bill of quantities sample22222

22
Phillip J Morris & assoc. 2011 Bill of Quantities 19 December 2011 Page 1 of 22 SAMPLE Job PROSPECTIVE BUILDER SAMPLE ESTIMATE RENOVATION AND ADDITION 2 STOREY RESIDENCE 2 HIRE ITEMS Item Rate Amount Description Quantity Units Lvl Ld 0034 1 $945.00 $945.00 extra 1 1 POWER POLE (UNDERGROUND) 26 WEEKS 0039 1 $540.00 $540.00 ea 1 1 TOILET WATER SEAL-WATER FLUSH 14 WKS Includes pump out every 4 weeks, delivery and pickup 0040 16 $617.60 $38.60 week 1 1 TOILET WATER SEAL-WATER FLUSH AFTER 14 WKS Includes pump out every 4 weeks 0041 1 $160.00 $160.00 ea 1 1 FOOTPATH CROSSING 14 WKS Free delivery and pickup if delivered with toilet or power pole 0042 16 $140.80 $8.80 week 1 1 FOOTPATH CROSSING AFTER 14 WKS 0057 1 $320.00 $320.00 ea 1 1 SEC CONNECTION & POWER FOR 14 WEEKS 0058 7 $420.00 $60.00 ea 1 1 CHEMICAL TOILET PUMP OUT ON REQUEST Pump out every 4 weeks 0081 20 $200.00 $10.00 m 1 1 TEMPORARY FENCING UP FOR 3-6 MONTHS Include 10m for rubbish enclosure ($300 min) Total 2 HIRE ITEMS $3,343.40 4 PLANT HIRE Item Rate Amount Description Quantity Units Lvl Ld 0071 1000 $1,000.00 $1.00 ea 1 1 PLANT HIRE AS LISTED Acro props, lifters, hammers etc Total 4 PLANT HIRE $1,000.00 5 SITE PREPARATION Item Rate Amount Description Quantity Units Lvl Ld 0153 2 $1,000.00 $500.00 ea 1 1 SITE SCRAPE FOR SLAB (SOIL REMOVED FROM SITE) Cost per 50M2 Total 5 SITE PREPARATION $1,000.00 7 SET OUT Item Rate Amount Description Quantity Units Lvl Ld 0111 20 $1,000.00 $50.00 ea 1 1 SET OUT (PER LINE) Total 7 SET OUT $1,000.00 9 FOOTINGS Item Rate Amount Description Quantity Units Lvl Ld 0143 97 $1,067.00 $11.00 m2 1 0 SLAB AS LISTED c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Upload: ronnie-albert-montero

Post on 08-Nov-2014

102 views

Category:

Documents


16 download

DESCRIPTION

YES FM AND SOMETHING THAT CANNOT BE MOVED

TRANSCRIPT

Page 1: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 1 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

2 HIRE ITEMS

Item Rate AmountDescription Quantity Units Lvl Ld

0034 1 $945.00$945.00extra 1 1POWER POLE (UNDERGROUND) 26 WEEKS

0039 1 $540.00$540.00ea 1 1TOILET WATER SEAL-WATER FLUSH 14 WKS

Includes pump out every 4 weeks, delivery and pickup

0040 16 $617.60$38.60week 1 1TOILET WATER SEAL-WATER FLUSH AFTER 14

WKS

Includes pump out every 4 weeks

0041 1 $160.00$160.00ea 1 1FOOTPATH CROSSING 14 WKS

Free delivery and pickup if delivered with toilet or power pole

0042 16 $140.80$8.80week 1 1FOOTPATH CROSSING AFTER 14 WKS

0057 1 $320.00$320.00ea 1 1SEC CONNECTION & POWER FOR 14 WEEKS

0058 7 $420.00$60.00ea 1 1CHEMICAL TOILET PUMP OUT ON REQUEST

Pump out every 4 weeks

0081 20 $200.00$10.00m 1 1TEMPORARY FENCING UP FOR 3-6 MONTHS

Include 10m for rubbish enclosure

($300 min)

Total 2 HIRE ITEMS $3,343.40

4 PLANT HIRE

Item Rate AmountDescription Quantity Units Lvl Ld

0071 1000 $1,000.00$1.00ea 1 1PLANT HIRE AS LISTED

Acro props, lifters, hammers etc

Total 4 PLANT HIRE $1,000.00

5 SITE PREPARATION

Item Rate AmountDescription Quantity Units Lvl Ld

0153 2 $1,000.00$500.00ea 1 1SITE SCRAPE FOR SLAB (SOIL REMOVED FROM

SITE)

Cost per 50M2

Total 5 SITE PREPARATION $1,000.00

7 SET OUT

Item Rate AmountDescription Quantity Units Lvl Ld

0111 20 $1,000.00$50.00ea 1 1SET OUT (PER LINE)

Total 7 SET OUT $1,000.00

9 FOOTINGS

Item Rate AmountDescription Quantity Units Lvl Ld

0143 97 $1,067.00$11.00m2 1 0SLAB AS LISTED

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Page 2: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 2 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

9 FOOTINGS

Item Rate AmountDescription Quantity Units Lvl Ld

Topping for polishing

0155 10 $210.00$21.00m 1 1STEP IN SLAB

0164 28.6 $4,719.00$165.00m3 1 1CONCRETE 20mpa

0168 15.85 $475.50$30.00m3 1 1PACKING SAND

0172 2.5 $100.00$40.00ea 1 1TRENCH MESH L11TM3

0173 14 $783.30$55.95ea 1 1TRENCH MESH L11TM4

0175 97 $107.67$1.11ea 1 1TRENCH MESH SUPPORTS

TMS11TM

0177 162 $97.20$0.60ea 1 1BAR CHAIRS

SOG7590 75/90mm

SOG7590 75/90mm

0180 207.75 $228.53$1.10m2 1 1POLYTHENE FILM

Orange Premium 200um

0188 1.5 $224.93$149.95ea 1 1HARCMESH FABRIC SL82

0189 9 $1,705.86$189.54ea 1 1HARCMESH FABRIC SL92

0209 214 $12,840.00$60.00hr 1 1LABOUR

Setout slab and ribs

Box up

Remove top soil and dig for beams

Spread sand and place poly

Place mesh

Pour concrete and trowel off

Strip boxing and clean up

Allowance for overhead and profit (20%)

Total 9 FOOTINGS $22,558.98

10 CONCRETE PUMP

Item Rate AmountDescription Quantity Units Lvl Ld

0219 1 $980.00$980.00ea 1 1CONCRETE PUMP

3 Hr hire and 50 M3 conc.

Total 10 CONCRETE PUMP $980.00

14 STUMPS

Item Rate AmountDescription Quantity Units Lvl Ld

0402 4.5 $32.08$7.13m 1 1CONCRETE STUMPS 100 X 100 (500-1300)

Re-stump bathroom

0497 4.2 $37.80$9.00m 1 1CYPRESS PINE SAWN 100 X 100

Stumps to external walls

Total 14 STUMPS $69.88

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Page 3: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 3 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

