflow gets optimized
Tuesday 14 June 2011
![Page 34: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/34.jpg)
Result
•Planning: major improvement
•Monitoring: nothing gets forgotten
•Overview: very clear
•Workflow gets optimized
•Open communication between teams
Tuesday 14 June 2011
![Page 35: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/35.jpg)
More result
•Measurement: velocity
•feedback for the planning-meeting
Tuesday 14 June 2011
![Page 36: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/36.jpg)
Issues
Tuesday 14 June 2011
![Page 37: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/37.jpg)
Issues
•Our board is too small
Tuesday 14 June 2011
![Page 38: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/38.jpg)
Issues
•Our board is too small
•Planning: only one week
Tuesday 14 June 2011
![Page 39: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/39.jpg)
Issues
•Our board is too small
•Planning: only one week
•Existing ticketting system
Tuesday 14 June 2011
![Page 40: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/40.jpg)
Issues
•Our board is too small
•Planning: only one week
•Existing ticketting system
•Flexible working hours & morning-meeting
Tuesday 14 June 2011
![Page 41: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/41.jpg)
Issues
•Our board is too small
•Planning: only one week
•Existing ticketting system
•Flexible working hours & morning-meeting
•Person still decides what to work on
Tuesday 14 June 2011
![Page 42: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/42.jpg)
Post-itsThey don’t stick as they
advertise!
Tuesday 14 June 2011
![Page 43: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/43.jpg)
ISO 9001
•We have ISO certification
•Kanban is a perfect fit
•Auditor loved the idea
Tuesday 14 June 2011
![Page 44: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/44.jpg)
Bottom line
•It works
•No problem making your own version
•Routine
•Digital board?
•Bigger teams?
Tuesday 14 June 2011
![Page 45: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/45.jpg)
Q & A
Tuesday 14 June 2011
![Page 46: Applied Kanban - Bizcamp 2011](https://reader033.vdocument.in/reader033/viewer/2022052619/5550fce6b4c90501448b4cb6/html5/thumbnails/46.jpg)
Applied Kanban
Bernard Grymonpon - Openminds
@openminds / @wonko_behttp://www.openminds.be/
Tuesday 14 June 2011