15 CONCRETE TO STUMPS & POST PADS

Item Rate AmountDescription Quantity Units Lvl Ld

0421 00.2 $42.80$214.00m3 1 1CONCRETE FOR STUMPS & POSTS (MIN 0.4M3)

Min charge $140

0422 4 $35.20$8.80bag 1 1CONCRETE MIX (RAPID SET) 40 Kg BAG

15.020 1.6 $12.99$8.12m 1 1SOLE PLATES 250 X 50 RED GUM

To external walls

Total 15 CONCRETE TO STUMPS & POST PADS $90.99

19 SCANTLING PINUS

Item Rate AmountDescription Quantity Units Lvl Ld

0484 113.4 $196.18$1.73m 1 1PINE 90 X 35 MGP10

Temporary bracing and eave trim

0485 1307.2 $3,071.92$2.35m 1 1PINE 90 X 45 MGP10

9/5.4 111/3.6 122/2.7 89/2.4 314/1.0 2/1

19.1012 147 $605.64$4.12m 1 1140 X 35 MGP10 PINE

Incl battens to flat roof (1.22 per M2) 147/1.0

19.1015 81 $515.16$6.36m 1 1190 X 45 MGP10 PINE

Rafters @ 600 C-C to cathedral 81/1.0

19.1019 260 $2,210.00$8.50m 1 1240 X 45 F7 PINE

Rafters to flat roof @ 600 c (2.15 m per M2) 260/1.0

19.1019 74.4 $633.14$8.51m 1 0240 X 45 F7 PINE

Plates to steel

19.1020 20 $227.00$11.35m 1 1290 X 45 F7 PINE

Roof and floor beams 20/1.0

Total 19 SCANTLING PINUS $7,459.05

20 SCANTLING KDHW

Item Rate AmountDescription Quantity Units Lvl Ld

20.051 34.1 $119.35$3.50m 1 190 X 35 KDHW F17

3/2.1 1/1.8 26/1

20.052 47 $217.61$4.63m 1 190 X 45 KDHW F17

47/1

20.055 2.4 $11.06$4.61m 1 1120 X 35 KDHW F17

1/2.4

20.057 14.7 $93.20$6.34m 1 1140 X 35 KDHW F17

1/3.3 2/3.0 2/2.7

20.059 10.8 $104.76$9.70m 1 1190 X 35 KDHW F17

1/4.2 2/3.3

20.064 22 $404.80$18.40m 1 1290 X 45 KDHW F17

Roof and floor beams 22/1.0

Total 20 SCANTLING KDHW $950.78

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Page 4: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 4 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

21 STRUCTURAL TIMBER BEAMS

Item Rate AmountDescription Quantity Units Lvl Ld

0575 00.295 $407.10$1,380.00m3 1 1L.V.L. HYSPAN BEAMS H2 TREATED

Roof and floor beams

Total 21 STRUCTURAL TIMBER BEAMS $407.10

22 UPPER FLOOR JOISTS

Item Rate AmountDescription Quantity Units Lvl Ld

22.0410 165 $3,960.00$24.00m 1 1POSI-JOISTS 300mm or 400mm (INCL

ANCILLERIES)

165/1

8401 100 $100.00$1.00ea 1 1CARTAGE/TRAVELLING AS LISTED

Total 22 UPPER FLOOR JOISTS $4,060.00

23 BRICK & CONCRETE CUTTING

Item Rate AmountDescription Quantity Units Lvl Ld

23.100 51 $5,610.00$110.00m 1 1BRICK CUTTING HYDROLIC EQUIPMENT

For cutting internal walls

23.110 18 $1,620.00$90.00m 1 1BRICK CUTTING CLEAN UP

After hydrolic cutting inside residence

23.600 1 $75.00$75.00ea 1 1BRICK & CONCRETE CUTTING SURCHARGE

Total 23 BRICK & CONCRETE CUTTING $7,305.00

24 SHEET FLOORING

Item Rate AmountDescription Quantity Units Lvl Ld

2219 18 $73.94$4.11ea 1 1STURDI BOND 330ml FLOORING GLUE

24.051 26 $892.84$34.34sheets 1 1PARTICLE BOARD FLOORING "YELLOW"

TOUNGE" 3600 X 900 X 19

Total 24 SHEET FLOORING $966.78

27 FASCIA & ROOF PLUMBING

Item Rate AmountDescription Quantity Units Lvl Ld

0524 33 $524.70$15.90m 1 1FASCIA 230 X 32 TRTD PINE (PRIMED)

Total 27 FASCIA & ROOF PLUMBING $524.70

28 WALL BRACING

Item Rate AmountDescription Quantity Units Lvl Ld

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Page 5: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 5 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

28 WALL BRACING

Item Rate AmountDescription Quantity Units Lvl Ld

0604 80.8 $105.04$1.30m 1 1ANGLE BRACING

Total 28 WALL BRACING $105.04

30 FRAME HARDWARE

Item Rate AmountDescription Quantity Units Lvl Ld

0330 10.6 $4.35$0.41m 1 1PLASTIC FLASHING 110mm

0331 4.4 $3.74$0.85m 1 1PLASTIC FLASHING 230mm

0721 45 $261.90$5.82ea 1 1SMART FRAME 24051F "TOP" FIX BRACKET

Brackets for upper floor joists

0841 252 $252.00$1.00ea 1 1HARDWARE AS LISTED

Brackets, Bolts etc as required

0865 4 $72.80$18.20box 1 1GALV.NAILS 50 X 2.8 BH 2Kg

Nails for roof& frame tie down

0873 6 $39.36$6.56box 1 1CONCRETE NAILS 75mm 0.5 Kg

0877 3 $90.00$30.00box 1 1GUN NAILS 75mm

0971 2 $26.50$13.25roll 1 1HOOP IRON 0.8 X 15M

0973 15 $262.50$17.50roll 1 1HOOP IRON 1.0 X 15M

Roof tie down (0.12 rolls/m2)

0979 52 $13.00$0.25ea 1 1GANG NAILS 100 X 50

Total 30 FRAME HARDWARE $1,026.15

31 WINDOWS TIMBER

Item Rate AmountDescription Quantity Units Lvl Ld

31.900 200 $265.64$1.33ea 1 1REGLAZE BROKEN WINDOWS

Total 31 WINDOWS TIMBER $265.64

32 WINDOWS ALUMINIUM

Item Rate AmountDescription Quantity Units Lvl Ld

1101 1 $45,000.00$45,000.00total 1 0ALUMINIUM WINDOWS AS LISTED

Skyrange steel windows

Estimate only

Total 32 WINDOWS ALUMINIUM $45,000.00

33 FRAME CARPENTER

Item Rate AmountDescription Quantity Units Lvl Ld

33.005 176 $9,240.00$52.50hr 1 1LABOUR

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Page 6: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 6 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

33 FRAME CARPENTER

Item Rate AmountDescription Quantity Units Lvl Ld

14 Strip out existing kitchen and bathrm

2 Remove door to living rm

18 Demolish existing shed

12 Demolish garage

14 Streip out existing bathroom and kitchen

4 Remove robe to kids bed

2 Remove door to living

20 Prop verandah roof, remove window and floor, re-install window after

installation of new floor

12 Demolish garage

20 Demolish shed

12 Tarps

12 Sweepout

16 Clean and stack rubbish

12 Make good

124 Total Allow 22 Days

33.105 17.3 $346.56$20.03m2 1 1STUMP BEARER & JOIST

To brick veneer construction

33.106 7 $131.79$18.83m 1 1STUMP TO EXT. WALLS OF WEATHERBOARD

Additional stumps to external walls

33.115 58.8 $806.31$13.71m2 1 1UPPER FLOOR JOISTS

33.120 17.3 $108.75$6.29m2 1 1LAY PYNEBOARD FLOOR TO GROUND FLOOR

33.121 58.8 $403.15$6.86m2 1 1LAY PYNEBOARD FLOOR TO FIRST FLOOR

33.130 93 $2,010.35$21.62m 1 1FIX JOISTS ETC TO FACE OF STEEL/TIMBER BEAM

33.205 62.4 $1,282.18$20.55m 1 1WALLS UP TO 2.7 HIGH

Ground and first floor

33.206 37.2 $1,076.59$28.94m 1 1WALLS 3.0 HIGH

Ground and first floor

33.220 57 $591.92$10.38m 1 1EXTRA FOR FIRST FLOOR WALLS

33.223 22.2 $810.34$36.50m 1 1EXTRA TO CONSTRUCT WALL INSIDE EXISTING

RESIDENCE

For alterations and renovations

33.230 19.6 $82.36$4.20m 1 1PLATE TO BRICK WALL

Fix plate on top of brick wall with hoop iron (fitted by bricklayer)

Fix plate on top of brick wall with hoop iron (fitted by bricklayer)

33.305 30.32 $657.75$21.69m2 1 1CEILING & ROOF FRAMING TILED ROOF

Rafters and ceiling joists @ 600 c-c

Fix fascia

Including 4 hips (valleys not included)

33.310 120.5 $1,927.14$15.99m2 1 1ROOF FRAMING FLAT ROOF WITH GRADED

BATTENS

33.320 30.32 $346.16$11.42m2 1 1CATHEDRAL CEILING

Extra over normal pitched roof

33.332 12.5 $1,050.51$84.04m 1 1CLEARSTOREY & WINDOWS

Construct wall framing and fit windows

33.335 26.4 $181.01$6.86m 1 1STANDARD FASCIA

To be used where there is no roof framing

33.339 58.8 $1,275.58$21.69m2 1 1EXTRA FOR 2 STOREY ROOF

33.370 58.8 $3,049.63$51.86m2 1 1REMOVE ROOF & PREPARE FOR 1st FLOOR

ADDITION

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Page 7: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 7 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

33 FRAME CARPENTER

Item Rate AmountDescription Quantity Units Lvl Ld

Remove roof covering

Cut off and rmove roof frame

Prop ceiling and remove hangers

Fit plates and level for upper floor joists

33.605 37.8 $431.56$11.42m 1 1ROOF & FLOOR BEAMS

33.606 65.5 $1,513.77$23.11m 1 1STEEL ERECTION

33.615 120.5 $843.91$7.00m2 1 1HIGH WIND TIE DOWN

Tie down roof battens, rafters, walls etc with hoop iron or as specified

Total 33 FRAME CARPENTER $28,167.31

34 TARP HIRE

Item Rate AmountDescription Quantity Units Lvl Ld

34.0050 4 $148.00$37.00week 1 1TARPS HIRE 7.2M X 6M

34.0065 4 $328.00$82.00week 1 1TARPS HIRE 12M X 8M

Total 34 TARP HIRE $476.00

36 STEEL - STRUCTURAL

Item Rate AmountDescription Quantity Units Lvl Ld

0002 1 $0.01$0.01ea 1 0****** NOTE ******

As the engineering has not yet been designed, an assesment only has

been made of the possible beam and column location and sizes.

1251 1 $250.00$250.00ea 1 0STRUCTURAL STEEL AS LISTED

Brackets, bolts etc

1300 8.4 $962.01$114.52m 1 1UNIVERSAL BEAM 310 UB 40

1326 4.6 $296.12$64.37m 1 1M.S. CHANNEL 200 X 75 (22.9kg)

1328 36.9 $3,679.79$99.72m 1 1M.S. CHANNEL 250 X 90 (35.5kg)

1329 9.8 $1,130.03$115.31m 1 1M.S. CHANNEL 300 X 90 (40.1kg)

1358 6.6 $1,530.13$231.84m 1 1CIRCULAR HOLLOW TUBE 300mmDIA X 6 GALV

1390 12 $2,040.00$170.00hr 1 1CRANE HIRE (MIN 2 Hr)

1395 120 $8,400.00$70.00hr 1 1LABOUR

Fabrication and erection

Total 36 STEEL - STRUCTURAL $18,288.09

37 PLUMBER

Item Rate AmountDescription Quantity Units Lvl Ld

1411 1 $500.00$500.00total 1 0PLUMBER AS LISTED

Disconnect and stop off existing

1413 1 $4,356.93$4,356.93ea 1 1INTERNAL PLUMBING (1 BATHROOM)

KITCHEN,BATHROOM,L'DRY & W.C. ONLY NO GAS

FITTINGS NO TAPS

1414 2 $1,401.11$700.56ea 1 1EN/SUITE (WC,BASIN,SHOWER)

1419 6 $468.83$78.14ea 1 1EXTRA FOR 2 STOREY (PER POINT)

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Page 8: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 8 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

37 PLUMBER

Item Rate AmountDescription Quantity Units Lvl Ld

1424 16 $905.34$56.58m 1 1PLUMBING WASTE IN SLAB OR UNDERFLOOR

1429 1 $311.21$311.21ea 1 1DISHWASHER INSTALLATION

1432 6 $1,123.59$187.26ea 1 1EXTRA FOR SOLID BRICK PER POINT

1433 13 $1,628.79$125.29ea 1 1EXTRA FOR ADDITION/ALTERATION PER POINT

1437 1 $311.21$311.21ea 1 1GAS H/PLATE

1439 1 $311.21$311.21ea 1 1GAS HWS

1442 1 $311.21$311.21ea 1 1GAS POINT TO DUCTED HEATING INCLUDING

CONNECTION

1444 3 $933.63$311.21ea 1 1FLUEING FOR W/OVEN R/HOOD E/FAN

1496 1 $150.00$150.00ea 1 1CERTIFICATES OF COMPLIANCE

3 off

Total 37 PLUMBER $12,713.05

38 HOT WATER SERVICE

Item Rate AmountDescription Quantity Units Lvl Ld

38.110 1 $4,000.00$4,000.00ea 1 0SOLAR HWS

Supply and install

Total 38 HOT WATER SERVICE $4,000.00

39 ELECTRICIAN

Item Rate AmountDescription Quantity Units Lvl Ld

1571 1 $150.00$150.00ea 1 0ELECTRICIAN AS LISTED

Underground power to automatic gates

1571 1 $750.00$750.00ea 1 0ELECTRICIAN AS LISTED

Disconnect existing and make safe

1572 57 $2,565.00$45.00ea 1 1LIGHT POINT

1573 4 $200.00$50.00ea 1 1LIGHT POINT 2 WAY

1576 8 $328.00$41.00ea 1 1POWER POINT SINGLE

1577 32 $1,376.00$43.00ea 1 1POWER POINT DOUBLE

1581 50 $950.00$19.00ea 1 1EXTRA FOR RENOVATIONS PER POINT BRICK

VENEER

1582 62 $1,426.00$23.00ea 1 1EXTRA FOR RENOVATIONS PER POINT SOLID

BRICK

1583 4 $320.00$80.00ea 1 1EXHAUST FAN WIRE & INSTALL

1584 1 $75.00$75.00ea 1 1RANGEHOOD WIRE & INSTALL

1587 3 $150.00$50.00ea 1 1T.V. AREAL POINT CO-AXIAL

1601 1 $150.00$150.00ea 1 1ELECT W/O

1610 4 $420.00$105.00ea 1 1SMOKE ALARM 240V/9V MAINS WIRED WITH

BATTERY BACKUP

1617 1 $800.00$800.00ea 1 1SWITCHBOARD WITH CIRCUIT BREAKER (RCD) &

CONECTION OF SEC MAINS

1618 5 $1,250.00$250.00ea 1 1EXTRA CIRCUIT

Including Safty Switch

1622 57 $684.00$12.00ea 1 1FIT LIGHT FITTINGS

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Page 9: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 9 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

39 ELECTRICIAN

Item Rate AmountDescription Quantity Units Lvl Ld

1625 3 $540.00$180.00ea 1 1SWITCHBOARD EXTRA FOR LIGHTING R.C.D. (1 per

20 light points)

1681 1 $30.00$30.00ea 1 1PRESCRIBED INSTALLATION FORM

1682 1 $90.00$90.00ea 1 1INSPECTION FEE

1685 1 $30.00$30.00ea 1 1TRANSFER FEE

Total 39 ELECTRICIAN $12,284.00

40 METER BOX

Item Rate AmountDescription Quantity Units Lvl Ld

1672 1 $280.00$280.00ea 1 1B & R METAL METER BOX 4 COMDIN

Total 40 METER BOX $280.00

42 TOP BRICKS

Item Rate AmountDescription Quantity Units Lvl Ld

0242 757 $1,328.16$1.75ea 1 1BESSER BLOCK 390 X 90 X 190 HOLLOW GREY

(10.01)

0246 6400 $2,553.60$399.00 1 1CONCRETE BRICKS 230 X 110 X 76

Total 42 TOP BRICKS $3,881.76

43 TOP BRICK MATERIALS

Item Rate AmountDescription Quantity Units Lvl Ld

0303 8.8 $374.00$42.50m3 1 1BRICK SAND

0306 35 $253.75$7.25bag 1 1CEMENT

(Type A)

0308 13 $124.80$9.60bag 1 1LIMIL

0309 7.1 $18.89$2.66m 1 1FLEXIBLE EXPANSION JOINT 100 X 10

0319 268 $58.96$0.22ea 1 1WALL TIES SOLID BRICK "U" 3.15mm 175mm CAVITY

TIE

0322 340 $34.00$0.10ea 1 1WALL TIES FACE OF WALL INCL NAILS

0333 33.8 $62.53$1.85m 1 1PLASTIC FLASHING 300mm

Total 43 TOP BRICK MATERIALS $926.93

44 TOP BRICKLAYER

Item Rate AmountDescription Quantity Units Lvl Ld

0352 216 $11,340.00$52.50hr 1 1BRICKLAYER LABOUR

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Page 10: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 10 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

44 TOP BRICKLAYER

Item Rate AmountDescription Quantity Units Lvl Ld

10 Remove playroom windows, door, wall and rear access door

6 Fit lintols & remove bwk to garage door

8 Remove kitchen rear window and door to rear passage

4 Remove side window to kitchen and enlarge opening

4 Remove door between kitchen and dining and enlarge opening

24 Remove chimney to dining and make good

12 Remove brickwork over stove and create door opening

6 Remove door to dining-passage and brick up

6 Fit lintols and ramove bwk for doors to store and wir

24 Demolish chimney to lounge and make good

12 Alter fireplace to master bed to accommodate new fire

6 Remove bwk to existing bathrm

16 Remove and stack rubbish

16 Make good as required

138 Total Allow 27 days

0355 6400 $6,720.00$1,050.00 1 1BRICKLAYER GROUND FLOOR

0357 831 $3,695.04$4.45ea 1 1LAY MASONRY BLOCKS 400 X 200 X 100 HOLLOW

0369 1.8 $51.27$28.49m 1 1SILLS

0381 121.3 $970.46$8.00m2 1 1BAGGED BRICKWORK

0396 4.8 $86.93$18.11m2 1 1EXTRA FOR 1st FLOOR BRICK/BLOCKWORK

Total 44 TOP BRICKLAYER $22,863.71

45 SCAFFOLD HIRE

Item Rate AmountDescription Quantity Units Lvl Ld

1802 120 $5,472.00$45.60m2 1 1SCAFFOLD HIRE (KWIKSTAGE INCL ERECT &

DISMANTLE MIN 4 WEEKS

1803 480 $2,064.00$4.30m2 1 1SCAFFOLD HIRE (KWIKSTAGE PER WEEK AFTER 4

WEEKS

Allow 4 weeks additional hire

Total 45 SCAFFOLD HIRE $7,536.00

46 STEEL LINTOLS

Item Rate AmountDescription Quantity Units Lvl Ld

1252 2.2 $42.94$19.52m 1 1M.S. FLAT 75 X 10

2/1.1

Total 46 STEEL LINTOLS $42.94

49 CEMENT SHEET PRODUCTS

Item Rate AmountDescription Quantity Units Lvl Ld

2640 44.05 $1,052.80$23.90m2 1 0CEMENT SHEET PRODUCT AS LISTED

Hardies Scyon "Matrix" fascia cladding

Hardies Scyon "Axon" fascia cladding

2640 1 $350.00$350.00m2 1 0CEMENT SHEET PRODUCT AS LISTED

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Page 11: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 11 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

49 CEMENT SHEET PRODUCTS

Item Rate AmountDescription Quantity Units Lvl Ld

Ancillary items for Hardies Axon and Matrix

Total 49 CEMENT SHEET PRODUCTS $1,402.80

51 ROOF

Item Rate AmountDescription Quantity Units Lvl Ld

1451 7.2 $128.34$17.83m 1 1SPOUTING 115mm QUAD ZINCALUME

1457 7.2 $44.64$6.20m 1 1EXTRA FOR DOUBLE STOREY SPOUTING

1467 6 $540.00$90.00ea 1 1DOWNPIPES 100 X 50 ZINCALUME SINGLE STOREY

1469 2 $56.00$28.00ea 1 1DOWNPIPES 100 X 50 EXTRA FOR 2 STOREY

1472 4 $600.00$150.00ea 1 1RAINWATER HEAD

1477 47.8 $956.00$20.00m 1 1CAP FLASHING

Colourbond flashing to barge boards etc

1480 42.6 $2,209.45$51.87m 1 1UNDER & OVER FLASHING

1483 26.5 $1,590.00$60.00m 1 1BOX GUTTER & FLASHING C'BOND TO PARAPET

2057 33.95 $1,622.71$47.80m2 1 1TERRACOTTA TILE ROOF (incl ridge hips etc) LIGHT

COLOUR (UNGLAZED)

2067 63.97 $296.00$4.63m2 1 1EXTRA FOR 2 STOREY

2068 33.39 $362.82$10.87m2 1 1EXTRA FOR SARKING BRADFORD #439

2123 90.6 $4,312.41$47.60m2 1 1SUPPLY & FIX STEELDECK 0.42MM B.M.T.

ZINCALUME w/- SARKING

Total 51 ROOF $12,718.37

52 INSULATION

Item Rate AmountDescription Quantity Units Lvl Ld

2152 99.6 $498.00$5.00m2 1 1GLADIATOR WRAP - TO EXTERNAL WALLS

Double sided foil

2153 1 $170.00$170.00ea 1 1EXTRA FOR 2-STOREY OR OVER 1.2M FALL

2156 93.6 $883.58$9.44m2 1 1R2.5 BATTS (100mm Thick) ****NO LONGER

AVAILABLE****

To external walls

Polyester batts

2157 142.29 $1,124.09$7.90m2 1 1R3.5 BATTS (160mm Thick)

Polyester batts

To ceiling

52.515 48 $52.80$1.10m2 1 1FOIL TO EXTERNAL WALLS - "EXTRA FOR FIRST

FLOOR"

Total 52 INSULATION $2,728.48

53 FLOORING

Item Rate AmountDescription Quantity Units Lvl Ld

2205 120 $416.40$3.47m 1 1KDHW FLOORING 85 X 19 Standard

To sunroom floor

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Page 12: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 12 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

53 FLOORING

Item Rate AmountDescription Quantity Units Lvl Ld

2220 1 $155.00$155.00drum 1 1ADHESIVE FOR STICK ON FLOORING

Bostic "Ultraset" 15 litre drums

1.13M2 / litre coverage = 17 M2 per drum

Total 53 FLOORING $571.40

54 EXTERNAL DOORS

Item Rate AmountDescription Quantity Units Lvl Ld

2251 4 $927.20$231.80ea 1 0EXTERNAL DOOR AS LISTED

Doors to store

2340 x 870 Solid core flush panel waterproof

2902 1 $50.00$50.00ea 1 0EXTERNAL DOOR FURNITURE ENTRANCE SET AS

LISTED

To store doors

2930 2 $24.00$12.00ea 1 1PROJECT KEY (perdoor)

2935 12 $76.32$6.36ea 1 1STAINLESS STEEL HINGES WITH SCREWS 89m

Total 54 EXTERNAL DOORS $1,077.52

55 CAVITY SLIDE DOOR FRAMES

Item Rate AmountDescription Quantity Units Lvl Ld

2302 2 $224.00$112.00ea 1 1CAV.SL.DR.FRAME 2040 X UP TO 820

Total 55 CAVITY SLIDE DOOR FRAMES $224.00

60 SKYLIGHTS

Item Rate AmountDescription Quantity Units Lvl Ld

1921 1 $1,200.00$1,200.00ea 1 0SKYLIGHT AS LISTED

Supply and install Velux window to first floor bathrm

980 x 550 D/glazed openable

Total 60 SKYLIGHTS $1,200.00

61 LOCK UP TIMBER

Item Rate AmountDescription Quantity Units Lvl Ld

2384 60 $243.00$4.05m 1 1F7 TREATED PINE ROUGH HEADED 90 X 45 (H3)

Fascia frame

2544 7.5 $15.00$2.00m 1 1PINUS SAWN TREATED 150 X 25

Plinth boards

2771 00.5 $0.48$0.95m 1 1QUAD 19mm SPLAYED

2773 4 $52.00$13.00pkt 1 1MASONITE PACKING STRIPS 20 PIECES/PKT

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Page 13: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 13 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

Total 61 LOCK UP TIMBER $310.48

62 LOCK UP HARDWARE

Item Rate AmountDescription Quantity Units Lvl Ld

0845 1 $25.20$25.20box 1 1NAILS 75 X 3.75 BH 5Kg

0850 1 $25.20$25.20box 1 1NAILS 50 X 2.8 BH 5Kg

0853 2 $22.60$11.30box 1 1NAILS 40 X 2 BH 2Kg

0883 2 $12.80$6.40box 1 1SOFT SHEET NAILS 25 X 1.8 500g

Total 62 LOCK UP HARDWARE $85.80

63 LOCK UP CARPENTER

Item Rate AmountDescription Quantity Units Lvl Ld

3002 24 $1,260.00$52.50hr 1 1LABOUR

8 Fascia frame

12 Make good

3019 120 $669.77$5.58m 1 1STRIP FLOORING SECRET NAILED or DIRECT STICK

3040 24 $912.88$38.04m 1 1EXTRA FOR 2 STOREY EAVES

3046 4 $829.89$207.47ea 1 1EXTERNAL DOOR TO TIMBER FRAME INCL.

FURNITURE

3049 2 $91.31$45.66ea 1 1FIT CAV. SL. DOOR FRAME

3055.060 210 $918.75$4.38m2 1 1STRAIGHTEN WALLS ARCHITECTURAL

To accommodate "Level 5" plaster finish

3071 7.5 $38.90$5.19m 1 1EXTERNAL LINING BOARDS

Plinth boards

3075 45 $2,816.64$62.59m2 1 1FIX COMPRESSED CEMENT SHEET TO

DECKS/WALLS

Hardies Scyon cladding to walls and fascia

3082 3 $213.99$71.33ea 1 1INSTALL SHOWER BASE

900 x 900 pre-cast polymarble etc

4718 4 $113.40$28.35ea 1 12340 HIGH DOORS

4719 4 $165.38$41.34ea 1 1SOLID CORE DOORS EXTRA PER DOOR

Total 63 LOCK UP CARPENTER $8,030.90

64 PLASTERER

Item Rate AmountDescription Quantity Units Lvl Ld

3301 1 $1,200.00$1,200.00total 1 0PLASTERING AS LISTED

Make good to existing where works have taken place

3303 378.83 $6,830.53$18.03m2 1 1SUPPLY & FIX 10mm PLASTERBOARD & TO WALLS

INCLUDING W.R. BRD TO WET AREAS 55mm

SCOTIA CORNICE

To "Level 4" finish

To "Level 4" finish

3304 195.35 $3,522.28$18.03m2 1 1SUPPLY & FIX 10mm SUPERSEAL PLASTER

CEILINGS

To "Level 4" finish

3306 1 $612.15$612.15ea 1 1EXTRA FOR 2 STOREY

3307 574.18 $5,157.57$8.98m2 1 1EXTRA FOR "LEVEL 5" FINISH

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Page 14: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 14 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

64 PLASTERER

Item Rate AmountDescription Quantity Units Lvl Ld

3313 30.32 $335.20$11.06m2 1 1EXTRA FOR CATHEDRAL CEILING

3314 119.88 $1,159.67$9.67m2 1 1EXTRA FOR PLASTERING INSIDE EXIST RESIDENCE

3324 59.4 $492.52$8.29m 1 1EXTRA FOR 3.0 HIGH WALLS PER LM OF

PLASTERED WALL

3326 175.7 $3,195.35$18.19m 1 1SQUARE SET CORNICE IN LIEU OF 55mm SCOTIA

3327 2.1 $44.98$21.42m 1 1REVEALS TO ARCHES, BALUST. TOP, WINDOWS

ETC

Total 64 PLASTERER $22,550.26

65 HARD PLASTERER

Item Rate AmountDescription Quantity Units Lvl Ld

ps 1 $1,500.00$1,500.00ea 1 0***** PROVISIONAL SUM *****

Make good to existing

Total 65 HARD PLASTERER $1,500.00

66 STAIRS & BALUSTRADE

Item Rate AmountDescription Quantity Units Lvl Ld

3502 18 $1,440.00$80.00ea 1 1STAIRS PER TREAD PINE NO BALUSTRADE

3503 3 $480.00$160.00ea 1 1STAIRS PER WINDER PINE

3542 2.5 $187.50$75.00m 1 1TIMBER BALUSTRADE WITH SQUARE BALUSTERS

KDHW

3549 7.5 $262.50$35.00m 1 1HANDRAIL TO WALL KDHW

Including brackets (1000 c-c)

Total 66 STAIRS & BALUSTRADE $2,370.00

67 CABINET MAKER

Item Rate AmountDescription Quantity Units Lvl Ld

ps 1 $60,000.00$60,000.00ea 1 0***** PROVISIONAL SUM *****

Supply and install cabinets to

Kitchen

L'dry

Bathrm

Ens

Dining-iving

Shelving to

Pantry

Wir

External store

Robes to Bed 1,2, guest

Total 67 CABINET MAKER $60,000.00

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Page 15: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 15 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

70 DOORS & JAMBS

Item Rate AmountDescription Quantity Units Lvl Ld

2421 5.1 $159.38$31.25m 1 1KDHW 290 X 19 (STANDARD)

1/5.1

4123.100 7 $560.00$80.00ea 1 1SEMI-SOLID CORE MDF DOOR 2040 X 820

4135 3 $15.00$5.00ea 1 1GROOVE BOTTOM RAIL

4195 15.6 $42.12$2.70m 1 1MDF JAMB MATERIAL 110mm

2/4.8 1/3.3 1/2.7

4210 2 $27.24$13.62ea 1 1RAVAN DOOR SEAL RP3 900mm (EXT.DOORS)

For bottom of external hinged doors (Open in)

4211 2 $11.70$5.85roll 1 1RAVAN DOOR SEAL RP59 (DOOR JAMBS)

Soft foamed rubber door frame seal (5M roll)

4232 4 $64.00$16.00ea 1 1JAMBS & STOPS MDF SINGLE 2040 HIGH

Total 70 DOORS & JAMBS $879.44

71 ARCHS SKIRTING & MOULDINGS

Item Rate AmountDescription Quantity Units Lvl Ld

2771 36 $34.20$0.95m 1 1QUAD 19mm SPLAYED

2772 24 $19.68$0.82m 1 1QUAD 12mm SPLAYED

4354 129.6 $395.28$3.05m 1 1SKIRTING / ARCHITRAVE 140 X 18 MOULDED

MDF (PRIMED)

Skirting

4357 194.4 $482.11$2.48m 1 1SKIRTING / ARCHITRAVE 92 X 18 MOULDED

MDF (PRIMED)

Architrave 36/5.4

Total 71 ARCHS SKIRTING & MOULDINGS $931.27

72 FIXING TIMBER

Item Rate AmountDescription Quantity Units Lvl Ld

2411 1.8 $3.33$1.85m 1 1KDHW 42 X 19 (STANDARD)

1/1.8

2412 4.2 $13.02$3.10m 1 1KDHW 67 X 19 (STANDARD)

2/2.1

2414 3.9 $22.62$5.80m 1 1KDHW 117 X 19 (STANDARD)

1/3.9

4411 124.2 $1,242.00$10.00m 1 1LINING BOARDS REBATE/REGENCY 137 X 10

W.R.CEDAR

Eaves lining to verandah

Total 72 FIXING TIMBER $1,280.97

73 FIXING HARDWARE

Item Rate AmountDescription Quantity Units Lvl Ld

0847 1 $25.50$25.50box 1 1NAILS 65 X 2.8 BH 5Kg

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Page 16: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 16 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

73 FIXING HARDWARE

Item Rate AmountDescription Quantity Units Lvl Ld

0850 1 $25.20$25.20box 1 1NAILS 50 X 2.8 BH 5Kg

0853 1 $11.30$11.30box 1 1NAILS 40 X 2 BH 2Kg

0854 2 $7.16$3.58box 1 1NAILS 25 X 1.6 BRADS 500g

4504 4 $18.00$4.50ea 1 1DOOR LATCH

4509 4 $520.00$130.00ea 1 1DOOR FURNITURE PASSAGE SET

(ARCHITECTURAL)

4545 6 $90.00$15.00ea 1 0FLUSH PULLS PLAIN (GAINSBOROUGH)

4550 12 $27.60$2.30ea 1 1HINGES 85mm LP

4552 2 $3.70$1.85ea 1 1HINGES 65mm LP

4566 5 $55.00$11.00box 1 1SCREWS 25 X 8# C.S.K. POZZIDRIVE (100)

4581 1 $70.00$70.00ea 1 0SLIDING DOOR TRACK SYLON TWIN BALL 760 - 920

4602 3 $18.00$6.00ea 1 0DOOR STOPS 75mm

4623 1 $6.27$6.27ea 1 1SELLEYS CLEAR SILICON 320 gram

4625 1 $10.18$10.18ea 1 1SELLEYS AQUADHERE 500ml

Total 73 FIXING HARDWARE $887.91

74 FIXING CARPENTER

Item Rate AmountDescription Quantity Units Lvl Ld

4702 17 $892.50$52.50hr 1 1FIXING CARPENTER LABOUR

Make good

Extra for door in brick wall

4708 4 $456.44$114.11ea 1 1SINGLE DOOR SITE HUNG INCL ARCH'S &

HARDWARE

4714 1 $128.38$128.38ea 1 1SURFACE SLIDING DOOR INCL ARCH'S & H'WARE

4716 2 $142.66$71.33ea 1 1CAVITY SLIDING DOOR INCL ARCH'S & H'WARE

4725 2 $125.46$62.73ea 1 1FIT JAMB & ARCH'S ONLY

4736 129.6 $937.37$7.23m 1 1SKIRTING (MOULDED)

4737 11 $376.66$34.24ea 1 1ARCHITRAVES TO WINDOWS

4739 36 $164.69$4.57m 1 1EXTRA TO FIX SKIRTING TO BRICK

4741 2 $54.34$27.17ea 1 1FIX DRAUGHT EXCLUDER TO HINGED DOOR

4748 124.2 $863.77$6.95m 1 1LINING BOARDS TO CEILING

Verandah ceiling

4799 58.8 $161.04$2.74m2 1 1EXTRA FOR 2 STOREY

Total 74 FIXING CARPENTER $4,303.31

75 WALL & FLOOR TILES

Item Rate AmountDescription Quantity Units Lvl Ld

4900 23.6 $1,416.00$60.00m2 1 0FLOOR TILES "SUPPLY ONLY"

4.5 L'dry

5.5 Bathroom

9.5 Ens 1

4.1 Bthroom firdt floor

4901 51.6 $2,580.00$50.00m2 1 0WALL TILES "SUPPLY ONLY"

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Page 17: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 17 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

75 WALL & FLOOR TILES

Item Rate AmountDescription Quantity Units Lvl Ld

21.0 Ens 1 (2100h all walls)

16.5 Bathroom ground floor (2100h all walls)

12.6 Bathroom first floor (2100h all walls)

1.5 L'dry (1200h all walls 2100h shower)

4920 4 $120.00$30.00ea 1 0SOAP HOLDERS SUPPLY ONLY

4950 51.6 $2,580.00$50.00m2 1 1LABOUR FOR WALL TILES INCL SUPPLY GLUE &

GROUT

4951 23.6 $1,180.00$50.00m2 1 1LABOUR FOR FLOOR TILES INCL SUPPLY GLUE &

GROUT

Bath, WC, L'dry, En-suite

4954 23.6 $684.40$29.00m2 1 1SUPPLY & LAY 6mm F.C. CERAMIC U'LAY ONLY

4956 3.6 $491.40$136.50m2 1 1FORM & TILE SHOWER BASES

Total 75 WALL & FLOOR TILES $9,051.80

76 WATERPROOF MEMBRANE

Item Rate AmountDescription Quantity Units Lvl Ld

3805 41.1 $2,055.00$50.00m2 1 1WATERPROOF MEMBRANE

Wet area floors and shower walls

Total 76 WATERPROOF MEMBRANE $2,055.00

78 HEATING

Item Rate AmountDescription Quantity Units Lvl Ld

ps 1 $7,000.00$7,000.00ea 1 0***** PROVISIONAL SUM *****

Gas log fire to living

ps 1 $15,000.00$15,000.00ea 1 0***** PROVISIONAL SUM *****

Central heating

Total 78 HEATING $22,000.00

79 AIR CONDITIONING

Item Rate AmountDescription Quantity Units Lvl Ld

ps 1 $5,000.00$5,000.00ea 1 0***** PROVISIONAL SUM *****

(Labour & Material)

Total 79 AIR CONDITIONING $5,000.00

80 APPLIANCES

Item Rate AmountDescription Quantity Units Lvl Ld

6728 1 $4,000.00$4,000.00ea 1 0WALL OVEN ELECTRIC (TOP RANGE)

6775 1 $2,000.00$2,000.00ea 1 0HOT PLATE ELECTRIC (TOP RANGE ie Induction)

6858 1 $2,000.00$2,000.00ea 1 0DISHWASHER (TOP RANGE)

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Page 18: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 18 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

80 APPLIANCES

Item Rate AmountDescription Quantity Units Lvl Ld

6910 1 $2,500.00$2,500.00ea 1 0RANGEHOOD (TOP RANGE)

Total 80 APPLIANCES $10,500.00

84 PLUMBING FIXTURES

Item Rate AmountDescription Quantity Units Lvl Ld

6401 1 $4,000.00$4,000.00ea 1 0BATH AS LISTED

6421 1 $1,000.00$1,000.00ea 1 0SINK AS LISTED

6470 1 $298.91$298.91ea 1 1LAUNDRY TROUGH CLARK 45 LITRE 8510

SINGLE INSERT SINGLE RINSE BYPASS

6491 3 $1,397.64$465.88ea 1 1SHOWER BASE Uniw0912 910 x 1230 (FOR

TILING)

6500 3 $1,200.00$400.00ea 1 0BASIN AS LISTED

6536 3 $2,100.00$700.00ea 1 0W.C. SUITE AS LISTED

Total 84 PLUMBING FIXTURES $9,996.55

85 TAPS

Item Rate AmountDescription Quantity Units Lvl Ld

pc 1 $6,000.00$6,000.00ea 1 0****** P. C. ITEM ******

To shower recess

Total 85 TAPS $6,000.00

86 BATHROOM ACCESSORIES

Item Rate AmountDescription Quantity Units Lvl Ld

5103 3 $165.00$55.00ea 1 0TOILET ROLL HOLDER AS LISTED

5105 3 $255.00$85.00ea 1 0TOWEL RAIL AS LISTED

Total 86 BATHROOM ACCESSORIES $420.00

88 SHOWER SCREENS

Item Rate AmountDescription Quantity Units Lvl Ld

7341 3 $5,730.00$1,910.00ea 1 1FULLY FRAMELESS SHOWER SCREEN 1500X 900

Total 88 SHOWER SCREENS $5,730.00

89 INTERNAL GLAZING & MIRRORS

Item Rate AmountDescription Quantity Units Lvl Ld

7458 3 $587.13$195.71ea 1 1MIRROR 4mm SILVER GLUED TO WALL 900 X 1500

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Page 19: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 19 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

89 INTERNAL GLAZING & MIRRORS

Item Rate AmountDescription Quantity Units Lvl Ld

Total 89 INTERNAL GLAZING & MIRRORS $587.13

91 LIGHT FITTINGS

Item Rate AmountDescription Quantity Units Lvl Ld

pc 1 $3,500.00$3,500.00ea 1 0****** P. C. ITEM ******

(Material only)

Total 91 LIGHT FITTINGS $3,500.00

94 PAINTING

Item Rate AmountDescription Quantity Units Lvl Ld

7621 1 $14,500.00$14,500.00total 1 0PAINTING AS LISTED

3rd coat of paint

7640 18.81 -$274.62-$14.60m2 1 1DEDUCT FOR ALUMINIUM WINDOWS

7642 18.81 $952.42$50.63m2 1 1TIMBER WINDOWS STAINED 2 COATS (EXTRA

OVER PLASTER)

7650 7 $406.43$58.06ea 1 1STANDARD PAINT FINISH TO INT DOORS 2 COATS

PAINT (EXTRA OVER PLASTER)

7668 7.5 $391.37$52.18m 1 1BALUSTRADE VERTICAL BALUSTERS 2 COATS

PAINT

7671 20.7 $173.27$8.37m 1 1SKIRTING BASIC PAINT FINISH 2 COATS PAINT

7676 634.07 $4,601.83$7.26m2 1 1WALLS & CEILINGS 2 COATS PAINT

7677 30.32 $316.87$10.45m2 1 1EXTRA FOR CATHEDRAL CEILING

7686 24 $150.67$6.28m 1 1HEIGHT ALLOWANCE

7687 16.48 $404.27$24.53m2 1 1PAINT LINING BOARDS 2 COATS PAINT

Plinth boards

7688 124 $2,590.34$20.89m2 1 1PAINT BRICKWORK 2 COATS ONLY

7689 44 $582.78$13.25m2 1 1EXTERNAL CEMENT SHEET 2 COATS PAINT

7696 66.6 $557.47$8.37m 1 1FASCIA & SPOUT 2 COATS PAINT

7700 15.3 $958.29$62.63m 1 1PICKET FENCE

7732 390 $10,067.03$25.81m2 1 1RE-PAINT WALLS & CEILING GOOD CONDITION 2

COATS PAINT

7735 6 $360.78$60.13ea 1 1RE-PAINT FLUSH PANEL DOOR 2 COATS PAINT

7741 33.5 $3,201.61$95.57m2 1 1RE-PAINT WINDOWS BOTH SIDES GOOD

CONDITION 2 COATS PAINT

7746 33 $3,153.83$95.57m 1 1RE-PAINT EAVES & FASCIA TIMBER LINED OVER

EXPOSED RAFTER 2 COATS PAINT

Total 94 PAINTING $43,094.61

96 SEWER/SEPTIC

Item Rate AmountDescription Quantity Units Lvl Ld

ps 1 $500.00$500.00ea 1 0***** PROVISIONAL SUM *****

(Labour & Material)

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Page 20: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 20 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

Total 96 SEWER/SEPTIC $500.00

97 S. W. DRAINS & STORAGE TANKS

Item Rate AmountDescription Quantity Units Lvl Ld

7580.010 1 $3,000.00$3,000.00ea 1 0WATER STORAGE TANK AS LISTED

ps 1 $750.00$750.00ea 1 0***** PROVISIONAL SUM *****

(Labour & Material)

Total 97 S. W. DRAINS & STORAGE TANKS $3,750.00

98 FENCING

Item Rate AmountDescription Quantity Units Lvl Ld

0005 1 $5,500.00$5,500.00ea 1 0ITEM AS LISTED

Auto gates to drive

Estimate only

6221 12.3 $863.46$70.20m 1 1PICKET FENCE 1200 HIGH WITH CAP

Total 98 FENCING $6,363.46

99 PAVING

Item Rate AmountDescription Quantity Units Lvl Ld

0122 1 $1,500.00$1,500.00m3 1 0EXCAVATION

Break up and remove existing concrete paving

Excavate and remove soil for paving

6301 1 $6,000.00$6,000.00total 1 0PAVING AS LISTED

Supply & lay "Cobble" pavers

Pavers at $65/M2

6313 52.65 $2,695.45$51.20m2 1 1PAVING 100mm REINFORCED F72

Length Width Quantity

19.50m X 2.70m 1 OFF Driveway

6329 5 $487.86$97.57ea 1 1FOOTPATH REPAIRS

Per bay

6343 1 $0.01$0.01m2 1 0BRICK PAVING "DRIVES" SUPPLY & LAY ON 100mm

CROSHED ROCK & SAND BED

In lieu of "Cobble" pavers $5,600

Total 99 PAVING $10,683.31

1B PRELIMINARIES

Item Rate AmountDescription Quantity Units Lvl Ld

1B.020 1 $350.00$350.00ea 1 1SITE SIGNAGE

Total 1B PRELIMINARIES $350.00

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Page 21: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 21 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

101 FLOOR FINISHES & COVERINGS

Item Rate AmountDescription Quantity Units Lvl Ld

101.010 1 $10,000.00$10,000.00m2 1 0FLOOR COVERING AS LISTED

Polished concrete to kitchen, dining, living, porch

Allow basic grind and polyurathane finish.

(If is to be polished without poly coating allow $24,000)

7827 62 $1,941.84$31.32m2 1 1SANDING & POLISHING "EXISTING FLOORS" (MIN

CHARGE 20 M2)

Acrylic finish to entry, living and master bed, wir

7828 10 $291.60$29.16m2 1 1SANDING & POLISHING "SECRET NAILED" (MIN

CHARGE 20 M2)

Acrylic finish

Total 101 FLOOR FINISHES & COVERINGS $12,233.44

102 FLYWIRE SCREENS

Item Rate AmountDescription Quantity Units Lvl Ld

7851 1 $750.00$750.00ea 1 0FLYWIRE SCREENS/DOORS AS LISTED

Flywire doors

7855 11 $451.00$41.00ea 1 1FLYWIRE SCREENS ALUMINIUM FRAME

FIBREGLASS MESH

Total 102 FLYWIRE SCREENS $1,201.00

103 BRICK CLEAN

Item Rate AmountDescription Quantity Units Lvl Ld

7751 1 $420.00$420.00total 1 0BRICK CLEAN AS LISTED

7752 4 $177.60$44.40hr 1 1BRICK CLEAN LABOUR

Clean concrete blocks

7755 -4800 -$201.60$42.00 1 1BRICK CLEAN SINGLE STOREY

Total 103 BRICK CLEAN $396.00

104 INTERNAL CLEAN

Item Rate AmountDescription Quantity Units Lvl Ld

7785 261 $1,644.30$6.30m2 1 1HOUSE CLEANING

7786 24 $144.00$6.00m 1 1HEIGHT ALLOWANCE

Total 104 INTERNAL CLEAN $1,788.30

105 SITE CLEAN

Item Rate AmountDescription Quantity Units Lvl Ld

7801 1 $4,000.00$4,000.00ea 1 0SITE CLEAN AS LISTED

Total 105 SITE CLEAN $4,000.00

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45

Page 22: Bill of Quantities Sample22222

Phillip J Morris & assoc. 2011

Bill of Quantities

19 December 2011

Page 22 of 22

SAMPLEJob PROSPECTIVE BUILDER

SAMPLE ESTIMATE

RENOVATION AND ADDITION

2 STOREY RESIDENCE

111 FIT OFF LABOUR

Item Rate AmountDescription Quantity Units Lvl Ld

8054 210 $583.21$2.78m2 1 1FIT OFF LABOUR

Total 111 FIT OFF LABOUR $583.21

112 SUPERVISION

Item Rate AmountDescription Quantity Units Lvl Ld

8082 1 $25,000.00$25,000.00ea 1 0SUPERVISION

Total 112 SUPERVISION $25,000.00

114 SURVEYOR

Item Rate AmountDescription Quantity Units Lvl Ld

8207 1 $850.00$850.00total 1 1SURVEYOR ALL BOUNDARIES

Total 114 SURVEYOR $850.00

117 INSURANCE & MAINTENANCE

Item Rate AmountDescription Quantity Units Lvl Ld

8351 1 $1,710.00$1,710.00total 1 0H.O.W. (HOME OWNERS WARRANTY)

8355 1 $1,250.00$1,250.00total 1 0INSURANCE PUBLIC LIABILITY FIRE & THEFT

8360 1 $1,500.00$1,500.00total 1 0MAINTENANCE

Total 117 INSURANCE & MAINTENANCE $4,460.00

118 CARTAGE & TRAVELING

Item Rate AmountDescription Quantity Units Lvl Ld

8402 1 $1,000.00$1,000.00ea 1 1CARTAGE OF MATERIALS EX YARD

Total 118 CARTAGE & TRAVELING $1,000.00

119 CONTINGENCY

Item Rate AmountDescription Quantity Units Lvl Ld

8451 1 $25,000.00$25,000.00ea 1 0PRICE RISE & CONTINGENCY

Total 119 CONTINGENCY $25,000.00

Total SAMPLE PROSPECTIVE BUILDER $548,719.96

c2009 Databuild www.databuild.com.au 2 - 33 C:\DBW32ADO\reports\C10dbill.rpt PHILLIP 14:45